ML14176A799

From kanterella
Jump to navigation Jump to search
Emergency Operating Procedures Insp Rept 50-261/89-16 on 890918-29.No Violations or Deviations Noted.Major Areas Inspected:Verification That Two Emergency Operating Procedures for Plant Technically Correct
ML14176A799
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 11/01/1989
From: Lawyer L, Peebles T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14176A798 List:
References
50-261-89-16, NUDOCS 8911200146
Download: ML14176A799 (72)


See also: IR 05000261/1989016

Text

pg REG~

UNITED STATES

o 0

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W.

ATLANTA, GEORGIA 30323

Report No.:

50-261/89-16

Licensee:

Duke Power Company

422 South Church Street

Charlotte, NC 28242

Docket No.: 50-261

License No.: DPR-23

Facility Name: H. B. Robinson

Inspection Cond *ted: Septe

r 18 o 29, 1989.

Inspectors:

L. LawD r, Tam

nered

Team Members:

G. Bryan, Jr.

G. Galletti

L. Garner

G.. Salyers

R. Schin

A. Sutthoff

Approved By:

T. A. Peebles, Chief

Date Signed

Operations Branch

Division of Reactor Safety

SUMMARY

Scope:

This was a special announced Emergency Operating Procedure (EOP) team inspection.

Its purpose was to verify that the Robinson 2 EOPs were technically accurate,

and that their specified actions could be accomplished using existing equipment,

controls, and instrumentation.

The inspection. evaluated the adequacy of the

licensee's EOPs [including Abnormal Operating Procedures (AOPs)],

conformance

of these procedures

to the Westinghouse Owners'

Group Emergency Response

Guidelines

(ERGs),

and conformance to the approved writer's guide.

The

inspection included a.comparison of the EOPs to Westinghouse generic technical

guidelines, a technical adequacy review of the procedures, control room and in

plant walkthroughs, simulator evaluation of selected procedures, a review of

on-going control of these procedures, and interviews of operators who use the

procedures.

8911 200)1 46. 89110(:7

PDR, ADOCK

05C)C002

6 1

2

Results:

The overall assessment concluded that the EOPs adequately covered the broad range

of accidents ahd equipment failures necessary-for safe shutdown of the plant.

The team identified weaknesses in availability of equipment, paragraph 4; plant

design,

paragraph 4; level of detail in procedures,

paragraph 4; technical

documentation, paragraphs 2 and

4; conformance with the. writervs guide,

paragraphs 2, 3. and 4; and management control of the EOP program, paragraph 6.

The team reviewed the draft Safety Evaluation Report (SER)

on the licensee's

Procedures Generation Package (PGP)

commitments and determined that, when the

Inspector Followup Items (IFIs)

in this report are completed, all licensee

actions necessary in response to the SER will be completed.

Violations or

deviations were not identified in this report.

REPORT DETAILS

1. Persons contacted

Licensee employees

S. Allen, Manaqer-

License Training

J. Barry, Reactor Operator

  • C. Baucom, Senior Specialist -

Regulatory Compliance

  • D. Beith, Human Factors Specialist -

Human Factors Interfaces

  • C. Bethea, Manager -

Training

D. Blakeney, Senior Engineer -

STA

J. Boyd, Senior Specialist -

Simulator Support

T. Byron, Senior Specialist -

License Training

H. Carter, Senior Specialist -

License Training

D. Cook, Auxiliary Operator

J. Curley, Manager -

Environmental and Radiation Control

W. Cutright, Reactor Operator

  • C. Dietz, Manager - Robinson Nuclear Project Department

W. Flanagan, Manager - Outage Modifications

S.-Griggs, Technical Aide -

Regulatory Compliance

J. Harding, Senior Control Operator

  • E. Harris, Jr., Manager -

Onsi-te Nuclear Safety

T. Hodges, Administration

R. Ivey, Auxiliary Operator

  • J. Kloosterman, Director -

Regulatory Compliance.

D. LaBelle, Project Engineer - Onsite Nuclear Safety

F. Legette, Senior Control Operator

B. McFeaters, Project Specialist - Corp. Emergency Planning

R. Moore, Shift Foreman

  • R. Morgan, Plant General Manager

D. Neal, Senior Specialist -

License Training

  • D. Quick, Manager -

Plant Support

D. Seagle, Shift Foreman

  • J.

Sheppard, Manager -

Operations

  • E. Shoemaker, Project Engineer - Operations

V. Smith, Senior Specialist -

License Training

  • D. Stadler, Onsite Licensing-Engineer

R. Stebbins, Senior Specialist -

License Training

B. Stover, Senior Control Operator

T. White, Reactor Operator

  • L. Williams, Supervisor - Emergency Planning & Security
  • H. Young, Manager - Quality Assurance and Quality Control

Other licensee employees contacted included engineers,

technicians,

operators and office personnel.

0II

2

NRC Personnel

  • R. Lo, Project Manager -

Robinson, NRR

.*W.

Regan, Chief

Human Factors Assessment Branch, NRR

NRC Resident Inspectors

K. Jury

  • Attended exit interview-on September 29, 1989.

Procedures reviewed during this inspection are listed in Appendix A.

A list of abbreviations used in this report is contained in Appendix E.

2.

EOP/GTG Comparison

The team reviewed the development of the Robinson emergency operating

procedures (EOPs) as the basis for evaluating the relationship of the

EOPs to the plant specific technical guidelines (PSTG).

The Robinson Operations Department developed Revision 0 of the

Robinson EOPs directly from the emergency response guidelines (ERGs).

The EOPs were produced by application of the principles in the Robinson

writer's guide to the technical information in the ERG,

the Robinson

setpoint document

and other sources.

The licensee submitted an

EOP

Procedure Generation Package.(PGP), including a writer's guide, to the NRC

for review and approval in 1984.

The licensee conducted simulator validation of the EOPs on-the Shearon

Harris simulator in June 1983. Procedures that could not be validated on

the simulator were validated by control room walkthroughs during.July and

August of 1984.

No other plant walkthroughs were conducted as part of

the

EOP validation.

.The

licensee revalidated a limited number of the

EOPs on the Robinson plant specific simulator in 1987. Therefore,

not

all of the Robinson

EOPs

had been validated on the plant specific

simulator.'

Robinson licensed operators conducted verification of the

EOPs in July 1984 through tabletop reviews.

The licensee conducted a

final technical

review of the

EOPs

in August 1984.

The licensee

implemented Revision 0 of the EOPs on November 17, 1984.

In early 1985 the CP&L nuclear safety review group conducted a technical

review of the EOPs. Their major finding was the lack of a plant specific

technical document. Robinson QA conducted a review of the EOP program in

January of 1987 and issued a report in March 1987 with the major concern

that the transition documentation was incomplete.

In March 1988,

the

licensee issued an Emergency Operating Procedures Transition Document

(TD).

The purpose of the TD was to compare the Robinson plant to the

Westinghouse Owners Group -

Low Pressure Emergency Response Guidelines

(WOG-LP

ERG)

reference plant, document a step by step comparison of the

ERGs

and the EOPs and justify step deviations between them,

and to

justify setpoints used in the EOPs.

3

The EOPs were developed without the use of an adequate PSTG in that the

TD was incomplete, and were revised over a period of more than three years

under the same conditions.

The team compared the EOPs to the Robinson TD and found that the TD was

not up-to-date. As a result, they found numerous deviations between the

current revision of the EOPs and -the EOP -supporting documentation in the

TD. The Team identified these deviations from the TD by the designation

"PSTG DEV" in appendix B.

In addition,

the TD was, incomplete.

The setpoint document was not

maintained to reflect procedure revisions including setpoint additions.

Although a number of setpoints referenced other sources for supporting

calculations, finding the appropriate documentation was often difficult.

The licensee could not trace at least one setpoint to the calculations

which established it. The team has addressed incomplete TO documentation

more fully in other sections of this report.

The team met with the licensee to discuss the development and

implementation of the as found PSTG. The licensee described this PSTG as

"the Robinson

PSTG consisted of the

.11 volume

TD plus Revision. 1A

WOG ERG-LP."

The licensee indicated that in this form,

the PSTG had

been difficult to maintain current and difficult to

use for the

development of the EOPs.

The inspection team indicated to the licensee

that a PSTG was required which could be maintained and used effectively

for the development and revision of the EOPs. The licensee committed to

develop a new

PSTG,

including an improved setpoint document and step

deviation document. The detailed description of this PSTG and schedule

for its development are to be addressed by the licensee in their response

to this inspection report.

Resolution of this issue was identified as

IFI 50-261/89-16-01.

The team compared the Robinson

EOPs to the ERGs and in general found

close agreement.

The

accident mitigation sequence. of the ERG was

generally followed in the EOPs and the EOPs were, adequate to cover the

broad range of accidents and equipment failures addressed in the ERG.

The team reviewed the role of the Robinson Quality Assurance Department

(QA)

in the development of the PSTG and upgraded EOPs.

Robinson QA

conducted technical comparisons of the EOPs against the ERGs in

November 1984. The documentation describing these reviews consisted of

approximately 19 pages; 5 pages bear no comments and the remaining pages

contained a limited description of the procedures reviewed

and

no

description of the review process.

The few issues raised in the reviews

were resolved prior to EOP implementation.

The team concluded that the

level of QA involvement in EOP development prior to implementation was

not adequate. However, the team found that other management controls, as

discussed above; were applied subsequent to implementation in lieu of a

more aggressive QA involvement.

4

Review of the

EOPs against the requirements of the writer' s guide

identified a number

of deviations.

These

deviations

suggested

inadequate verification of the procedures against the writer's guide.

The team found that. the format and wording of the abnormal operating

procedures (AOPs)

were substantially different from the other EOPs.

The

writer's guide. had not been applied to. the Robinson AOPs,

and this had

created for the operator a discontinuous and potentially confusing

interface with the EOPs. The AOPs and EOPs used different formats (one

column vs two column), different.action verbs, and different transition.

methods. In one example, if operators tranitioned from the A0P for loss

of CCW to the EOP for reactor trip by using an EOP method of transition,

they would not have continued concurrently with the AOP. This could have

resulted in immediate damage to all RCPs and CCW pumps. The licensee has

committed to developan AOP writer's guide. Resolution of this issue was

identified as IFI 50-261/89-16-02.

There were no violations or deviations noted in this area.

3.

Independent technical adequacy review of the EOPs

The team reviewed the procedures listed in Appendix A and found that

generally the vendor recommended accident mitigation strategy and action

sequence was followed.

The main entry into the

EOP network was via

Path-1 on a reactor trip or safety injection.

The only other EOPs that

were entered directly were EPP-1,

Loss of all AC power; EPP-5,

Natural

circulation cooldown;

EPP-21,

Energizing pressurizer heaters

from

emergency busses; and the AOPs.

The EOP procedure entry and transition

conditions closely followed the ERG.

Cautions and notes were often incorrect in application of the writer's

guide.

For example, cautions and notes were often found lacking

identification of the potential hazard to equipment or personnel as

required by the writer's' guide.

Both notes and cautions were written

containing action steps or conditional steps, which is also contrary to

the writer's guide.

Specific examples are delineated in Appendices B

and C.

Place keeping aids, such as pencil check marks or page markers, were not

addressed in the writer's guide and were not used during implementation

of the EOPs, with .the exception of the grease pencils used to traverse

the path procedures. Since most EOP steps were initiated without regard

to completion of prior steps and there were many transitions between

procedures, place keeping aids were important for keeping track of action

steps that had been initiated and steps that had been completed. Because

of the increased chance of operator error while transitioning within or

between procedures, there was a need for clearly established place keeping.

5

The EOP. procedures did not adequately reference nomographs, graphs, or

additional procedures required to carry out steps. This lack of adequate

reference

required the

operators to memorize

reference material

identifications or scan through manuals for the required information.

The quality of several operator. aids was

poor for determining the

information required to carry out specified actions.

For example, many

of the operator aids in the curve book. were not maintained to original

quality standards. Reproductions had lost their clarity due to excessive

photocopying.

The team also observed examples of poor contrast between

coordinate. values and background, and inappropriate scale to present the

full range of needed information.

The team inspected selected control room drawings to verify that EOP

specified components were accurately presented.

No discrepancies were

noted.

Operator action- setpoint values and justifications were contained in the

EOP/ERG setpoint study of the TO.

The team reviewed samples of these

values and found them to be adequately documented and justified, except

as listed in Appendix B.

The team found the degree of EOP adherence to the ERG to be generally

acceptable.

However,

the

TO was

not current and there were

many

differences between it

and the EOPs.

This was primarily due to the

licensee having made updates to the EOPs to reflect revision 1A to the ERG.

The licensee completed these EOP updates in early 1989 without updating

the TD. The existing, out of date,

TO could not perform its required

function of providing a basis for subsequent EOP revisions. The TO also

failed to provide adequate justification for many

EOP step deviations

from the ERG.

There were no violations or deviations noted in this area.

4. Review of the EOPs by inplant and control room walkthroughs

The NRC found the relationship of procedure nomenclature to the equipment

labeling to be difficult to compare because the procedures did not

reference exact equipment labels in most cases.

Because a precisely

defined method of referencing equipment nomenclature was not addressed in

the supporting EOP development documentation, the references to equipment

and controls used in the EOP procedures was not consistent. In addition,

steps requiri.ng lccal actions did not consistently reference equipment or

.,controller labels. The team conducted inplant and control room walkthroughs

of the emergency and abnormal procedures listed in Appendix A.

Where

required by the writer's guide, the EOP nomenclature appeared to be

generally consistent with installed equipment. The team enumerated noted

discrepancies in.

Appendix D. The licensee committed to review these and

make changes as appropriate. Resolution of this issue was identified as

IFI 50-261/89-16-03.

6

Indications, annunciators and controls referenced in the EOPs were found

to be available to the operators except as noted in Appendix B. Two sets

of emergency and abnormal procedures were maintained in the Control

Room

at. all times. These procedures were the latest revision.

While the results of the walkthroughs were generally acceptable, many

discrepancies in- the areas of technical adequacy, writer's guide

adherence,

and human factors were noted.

Technical and human factors

discrepancies are noted in Appendix B while writer's guide discrepancies

are noted in Appendix C. Appendix B.and C discrepancies were identified

as IFIs 50-261/89-16-04 and 05 respectively.

Important items noted by

the team during the walkthroughs included:

The availability and prestaging of needed equipment was weak

for some required actions; Appendix B, paragraphs VI.14.h & k

and III.1.n.

-P

Two procedural weaknesses in assuring compliance with technical

specifications were noted; Appendix B, paragraphs VI.27.d and

III.6.a.

o

Design weaknesses that inhibited the operator's ability to respond to

flooding in the service water pump pit and flooding in the

residual. heat removal pump pit were noted; Appendix B,

paragraphs VI.22.e and III-.9.1.

o

The level df detail in the EOPs was inadequate in some cases;

Appendix B, numerous examples.

Some plant modifications that impacted the usability of the

EOPs did not result in a proper EOP revision; Appendix B,

paragraphs VI.27.a & c, IJI.21.s, VII.2.b, and IV.4.c.

The HBR verification and validation program established in paragraph 5.6

of OMM-013, the writer's guide, did not apply to the AOPs or the alarm

response procedures but was limited to the PATHs,

EPPs,

FRPs and CSFSTs.

V&V was required for all EOP revisions.

V&V did not require in plant

procedure walkdown. Either -one SRO or two ROs were required for the

verification process; for control room walkthrough validation, a minimum

of one shift licensed operator was required.

Of the two validation

options,

control

room and simulator,

the latter was defined as the

preferred method.

The NRC evaluated the V&V program requirements and sampled supporting

records for the initial EOP transition to the ERG Revision 0, the EOP

upgrade to ERG Revision 1, and the EOP upgrade to ERG revision 1A,

and

found the following:

Except for the absence of validation checklists, the procedure

review and approval packages inspected were complete to the

current program requirements.

O7

Simulator

validation

was conducted on all

possible EOPs

incident to the upgrade to

ERG Revision 1.

No

simulator

validation was conducted incident to the upgrades

to ERG

Revisions 0 or 1A.

o

Although V&V was applied during the upgrade to ERG revision -lA,

the latest revision, the process was insufficient in that it

failed to identify the fact that the transition documen't (set

points, deviations, generic to plant specific differences and

I&C task analysis) had not- been upgraded to ERG revision 1A.

Since the transition document was a principal constituent of

the HBR PSTG and was not upgraded,

the NRC concluded that the

HBR EOPs were not adequately based upon the PSTG and that the

V&V process fail&d to identify that shortcoming.,

The

licensee's

V&V

program did not require in plant

EOP

walkdowns.

During this inspection,

NRC walkdowns of EOPs

identified many procedure deficiencies.

o

These V&V deficiencies constituted a serious weakness in the

HBR V&V program.,

The licensee agreed with the V&V findings listed above.

Resolution of

this issue was identified as.IFI 50-261/89-16-06.

There were no violations or deviations noted in this area.

5. Simulator observation

The team observed a crew-performing the following five major scenario

categories on the HBR Simulator.

(1) Loss of all feedwater

(2) Intermediate size LOCA

(3) Steam line break inside containment

(4) Steam generator tube rupture with ATWS

(5) Loss of CCW

The simulator performed satisfactorily with one exception. The simulator

would -not model a loss of offsite power when grid voltage. was degraded.

The team looked closely at reactor vessel head voiding during natural

circulation, and the simulation was satisfactory.

The procedures provided operators with sufficient guidance to fulfill

their responsibilities and required actions during the emergencies, both

individually and as a team.

The procedures did not duplicate operator

actions unless required.

The procedures did not cause the operators to physically interfere with

each other while performing the EOPs.

0

8

The simulator group utilizes a computer tracking system to track relavent

simulator modification requests (SMRs) which reflected modifications to the

control room. This tracking of the differences was used to maintain the

fidelity of the simulator. There were 56 open SMRs in varying degrees of

completion, some only requiring documentation to be completed for close

out. The simulator instructors felt obligated to inform the students of

15 of these SMRs,

due to the SMR's significance, prior to a simulator

session.

6. Management.control of EOPs

The team found that weaknesses.in management control of EOPs allowed them

to degrade over time.. Some of. these weaknesses were described in

previous paragraphs:

Failure to revise EOPs when a plant modification was performed,

paragraph 4.

o

Failure to provide adequate guidance to operators to help ensure

compliance with the TS, paragraph 4.

o

Failure to orovide justification for EOP step deviations from

the ERG and to keep the PSTG current, paragraph 2.

o

Deficiencies in .the V&V program, paragraph 4.

The team reviewed the quality assurance measures utilized to incorporate

operational and tr'aining experience into the EOPs.

Training instruction

909,

Simulator Conduct of Operations and Instructor Qualifications, was

issued in October 1988.

This TI required a "procedure

discrepancies"

book be made available to instructor and students. during simulator

training to collect any procedure problems identified in plant procedures.

These comments were reviewed by the training staff and then forwarded to

the Manager of-Operations for resolution.

Review of the comments indicated

that both the training staff and operators were actively participating in

the process. However, a potential weakness in the process was the lack

of feedback to the comment orginators. Failure to provide feedback could

eventually discourage participation in the process. The team verified that

some comments had been incorporated into the EOPs.

The process did not

solicit comments from classroom training sessions.

Revisions to the EOPs were prepared in accordance with OMM-013, Emergency

Operating Procedure Writer's Guide,

and approved in accordance with

AP-004,

Development,

Review and Approval of Procedures, Revisions, and

Temporary Changes. Section 5.6, verification and validation program of

OMM-013 required that the verification worksheet, Attachment 6..12,

be

completed prior to implementing the revision.

The worksheet steps were

general in nature

and lacked detail to ensure that the steps were

adequately addressed by the reviewer. This section also required that

validation be performed on EOP revisions.

The validation was to include

a simulator or control room walkthrough validation or both.

Interviews

with plant personnel revealed that this validation process had not yet

been implemented.

-9

7.

EOP user interviews

The team conducted interviews with twelve licensed operators.

The

operators felt that the EOPs had been improved with the recent revision.

Those interviewed expressed their belief that the level of detail in the

EOPs could be improved, but was adequate -for the level of knowledge of

the typical

operator.

Overall, the operators had confidence. in the

ability of the EOPs to perform their intended function although the level

of detail in the EOP was inadequate in some cases.

Section 5.1.4,

pages 7 and 8 of the. writer's guide, stated that Path

procedures relieve the operator

of the burden of memorization

of

immediate actions.

The

ERG background document for E-0 stated that

immediate actions "are those actions which the operator should be able to

perform before opening and reading his emergency procedures."

Whether

the procedure is in a two-column or flow chart format is immaterial. The

writer's guide must be clarified regarding the memorization of immediate

operator actions and their training adjusted accordingly.

If memorization is not required, this deviation should be technically

justified.

This

justification

should specifically

address

both

section 3.3.1 "Immediate action steps" and section 2 "Control

room usage

of guidelines" of the WOG ERG writer's guide.

Resolution of this issue

was identified on IFI 50-261/89-16-07.

The operators noted that the AOPs were not at the same useability level

as the other EOPs. 'Those

interviewed felt that an upgrade to the AOPs

similar to that which the other EOPs received would be beneficial.

There were no violations or deviations noted in this area.

8.

Exit Interview

The inspection scope and findings were summarized on September 29,

1989,

with those persons indicated in paragraph 1. The NRC described the areas

inspected and discussed in detail the inspection findings listed below.

No proprietary material is contained in this report.

No dissenting

comments were received from the licensee.

Item Number

Status

Description/Reference Paragraph

IFI 261/89-16-01

Open

Develop a new PSTG (paragraph 2).

IFI 26.1/89-16-02

Open

Develop an AOP writer's guide

(paragraph 2).

IFI-261/89-16-03

Open

Review each Appendix D item

(paragraph 4).

IFI 261/89-16-04

Open

Review each Appendix B item

(paragraph 4).

10

.

IFI 261/89-16-05

Open

Review each Appendix C item

(paragraph 4).

IFI 261/89-16-06

Open

Correct V&V deficiencies

(paragraph 4).

IFI 261/89-16-07

Open

Review memorization of operator

immediate actions.

(paragraph 7).

APPENDIX A

PROCEDURES REVIEWED

CFST - 1

Critical Safety Function Status Tree

REV 3

CFST - 2

Critical Safety Function Status Tree

REV 3

CFST - 3

Critical Safety Function Status Tree

REV 3

CFST - 4

Critical Safety Function Status Tree

REV 3

CFST - 5

Critical Safety Function Status Tree

REV 3

CFST - 6

Critical Safety Function Status Tree

REV 3

EPP-Foldouts

Foldouts

REV 6

EPP-SUPP.

Supplements'

REV 5

EPP-1

Loss of All AC Power

REV 5

EPP-2.

Loss of All AC Power Recovery without SI Required

REV 5

EPP-3

Loss of All AC Power Recovery with SI Required

REV 4

EPP-4

Reactor Trip Response

REV 4

EPP-5

Natural Circulation Cooldown

REV 3

EPP-6

Natural Circulation Cooldown with Steam Void in Vessel REV 2

EPP-7

SI Termination

REV 6

EPP-8

Post LOCA Cooldown and Depressurization

REV 4

EPP-9

Transfer to Cold Leg Recirculation

REV 6

EPP-10

Transfer to Hot Leg Recirculation

REV 3

EPP-11

Faulted Steam Generator Isolation

REV 2

EPP-12

Post-SGTR Cooldown Using Backfill

REV 3

EPP-13

Post-SGTR Cooldown Using Blotdown

REV 3

EPP-14

Post-SGTR Cooldown Using Steam Dump

REV 3

.

EPP-15

Loss of Emergency Coolant Recirculation

REV 3

EPP-16

Uncontrolled Depressurization of All Steam Generators REV 4

EPP-17

SGTR with Loss of Reactor Coolant:

Subcooled Recovery REV 4

EPP-18

SGTR with Loss of Reactor Coolant:

Saturated Recovery REV 4

EPP-19

SGTR without Pressurizer Pressure Control

REV 3

EPP-20

LOCA Outside Containment

REV 2

EPP-21

Energizing Pressurizer-Heaters from Emergency Busses

REV 3

EPP-22

Energizing Plant Equipment using the Dedicated

Shutdown Diesel Generator

REV 2

EPP-23

Restoration of Cooling Water Flow to Reactor

Coolant Pumps

REV 3

FRP-C.1

Response' to Inadequate Core.Cooling

REV 2

FRP-C.2

Response to Degraded Core Cooling

REV 2

FRP-C.3

Response to Saturated Core Cooling

REV 2

FRP-H.1

Response to Loss of Secondary Heat Sink

REV 2

FRP-H.2

Response to Steam Generator Overpressure

REV 2

FRP-H.3

Response to Steam Generator High Level

REV 3

FRP-H.4

Response to Loss of Normal Steam Release Capability

REV 2

FRP-H.5

Response to Steam Generator Low Level

REV 2

FRP-I.1

Response to High Pressurizer Level

REV 2

FRP-I.2

Response to Low Pressurizer Level

REV 2

FRP-I.3.

Response to Voids in Reactor Vessel.

-

REV 3

FRP-J.I

Response to High Containment Pressure

REV 2

FRP-J.2

Response to Containment Flooding

REV 1

FRP-J.3

Response to High Containment Radiation Level

REV 2

FRP-P.1

Response to Imminent Pressurized Thermal Shock

REV 2

FRP-P.2

Response to Anticipated Pressurized Thermal Shock

REV 2

FRP-S.1

.

Response to Nuclear Power Generation ATWS

REV 2

FRP-S.2

Response to Loss of Core Shutdown

REV 2

PATH-1

.

PATH-1

REV 5

PATH-2

PATH-2

REV 5

AOP-001

Malfunction of Reactor Control.System

REV 3

AOP-002

Emergency Boration

REV 2

AOP-003

Malfunction of Reactor Make-Up Control

REV 2

AOP-004

Control Room Inaccessibility

REV 2

AOP-005

Radiation Monitoring System

REV 5

AOP-006

Turbine Vibration

REV.2

AOP-007

Turbine Trip without Reactor Trip Below P-7

REV 0

AOP-008

Accidental Release of Liquid Waste

REV 0

AOP-009

Accidental Release of Waste Gas

REV 0

AOP-010

Inadequate Feedwater Flow

REV 4

AOP-011

Loss of Circulating Water Pump

REV 0

AOP-012

Partial Loss of Condenser Vacuum

REV 4

AOP-013

Fuel Handling Accident

REV 2

AOP-014

Loss of Component Cooling Water

REV 0

AOP-015

Secondary Load Rejection

REV 1

AOP-016

Excessive Primary Plant Leakage

REV 5

AOP-017

Loss .of Instrument Air

REV 5

AOP-018

Reactor Coolant Pump Abnormal Conditions

REV 1

AOP-019

Malfunction of. RCS Pressure Control

REV 1

AOP-020'

Loss of Residual Heat Removal (Shutdown Cooling)

REV 6

AOP-021

Seismic Disturbances

REV 3

AOP-022

Loss of Service Water

REV 2

AOP-023

Loss of Containment Intergrity

REV 3

AOP-024

Loss of Instrument Buss

REV 1

AOP-026

Low Frequency Operation

REV 0

AOP-027

.

Operation with Degraded System Voltage

REV 0

AOP-028

ISFSI Abnormal Events

REV 0

APPENDIX B

TECHNICAL AND HUMAN FACTORS COMMENTS

This appendix contains technical and human factors comments and observations.

Unless, specifically stated, these comments are not regulatory requirements.

However, the licensee -acknowledged that the factual content of each of these

comments was correct as stated.

The licensee further committed to evaluate

each comment, to take appropriate action and to document that action (proposed

or completed) in its answer to IR-89-16.

These items will be reviewed during

a future NRC inspection.

I. General comments:

1. Although the TD

intended to provide operator action setpoints

required by the HBR EOPs, there was no setpoint document to serve

AOP unique requirements.

2.

PSTG

DEV:

No deviations should have existed between'the PSTG and

the EOPs. Since the PSTG had been defined as a set of documentation

which included the GTG, all deviations between the GTG and the EOPs

became deviations between the PSTG and the EOPs,

by definition.

Although the EOPs were revised to conform to ERG rev.

1A,

the PSTG

.had not been (e.g. setpoint, deviation and plant comparison documents).

As a result, the Robinson revised EOPs were not adequately based upon

plant specific technical guidance. The NRC considered this a significant

weakness as documented in paragraph two.

3.

As stated in the writer's and user's guides, there were .no declared

immediate action steps in the EPPs and PATHs.

The NRC found that

elimination of immediate action steps and of the requirement that

operators commit these steps to memory was unacceptable and

constituted a weakness in the

EOP

program.

(see paragraph 7,

interviews).

4. HBR did not declare an NOUE based upon hurricane HUGO. The HBR EALs

did not conform to the guidance of NUREG-0654 Appendix I,

EAL 13 d,

to declare a NOUE given "Natural

phenomenon being experienced or

projected beyond usual

levels... any hurricane".

Hurricane

HUGO

passed

through

the area during the inspection.

The area was

declared a disaster area. Brunswick,. a sister CP&L plant, declared

a NOUE. HBR did not. HBR unit 2 was in cold shutdown; the control

.room

wind velocity instrumentation was inoperative; and hurricane

preparations were made.

The operators were aware that Brunswick had

declared a NOUE,

that the hurricane eye was projected. to pass

nearby, that it

was a category four hurricane. and that winds were

projected in excess of 135 mph when the hurricane came ashore near

Charleston.

As the local wind velocity increased, grid problems,

telephone .outages and on site wind damage were experienced. The HBR

applicable NOUE stated "Hurricane or tornado within site boundary".

The NRC concluded the hurricane impacted the site and that in the

absence

of wind velocity data,

the operators

were unable to

determine whether it

was or was not above hurricane velocity (e.g.

73 mph).

2

5. The licensee had organized neither the EPPs nor the AOPs such that

multiple local actions to accomplish a single goal were contained in

a procedure attachment which could be provided to the AO. Conversion

to this format would have, in many cases, relieved the control room

staff of a significant communications burden and would have enhanced

the successful completion of the step.

6.

I&C

provided. support in

EOP actions

(e.g.

jumper installation;

determination of NI undercompensation, etc.).

I&C did not provide

round the clock shift coverage nor were I&C personnel trained in the

performance of I&C responsible EOP steps.

Il

PATH comments:

NOTE:-

Since PATH

steps were not numbered,

step location is

specified belpw by grid location.

1. PATH-1

a. Grid D-16,

Paragraph 5.3.3 of the User's Guide required that

CSFST monitoring be initiated at a particular step in PATH-1 or

upon exit from PATH-P-.

Contrary to that requirement, the exit

to EPP-11 at grid D-16 was made without initiation of CSFST

monitoring nor was monitoring initiated within EPP-11.

b. Grid D-5,

CV fans:

The- GTG required that CV fan coolers be

verified running

in the emergency mode.

HBR required

verification that the fans were running since there was no

method of verifying that the intake dampers had shifted to the.

emergency position. No deviation existed.

c. Grid B-7 and elsewhere in the PATHs and EPPs,

RCS pressure

greater than or equal to 1520:

Recorder PR-444 and meters

PI-402 and 501

had scale increments of 50 psig.

Using the

half division rule, they could not be used to determine a

value of 1520.

d. The three AFW flow.controllers used in many places in the PATHs

and the EPPs (FIC-1425,

1426,

& 6416) were times 10 meters but

were not so labeled.

e. Grid C-10 and elsewhere in the PATHs

and EOPs; verify DG

capacity to assume additional loads:

The process by which the

operator determined whether sufficient DG capacity existed to

bring on additional loads was cumbersome and in some cases

inadequate. Since DG KW was not available from the board meters,

to verify that sufficient capacity existed to bring on additional

load's the operator was required to read DG volts and amps and

calculate KW from a curve.

3

The operator aid then directed the operator to FSAR table

8.3.1-1 to determine the load bf the oncoming equipment.

If

the oncoming load was less

than remaining capacity, the

equipment could be loaded to the bus.

Some loads (e.g.

the

charging pumps) were not shown in FSAR table 8.3.1-1, the source

referenced on the operator aid.

f. Grid C-11, restart ES equipment:

This step was illustrative of

a aeneral problem which existed in the PATHs

and the EPPs;

insufficient definition.

g.

Radiation monitoring units, R-19 A/B/C:

Neither the recorder

nor the edge meters had engineering unit labels.

h. The CV water level meters did-not have engineering unit labels.

No instrument number labeling was provided.

There

was

no

standard

convention

for

steam

generator

designation. They were identified as units A, B or C; I, II or

III; or 1, 2, or 3

(e.g.

15 edge. meters on the RTGB and

annunciator panel APP-006 used the I, II or III convention;

most .RTGB

instruments used the A, B or C convention; plant

valves generally used 1, 2 or 3).

jI

,The .HBR standard abbreviation for pressurizer (PZR)

had not

been implemented universally.

PZR and PRZR were both used

(e.g. LI-459 meter vs. panel label).

1. Grid F-15'and elsewhere in the PATHs and EPPs,

emergency oil

pumps: This step did not clearly define which seal oil backup

pump was to be started.

During walkthroughs,

two operators

correctly started the air side DC seal oil backup pump; a third

started the AC pump adjacent to the emergency oil pump on the

RTGB.

m. Grid B-9 and elsewhere in other procedures:

The 300 gpm AFW

flow parameter for decay heat removal stemmed from-the setpoint

document generic footnotes attachment 1.0.

The GTG bases

document required allowances for normal channel accuracy. None

were included in the HBR setpoint calculation.

n. HBR setpoint document, generic footnotes, attachment 2.0:

Typo; paragraph 4.2 follows 2.1. Other typos; "valves" should

be "values" in paragraph 4.2; attachment 8.0 mid page, "syste".

o.

HBR. setpoint document,

attachment 1 pg.

2 and frequently

elsewhere:

the percent symbol was missing in the calculation

string (e.g. item 6, 0.5 of span).

4

III. EPP comments:

1. EPP-1

Loss of all ac power

a.

PSTG DEV, Step 3.0:

The ERG note that stated steps 1 - 4 were

immediate action steps has been deleted from this procedure.

The ERG required immediate action steps to be memorized by the

operators.

The TD attempted to justify this step deviation

based on

the use

of flow charts.

This was not adequate

justification for operators not to memorize these steps.

b. PSTG DEV, Step 3.1:

The word "check" in thi-sstep deviated from

'the word "verify" in the TD.

This same deviation appeared in

steps 2, 3, 4, 6a2, 6b, 8c, Se, 12b, 14, 15, 16, 17c and d, 18,

19, 20, 21, 22, 23, 24, 25, and 27.

c.

PSTG DEV, Step 3.1: The ERG required the operator to check rod

bottom lights and

RPIs to verify reactor trip, 'and these

actions were not included in this procedure.

The TD attempted

to justify this by stating that these indicators were not

powered from the batteries.

This justification was not

adequate to explain the fact that these indicators were not

powered in this instance.

d.

Step 3d:

The operator was unable to check some of these RCS

ventilation system valves closed, because the power to them was

deenergized and the position indicating lights were not lit.

e.

PSTG DEV,

Step 4a RNO:

The steam generator levels in this step

were different from those in the TD.

This

same deviation

appeared in steps 14 and 17.a.

f. PSTG DEV, Step 5d:

This item was not in the TD.

g. PSTG DEV, Step 7:

The charging pumps were included in the ERG

and were missing from this step.

The TD justification was not

adequate to explain the fact that the charging pumps were not

automatically started on safety injection.

h. Step 9: This step required operators to contact I&C to connect

steam line PORVs to nitrogen accumulators so they could be

operated.

I&C

personnel

were not always .available and

operators could do this step.

1.

PSTG DEV, Step 10:

Before this step, the TD included a step to

locally close valves to isolate

RCP

seals.

This step was

missing from the procedure,

due to use of the

DS diesel to

operate a charging pump.

5.

j.

PSTG DEV, Step 12, caution 2:

This caution in the.,procedure was

not in the TD.

k.

PSTG

DEV,

Step 13:

The

ERG. included condenser air ejector

radiation as a symptom of a. ruptured steam generator, but this

was not included in the procedure.

The TD justification that

this instrument was deenergized was not adequate to explain the

fact that it was deenergized.

1. Step

16

RNO:

The operator was required to switch to an

alternate AFW water supply,

but was given no -guidance- on

priority of alternate supply.

Interviews with operators

revealed.that not all would choose the same alternate supply.

m.

Step 16 RNO:

The operator was directed to align Unit 1 fire

main with unit 2 fire main, but was given no guidance on how or

where to do this. The location of these valves and the tool to

operate.them were not common knowledge among operators.

n. Step 16 RNO:

The operator was directed to fill the CST using

fire hoses, but no dedicated pipe fittings were provided. In

tact, a large flange fitting would have had to be manufactured.

The operators needed to have all tools and equipment required

to perform emergency actions to be readily available.

o. PSTG DEV, Step 17 caution 2:

This caution was not in the TD.

p.

Steps 20 and 21:

The arrangement of these lights on the RTGB

was poor.

Not all containment isolation phase-A lights were

grouped together.

Also, containment ventilation

isolation

lights were mixed with control room ventilation lights.

This

arrangement made it difficult for the operator to accurately

check status as required.

q. PSTG DEV, Step 22:

The TD included three items to check that

were not in the procedure.

r. PSTG DEV, Step 23: This step required the operator to check CV

radiation less than 1000 R/hr, while the TD used 100 R/hr.

s.

PSTG

DEV,

Step 24 RNO:

This step required the operator to

return.to the step 12 caution, while the TD required a return

to step 17.

t.

Step 25 caution: This cautioned the operator that loads placed

on the E-1 or E-2 emergency busses

should not exceed the

capacity of the power source, but did not provide a reference

to the information the operator would need to do this, such as

an emergency load list including KW.

6

u. Step 26a:

The

labeling of the

RTGB

steam

generator PORV

controllers was inadequate. The demand signal was labeled from

0 to 100 percent, which represented a demanded setpoint of 1500

to 0 psig. The normal setpoint of 1035 psig was thus shown on

the indicator as 31 percent.

Operators had written "closed"

and "open" in pencil on the RTGB by the 0 and 100 percent. In

interviews, operators stated that better labeling was needed to

assist them in proper operation of these Valves.

v.

PSTG DEV, Step 27:

This step directed the.operator to check SW

booster pumps, which was not included in the TD.

W. Attachment A, page 4:

To. shed circuit 23 as directed, the

operator would need a 10 amp fuse puller, which was available

only in the control room.

Information needed by the operator

to get the correct tools for the job was not included in the

procedure where it could avoid unnecessary loss of time.

x. Attachment A, page 5:

The procedure did not adequately describe

loads to be shed. Breaker or circuit numbers were not specified

and load names did not match with labels on the panels. Operators

could not identify by using this list all of the correct loads

to shed.

2.

EPP-2 Loss of all ac power, recovery without SI required

a.

Step 17a RNO: This step required, the operator to observe the

caution statement prior to. step 18 and go to step 18.

There

was .no caution statement.prior to step 18.

b.

Step 18 RNO:

Increasing *feed flow and raising level to maximum

allowed would assist in reestablishing SCM.-

This alternative

was not included.

c.

Step 18:

The structure for natural circulation verification

steps differed between procedures.

This step consisted of a

check with an RNO to establish natural circulation.

EPP-16

step 29 RNO verified natural circulation.

Since the end result

is identical in both cases, the format should be standardized.

d.

Step 23a:

Backfeeding the aux transformer from offsite power

is a lengthy, complex and infrequent operation.

The backfeed

procedure in OP-603 was not cited.

e. Step 23a:

The alternative of shipping power from unit one was

described in some procedures as

"...IC

turbines or unit one

... "

and in others as "...

IC turbines and unit one '."

The

format was not standardized. (e.g.

EPP-16,

step 28 RNO and

elsewhere)

II7

.3. EPP-3

Loss of all ac power, recovery-with SI required

a. Step 3 RNO:

These procedural directions contained no verb.

b.

Step

6:

The verb used in this step was not defined in the

action verb list.

C.

PSTG DEV, Caution 9:

The key utility decision point contained

in the GTG caution 8 was missing from this procedure with the

result that the operator was not warned against establishing

component cooling water to the thermal barrier of an RCP which

has excessive seal leakage.

d.

Caution 2:

The ERG contained a caution prior to step 2 which

was not in EPP-3.

e. PSTG DEV, Step 4: In addition to other equipment, step 4 of the

TD required the operator to start the SW pumps and the SWB.

pumps. EPP-3 step 4 did not contain this requirement.

f.

PSTG

DEV,

Step 6:

The

TD step. 6 instructed the operator to

"rack in CV

spray pump breakers", but the corresponding EPP-3

step instructed the operator to "locally install control power

fuses for the CV spray pump breakers".

g.

PSTG DEV, Step 7:

Step 7 of EPP-3 stated "Check if CV spray is

required". The ERG and the TD did not contain a corresponding

step.

h.

Step 2a:

This step did not provide the operator a valve list

for guidance.in aligning SI valves for cold leg injection..

i.

Step 4b:

This step did not specify which RHR pumps to load.

j.

Step 4d:

This step did not specify which HVH units to load.

k. .

Step 5:

This step -instructed the operator to control AFW flow

and maintain S/G levels. It did not address control of the S/G

pressure or verification of natural circulation.

1. Step 6: *This step locally.,installed control power fuses for

the' CV Spray Pump Breaker.

There was not a preceding step

instructing the operator to "Reset

CV signal"; -such a step

would prevent the breaker from 'auto -closing if

a signal was

present when the operator was inside the open breaker cubical

installing fuses.

m. Step 7a:

The step did not specify the action to be taken if CV

pressure had "ever" increased to or was presently greater than

20 PSIG.

n. Step 7d RNOj:

This step required the operator to adjust the

fIowrate but did not specify a valve name or number. Adjusting

this flowrate is an infrequent operation.

4.

EPP-4

Reactor trip response

a.

Step 3 RNO:

The first asterisk does not specify how to dump

steam to the condenser.

b.

Step 4c RNO:

Parta of step'5 RNO did not specify the number

of pumps required for emergency boration.

c. Step 5, NOTE:

This note did not inform the operator that

letdown isolation could deenergize the PZR heaters. A level of

14.4 percent in the PZR will deenergize the heaters.

d.

Step 5a RNO:.

Part a of step 5 RNO did not specify. the number

of pumps required for emergency boration.

e. Step, 5b RNO:

This subpart was confusing as written and

contained more than two actions in each subpart.

f.

Step 5d RNO:

Part d of step 5 RNO had, as an option, "Open AUX,

4 '

PZR

SPRAY,

CVC

311".

This statement did not

inform the

operator of the maximum delta T limit of 320 degrees F between

the pressurizer temperature and the aux spray temperature.

g. Step 6a RNO:

Step 6.a.1 RNO did not contain the valve name or

number to be used to verify letdown isolation.

h. Step 6a RNO: Step 6.a.4 RNO was misleading in that it implied

that: the operator only "resets"

a particular bank. of

PZR

heaters "as

necessary" after clearing , a low level of 14.4

percent.

i.

Step 7a RNO:

This item did not specify how Safety Injection

was to be initiated.

j.

Step 7b RNO:,

Step 7b.2g RNO did 'not inform the operator which

RCP is associated with which spray valve. B PZR spray valve

was not associated with the B RCP.

k. Step 9 RNO:

Step 9 RNO was not clear. The step implied that

the operator was required to start and load the EDG's on the El

and E2 busses even if power to them had not been lost.

1. Step 9 RNO: Step 9 RNO instructed the operator to "Verify EDGs

have assumed the proper loads".

No guidance was provided to

4

the operator defining either "proper loads" or the KW rating of

the individual loads.

There was no

EDG

KW meter nor other

indication of EDG KW in the control room to aid the operator in

loading the EDG.

9

M. Step 9 RNO:

Step 9.c. There was no KW meter nor indication of

KW for the EDGs in.

the control room to aid the operator in

verifying adequate EDG capacity and loading the. instrument

air compressor(s)

and battery charger(s).

The step did not

give the operator the. KW rating of the instrument

air

compressor(s) nor that of the battery chargers.

n.

Step 10 RNO:

This step stated "start pumps". The step did not

specify which pumps to start. the starting priority of the

pumps nor the number of pumps.to be started.

o. Step 11

RNO:

This step did not define whether the operator

should dump steam to heat up,

cool

down,

or to maintain a

constant S/G pressure.

p.

Step 12 NOTE:

The note d.id not instruct the operator on which

RCP produced the most effective PZR spray.

q. PSTG DEV, Step 8:

Step 8 of EPP-4 which corresponds to step 6

of the ERG: "Check S/G levels" was not addressed by a deviation

in the TD.

r.

PSTG DEV, Caution 9:

The TD contained a CAUTION C-9 (EOP: TD

EPP-4 37) "On Natural Circulation, RTD bypass temperatures and

associated function will be inaccurate" is not in EPP-4.

S.

PSTG

DEV,

Step 13:

Step 13 of EPP-4 and step 10 of the ERG

"Check if Source Range detectors should be energized" is not

addressed in the T.D..

5.

EPP-5 Natural circulation cooldown

a..

Entry Condition:

The TD referred to pages 23,

16 and 27.

The

correct references are pages 24, 17 and 28.

b. Step 1, note 1:

This note required the RCPs to be run in order

of priority to provide PZR normal

spray.

The note did not

provide the preferred order.

C. Step 2a:

This step established conditions per OP-101 for

running an RCP.

The OP-101 sections contained actions which

are not essential to starting an RCP.

d..

Step 2b:

This step started RCP(s).

In other EOP steps, this

was combined with the previous step, thereby requiring the

RCP(s) to be started per OP-101.

e. Step 3, note:

This note stated that boron addition should be

based on total system volume.

The aids used by operators to

determine boron addition quantities are based on less than

total system volume.

10

Step 4, note 2:

This note. indicated sample results should

indicate an overborated condition to prevent dilution below

cold shutdown concentration if a PZR outsurge occurred.

During

walkthroughs, the operator did not know how much overboration

would be required.

There was ano specific guidance defining

"overborated condition".

g. Step Sc:

This step was not included in the TD.

.h. Step 7, caution:

This caution was a restatement of the AFW

supply switchover criteria in Foldout A.

Step 8:

This step required hot leg temperatures -to be less

than 540 degrees F. Step 7 of ERG ES-0.2 indicated less than

550 degrees F. The TD indicated 550 degrees F. Thus, the TD

did not provide justification for the difference.

  • j.

Step 9, caution:

This caution warned that the SI initiation

circuits would automatically unblock if

PZR pressu'e increased

to greater than 2000 psig or Tavg increased to greater than 543

degrees F.

The caution in ERG-0..2 did not include the Tavg

criteria. The TD did not include the Tavg criteria. Thus, the

TD did not justify.the additional criteria..

Ak.

Step 10:

This step blocked safety injection due to PZR

Press/Hi stm line dp and Tavg.

Step 9 of ERG ES-0.2 did not

require the Tavg function to be bypassed.

The TD did not

require the Tavg function to be bypassed. Thus, the TD did-not

justify the difference.

1 .

Step 27:

This step maintained required RCP seal injection

flow. There was no guidance defining "required ...

flow".

m. Step 29b:

This step was described in the TD as part of step 28.

6. EPP-6

Natural circulation cooldown with

steam void in vessel

(without RVLIS)

a. Step 4c:

This step required operators to maintain RCS

temperature and pressure within the limits of curve

3.4,

"Reactor coolant system pressure -

temperature limitations for

cooldown".

The curve

was

not labeled with all

of the

information needed to ensure compliance with it,

nor was this

information provided *in the procedure (eg.

which instrument

readings to

compare with which part of the curve).

In

interviews, two of six licensed operators (33

percent) could

not describe correctly how to comply with this curve.

Some of

these operators also did not know what the expected difference

should be between the hot leg and the cold leg temperatures

II

when on natural circulation cooling.

11

Curve 3.4 consisted of two parts:

TS

cooldown limits on

maximum pressure . allowed at any given cold leg temperature

(to protect

RCS integrity),

and

EOP

saturation limits on

minimum pressure allowed at any given core exit or hot leg

temperature (to maintain core cooling).

The operators needed

to be able to use this curve correctly.

7.

EPP-7

SI termination

a. Step 3:

This step contained multiple actions contrary to the

writer's guide.

b.

Step 3:

The alpha numeric listing rules of the-writer's guide

were

not followed in listing the sequence dependent steps

resetting

the reactor trip breakers and

resetting feed

i solation.

c. Step 4 RNO:

The procedure did not indicate this step as a

local action.

d.

Step 6:

This step directed "stop SI and RHR pumps". There was

no RNO. Therefore the substep bullets were superfluous.

e. Step 9: -The step.did not provide boration completion criteria.

The worth of the

most reactive rod

was

not promulgated

officially nor was it

documented in the control room.

Only

through training were the operators informed of the value and

then only once per cycle.

f.

Step 9 RNO:

Since the step was identical to components of

AOP-002, the step.would be simplified by referring to AOP-002.

g. Step

14:

This step checked whether

seal

flow should be

established.

Substep

f, establishing . seal

flow, was

inappropriate and should.stand as a separate step.

h.

Step 20 RNO c:

This step provided insufficient definition as

to which seal oil backup

pump

was to be started.

During

walkthroughs, two operators correctly started the air side DC

seal oil backup pump; a third started the AC pump adjacent to

the emergency oil pump switch on the RTGB.

i.

Step 20

RNO e:

Backfeeding the aux transformer from offsite

power . is a lengthy,

complex and infrequent operation.

The

backfeed procedure in OP-603 was not cited.

j.

Step 21

RNO a2 and elsewhere in other procedures:

This step

required trended values to verify natural circulation.- Other

equivalent

EPP

steps did not require trended values.

The

format is not standardized.

Some of the operators were unable

to expeditiously establish simultaneous trending on the three

values which were not on recorders.

This indicated a minor

ERFIS training problem since

ERFIS would support three,

simultaneous trends.

k. Step

21

RNO a2:

This step

neglected increasing feed flow

within established S/G level limits.

1. Step 25a:

The four manual

actuation zone switches on the

containment fire protection system panel did not have open or

closed position indication labels.

m.

Steps d, e. g and h:

These steps were not shown as local

actions.:

n. Step 28:

The substeps did not include a hold point at step b.

The plant operations staff decision is mandatory prior to

return to power, natural circ cooldown or forced flow cooldown.

8.

EPP-8 Post-LOCA cooldown and depressurization

a. Step 2:

Step 2 began on page 4 of 26 and ended on page 5 of

26.

The high level step number "2" was shown only on page 4.

Only the substep identifier was shown on page 5.

Therefore,

there was no complete identifier for the substeps on page 5.

b.

PSTG DEV, Step 2:

The verb "check" was used, rather than the

verb "verify," 'as in the PSTG.

c. Step 3, caution:

This caution

incorrectly contained a

conditional action -step.

d.

PSTG DEV,, Step 10b, RNO:

The words "Observe CAUTION and NOTE

prior to step 11 AND" was not included in the PSTG.

e. PSTG DEV, Step 11, cauti&n: This caution incorrectly contained

a conditional action step.

f.

Step 11:

Step 11 began on page 11 of 26 and ended on page 12

of' 26.

The high level step number "11"

was shown only on page

11.

Only the substep identifier was

shown

on

page

12.

Therefore, there was no complete identifier for the substeps on

page 12.

g.

PSTG DEV, Step 11c, RNO:

The words "Observe CAUTION prior to

step 10 AND" were not included in the PSTG.

h.

PSTG

DEV,

Step 11dl:

The words

"AND start one

RCP"

were

correctly shown in.the PSTG as a distinct substep.

i.

Step 12:

Step 12 began on page 13 of 26 and ended on page 14

of 26.

The high level step number "12"

was shown only on page

13.

Only the substep identifier was shown on page 14.

Therefore,

there was no complete identifier for the substeps on page 14.

j.

PSTG DEV, Step 12a:

This step was not included in the PSTG.

13

k. PSTG DEV,

Step

12a,

RNO:

This step was not included in the

PSTG.

1.

PSTG DEV,

Table, page 13:

The adverse containment value of 68

degrees F shown for required RCS subcooling when two or three

SI pumps are running

and

two or more charging- pumps

are

available was different from the PSTG value of 70 degrees F.

m.

Step 14:

Step 14 began on page 15 of 26 and ended on page 16

of 26.

The high level step number "14" was shown only on page.

15.

Only the substep identifier was shown on page 16.

Therefore, there was no complete identifier for the substeps on

page 16.

n. Step

14,

caution:

This caution incorrectly contained a

conditional action step.

o.

PSTG DEV, Step 14:. The PSTG included a caution prior to this

step that was missing in this procedure. The caution read "On

natural circulation,

RTD

bypass temperatures and associated

functions will be inaccurate."

p.

PSTG

DEV,

Step 14al,

RNO:

The words "start one RCP"

were a

separate substep in the PSTG.

q. PSTG DEV, Step 15b:

The words "turn on" were shown instead of

the verb "control" that was shown in the PSTG.

r.

PSTG

DEV,

Step 15c:

The expected response values for RCS

subcooling (35 degrees F; 55 degrees F for adverse containment)

differed from those shown in the PSTG (25 degrees F; 45 degrees

F for adverse containment).

s. PSTG

DEV,

Step 16:

The verb "check" differed from the verb

"verify" used in the PSTG.

t.

PSTG

DEV,

Step 17:

The verb "check" differed from the verb

"verify" used in the PSTG.

u. PSTG DEV, Step 17b, RNO:

The words "Observe CAUTION prior to

step 10 and" were not shown in the PSTG.

v. PSTG DEV, Step 18a:

See comment for step 15c above.

w.

PSTG DEV, Step 18a, RNO:

Only the words "go to step 19" were

shown in the PSTG. The setpoint of 370 degrees F differed from

the 400 degrees. F shown in the ERG.

x.

PSTG DEV, Step 18b: This step and its associated RNO step were

not shown in the PSTG.

The step "go to step 20"

shown in the

PSTG was not included in the procedure.

14

y.

PSTG DEV,

Step 20a, RNO 3:

The terms "EMERG OIL PUMP and SEAL

OIL BACKUP PUMP" differed from the terms used in the PSTG of

"DC lube oil and seal oil backup pumps."

z. PSTG DEV, Step 20a, RNO 4 and 5:

These steps did not appear in

the PSTG.

aa.

PSTG DEV., Step 20:

This step did not appear in the PSTG.

ab.

PSTG

DEV,

Step 21:

This step did not include the item "RCP

upper and lower bearing oil cooling -

NORMAL" that was shown in

the PSTG.

ac.

PSTG

DEV,

Step 21,

RNO:

The transition to EPP-23 was

not

included in the PSTG.

ad.

PSTG

DEV,

Step 22b:

The upper setpoint of 65 PSIG differed

from the value of 75 PSIG shown in the PSTG.

ae.

PSTG DEV, Step 22d:

This substep did not appear in the PSTG.

af.

PSTG.DEV., Step 27b:

This substep did not appear in the PSTG.

ag.

PSTG DEV, Step 17, RNOs a and b:

These steps did not appear in

the PSTG.

an.

PSTG DEV, Step 27cl: The 'word "locally" was not shown in the

PSTG.

ai.

PSTG DEV, Step 27c:

The PSTG also included substeps c3 and c4.

aj.

PSTG DEV, Step 28a and 28a, RNO:

These steps were not included

in the PSTG.

ak.

PSTG DEV, Step 30, RNO:

The words "observe caution prior to

step 5 and" were not included in the PSTG.

9. EPP-9 Transfer to cold leg recirculation

a. PSTG DEV, Step 1:

In the TO, there was a step 1 that required

the operator to open foldout B. That step was missing from the

procedure.

b.

PSTG DEV, Step 2:

This step, which required the operator to

reset containment spray, was not in the TD.

c. PSTG DEV, Step 4 caution: This caution was not in the TD.

d.

PSTG DEV, Step 4:

This step was in a different sequence than

the equivalent steps in the TD.

j~j.

15

e.

PSTG DEV

Steps 8b, c, and d:

These steps were in a different

sequence than the equivalent steps in the TD.

f. PSTG DEV, Step 9:

This step used the word "check" where the TD

used the word "verify".

This same deviation was in steps 10,

11, 14. 16, 22, 23, and 24.

g.

PSTG, DEV,

Step 10:

This step checked service water system

operation and was not in the TD.

h.

PSTG DEV, Step 12:

This step was not in the TD.

i.

PSTG DEV, Step 13 and caution: This caution and step were in a

different sequence than in the TD.

Step 18 caution:

This caution needed to be located prior to

the step to which it applied; step 20.

k. PSTG DEV, Step 24:

Three steps in the TD were missing from this

procedure prior to step 20:

close SI hot leg header valve,

open loop 3 and 2 hot leg injection valves, and open breakers

for RHR cold leg injection valves.

1. Attachment A, page

14:

The

inspectors observed design

deficiencies that would inhibit operator actions in responding

to flooding in the RHR pump pit.

These included:

pit level

alarms not supplied with vital power and not EQ, sump pumps not

supplied with vital power,

and expected high radiation levels

in the area of the isolation valves for CCW to the RHR pump pit

during the recirculation phase.

10.

EPP-10 Transfer to hot leg recirculation

a. Step 3, note:

This. note incorrectly contained a conditional

action step directing a transition to step 10.

b.

PSTG

DEV,

Step 3d,

RNO:

This step was not included in the

PSTG.

c. PSTG DEV, Step 4b:

The. phrase "as available" was not included

in the PSTG.

d.

PSTG DEV, Step 4c:

This step was not included in the PSTG.

e.

Step 5:

Flow indicator FI-605 used to determine flow rate did

not contain adequate resolution to precisely read desired flow

rate.

f.

Step 7a:

Step 7a did not adequately identify other available

isolation valves.addressed in the step (SI-878B & SI-888C).

16

g..

Step 9:

Step 9 began on page 8 of 10 and ended on page 10 of

10.

The high level step number "9'"

was shown only on page.8.

Only the substep identifier was shown

on. pages 9 an d 10.

Therefore, there was no complete identifier for the substeps on

page 9 and at the top of page 10.

h;

PSTG DEV, Step 9b2:

The expected response was not included in

the PSTG.

i.

PSTG .DEV, Step 9b6:

The words "aligned to" were not included

in the PSTG.

11.

EPP-11 Faulted steam generator isolation

a.

Entry Condition:

Entry was specified whenever a faulted steam

generator is identified or suspected. , The entry condition

stated in ERG E-2 did not address "or suspected".

The TD did

not address this addition.

b. Step 4, caution,:

This caution was an instruction on how-to

accomplish an item of step 4.

c..

Step 4:

This step 'closed the steam generator blowdown

isolation valves.

No preferred method to accomplish this task

was provided.

During walkthroughs, operators indicated that

placing the RM-19 in alarm or locally actuating the valves

would be possible ways to close the valves.

12.

EPP-12 Post SGTR cooldown using backfill

a.

Step 1, note:

This note incorrectly contained a conditional

action step containing transitions.

b.

PSTG

DEV,

Step 4:

The action verb "check" differed from the

verb "verify" used in the PSTG.

c. Step 5, caution:-

This caution

incorrectly contained a

conditional action step..

d.

Step 6, caution:

This caution was overly complex.

e.

PSTG

DEV,

Step 10b:

The valve-number "SI-869" differed from

that shown in the PSTG ("SI-889").

f.

PSTG

DEV,

Step 11b and 11b,

RNO:

These substeps were not

included in the PSTG.

g.

PSTG

DEV,

Step 11c,

substeps 1 and 2:

The word "locally" was

not included in the PSTG.

h

PSTG DEV, Step 11c:

The PSTG also contained substeps 11c3 and

11c4.

i. PSTG DEV, Step 12:

This step was not included in the PSTG.

j.

PSTG

DEV,

Step 13a:

The adverse containment value was not

included in the PSTG.

k.

PSTG DEV, Step 13b:

The adverse containment value of 320 PSIG

differed from that shown in the PSTG (345 PSIG).

13.

EPP-13 Post-SGTR cooldown using blowdown

a. Step 8b:

This step required "energize"

control

power for

selected valves. The .ECCS valve's control power defeat panel

switches were-labeled "normal" and "defeat".

b. Steps 16c & 17a:

Step 16c directed cooldown per GP-007.

.The

cooldown rate limits in paragraph 5.2.11.3 of GP-007 were more

restrictive than the "less than 100 degrees per hour listed in

step 17a.

14.

EPP-14

Post-SGTR cooldown using steam dump

a.

First caution before step 1: The NRC found that survival of the

control

room dose calculation. capability under accident

conditions was degraded because of

its dependency upon

establishment of a link between the control room console and

the Raleigh main frame computer.

b.

Step 8b:

This step required "energize"

control power for

selected valves.

The ECCS valve's control power defeat panel

switches were labeled "normal" and "defeat".

c. Steps 16c & 17a:

Step 16c directed cooldown per GP-007.

The

cooldown rate limits in paragraph 5.2.11.3 of GP-007 were more

restrictive than the "less than 100 degrees per hour listed in

step 17a.

15.

EPP-15

Loss of emergency coolant recirculation

a. Step la RNO: Step la RNO did not give the operator guidance on

what actions to take if a component had not functioned

properly.

If

an

MOV

failed to open,

it could have been

manually operated.

b.

Step 3:

Step 3 required that the operator "Initiate

RCS

Cooldown

to Cold Shutdown",

but did not give the operator

guidance on what S/G levels to maintain.

c.

Step 10, NOTE:

The note did not provide the operator with

priority guidance on which RCP. produced.the most effective PZR

spray.

d.

Step 10b RNO:

Step 10b.

the RNO had a typo. The

RNO was

labeled a. and should have been labeled b..

e. Step 10c:

Step 10c

did not

have

an RNO for operator

auidance if the RCP could not be started.

f.

Step 15b RNO:

Step 15b2 stated "Start CHARGING-PUMP(s)" and

did not give the operator guidance on the number of charging

pumps, or charging flow needed..

g.

Step 17a:

Step 17a instructed the operator to use PZR spray to

depressurize to decrease subcooling.

At this point only one

RCP was running.

The step did not give the operator

any

guidance on which spray valve was associated with which RCP,

ie. B spray valve goes to .C RCP.

h. Step 18a:

This step required the operator to take. actions

based on

RCS temperature.

The step did not specify which RCS

temperature to use. ie. Th, Tc, T/C.

i

.

Step 20b and 29b RNO: Venting an accumulator was an infrequent

operator action. - There was no guidance given to the operator

addressing required valve alignment.

j.

Step 22:

This step required the operator to take actions based

on RCS

temperature.

The step did not specify which

RCS

temperature to use. ie. Th, Tc, T/C.

k.

PSTG

DEV,

Steps 8 & 9:

EPP-15 action steps 8 & 9, and the

corresponding steps in the ERG were in the reverse order of the

way they appear in the TD.

1. PSTG DEV, Steps 11 thru 23:

Steps 11 thru 23 of EPP-15 were not

addressed in the TD.

EPP-15 was written against Rev 1A of the

'ERG and the TD was written to Rev. 1 of the ERG.

16.

EPP-16 Uncontrolled depressurization of all steam generators

a. PSTG DEV, Step 3:

The GTG bases for this procedure indicated

that the first of three major decisions was. the control room

decision regarding which generator to concentrate

their

isolation efforts on.

The assumption was that concentrating

on one generator might allow.early transfer from EPP-16 to

EPP-11. The procedure did not isolate one generator at a time

nor was there any caution or note concerning the need for that

decision.

19

b. Step 4 RNO

a:

Aux feed flow could not

be throttled to

individual generators from the control room; only total flow

throttling capability and individual S/G-feed valve open/closed

conditions were possible.

To maintain 25 gpm per S/G,

an AO

would have had to be dedicated to throttling local valves at a

time when AO talent was in short supply due to the isolations

in progress and rapidly decreasing CST inventory. Selection of

the conflicting alternatives of dedicating

an

AO to local

throttling or doing the best that can be done from the control

room to insure minimum constant flow to all three S/Gs was not

covered in the procedure.

c. Step 31 RNO a5:

The PZR heater transfer to the emergency bus

which was accomplished in step 31 RNO a4 was not restored to

normal after the substep 5 restoration of offsite power.

d.

Step 29, caution 1:

The GTG step description table for ECA-2.1

was incorrectly titled ES-1.1

on pages 66 and 67 of the LP

plant set.

e. Foldout B-F:

Item E of foldout D directed the user to go to

EPP-24 if an RHR pit level reached the limit level.

Since it

was important to continue EPP-16 actions concurrently, the "go

to" appeared to be in error; an instruction to refer to EPP-24

and continue concurrently in EPP-16 would

have been more

appropriate to the mitigation strategy.

f.

Step

24

RNO:

VCT

level

was one

inch per gradation.

The

scaling was inconsistent with a parameter value of 12.4.

17.

EPP-17 SGTR with loss of reactor coolant: subcooled recovery

a. Step 5 RNO and step 27a RNO:

This -RNO required an attempt to

restore offsite power.

No reference was provided for the

appropriate procedure to be used. During the walkthrough, the

operator indicated that he would use a procedure to perform

this task.

b. Step 5 RNO d and step 27a RNO 4: These RNO steps required

verification of adequate

DG capacity to load instrument air

compressors and battery chargers. These steps did not provide

the load that these components would require. No procedure was

referenced for loading the battery chargers.

c.

Step 5 RNO: Step 4 RNO of ERG ECA-3.1 required verification of

adequate DG capacity to load charging pumps and

shed non

essential loads if necessary. The TD did not justify why this

action was moved to step 9.

20

d. Step 6b

RNO:

This step directed that the CV spray pumps be

stopped when CV pressure is less than 4 psig.

Footnote 2 of

ERG ECA-3.1 required use of the CV . signal reset value.

The

setpoint document indicated that a value of 4 psig is used

instead of 20 psig.

the initiation setpoint (reset

value).

The justification indicated that using the value corresponding

to the adverse containment was more conservative.

The more

rapid depletion of the

RWST

supply was not addressed in the

justification.

e. Step

16:.

This step required PZR heaters to maintain

RCS

pressure and subcooling. Step 15 of ERG ECA-3.1 required the

heater switches to be turned off. The TD-did not address this

difference.

f. Step 18 and 21, notes:

These notes required RCP(s) to be run in

order of priority to provide PZR normal spray.

The order was

not specified.

g. Step 21a

RNO:

This RNO required that if natural circulation

was not verified, then increase dumping

steam

from intact

S/G(s).

The

RNO of step .20 of ERG ECA-3.1 did not limit

dumping steam to only the intact S/G(s). The TD did not address

this difference.

n. Step 22b:

This step required turning

on

PZR heaters as

necessary.

There

was

no

guidance defining "as

necessary".

During the walkthrough,

an operator thought that this was to

establish saturation temperature. in.

the PZR.

However, he was

unsure that this was the intent of the step.

i.

Step 23d:

This step required shutdown margin to be adequate.

There was no guidance defining "adequate".

j.

Step

33

RNO:

This

RNO required refilling the S/G(s).

No

precaution was provided to slowly refill the S/G(s) so that the

adverse conditions in the RNO might be avoided.

18.

EPP-18

SGTR with loss of reactor coolant: saturated recovery

a. This procedure contained many step deviations from the TD,

similar to those listed for other EPPs.

19.

EPP-19 SGTR without pressurizer pressure control

a. Step 4a RNO:

This RNO restored power to the PZR PORV valves.

There was no guidance on how to accomplish this task. During

the walkthrough,

it took the operator between 3 and 4 minutes

to determine which panels and circuits feed the valves.

  • ~

21

Step 5 RNO:

This .RNO started a charging pump if

one was not

running.

No check was performed to see if the RCP seal supply

valves should be closed to prevent thermal damage to the RCP

seals. Such a check was contained in the step 10b RNO.

c.

Step

6, caution:

This caution was the

same

as the AFW

switchover criteria of Foldout G.

d.

Steo 10a RNO:

This RNO provided no guidance on how to attempt

to restore offsite power to the emergency busses.

During the

walkthrough, the operator indicated that he would not attempt,

this without a procedure.

e. Step .16a RNO 4: This RNO required verification of adequate DG

capacity to

load instrument air compressors

and battery

chargers.

The anticipated air compressor and battery charger

loads were not provided in the procedure., During the walkthrough,

an operator required between 3 and 4-minutes to locate the

information. Interview of another operator revealed that he

did not know where this information could be obtained.

Both

operators indicated that they would not load a battery charger

without a procedure.

No procedure reference for performing

this task was provided.

,f.

Step 22, note:

This note conditionally transferred to PATH-2,

Entry Point M. The ERG note of ECA-3.3 transferred to step 29

of E-3.

Entry Point M transferred to step 30 of E-3.

Entry

Point M transferred below the caution associated with step. 30.

Step 29 of E-3 was sequenced to be completed before step 30.

The transfer point difference was not justified in the TD.

g. Step 26, caution: This caution required pressures in the RCS

and the ruptured S/G be maintained less than the ruptured steam

line PORV setpoint. The procedure did not require the setpoint

to be adjusted to maximum. The caution did not provide a value

for what the.maximum allowed pressure should be.

h. Step 29 RNO: This RNO did not require the ruptured S/G to be

refilled at a specified slow rate.

The discussion on p. 82 of

ERG ECA-3.3 described that the refill should be slow to prevent

the adverse consequences listed in the.RNO.

i. Step 30, caution 1:

This caution stated that steam should not

be released from any ruptured S/G if water existed in its steam

line.

The method for determining if water existed in the steam

line was not specified.

Control

room instrumentation can be

offscale without water being in the steam lines.

22

j.

Step 30a:

This step provided three methods for depressurizing

the RCS and ruptured S/G(s). The third method, dump steam from

ruptured S/G(s),

could be accomplished by two means, dumping

steam to the condenser or- to the atmosphere.

Discussion

contained on p. 87 of ERG ECA-3.3 indicated that dumping steam

to the atmosphere was the least desirable alternative.

This

was not specified in the step.

k. Step'32d:

This step checked that shutdown margin was adequate.

inere was.no guidance defining "adequate".

20.

EPP-20

LOCA outside containment

a.

PSTG

DEV,

Step 1:

The verb "check" differed from the verb

"verify" used in the PSTG.

21.

EPP-21

Energizing pressurizer heaters from emergency busses

a. Step 1, RNO:

The verb used in this step could not'be used for

breakers as defined in the action verb list.

b. Step 1:

The abbreviations SERV, TRANS, HTR, KW, AUX, BLDG, MG,

TURB,

and GEN were not on the "Abbreviations used in the EOP

network" list.

c. Step

1:

The use of the verb "check" together with "removed"

(see page 5, bottom) is inconsistent and conflicting.

d.

Step 2:

The abbreviation EDG was not on the "Abbreviations

used in the EOP network" list.

e. Step 3:

The abbreviations BKR,

ARM,

PRESS,

HTR,

PNL,

EDG,

KW,

PRZR,

and RTGB were not on the "Abbreviations used in the EOP

network" list.

f.

Step 3:

This instruction contained no verb.

g. Step 3c:

The verbs used in this step were not defined in the

action verb list.

h. Step 3d:

The verb used in this step could not be used for

breakers as defined in the action verb list.

i.

Step 3f RNO:

The verbs used in this step were not defined in

the action verb list.

j. Step 4:

The verb used in this step was not defined in the

action verb list.

k.

Step 4c:

The verbs used in this step were not defined in the

action verb list.

23.

Steps 4c&d:

The abbreviations BKR,

ARM,

PRESS, HTR, and PNL

were not on the "Abbreviations used in the EOP network" list.

m. Step 4.f RNO:

The verbs used in this step were not defined in

the action verb list.

n. Step 4g:

This step required "Run. controller down to obtain

maximum output". This phraseology was confusing and- needs to

be reviewea.

o. Note 5:

The "multiple statements within this note" wer.e not

"separately identified by noting them with asterisks" as is

required by the writer's guide.

p. Step 5:

The wording of this step was

not definitive in

specifying the "as required" action.

q. Step 6:.

The verb used in this step was not defi'ned in the

action verb list.

r. Step 1:

One instruction stated "52/14C, Fuses Removed". There

was confusion on the part of the operator regarding what fuses

to remove.

s. Step 1:

Breakers 52/22B, Power supply to B SI Pp and breaker

52/29b Power supply to B SI

Pp were part of the B SI Pp

Modification and were no longer required to be on the list.

t. Step 3:

This step did not provide the operator with any

reference to Group A power supply.

u. Step 3a:

This step did not provide the operator with the

physical location of the disconnects for SST-2A and 2F.

During

the walkthrough of the procedure,

the operator was unable to

locate the disconnects without assistance.

v. Step 3b:

While performing the walkthrough of the procedure,

step 3b. could not be performed because the 480V bus E-1 Main

breaker tool could not be located.

w.

Step 3f 1, 2 & 3:

This step instructed the operator to

"monitor emergency bus response to prevent DG overload." There

was no indication 'of emergency bus current or voltage, but there

was an indication of EDG current and voltage.

x. Step 4:

This step did not provide the operator with any

reference to control heater power supply.

y.

Step 4f,

1, 2 & 3:

These steps instructed the operator to

'"monitor emergency bus response to prevent EDG overload. There

was no indication of emergency bus current or voltage, but there

was an indication of EDG current and voltage.

Step

4g:

This

step

was

inconsistent between controller

indication (process) and the procedure instruction. This was a

reverse acting controller.

22.

EPP-22

Energizing plant equipment using the' dedicated shutdown

diesel generator

a.

This procedure contained step deviations from the PSTG, similar

to those listed for other EOPs.

23.

EPP-23

Restoration of cooling water flow to reactor coolant pumps

a.

Step 4 RNO:

This 'RNO required emergency cooling water to be

established to the charging' pump oil cooler. The materials to

perform this task were not pre-staged.

b. Step 9a:

This step checked that the charging flow control

valve HCV-121 was open.

The only indication in the control

room was a demand signal on- the flow controller.

Actual valve

position determi'nation would have required local verification.

Because the step required HCV-121 to be checked open instead of

verified open,

the operator would have had- to perform the RNO

to open the HCV-121 bypass valve instead of attempting to open

HCV-121.

C.

Step 9b RNO:

This RNO opened the loop 1 hot leg charging valve

without trying to open the loop 2 cold leg charging valve

because step 9b stated "check" instead of "verify".

24.

EPP-24 Isolation of leakage in the RHR pump pit

a. Step 1:

This step required the use of a formula or graph to

find the

RHR pit level because .of

the use of the verb

"determine".

This was not the, proper verb for

this

application.

b. Step

1:

Substeps a and b were methods of accomplishing the

action of step 1,. unlike substep 1c which was an entirely

unrelated action.

c. Step 1c:

The verb used in this step was not defined in the

action verb list.

d. Step *2c:

This

substep could

not be started prior to

completion of substeps la and lb.

However,

this important

ordering of actions was not "specifically stated in- the step

containing the task nor in an associated note" as required by

the writer's guide.

e. Step 2c:

The verb used in this step was not defined in the

action verb list.

25

f. Step 2d:

The verb used in this step was not defined in the

action verb list.

g. Step 2d:

The abbreviations CV,

RECIRC,

HX,

and DISCH were not

on the "Abbreviations used in the EOP network" list.

h. Step 3 RNO: The three verbs used in this step were not defined

in.the action verb list.

i.

Step 3 RNO:

The abbreviations CV,

RECIRC,

HX,. and DISCH were,

not on the "Abbreviations used in the EOP network" list.

j Step Sc:

The verb used in this step was not defined in the

action- verb list.

k.

Step Sd:

The verb used in this step was not defined in the

action verb list.

1. Step 5d:

The abbreviations CV,

RECIRC,

HX,

and DISCH were not

on the Abbreviations used in the EOP network" list.

m.

Step 5d:

Some of these five valves were already in the

desired position and therefore the verb

"perform" was

inappropriate.

n.

Step 6 RNO:

The abbreviations CV,

RECIRC,

HX,

and DISCH were

not on the "Abbreviations used in the EOP network" list.

o.1

Step 7:

The verb used in this step was not defined in the

action verb list.

25.

EPP-Supplements

a.

No comment.

.26.

EPP-Foldouts

a.

Foldout A:

1.

Step b:

This step contained the SI actuation criteria.

During the walkthroughs,

an operator, when asked how he

would manually determine that RCS subcooling was less than

25 degrees F, indicated that he would use the cold leg

temperature Tc. In this application, Tc would not provide

the most limiting value.

2. Step b:

Generic footnote, attachment 9.0 of the setpoint

study addressed the error associated with the core exit

thermocouple/core cooling monitor system as the basis for

the selection of the 25 degree F setpoint value for the SI

actuation criteria.

The attachment did not address .

whether or not 25 degrees F bounded the errors if

the

value had to be determined manually from other process

instrumentation.

26

IV. FRP comments:

1. FRP-C.1

Response to inadequate core cooling

a. Step 1 RNO:

This step required the operator to "Align valves"

in response to an SI.

There was no list of valves provided.

b.

Steo 2c RNO:

This step required the operator to "Align valves"

in resoonse to an SI.

There was no list of valves provide.

.

C. Step 2d:

This step required the operator to take action based

on an RCS pressure of 170 psig. This pressure was based on the

maximum pressure at which RHR would inject into the RCS.

This

figure was

based

on suction pressure, pump Delta P and

instrument error. If the operator could not verify flow from

the RHR system,

he was to assume that there was a problem with

the RHR system,

and perform -a valve line 'up as a method of

investigating the loss of RHR flow. -The suction pressure from

the RWST was 13#, and the delta P across the pump ranged from

126 to 138 psig which would have produced the maximum pressure

of

151#

and the flow would have been zero.

From this it

appeared that instrument inaccuracies may have been applied in

the wrong direction.

d. Step 6a:

This step instructed the operator to obtain a

hydrogen concentration measurement

but provided no detailed

guidance.

e. Step 6b:

The operators did not know whether 'the containment

hydrogen concentration monitors

i.n

the control

room were

calibrated for varying containment humidity following a

degraded containment condition.

f.

Step 7a:

The main step stated "levels" and part a of the step

stated "level".

The

number of S/G levels needed to satisfy

step 7a was not specified.

g.

Step 7b:

This step was inconsistent with the rest of the EOPs

in referring to feed, flow.

Other EOPs referred to "total feed

flow" as meaning main

and AFW flow, or AFW flow to

mean

strictly AFW flow.

h.

Step 9c:

The purpose of step 9 was to depressurize the S/G to

160 psig in order to depressurize the RCS to 160 psig and empty

the accumulators to a point just before the nitrogen was

introduced into the RCS.

Step 9c required that "at least two

hot leg temperatures less than 370 degrees F" be met before

depressurizing. If the core was in a degraded condition with

TCs greater than 1100 degrees F, the RTDs may have been in an

area that was voided. The 370 degree F criteria may have been

inappropriate in this case.

27

i. Step 10.:

The conditions for isolating an accumulator in step

10 "two

hot leg temperatures less than 370 degrees F" were

different than the equivalent step 18 "RHR pump flow indication"

in this procedure.

The comment on step 9c of this procedure

applied here also.

j.

Step 10b RNO:

Venting. an

accumulator

was

an

infrequent

operator action. However,

there was. no guidance given to the

operator addressing required valve alignment.

k. Step 14b, .19a, and 21a: The 350 degree provision was a generic

Westinghouse number corresponding to a 1200 degrees F core exit

T/C temperature for inadequate core cooling. The 1200 degrees F

was changed for HBR to 1100 degrees F. The use of 350 degrees F

was not justified.

1.

Step

16

RNO:

This statement, "Start RCPs as necessary until

Core Exit T/Cs less than 1100 degrees F" was not clear.

There

was no operator guidance on the number of RCPs to be started or

the time or other conditions between RCP starts.

m.

Step 17:

in the statement, "Try to locally depressurize all

intact S/Gs to atmospheric pressure",

the word:

"locally"

needed clarification.

n. Step 20:

Step 20 instructed the operator to check for "SI

flow".

There was no guidance on what constituted an adequate

amount of SI flow.

2.

FRP-C.2 Response to degraded core cooling

a.

Step 1, caution:

This

caution

incorrectly contained a

conditional action step directing a transition.

b.

PSTG DEV, Steps 1 and 2:

The verb "check" differed from the

verb "verify" used in the PSTG.

c. Step 2b:

Step 2b required a pressure reading of 1520 PSIG.

The.. pressure indicators PI-402

and PI-501 did not exhibit

adequate resolution to precisely read.desired pressure.

d.

Step 3, caution:

This caution

incorrectly contained a

conditional action step.

e. Step 4, note:

This note incorrectly contained a conditional

action step.

f.

PSTG

DEV,

Step 8, caution:

This caution was not addressed in

the deviation document.

28

g. PSTG DEV, Step 10a:

The expected response value of 370 degrees

F differed from the value of 400 degrees F that was included in

the PSTG.

h.

PSTG DEV. Step 13:

The verb "check" differed from the verb

"verify" used in the PSTG.

3.

FRP-C.3

Response to saturated core cooling

a.

Step 2a:

This step checked SI and RHR pumps running.

The

associated

RNO started pumps.

No caution was provided to

prevent both RHR pumps from running greater than 9 minutes with

RCS pressure greater than 170 psig.

The vendor had indicated

that operation of both RHR pumps for greater than 9.3 minutes

under these conditions could result in pump damage. This was

included in applicable foldouts as an RHR Pump Trip Criteria.'

No Foldouts are applicable during execution of this procedure..

b.

Step 2c RNO:

This RNO aligned 'SI pump valves.

During

walkthroughs, the operators failed to identify that the hot leg

injection -path is available if

the cold leg path is not

available.

c. Step 3, caution: This caution contained an action step related

to the performance of Step 3a.

d.

Step 3a:

This step says to check PZR PORVs closed.

The ERG

Background document FR-6.3 indicates that PZR PORVs are closed

to preclude the possibility of an undetected stuck open valve.

Turning the control switch to close may be required to fully

close a PORV.

'Thus

checking position i.ndication may not be

sufficient.

e. Step 3c: This step required.other RCS vent paths to be closed.

The phrase "other RCS vent paths" was not defined.

4.

FRP-H.1

Response to loss of secondary heat sink

a. Step 1, caution:

The shift to RCS feed and bleed.with any S/G

wide range level greater than or equal to 60 percent appeared to

be premature since level in the other two units could have been

on scale, greater than or equal to 25 percent NR and immediately

recoverable (e.g. aux feed pump switching or feed flow increase).

The licensee was aware of this and was conducting a plant specific

analysis to determine the feasibility of relaxing the 60 percent

in any S/G criteria.

b.

Step 4, caution:

I&C

was

required

to

install

the

jumpers in case of a false high level

signal.

No jumper

installation

procedure

existed to

support

this

step.

Therefore,

valuable time would

have been lost chasing the

wiring diagrams and making up a temporary procedure.

The procedure did not reflect the plant modification which

shifted primary containment air to an external nitrogen supply,

backed up by internal N2 supplies and external instrument air.

(e.g. step 11 concentration on instrument air restoration while

N2 restoration was not-considered).

d.

Step 11:

Since step 11 was no longer critical due to the N2

modification, It

appeared- that the procedure

should be

reordered to

put instrument air restoration after feed and

bleea initiation.

e.

Step 21: This procedure placed the operator in a loop between

step

21 and

23.

The

ERG,

at this point is looping until

inventory addition can be terminated and normal charging and

letdown

established.

FRP-H.1. as written did not accomplish

this and the deviation document did not justify the difference.

5.

FRP-H.2

Response to steam generator overpressure

a.

PSTG

DEV,

Step

1:

The verb "check" differed from the verb

"verify'.' used in the PSTG. In addition, the item "FW isolation

vlvs" was included in the PSTG.

b. Step 4, caution:

This caution -incorrectly

contained a

conditional action step.

c. PSTG DEV, Step 7:

The RCS setpoint of 540 degrees F differed

from the value of 535 degrees F shown in the PSTG.

6.

FRP-H.3 Response to steam generator high level

a. This procedure contained step

deviations from the PSTG,

similar to those listed for other EOPs.

7.

FRP-H.4 Response to loss of normal steam release capability

a.

No comment.

8.

FRP-I.1 Response to high pressurizer level

-a. Step 2b: The procedure did not reflect the plant modification

which shifted' primary containment air to an external nitrogen

supply, backed. up by internal

N2 supplies and external

instrument air.

(e.g. instrument air restoration while N2

restoration was not considered).

9.

FRP-I.2 Response to low pressurizer level

a. Step 3c RNO:

This RNO did not specify a value for the amount

of charging flow required to cool letdown. Footnote 1 of ERG

FR-I.2 says to enter minimum indicated charging flow to provide

letdown cooling in the regenerative heat exchanger.

30

b. Step 6:

This step required turning on PZR heaters as necessary.

There was no guidance defining "as necessary".

The ERG Background

document FR-I.2 indicated that it was desirable to have stable

RCS pressure prior to returning to the guide and step in effect.

10.

FRP-1.3

Resoonse to voids in reactor vessel

a.

No comment.

11.

FRP-J.1

Response to high containment pressure

a. Step 2a: This step did not provide the operator clear guidance

concerning

proper containment ventilation isolation.

The

containment ventilation isolation panel

in the control

room

contained four windows that belong to other actuation signals.

b. Step 2a RNO:

The preferred method of "Alarming R-11 or R-12"

was not provided.

c. Step 3c and e RNO:

This step lacked sufficient detail

regarding proper valve alignment.

d. Step 6b: The step lacked detail regarding which valves were to

be isolated.

e..

Step 7a:

This step instructed the operator to obtain -a

hydrogen concentration measurement. Guidance was not provided

to the operator on where to obtain the sample or what methods

of indication were acceptable.

f. Step 7b: This step stated "LESS

THAN 0.5 percent IN DRY AIR".

The

operators did not iknow

if -the

containment )hydrogen

concentration monitors in control

room were calibrated for

varying containment

humidity following degraded containment

conditions.

12.

FRP-J.2

Response to containment flooding

a.

No comments.

13.

FRP-J.3 Response to high containment radiation level

a.

No comments.

14.

FRP-P.1 Response to imminent pressurized thermal shock

a.

Step le and

12e

RNO:

The three asterisked substeps gave

actions necessary to isolate the S/G, but did not specify "the

faulted S/G".

b.

Step le and

12e

RNO:

There was no guidance given to the

  • operator addressing which feed valves needed to be shut to

isolate the S/G.

31

.

c. Guidance to the operator addressing what actions to take if the

level was less than 12.4 inches was lacking.

d. Step 20:

This step did not provide guidance

as to what

pressure to maintain or the desired condition of the primary

system.

e. Step 21:

This step was restrictive and did not provide the

operator with a tolerance band.

f. Step 22al:

There was no operator guidance on when the clock

started for the one hour timed soak.

g.

Step 23c1: . There were no defined pressure limits to be

maintained on ATTACHMENT A.

h. Step 23c2:

This step contained a typo. The 50 degrees F should

be 50 degrees F per/hr.

15.

FRP-P.2

Response to anticipated pressurized thermal shock

Entry Condition:

This statement indicated *that the entry

condition was YELLOW. Revision 1A of ERG FR-P.2 indicated that

the entry condition is ORANGE.

ERG *F-1.4, revision 1,

indicated that the critical safety function status tree for

enterina

FRP-P.2

is YELLOW.

The TD did

not provide

justification for selecting YELLOW as the entry condition.

The licensee confirmed with the NSSS vendor that "ORANGE"

in the ERG was in error.

b.

Step -1:

The

ERG step 1 was preceded by a note defining a

faulted S/G.

No note was included in FRP-P.2 step 1.

The TD

did not justify the omission of the note.

c. Step

3:

The, referenced curve,. reactor coolant system

pressure-temperature limitations for cooldown,

listed RT(NDT)

after 15 EFPY for 1/4 T as 282 degrees F and 3/4 T as- 139

degrees F.

TS

Figure 3.1-2.b listed these values as

290

degrees F and 149 degrees F, respectively.

d.

Step 4b:

This step provided

RCS cooldown restrictions by

referencing those of

curve 3.4, reactor coolant system

pressure-temperature limitations for cooldown and GP-007, Plant

cooldown from hot shutdown to cold shutdown.

The TD did not

provide technical

justification that these restrictions are.

appropriate.

16.

FRP-S.1

Response to nuclear power generation/ATWS

a. Step 1:

This procedure did not specify "Steps 1 through 4 are

IMMEDIATE ACTION" as provided in ERG FR-S.1, Step 1, note.

.

32

b.

Step 1 RNO:

This step required an operator to be dispatched to

locally trip the reactor trip breakers or rod drive motor

generator sets. Page 70 of the ERG background document FR-S.1

indicated that boration

had

to

be initiated before time

consuminq local actions to trio the reactor were taken.

Local

operator actions to trip the reactor were addressed in ERG

FR-S.1, Step 5 RNO.

No justification for inclusion- of local

actions in Step 1 RNO was documented in the TD.

C. Step 3a:

This step required checking whether the AFW or FW

pumps were running,

and if

not running,

then to start the

pumps...

Step 3 of ERG FR-S.,1 did not require FW pumps to. be

checked or.started. No justification for inclusion of the FW

pump in the procedure was documented in the TD.

d.

Step 3b:

This step required the SD AFW pump to be running if

necessary. There was no guidance defining'"if necessary".

e.

Step 4b RNO:

This RNO defined alternative pathways for

boration if the emergency boration path was unavailable.

This

step did not address use of the other boric acid transfer pump

if the one aligned to the system failed to start.

f. Step 4d:

This step required the loop 2 cold leg charging valve

to'be checked open. If closed, the RNO action was to open the

loop 1 hot leg charging valve.

Thus,

no attempt was made to

open the loop 2 cold leg charging valve.

g. Step 4f RNO:

This RNO required radiation monitor R-11 or R-12

to be alarmed if containment ventilation isolation valves were

not closed. During walkthroughs, operators indicated that they

would either pull the fuse or source check one of the monitors

to generate an isolation signal.

This RNO did not adequately

specify the intended operator action.

h.

Step 4e RNO:

This RNO did not include alignment of the normal

charging flow path if no charging flow to the RCS existed.

i.

Step 5b RNO: This RNO required the operator to close the MSIVs

and MSIV bypass valves if

the turbine did not trip.

This step

did not address other actions such as tripping the turbine at

the front standard or securing the EH oil pumps.

j.

Step

11 caution 2:

This caution was a conditional action

statement.

k.

Step 12 RNO: This step did not reference the procedure number

for

restarting

the

battery chargers.

During procedure

walkthroughs, operators indicated that they would not perform

this task without a procedure in hand.

  • 33

Step 14, Note:

This note was identjfied as a caution in ERG

FR-S.1.

The

ERG caution read: "Boration

should continue to

obtain adequate

shutdown margin during subsequent actions".

This note read: "Boration should continue to obtain adequate

shutdown

maroin."

No justification for the differences was

addressed in the TD.

17.

FRP-S.2

Response. to loss of core shutdown

a. Step 1 RNO a:

Determination that an intermediate range NI

channel

was undercompensated' requi.red assessment by I&C

personnel. .I&C staff were not available .around

the clock.

This step did not clearly explain the operator actions when one

channel hangs up above 10E-10 while.the only other channel was

decreasing with negative SUR.

Two walkthrough operators

concluded that it

was appropriate to wait for I&C and not to

borate since undercompensation was unknown.

b.

Step 1 RNO,

last paragraph pg.

3:

There was uncertainty as to

the boration lineup during walkthroughs.

The operators were

uncertain whether normal or emergency boration was intended.

V.

CSFST comments:

1. Subcriticality

a.

No comments.

2. Core cooling

a..

No comments.

3. Heat sink

a.

No comments.

4.

Integrity

a.

No comments.

5. Containment

a.

No comments.

6.

Inventory

a.

CSFSTs 2 and 6. had been modified due -to the absence of RVLIS.

RVLIS had been installed for at least 17 months but was not yet

operational.

34

VI.

AOP comments:

1. AOP-001 Malfunction of reactor control system

a. Step 1.1.2.6:

The red pen on TR-408 was incorrectly labeled

"High Tav (Red)".

The instrument displayed median Tav as was

required by this step.

b.

Paragraph 4.3.2. step 11.

Three operators were unable to

perform this step; two were uncertain whether it

was an AO or

licensed operator step.

The external

cabinet doors were not

marked to reflect which

one of the three contained the

converter.

When

the converter was located, it had no

instrument label nor was it

identified in any fashion as the

P/A converter.

2. AOP-002 Emergency boration

a. Step 3.1.1.2:

CVC-358

was a local

valve; the others were

operated from the control room.

b. Step 3.2.10:

The procedure,did not refer to OP-301.

3. AOP-003 Malfunction of reactor make-up control

a. Step 3.1.1:

This step provided actions to secure potential

sources of water into the volume control tank. This step

secured the boric acid transfer pump but did not secure the

primary water pump.

4.

AOP-004 Control room inaccessibility

a. Step 3.2, caution:

This caution incorrectly contained a

conditional action step directing a transition.

b. Step 3.2.16.2:

This step did not provide the criteria

necessary to determine which containment fan coolers were to be

started.

C. The NRC observed several valves which did not follow the normal

convention of open counterclockwise, close clockwise.

This was

not indicated at the local operating station (e.g.

FCV-498C,

FCV-488B and FCV-478A).

5. AOP-005 Radiation monitoring system

a. Step 1.3.1.2,

substeps 3-5: The sequence incorrectly implied

that the paging system interrupted the evacuation alarm.

0I

35

b. Step 1.3.2.1.4:

This step referred to AOP-004 in the event of

a control room evacuation. A "go to" transfer appeared to be

more appropriate,

c.

Step 1.3.2.6:

No confirmation of sample station suction

ventilation was included in-the -step.

0

Meters RI-014 and Ri-018 on the unlabeled waste disposal boron

recycle panel both contained two scales and only one pointer.

There was no scale switching.

The scale ranges were 10EO-10E4

and 1OEO-10E6.

The operator was uncertain which scale was in

use and therefore was unable to read the instruments.

e. The

"green"

indicating lenses

on. the waste disposal boron

recycle panel ranged from green to washed out blue to almost

colorless.

f.

Step 2.3.2.4.2:

This step referred to service water flow but

only stated "check fan cooler flows and out-let temperatures".

6. AOP-006 Turbine vibration

a.

General:

The conclusion of the team was that the procedure as

written would not be an effective aid to the operator if needed

0 in handling an abnormal turbine vibration.

Two new recorders

have been installed in the control room,

and the procedure has

not been updated to reflect the new terminology.

7. AOP-007 Turbine trip without reactor trip below P-7

a. Step.3.2:8 This step instructed the operator to shut the MSIVs

and the MSIV bypasses if

the turbine start-up was going to be

delayed. more than one hour.

The purpose for shutting the

valves was not clear.

8t. AOP-008 Accidental release of liquid waste

a.

No comment.

9. AOP-009 Accidental release of waste gas

a. Step 3.2.3:

This step directed that fuel handling building

ventilation be shifted but did not specify the desired lineup.

b.

Step 3.2.5:

"...

REDUCE release rate

...".

This

step

neglected the option of increasing dilution flow.

-c. Step 3.2.7,

caution:

This step should be performed

under

the direction of RC personnel; E&C/RC personnel are not all HP

qualified..

36

10.

AOP-010

Inadequate feedwater flow

a.

Symptoms:

The following symptoms were duplications

1.1.5 High hotwell level (HOTWELL LEVEL Hi/Lo ALARM)

1.2.4 High hotwell level

1.1.6 Low feed pump suction pressure.

(LOW CONDENSATE HEADER

PRESSURE)

1.2.2 Low feed pump suction pressure

1.2.3 Low condensate pump discharge pressure

b.

Symptoms, 1.3.4:

This symptom was not appropriate as a control

room symptom.

There was

no indication for LCV-1530B in the

control room.

c.

Symptoms, 1.3.5:

Tavg and.Tc would increase on an inadequate

feedwater flow whereas the procedure did not address the

possibility of a feedwater control valve or bypass valve

failure.

d.

Step 3.0:

The procedure did, not address the possibility of a

feedwater control valve or bypass valve failure.

e. Step 3.1.1:

The priority for running the pumps was not given.

f. Step 3.1.2:

This step did not address the method or priority

of reducing turbine load.

g. Step

3.1.2:

The

maximum

power

for

the

different

feed/condensate pump combinations was not given.

h. Step 3.1.2:

There was no caution to the operator warning of a.

S/G level decrease due to shrink on load reduction.

i.

Step 3.2.1:

This step was superfluous and was extra material

the operator had to read through in a time critical situation.

j.

Step 3.2.3:

This -step did not specify that the only place

hotwell 'level could be read was locally.

k..

Step 3.2.4:

This step did not specify that the only place

drain tank level and feedwater heater level could be read was

locally.

1. Step 3.2.5: This step did not address the control rods as a

means of control.

Also the parameter the operator was.

controlling was Tavg/Tref and not equilibrium conditions.

m.

Step 3.2.6:

This step was superfluous and was extra material

the operator had to read through in a time .critical situation.

n. Step 3.22.:

This step was superfluous and was extra material

the operator had to read through in a time critical situation.

o. Step 3.2.8:

Reclosing HCV-1459 was not dependent upon starting

the heater drain pump.

p

Step 3.2.10:

This step was superfluous and was extra material

the operator had to read through in a time critical situation.

q. Step 3.2.11:

The step was superfluous and was extra material

the operator had to read through in a time critical situation.

11.

AOP-011

Loss of circulating water

a. Step 3.2.3:

This step failed to provide the criteria required

to determine adequate circulating water flow.

b.

Step 3.2.4:

This.step required local action without providing

adequate reference to location or pressure gauges required to

determine differential

pressure. The step failed to provide

the criteria required to determine high pressure.

c. Step 3.2.6:

This step failed to provide the the necessary

references required to take appropriate action.

12.

AOP-0 12-

Partial loss of condenser vacuum

a.

Step 3.2.3:

This step required local operator action without

providing adequate reference to the plant location.

This step

did not provide the criteria required to determine high DP nor

did it define high DP.

13.

AOP-013

Fuel handling accident

a.

No comments.

14. AOP-014

Loss of component cooling water

a.

Step 3.1.2.1: The name of valve DW-711 was missing from this

step.

b. Note 3.1.3:

This note stated that a plant cooldown should be

initiated, but did not tell the operators where to stop the

cooldown with- no

RHR available.

In this procedure,

the RHR

pumps have lost their CCW cooling water.

c. Step 3.1.3.1:

The

operator

needs to continue with this

procedure while concurrently using Path-1. Failure to continue

with this procedure could result in immediate damage to the CCW

pumps and the RCP shaft seals. This step did not clearly state

the requirement to continue with this procedure.

38

d.

Step 3.1.3.2:

This step did not state the size and location orf

the required fuse puller.

e. Step 3.1.3.3.b.

and c:

The operator could not monitor these

RCP temperature limits within two' minutes since the recorder

only printed approximately every five minutes.

RCP temperature

alarms were not included in this step as indicators to the

operator Tor stopping RCPs.

f.

Step 3.1.4:

The labeling on the charging flow-controller on

the

RTGB

was inadequate.

The

demand

signal indicator was

labeled from 0 to 100 percent, with 100 percent indicating a

demanded valve position of closed.

Operators described it as a

"backwards"

indication.

The operators who were interviewed

stated that improved labeling, such as "OPEN" and "CLOSED", was

needed.

g.-

Step 3.1.4:

This step failed to direct the operator to run

only

one charging

pump at a- time.

A previous procedure

required two charging-pumps to -be- operated. After charging -and

letdown flow were isolated in this step, only one charging pump

was needed.

Since the -pumps were not being supplied with

cooling water,

running only one would avoid overheating two

charging pumps.

h.

Step 3.1.4:

With charging and

letdown flow isolated,

the

operators had lost the ability to control pressurizer level.

Thus pressurizer level would have slowly increased due to RCP

seal -water

flow.

This was revealed as a potential problem

during simulator exercises that the team observed.

This

procedure did not provide for prompt supply of alternate

cooling water to the charging pumps (see step 3.2.9.2 below).

It also did not provide a method to drain water from the RCS,

to.prevent excessive increase in pressurizer level.

1.

Step 3.2.1:

This temperature was required to be read locally,

a.fact that was not so indicated.

j.

Step 3.2.3:

The names of the valves in this step were not

included. Also, required local action was not indicated as

"local".

k. Step 3.2.9.2: The licensee had not provided dedicated fittings

to enable the operators to supply temporary cooling water to

the charging pumps,

safety injection pumps,

and residual heat

removal pumps. These fittings were not readily available, and

would have had to be manufactured.

In this procedure, all of

these pumps had lost their CCW cooling water,

reducing the

operators'

ability to maintain the

RCP seals intact and to

inject water i.nto the RCS. A number of design features of this

component cooling water system made it

more susceptible to

failure than similar systems in newer plants.

0

39

For these

reasons,

good procedures for handling a loss of

component cooling water were especially. important,

including

readily available ,dedi.cated pipe fittings.

1. Step 4.3:

This step was misleading,

in that it

stated "the

only possible way of losing all three CCW

pumps is by the

complete. loss of on and offsite power."

The team observed a

numoe r of potential ways of losing all CCW,

such' as a fire 'or

flooding in the CCW pump room, a pipe break in,

the .CCW header,

or a loss of service water to the CCW heat exchangers.

15.

AOP-015 Secondary load rejection'

a.

Symptoms 1.3: This symptom inappropriately read Unit "export"

load. It should have read Unit "output" load..

b.

Symptom

1.10:

This symptom- is no longer applicable.

The

actuation circuit has been removed..

c.

Step 2.8:

This step is no longer applicable.-

The actuation

circuit has been removed.

d. Step 2.9:

The step is no longer applicable.

The actuation

circuit has been removed.

16.

AOP-016 Excessive primary plant leakage

a.

No comments.

17.

Loss of instrument air

a.

No comments.

18.

AOP-018 Reactor coolant pump abnormal conditions

a. Step 1.3.1.2.2:

This step addressed actions associated with

loss of all CCW which were also contained in AOP-014,

Loss of

component cooling water.

It may have been better to exit to

AOP-014 than stay in AOP-018 under those conditions.

19.

AOP-019 Malfunction of RCS. pressure control

a.

No comments.

20.

AOP-020 Loss of RHR (shutdown cooling)

a.

No comment.

21.

AOP-021 Seismic disturbances

a.

Step 3.2.2:

The "Operating Supervisor" title has been changed

to "Operation Coordinator".

40

22.

AOP-022 Loss of service water

a.

Step 1.3.2.1:

This step required local action; that the action

was local was not indicated. This same comment applies to many

other steps in AOPs.

b.

Step 3.3.2.1:

The labeling for these valves was

on the

adjacent wall, and had been covered by wall mounts for seismic

supports, such that the label for SW-18 was totally unreadable.

c. Step 3.3.2.2.3: This valve was not commonly operated, and was

located in an out-of-the-way place,

so that it

was difficult

for some operators to find. The operators needed its location

to be stated in the step. This comment also applied to several

other valves in this procedure that were located among the

piping in the overhead of the auxiliary building, such as SW-52

and 53, SW-100, and SW-109.

The operator needed

enough

information in the procedure to allow placement of a portable

ladder in the right place the first time.

d.

Step 4.3.2.10:

Operators had no dedicated pipe fittings for

use with hose

to supply alternate emergency cooling water to

the safety injection pumps.

e. Step 6.1:

Operators

needed pit level alarms in order to

effectively respond to flooding in the service water pump pits.

All service water

pumps plus motor operated discharge and

cross-connect valves were located in these pits, and the pits

were all connected at about three feet above the floor level of

the pits. The plant was operated with the cross-connect valves

normally open.

As a result, flooding in one of these pits

could disable all of these valves by causing them to be under

water. A single pipe break could thus be unisolable by the

time is was discovered,

and could result in a loss of all

service water. No pit level alarms were installed, and the pit

sump pumps ware not supplied with vital power.

f. Step 6.3.3.3:

Valve FP-10 was located underground.

The steel

plate above this valve at ground level was not painted red or

labeled, making it very difficult for operators to find. Also,

the name and location of this valve were not included in the

step. In addition, the tool required to operate the valve was

not painted red or labeled, and its location was not stated in

the step.

Similarly, the names and locations of FP-4 and FP-5

were not in the procedure.

23.

AOP-23 Loss of containment integrity

a.

Step

1.5:

The

stated symptoms

were outside of the alarm

setpoints.

The control room alarm setpoints for containment

pressure were +0.9 psig and -0.4 psig.

This alarm was not

included as a symptom.

41

D.

Step 3.2:

Many of these subsequent actions were copied from

the TS, and the TS section was not referenced in the procedure.

In order to assure compli.ance with the TS,

the. situation

required the operator to look at the TS directly.

24.

AOP-024

Loss of instrument bus

a.

Ste

3..2: This step required local actions without providing

adequate reference to the. plant location.

25. AOP-026

Low frequency operation

a.

Step 3.1.1:

This step did not require the operator to verify

that the RCPs were tripped automatically by the underfrequency

-trip.'

b.

Step 3.1.2..1:

A caution was-missing prior to this step.

When

picking up additional generator load,

the operator needs to

ensure that generator reduced KVA limits are not exceeded.

c. Step 3.2.2:

The procedure told the operator to adjust

generator KVA,

but. not how to get a KVA number.

In interviews,

some operators did not know how to do this.

To get the

KVA

number, calculation by the operator was required. Calculations

by operators should not be required to accomplish steps in this

Drocedure.

d.

Step 3.2.3:

This step directed the operator to verify proper

voltage and frequency to the" emergency busses.

Verify meant

that if

it

was not so,

action was to' be taken to make it so.

The operator could not control voltage and frequency of the

grid,

and in this step was not instructed to place the

emergency busses on the diesel generators.

26.

AOP-027 Operation with degraded system voltage

a.

Step 1.1:

The 230 KV switchyard voltage had no indication or

alarm in the

control

room, as this had been

removed

approximately one year before. Therefore, this symptom was hot

valid.

b. Step 1.2:

The

115

KV switchyard voltage low alarm in the

control room was set at 112.4 KV.

However, during the.

simulator scenarios,

operators found that the setpoint was

required to be 110.4 KV for this alarm.

c.

Step 3.2.3:

This step required the operator to verify that the

E1-E2 tie bus was powered from the running emergency diesel.

Due to a plant modification that was done about one year ago,

this step was no longer applicable.

42

Step 3.2.8:

This step was not consistent with the intent of

the TS.

The step stated that if

a plant start-up was in

progress,

then continue with the start-up. At this point in

the procedure, the plant had both emergency diesel generators.

supplying power to the v ital busses, with nonvital busses being

supplied with degraded voltage

from offsite power.

Plant

start-up with such a degraded electrical system was not within

the intent of the TS.

e. Step 4.1:

This step stated that the procedure was required if

the plant was

shut down or at less that 5 percent power.

During simulator exercises, operators used this procedure when

the plant was at 100 percent power. Initial conditions

specifying when this procedure should be used needed to be better

defined.

27.

AOP-028 ISFSI abnormal events

a.

Step 1.3.1.1.2:

This step required the use of a ladder to.

clear blockage from the outlets, however, there was no

dedicated ladder at the ISFSI.

b. Step 4.3.2.3:

The procedure required to perform this step was

not referenced (ERC-003).

VII.

Other document comments:

1. OMM-022 Emergency operating procedures user's guide

a. Paragraph 5.1.3:

This paragraph was in error; PATH-1 grid I-10

considered supplement D, not C.

b. Final paragraph of 5.3.4:

The discussion concerning heat sink

red path transfer to FRP-H.1 and hence to EPP-16 was in error.

c.

Final

paragraph of 5.3.4:

There was no EPP-16 caution

concerning

conditions

under

which

FRP-H.1

should

be

implemented.

2. Transition document, vol.1:

a. Table of contents:

In some instances, the page numbers listed

were incorrect.

b. Page 83,

pneumatic power:.

This section did not reflect the

plant .N2 CV modification.

APPENDIX C

WRITER'S GUIDE COMMENTS

This appendix contains writer's guide comments

and observations.

Unless

specifically stated, these comments were not regulatory requirements. However,

the licensee acknowledoed that the factual content of each of these comments

was correct as stated. The licensee further committed to evaluate each comment,

to take appropriate action and to document that action (proposed or completed)

in the response to IR-89-16. These items will be reviewed during a future NRC

inspection.

I. Deviations from the Writer's Guide

A sample of the EOPs was evaluated for deviations from the Robinson

writer's guide.

Types of deviations noted were characterized in this

section and accompanied by a list of examples of the specific deviations.

Note that some steps contained more than one example.

1. The following steps violated writer's guide directions for the

structure of logic steps or the use of logic terms:

EPP-8

Step 1, caution

Step 2d3 RNO

Step 3, caution

Step 4a RNO

Step 5, caution

Step 6, note

Step 6b

Step 11, caution

Step 12c RNO

Step 14, caution

EPP-10

Step Sa

Step 5b

Step 6c

Step 6d

Step 7

Step 8

Step 9

Step 9a3

Step 9a5

EPP-12

Step 1, note

Step 5, caution

Step Sa RNO

FRP-C.2

Step 1, caution

Step 3b RNO

Step 4, cote

Step 7, caution

FRP-H.2

Step 4, caution

PATH-1

A-5

B-3

B-11.

B-12

E-8

E-9

E- 10

E-11

F-2

H-7

H-9

H-10

PATH-2

A-10

B-2

B-9

B-12

B-13 (2 examples)

B-14

D-4 (2 examples)

0-12

G-9

G-12.

H-3

H-4

I-11 (2-examples)

2. The following steps violated writer's guide directions for the form

of transitions:

EPP-8

Step 2d3 RNO

Step 11d1

Step 14al RNO

Step 21 RNO

Step 28bi

EPP-12

Step 13c

FRP-C.2

Step 1, caution

Step 3, caution

PATH-1

H-6

PATH-2

A-10

H-5

1-12

FRP-C.2

Step 2c

Step 2e

Step 13

3. The following steps contained conditional actions within cautions or

notes, in violation of writer's guide direction.

EPP-8

Step 3, caution

Step 11, caution

EPP-12

Step 1, caution

Step 5, caution

FRP-C.2

Step 1, caution

Step 3, caution

Step 4, caution

FRP-C.3

Step 3, caution

FRP-H.2

Step 4, caution

FRP-S.1

-Step 11., caution

4. The

followina

steps violated writer's guide directions

for

referencing other procedures.

EPP-2

Step 23a

EPP-7

Step 20e RNO

EPP-17

Step 5 RNO

Step 27a RNO

II. Inadequacies in the Writer's Guide

The writer's guide did not thoroughly address each aspect of the procedures

nor did it define restrictively the methods designated for use in order to

assure consistency within and between

procedures

and to retain that

consistency over time and through personnel changes.

The Robinson writer's guide contained a number of areas where lack of

restrictive or thorough guidance had led to problems and inconsistencies in

the EOPs. These weaknesses were as follows:

1. Inclusion of contingent transitions was incorrectly allowed in

cautions by the writer's guide.

Because contingency steps and

transition steps required operator action, this contradicted other

writer's guide directions which specified that no actions would be

included in cautions.

Action steps by definition belong in the

numbered sequence of procedure steps.

2.

The writer's guide failed to provide directions for structure of

written steps, cautions, and notes in the path procedures.

3. Page 44 of 76 included a statement that proper logic statements were

to be used in foldout items.

That page also contained an example.

that included improper use of the logic term "if."

4.

The. wri.ter's guide failed to require special emphasis for the

transition terms

"go

to." - Because

transitions were

important

actions that could be difficult to perform,

special emphasis would

aid operators in their use of the procedures.

5. The writer's guide did not address nor require some method of

reminder to operators of steps that might be performed at some time

in the future (e.g., "WHEN condition, THEN action" sequences).

4

6. Attachment 6.8 of the wri.ter's guide, the abbreviation list, lacked

a number of acronyms commonly found in the EOPs. . For example:

F, SPDS, FW, SW, CV, EDG, PSID, GPM

7.

The writer's guide stated that. steps in the

RNO column would be

written in complete sentence format.

It failed to define complete

sentence format or to describe how it differed from the instruction

steps in the left hand column of the procedures.

8. The writer's guide failed to define a method for placekeeping.

9. The, writer's guide did not address the method for identifying

procedure steps when it was necessary to continue with that step on

the following page of a procedure.

10.

The writer's guide

allowed handwritten changes to- the path

procedures

and

CSFSTs.-

This method of revision contained the

potential for unreadable changes and was inappropriate.

11.

The writer's guide failed to define the type size, type style or

margins tobe used in the EOPs.

12.

The writer's guide failed to address the use of initial capitalization

in high level steps, although this method was applied in a number of

EOPs.

13.

The writer's guide allowed but did not require an alpha-numeric

border on path procedures.

14.

The writer's guide required line spacing in path procedures to be

"adequate".

No' objective criteria for determining

adequacy was

included.

15.

The writer's guide failed to define the use of parentheses or

quotation marks in the EOPs,

although these forms of punctuation

were used in the EOPs.

16.

The writer's

guide

stated that procedure designators used in

references in the path procedures must "positively and unambiguously

identify" the reference.

Specific directions and examples of

procedure designators were necessary but not provided to ensure

consistency.

17. Section 5.2.4.7,

page 12 of 76,

failed to provide criteria for'

editing the EOPs to meet the "expected minimum average level of

operator knowledge."

18.

The writer's guide

failed to describe a method for indicating

possible plural status.

For example,

as in the step "check faulted

S/Gs."

19.

The writer s guide failed to address certain action verbs used

throughout the

EOPs.

Examples included; running,

load,

faulted,

normal, contact, disconnect, and connect.

20.

The verbs "close" 'and "open"

were defined inconsistently in the

action verb list in that "close"

addressed both fluid flow and

electric current

whereas "open" addressed only fluid flow,

not

breaker ooeration.

This inconsistency led to undefined actions

.

Deing specified in the EOPs.

See for example EPP-21,

Energizing

pressurizer heaters from emergency busses, step 1 RNO.

21.

The writer's guide did not include a method for easily identifying

sections or subsections in the EOPs,

such as tabbing, in order to

facilitate rapid reliable movement within the EOP network.

22.

The writer's guide sections 5.3.4.6 and 5.3.4.7. provided guidance

for formatting tables and figures.

However,

it-

did not provide

examples of these formats to help procedure writers to prepare

consistently formatted tables and figures.

23.

The writer'-s guide section 5.3.4.14 provided guidance for labeling

of equipment or controls within the EOPs.

Clear criteria defining

"operator language" terms was not provided.

In addition, several,

examples

of

control

panel

equipment nomenclature and their

respective labels presented in the procedures were not provided.

III. AOPs

The AOPs were reviewed for application of human factors principles and

consistency with the presentation of information in the EOPs. Presentation

of information in ways that conflicted with the structure of the EOPs was

of concern because it required operators to cope with inconsistencies,

thereby increasing the burden on training and operator memory.

Specific

concerns were characterized below and accompanied by a list of examples.

Note that some steps contained more than one example.

.1.*

The following steps applied logic structure in a manner inconsistent

with that defined for use in the EOPs:

AOP-004

Step 3.2.5, note

Step 3.2.7.1

-

Step 3.2.8

Step 3.2.9.a

Step 3.2.10

Step 3.2.11, note

Step 3.2.12, note

Step 3.2.12

Step 3.2.14

Step 3.2.16

Step 3.2.16.2

Step 3.2.16.4

Step 3.2.19

6

AOP-011

Step 4 1

Step 4.2

AOP-012'

Step 3.2.1

Step 3.2.2

Step 3.2.9

Step 3.2.11

Step 3.

2 15

Step 4.2

AOP-013

Step 1.3.1.1.1

Step 1.3.1.2.2

Step 1.3.2.10

Step 3.3.1.2.1

Step 3.3.1.3

Step. 3.3.1.6

Step 3.3.2.2

Step 3.3.2.2.3

Step 3.3.2.2.6

Step 3.3.2.3

AOP-024

Step 2.1

Step 2.2

Step 3.2.3

Step 3.2.4

Step 4.3

Step 4.4

AOP-028

Step 1.3.1.1.2

Step 1.3.1.1.3

Step 1.3.2.3

Step 1.3.2.4

Step 1.3.2.5

Step 1.4.1

Step 1.4.2

Step 1.4.3

Step 2.4.1

Step 3.3.2.3

Step 3.3.2.4

Step 3.3.2.6

Step 3.4.1

2. The following steps structured transition steps

in a manner

inconsistent with that defined for use in the EOPs:

AOP-004

Step,3.2.19

AOP-005

Step 1.3.2.1.4

AOP-011

Step 3.2.8

7

AOP-012

Step 3.2.14

AOP-013

Step 1.3.2.1

Step 3.3.2.2.6

AOP-'024

-Step 3.1.2

AOP-028

Step 1.3.2.5

'Step 2.4.1

Step 2.4.2

Step 3.3.2.4

Step 3.3.2.5

Step 3.3.2.6

3. The following steps were preceded by cautions or notes structured in

a manner inconsistent with that defined for use in the EOPs:

AOP-004

Step 3.2

AOP-013

Step 1.3.2.7

AOP-028

Step 3.2.1

4.

The following steps used past tense,

passive voice,

or were not

written as directives, in contrast with the present tense, active

voice, directives used in EOPs and the rest of the AOPs:

AOP-004

  • Step 4.0

AOP-011

Step 3.1.1

Step 4.1

Step 4.2

Step 4.3

AOP-013

Step 1.4

Step 2.2.1

Step 2.4.1

Step 3.4.1

AOP-024

Step 4.0

Step 4.4

AOP-028

Step 1.4

Step 2.4

Step 3.4

5. The following steps included two actions,

in contrast to the

convention used in EOPs and the rest-of the AOPs:.

AOP-011

Step 3.2.4

Step 3.2.6

AOP-013

Step 1.3.2.4

AOP-024

Step 3.2.2

6. The following procedures used a typestyle that was different from

that used in EOPs and the majority .of AOPs:

AOP-011

A0 P-024

0

APPENDIX D

NOMENCLATURE

This appendix contains NRC observations of instances where Writer's Guide

apPlication to tne EOP would cause the reader to expect an exact nomenclature

match with component nomenclature, yet there was no identity. It also includes

instances where a complete match was neither required nor found and the mismatch

was sufficient-to cause concern. The licensee agreed in each case to evaluate

the difference and make the appropriate change. These items will be reviewed

during a future NRC inspection.

Procedure

Step/pg..

EOP nomenclature

Component nomfenclature

-

SD AFW

(ON

MCC9 & 9) STM

DRIVEN FWP ...

(ON

RTGB PHASE A ISOL.

STATUS PANEL) ACC NZ

SUPPLY VA 855 ...

EPP-1

16/4

CST Level.

Cond.

Storage Tank

Level

Attach. A/28

Control and Indication

?480 V Switchgear?

EPP-8

2.c RNO/4

SEAL OIL BACKUP PUMP

- TURNING GEAR AND SEAL

OIL

11.a/11

ALL STOPPED

OFF

-

19.b/19

ACCUMULATOR DISCHs

DISCH

SI-865A

DISCH

SI-865B

DISCH

SI-865C

26.c/23

SI-865A

V-865A

SI-865C

V-865C

EPP-10

2/3

STOPPED

status light OFF

3.a/4

CLOSED

status light SHUT

3.b/4

CLOSED

status light SHUT

9.b.1/9

HCV-121

HIC-121

9.b.4/9

CLOSED

status light SHUT

9.b.7/9

HCV-142

HIC-142

9.d/10

HCV-758

HIC-758

EPP-20

13

CLOSED

status light SHUT

EPP-21

1/5

52/11C Makeup water

MCC 20 Makeup water

Treatment

.

Treatment

EPP-21

1/6

52/22B, 480V Bus E-2

52/22B 480 Bus E-1

Tie Bus. Breaker

supply SI Pump .B

EPP-21

1/6

52/29B, 480V Bus E-2

52/29B 480 Bus E-2

Tie Bus Breaker

supply SI Pump B

EPP-21

3e/8

PRESS HTR PNL #1

Breaker 1, 2, & 3

No lables

EPP-21

4e/10

PRESS HTR PNL #3

Breaker 1, 2, & 3

No lables

EPP-SUPP

1.A/4

Injection Mode Valves

status lights SHUT

closed

1.B.6/5

IA-1716

PCV-1716

1.B.15-B.18/5 RC-516

VA-516

RC-519A

VA-519A

RC-519B

VA-519B

RC-553

VA-553

C-739

VA-739

S-855

VA-855

1.B.19/5

CC-739

VA-739

1.B.20/5

SI-855

VA-855

1.B.25-B.32/5 WD-1721

WDS:VA-1721

WD-1722

WDS:VA-1722

WD-1723

WDS:VA-1723

3

WD-1728

WDS:VA-1728

WD-1786

WDS:VA-1786

WD-1787

WDS:VA-1787

WD-1789

WDS:VA-1789

WD-1794

WDS:VA-1794

1.E/8

off

STOP

3.A.1/10

HCV-758

HIC-758

HCV-142

HIC-142

FRP-C.2

4.a/6

RUNNING

START

11/9

Stop

OFF

FRP-H.2

.2/3

FW RE.G(s)

FCV-478

A FEED REG VALVE

FCV-488

B FEED REG VALVE

FCV-498

C FEED REG VALVE

2/3

FW REG BYP(s)

FCV-479 A S/G FEED REG

VALVE BYPASS

FCV-489 B S/G FEED REG

VALVE BYPASS

FCV-499 C S/G FEED REG

VALVE BYPASS

2/3

FW HDR SECTION(s)

V2-6A

V2-6B

V2-6C

4/4

MSIV BYP(s)

MSIV V-3A

BYP MS-353A

MSIV V-3B

BYP MS-353B

MSIV V-3C

BYP MS-353C

4

FRP-J.2

2 /4

CV

not in abbr list

3/4

FW

not in abbr list

5/4

SPDS

not in abbr list

AOP-00i

1.1.2.6

...

MEDIAN ...

TR-408 HIGH Tav ...

AOP-004

3.2.4.3/4

START a Boric Acid

label.not on equipment

Transfer Pump

3.2.15.2/8

panel LP-28, circuit

circuit not labeled

No. 4

3.2.16.4/8

.

HVH-2

HUH-2

AOP-008

1.3.2.3.1

WASTE CONDENSATE

C WCT TO WASTE COND

RECIRCULATION PUMP

RECIRC PUMP

SUCTION VALVE

AOP-010-

1.1.2/3

LOW FEEDWATER FLOW

FWP A/B FLOW LOW

AOP-010

1.1.5/3

HIGH HOTWELL LEVEL

HOTWELL LEVEL HI/LO

AOP-010

1.1.7/3

Low Feed Pump Seal

FWP SEAL WTR PUMP A/B

Water DP

TROUBLE

AOP-010

1.1.8/3

Electrical fault on FW

FWP A MOTOR

pump

FWP B MOTOR

AOP-010

1.1.9/3

LOW LUBE OIL PRESSURE

FWP A LUBE OIL TROUBLE

FWP B LUBE OIL TROUBLE

AOP-010

1.2.1/3

Electrical fault on

COND PUMP A MOTOR

Condensate Pump

COND PUMP B MOTOR

AOP-010

1.3.4/4

Electrical fault on

HTR DR TANK PUMP A

Heater Drain Pump

MOTOR

HTR DR TANK PUMP B

MOTOR

AOP-011

3.2.3/4

S/G PORVs

handwritten labels on

-

equipment "open" and

"closed"

AOP-012

3.1.3/3

closed

SHUT

3.2.11/4

No. 2 LP guage

label not on equipment

AOP-013

1.2.1/4

stop HVE-15

OFF

C1

3 2.35

CLOSE

SHUT

AOP-014

3.1.2/4

PW MOV-832

Makeup CC-832

3.2.5/7

DW-711

CC-711

AOP-O15

1.83

STEAM DUMP ACTUATION

STEAM DUMP ARMED

ADP-022

i.3.1.i.1/4

South Supply

eader

SW Pump Disch

Isolation Valve

1.3.1:1.2/4

SW Pump Discharge

SW Pump Disch

Header Cross-Connect

1.3.2.2/5

Chemical Injection

Hypochlorite/SW

Supply Lines

Isol

1.3.2.3/5

deep well supply

Potable water

3.3.2.2.3/18

IVSW,Tank .

seal water injection

tank

5.3.2.2.4/14

E. H. Oil Pump

Gov Fluid Pump

6.3.3.3/16

jockey pump

booster pump

AOP-023

1.5/3

Internal pressure

CV pressure

SII

APPENDIX E

AC

Alternating Current

AFW

Auxiliary Feedwater

AO

Auxiliary Operator

AOP

Abnormal Operating Procedure

AP

Administrative Procedure

ATWS

Anticipated Transient Without Scram

AUX

Auxiliary

BKR

Breaker

BLDG

Building

CCW

Component Cooling Water

CP&L

Carolina Power and Light

CSFST

Critical Safety Function Status Tree

CST

Condensate Storage Tank

CV

Containment Vessel

CVS

Chemical and Volume Control

DC

Direct Current

DEV

Deviation

DG

Diesel Generator

DISCH

Discharge

DP

Differential Pressure

DS

Dedicated Shutdown

DW

Demineralized Water

EAL.

Emergency Action Level

E&C/RC

Environmental and Chemistry/Radiation Control

ECCS

Emergency Core Cooling System

EDG

Emergency Diesel Generator

EFPY

Effective Full Power Year

EH

Electro-hydraulic

EMERG

Emergency

EOP

Emergency Operating Procedure

EPP

End Path Procedure

ERC

Environmental/Radiation Control

ERFIS

Emergency Response Facility Information System

ERG

Emergency Response Guidlines

F

Fahrenheit

FCV

Flow Control Valve

FIC

Flow Indicating Controller

FP

Fire Protection

FRP

Functional Recovery Procedure

FW

Feedwater

GEN

Generator

GP

General Procedure

gpm

gallons per minute

GTG

Generic. Technical Guidelines

HBR

H. B. Robinson

HCV

Hand Control Valve

Hi

High

HP

Health Physics

hr

hour

HTR

heater

HVH

Heating Ventilation Handling

Hx

Heat Exchanger

I&C

Instrumentation and Control

IC

Internal Combustion

IFI

Inspector.Followup Item

IR

Inspection Report.

ISFSI

Independent Spent Fuel Storage Installation

KV

Kilovolt

KVA

Kilovolt Ampere

KW

Kilowatt

LCV,

Level Control Valve

LO

Low

LOCA

Loss of Coolant Accident

LP

Low Pressure

MG

Motor generator

MOV

Motor Operated Valve

MSIV

Main Steamline Isolation Valve

mph

mile per hour

N2

Nitrogen

NOUE

Notice of Unusual Event

NR

Narrow Range

NRC

Nuclear Regulatory Commission

OMM

Operations Management Manual

OP.

Operating .Procedure

P

Premissive

P

Pressure

P -

Page

P/A

Public'Address

Pg

Page

PGP

Procedures Generation Package

PI

Pressure Indication

PNL

Panel

PORV

Power Operated Relief Valve

Pp

Pump

PRESS

Pressure

PRZR

Pressurizer

PSID

Pressure Square Inch-differential

PSIG

Pressure Square Inch-gage

PSTG

Plant Specific Technical Guidelines

PZR

Pressurizer

QA

Quality Assurance

R.

Radiation

RC

Radiation Control

RCP

Reactor Coolant Pump

RCS

Reactor Coolant -System

RECIRC

Recirculation

RHR

Residual Heat Removal

R/hr

Roentgen/hour

RI

Radiation Indicator

RM

Radiation Monitor

RNO

Response Not Obtained

RO

Reactor Operator.

RPIS

Rod Position Information System

RTD

Resistance Temperature Device

RTGB

Reactor TurbineGenerator Board

RT(NDT)

Reference Nil-ductility Temperature

RVLIS

Reactor Vessel Level Information System

RWST

Reactor Water Storage Tank

SCM

Subcooling Margin

SER

Safety Evaluation Report

SERV

Service

S/G

Steam Generator

SGTR

Steam Generator Tube Rupture

SI

Safety Injection

SMR

Simulator Modification Request

SPDS,

Safety Parameter Display System

SRO

Senior Reactor Operator

SST

Station Service Transformer

STM

Steam

SUR .

Startup Rate

SW

Service Water

SWB

Service Water Booster

T

Temperature

T

Thickness

Tavg

Temperature-Average

Tc

Temperature-Cold

TC

Thermocouple

TD

Transition Document

Th

Temperature-Hot

TI

Training Instruction

TR .

Trend Recorder

Tref

Temperature-Reference

TRANS

Transformer

TS

Technical Specifications

TURB

Turbine

V

Volt

V&V

Verification & Validation

VCT

VolumeControl Tank

V/V

Valve

WOG-

Westinghouse Owners' Group

III