ONS-2013-029, Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License

From kanterella
(Redirected from ML13337A170)
Jump to navigation Jump to search

Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License
ML13337A170
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 11/26/2013
From: Batson S
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ONS-2013-029
Download: ML13337A170 (40)


Text

DUKE Scott L.

Batson ENERGY.

Oconee Nuclear Station Duke Energy ONOIVP 1 7800 Rochester Hwy ONS-2013-029 Seneca, SC 29672 o: 864.873.3274 f 864.873.4208 10 CFR 50.90 Scott.Betson@duke-energy.com November 26, 2013 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852

Subject:

Duke Energy Carolinas, LLC Oconee Nuclear Station (ONS), Units 1, 2, and 3 Docket Numbers 50-269, 50-270, and 50-287 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License Amendment Request (LAR) No. 2012-01, Supplement 4 On June 27, 2012, Duke Energy Carolinas, LLC (Duke Energy) submitted a License Amendment Request (LAR) requesting the Nuclear Regulatory Commission (NRC) approve a Technical Specification (TS) change that adds a temporary Completion Time to TS 3.8.1 Required Action (RA) C.2.2.5 to allow time to perform major maintenance on each Keowee Hydro Unit (KHU).

By letters dated December 14, 2012, May 28, 2013, and July 26, 2013, Duke Energy responded to NRC Requests for Additional Information (RAIs). During a meeting with the NRC on November 13, 2013, Duke Energy agreed to provide additional information and to revise the proposed TS change. Also, as a result of the meeting, Duke Energy is making additional regulatory commitments associated with the LAR. The revised proposed TS changes included in this supplement are bounded by the no significant hazards consideration submitted in the June 27, 2012, LAR. responds to specific NRC questions from the November 13, 2013, meeting and provides a description of the revised proposed TS changes. Enclosure 2 provides a list of the regulatory commitments made during the meeting. For completeness, Enclosure 2 also includes regulatory commitments made in previous supplements to this LAR. Attachments 1 and 2 provide revised TS markup pages and revised TS retyped pages. Attachments 3 and 4 provide revised TS Bases markup pages and revised TS Bases retyped pages.

The first Keowee generator pole rewind outage is scheduled to start January 28, 2014; therefore, Duke Energy requests NRC approval of this LAR by January 7, 2014. If there are any additional questions, please contact Boyd Shingleton, ONS Regulatory Affairs, at (864) 873-4716.

www.duke-energy.com Ac~bl

Nuclear Regulatory Commission License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on November 26, 2013.

Sincerely, Scott L. Batson Vice President Oconee Nuclear Station Enclosures

1. Additional Information Addressing NRC Questions
2. List of Regulatory Commitments Attachments
1. Revised TS Markup Pages
2. Revised TS Retyped Pages
3. Revised TS Bases Markup Pages
4. Revised TS Bases Retyped Pages

Nuclear Regulatory Commission License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 3 cc w/Enclosures and Attachments:

Mr. Victor McCree, Regional Administrator U. S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Mr. Richard Guzman, Senior Project Manager (by electronic mail only)

Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 0-8 C2 Rockville, MD 20852 Mr. Eddy Crowe Senior Resident Inspector Oconee Nuclear Site Ms. Susan E. Jenkins, Manager Radioactive & Infectious Waste Management Division of Waste Management South Carolina Department of Health and Environmental Control 2600 Bull St.

Columbia, SC 29201

ENCLOSURE I Additional Information Addressing NRC Questions 1.0 Introduction 1.1 Keowee Hydro Station Major Maintenance 1.2 Improved Keowee Generator Pole Outage Timeline 1.3 Diversity and Defense-in-Depth of ONS Electrical System 1.4 Backup Power for Emergency Power System 1.5 Alternate Methods Of Maintaining Safe Shutdown 1.6 Risk Reduction Measures 2.0 Description of Revised Proposed Technical Specification Change 3.0 Regulatory Commitments 4.0 Comparison of KHU and Switchyard Reliability and Unavailability 5.0 Significant PRA Model Changes and Assumptions 6.0 Standby Shutdown Facility (SSF) Ability to Mitigate Station Blackout 7.0 Control of Keowee Rotor Lifts License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 1.0 Introduction By letter dated June 27, 2012, Duke Energy Carolinas, LLC (Duke Energy), submitted an application to the Nuclear Regulatory Commission (NRC) for a proposed amendment for the Oconee Nuclear Station (ONS), Units 1, 2, and 3, which would revise the Technical Specification (TS) for the emergency power system. The revision would permit each of the two emergency power system generating units (Keowee Hydro Units) to be out of service for up to 75 days on a one-time basis for major maintenance work. By letters dated December 14, 2012, May 28, 2013, and July 26, 2013, Duke Energy responded to NRC Requests for Additional Information (RAls).

During a meeting with the NRC on November 13, 2013, Duke Energy provided additional justification and risk reduction measures to support the proposed LAR. Duke Energy also agreed to revise the proposed TS change to reduce the proposed Completion Time to 62 days as described in Section 2.0.

1.1 Keowee Hydro Station Major Maintenance Duke Energy recognized the need for extended outages to perform major maintenance activities not long after the Keowee Hydroelectric Station (KHS) was commissioned in 1971. The need for major maintenance outages was not identified during the initial review of ONS Technical Specifications. Duke Energy subsequently requested and NRC approved a 45 day Completion Time for one Keowee Hydro Unit (KHU) inoperable. The NRC issued Amendment Nos. 50, 50, and 47 for Oconee Nuclear Station, Unit Nos. 1, 2, and 3, respectively, on November 3, 1977, in response to Duke Energy's request dated October 13, 1976, as supplemented by letter dated September 29, 1977. The amendments revised the Technical Specifications to allow operation of the Oconee Nuclear Station with one KHU out of service from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> up to a maximum of 45 days (only once in a 3 year period) when the remaining KHU and both the overhead and underground transmission circuits are operable and the standby buses are energized by a Lee Combustion Turbine (LCT).

At the time of issuance of these amendments, the primary long term maintenance items identified as needing up to 45 days were hydro turbine runner and discharge ring welding repairs, which were estimated to be necessary approximately every six to eight years. Also, generator thrust and guide bearings were expected to require replacement approximately every six to eight years with a similar maintenance period. Duke Energy also indicated that other items which manifest as failures could possibly be resolved during the proposed maintenance periods without the need for special licensing actions.

Since issuance of the amendments in 1977, approximately 36 years ago, the 45 day Completion Time has been used eleven times. In 1979, KHU-2 was taken out of service for approximately 33 days to allow welding repair of the turbine blades. In 1982, KHU-2 was taken out of service for approximately 39 days to weld repair of the turbine blades. In 1984, KHU-2 was taken out of service for 16 days for emergent maintenance. KHU-2 tripped due to a generator field ground relay in November 1985 with the subsequent repair taking approximately 8 days. Since the 45 day Completion Time had already been used once in the previous 3 years, Duke Energy requested and received approval to use the remaining portion of the 45 day Completion Time for the repair. In License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 2 1987, KHU-1 was taken out of service for 17 days for generator stator maintenance. Maintenance requiring more than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> was not required again until major refurbishment upgrades were performed on KHU-1 and KHU-2 in 2004 and 2005, respectively. These upgrades included refurbishment of each units turbines and replacement of the governor, voltage regulator, and batteries. The KHU-1 refurbishment outage was 49 days while the KHU-2 outage was 34 days.

Due to the scope of work planned for 2004 and 2005 upgrades, Duke determined additional time beyond the 45 day Completion Time was required. As a result, Duke Energy requested and NRC approved a one-time 17 day extension to the 45 day Completion Time for one KHU inoperable and a cumulative 120 hour0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br /> extension to the 60 hour6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> Completion Time for both KHUs inoperable (dual KHU outage). The extension allowed sufficient time to seal the wicket gates which was necessary to allow turbine work to proceed.

Other than the current request and the LAR that supported the 2004 and 2005 refurbishment outages, Duke Energy has made one other request for an extension to the 45 day Completion Time. This request was made in September 2006 to allow repair of a pole jumper on KHU-2. This repair took approximately 27 days. Since the 45 day Completion Time had already been used once in the previous 3 years, Duke Energy requested and received approval to use the remaining portion of the 45 day Completion Time (11 days) plus an additional 30 days. KHU-1 was taken out of service in August 2010 for stator maintenance for approximately 23 days. In August 2013 and September 2013, KHU-2 and KHU-1 were taken out of service for approximately 24 days and 14 days respectively for maintenance activities associated with the Protected Service Water tie-in to the Keowee Hydroelectric Station.

During preventive maintenance inspections in 2008 and 2009 Duke Energy identified normal wear mechanisms in rotor pole assemblies that prompted the current project to refurbish/overhaul both Keowee generators. The first phase, scheduled for January 2014 for KHU-2 and July 2014 for KHU-1 refurbishes and replaces all 56 generator field poles on each KHU. The second phase, which refurbishes the stator for each KHU, is planned for 2016 and 2017. Duke Energy also has long-range plans to replace the Keowee main step-up transformer.

1.2 Improved Keowee Generator Pole Outage Timeline Since submittal of LAR 2012-01 on June 27, 2012, work scope and methods for the generator pole rewind outage have been better defined. As a result, the scheduled duration of the single KHU outage, including contingency, has been reduced from 75 days to 62 days. The 13 day reduction resulted from a re-evaluation of required tasks, eliminating the need to unwater the KHU to add balance shots, and eliminating some contingency time for the physical work, balance shots and the overall outage. The planned dual KHU outage time was reduced from 160 hours0.00185 days <br />0.0444 hours <br />2.645503e-4 weeks <br />6.088e-5 months <br /> to 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br /> by a change in method that allows adding balance shots without unwatering the KHUs. The remaining 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br /> of dual KHU outage time is needed to remove the rotor and install a shaft locking device, and subsequently remove the shaft locking device and re-install the rotor (planned 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> for each evolution) on the KHU undergoing maintenance.

License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 3 1.3 Diversity and Defense-In-Depth of ONS Electrical System ONS can receive offsite power from multiple offsite sources that approach from the north, southwest, southeast, and east. Either of two LCTs can provide power to the safety related electrical buses at ONS. During the single KHU outage, the remaining KHU will be available to provide power via the underground emergency power path with capability to align to the overhead emergency power path. The LCTs are located to the southeast of ONS and can provide power via an isolated power path (electrically isolated from the grid) to the ONS standby buses via Transformer CT5. This transformer is located on the opposite side of the station from the 230 kV switchyard. Either of two Jocassee Hydro Units can be electrically separated from the grid and aligned directly to provide power to the 230 kV switchyard Yellow Bus to power safe shutdown loads. The Jocassee Hydro Units are located north of ONS while the LCTs are located in the opposite direction, southeast of ONS.

1.4 Backup Power for Emergency Power System a)

Currently credited in LAR LAR 2012-01 credits a LCT as a backup power source to the inoperable KHU to support the originally proposed one-time 75 day Completion Time to maintain the defense-in-depth design philosophy of the electrical system to meet its intended design function. ONS TSs require a LCT to be energizing both standby buses via an isolated power path prior to exceeding the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time of TS 3.8.1 Required Action C.2.1 for the duration of the single KHU outages.

ONS TS Condition H requires a LCT to be energizing both standby buses via an isolated power path prior to entry into a dual KHU outage. During the planned extended outages, the remaining KHU is required by TSs to be operable and aligned to the underground emergency power path with capability to be manually aligned to the overhead emergency power path. Both required offsite power sources are required to be verified operable by TSs prior to exceeding 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in the extended outage. The proposed TS requires that the SSF and Emergency Feedwater (EFW)

Systems be administratively verified operable prior to entering the extended Completion Time and does not permit discretionary maintenance or testing on the SSF, EFW and essential AC power systems. By letter dated December 14, 2012, Duke Energy committed to prohibit discretionary maintenance on the offsite power system (230 kV Switchyard) during the extended Completion Time and to maintain operability of required offsite circuits at all times (note that this is also a TS requirement). By letter dated May 28, 2013, Duke Energy committed to use a Critical Activity Plan (CAP) for the generator pole rewind outages and include similar risk mitigation strategies to those that are currently used in CAPs for scheduled dual KHU outages. The CAP will also include requirements to notify the Transmission Control Center and System Operating Center to take action to ensure grid reliability and minimize risks.

b)

Additional backup power sources Duke Energy will provide an additional backup power source and implement risk reduction measures to ensure safe shutdown should a loss of all station power occur during the generator pole rewind outages. Duke Energy will use a nearby hydro unit (Duke Energy's Jocassee Hydroelectric Station) as an additional backup power source to provide additional defense-in-depth License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 4 for the electrical power system at ONS. A Jocassee Hydro Unit can be black-started, aligned and dedicated to ONS via a power path isolated from the grid in accordance with approved procedures within approximately one hour.

The Jocassee Hydro Station contains four units rated 195 MW each. All four units generate at 14.4 kV, which is then stepped up to 230 kV. The Jocassee Hydro Station has a similar switchyard layout to ONS. It has a 230 kV and 525 kV switchyard, both in a breaker-and-a-half configuration connected via an auto-transformer. In the unlikely event that all other power sources (Offsite Grid, KHU Overhead, KHU Underground, CT5) are unavailable, and ONS is experiencing a Station Blackout, the Emergency Operating Procedure will be entered. When all power sources are confirmed to be unavailable, the following steps will be taken at ONS to dedicate a Jocassee Unit via the Jocassee Black Line:

1) Transmission Control Center (TCC) is informed of the following "Jocassee Hydro is needed to power ONS and 230 kV Yellow Bus has been separated from the Grid"
2) Jocassee Black Line isolated
3) When notified by the TCC that Jocassee Black Line is energized, PCB 15 (Jocassee Black Line Yellow Bus Tie) is closed. (This energizes the Yellow Bus and each ONS unit's startup transformer.)

To further address NRC concerns with the vulnerability of ONS during a dual KHU outage, Duke Energy will provide a temporary diesel generator at the Keowee Hydro Station to allow recovering the remaining operable but dewatered KHU within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. This recovery time is consistent with the required 4-hour station blackout coping duration for ONS. The temporary diesel generator allows recovering of the KHU by providing power to operate Keowee Hydro Station electrical auxiliaries, the intake gate hoist to provide water to the remaining operable KHU, and the powerhouse crane to set the locking beam in place should the rotor be in transit to the pedestal.

Additionally, the Protected Service Water (PSW) system is installed and capable of aligning the Fant 100 kV line or a KHU to the SSF should the SSF diesel generator (DG) fail to start and run.

This provides additional contingency for failures of transformer CT5 and Keowee power paths and allows realignment of these sources to PSW and the SSF. The SSF provides an alternate means of maintaining safe shutdown for all three ONS units until power can be restored to ONS.

c)

Action that will be taken if backup power sources become unavailable TS 3.8.1 Required Action C.2.2.1 requires a LCT to be energizing both standby buses via an isolated power path within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and within one hour from subsequent discovery of a deenergized standby bus. If the transmission line fails or the LCTs cannot be started and aligned to energize the standby buses within one hour then entry into TS 3.8.1 Condition M is required and all three ONS units are required to be placed in MODE 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and MODE 5 within 84 hours9.722222e-4 days <br />0.0233 hours <br />1.388889e-4 weeks <br />3.1962e-5 months <br />. Should the Jocassee Hydro source become unavailable during the Keowee generator pole rewind outages, the Critical Activity Plan will require immediate action to restore the Jocassee Hydro source to available status.

License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 5 1.5 Alternate Methods of Maintaining Safe Shutdown The following systems/equipment can be used to maintain all three ONS units in a safe shutdown condition should a loss of all station power occur until power can be restored:

" Turbine Driven Emergency Feedwater Pump capable of feeding steam generators,

" SSF operable and capable of providing alternate shutdown capability, and

" Onsite diesel-driven feedwater pump capable of feeding steam generators.

A station blackout would result from the loss of all offsite power, the loss of the LCT energizing the standby buses, and the loss of the remaining KHU. Should this occur, emergency power will be restored within one hour by starting the second LCT and aligning to the standby buses, or starting one of the Jocassee Hydro Units and aligning to the Yellow Bus in the 230 kV switchyard. Should the remaining KHU be inoperable due to being dewatered during one of the two dual KHU outages, a temporary DG located at the KHS will be used to restore the KHU within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

1.6 Risk Reduction Measures ONS assesses and manages the increase in risk that may result from proposed maintenance activities in accordance with 10 CFR 50.65, Requirements for Monitoring Effectiveness of Maintenance at Nuclear Power Plants. Duke Energy's Risk Management Process requires a Critical Activity Plan (CAP) be written for the generator pole rewind outages. The CAP will include multiple risk mitigation strategies.

Based on past correspondence and the November 13, 2013, Duke Energy/NRC meeting, Duke Energy commits to include the following risk reduction measures in the CAP:

" ONS will not start the extended single KHU outage or a dual KHU outage if severe weather conditions are forecast.

" ONS will contact the system load dispatcher once per day to ensure no significant grid perturbations (high grid loading not able to withstand a single contingency of line or generation outage) are expected during extended TS completion time.

" ONS will control the steam-driven emergency feedwater pump on each ONS unit as "protected" equipment during the extended TS completion time.

" ONS will continuously staff the SSF during the dual KHU outages.

" LCT and Central Switchyard will be protected 2 nd LCT protected and available within one hour

" Prior to the start of the outage, verify a Jocassee Hydro Unit is available to be aligned to the Oconee 230kV Yellow Bus within approximately one hour

" Temporary DG located at Keowee Hydro Station with capability to restore available KHU unit to operable status within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> from dual KHU outage

" Reduced RCS Inventory not permitted during dual KHU outage

" Temporary Diesel-Driven pump available to feed each unit's steam generators

" PSW equipment installed and capable of aligning the Fant 100 kV line or a KHU to the SSF License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 6 2.0 Description of Revised Proposed Technical Specification Change In ONS LAR dated June 27, 2012, as supplemented by letter dated December 14, 2012, Duke Energy proposed a 3rd Completion Time for TS 3.8.1 Required Action (RA) C.2.2.5 of 75 days with specific restrictions. Duke Energy proposes to reduce that Completion Time to 62 days. The proposed change is restated below with this change and minor changes required due to the issuance of Amendment Nos. 382, 384, & 383:

AND NOTE ------------

1. No discretionary maintenance or testing allowed on SSF, EFW and essential AC Power Systems.
2. Only applicable one time for each KHU due to generator field pole rewind work and expires on January 1,2015.
3. Only applicable if the SSF and EFW are administratively verified OPERABLE prior to entering the extended Completion Time.

62 days from initial inoperability when Condition due to an inoperable KHU if entered to perform generator field pole rewind work.

Required Action C.2.2.3 will be modified to add the following Note:

NOTE -------------

Not applicable to remaining KHU and its required underground emergency power path or LCO 3.3.21 when in Condition H to perform generator field pole rewind work.

License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 7 This note is needed to allow entry into the 60-hour dual KHU outage to reassemble the refurbished KHU and return it to functional condition prior to declaring the refurbished KHU operable. Without this note, entry into Condition L would be required and only 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> (12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> allowed by the note to RA L. 1 and 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> allowed by the Completion Time for Required Acton L. 1) is allowed to restore the KHU and its required underground path. Only 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> is allowed to restore compliance with LCO 3.3.21.

The note from the second Completion Time of TS 3.8.1 Required Action C.2.2.5 is numbered as Note 1. A second note is added indicating it is not applicable to field pole rewind work or until one year after the KHU declared operable after the work:


NOTE------

1. Not to exceed 45 days cumulative per rolling 3-year time period for each KHU.
2. Not applicable during generator field pole rewind work or until 1 year after KHU declared OPERABLE following rewind work.

This note is added to avoid using up the 45-day Completion Time concurrent with the new 62 day Completion Time and will provide some time to allow Duke Energy to perform emergent maintenance work should the need arise after a one year waiting period.

The following administrative change is proposed:

Delete the following note from the TS 3.8.1, C.2.1, Required Action Completion Time since it is no longer applicable:

NOTE------

An additional 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> can be added to the following completion times. This expires on August 27, 2005

@1058 hours License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 8 3.0 Regulatory Commitments During the November 13, 2013, Duke Energy/NRC meeting to discuss the Keowee LAR, NRC staff expressed concern that the 45 day cumulative Completion Time of RA C.2.2.5 could be used during the same time period that the one-time 62 day Completion Time will be used. Duke Energy indicated in the meeting that a portion of the 45 day Completion Time has been used for each KHU for Protected Service Water (PSW) tie-in work (30 days available for KHU-1 and 22 days for KHU-2). Duke Energy currently has no plans to use the remaining time prior to the Keowee generator pole rewind work scheduled for 2014. To address NRC concerns, Duke Energy will not use the 2nd Completion Time for Required Action C.2.2.5 for planned Keowee work prior to the Keowee generator pole rewind outage. This is a regulatory commitment.

This regulatory commitment and other new regulatory commitments made in this submittal and in previous submittals associated with this LAR are listed in Enclosure 2, List of Regulatory Commitments.

4.0 Comparison of KHU and Switchyard Reliability and Unavailability 4.1 Reliability of Emergency Diesel Generators compared to KHU:

The KHUs have an unreliability of approximately 2.6E-03, compared to the best emergency diesel generator reliability in the Duke Energy nuclear fleet of 2.6E-02. This includes both failure to start and failure to run. Thus, the KHUs are about 10 times more reliable than an emergency diesel generator (EDG).

4.2 Unavailability of KHU compared to Emeraency Diesel Generators The KHU historical unavailability compared to EDGs is as follows:

The individual EDG unavailability across Duke Energy Nuclear Units ranges from 1.5E-02 (5.5 days per year per EDG) to 2.46E-02 (9 days per year per EDG).

Single KHU unavailability (either KHU) is 6.27E-02 (23 days per year), with each KHU representing 3.1 E-02 (11.5 days) on an average basis.

Both KHU units' unavailability is 1.14E-02 (4 days per year).

The KHU unavailability values above are based on a period of 10.5 years, which includes several previous extended outages for repair or refurbishment activities. The EDG unavailability provided is based upon a similar period of time.

One important difference between the KHU units and EDGs is that EDGs are not flexible in the load path and can only support a single essential bus with some limited cross connections in some cases. Each KHU is capable of supplying all emergency power loads and is flexible in that it can supply power via either the overhead lines or the underground lines to the Oconee Units. When an EDG is out a service, the typical arrangement has little in way of back-up power supplies that can support the affected essential bus. Thus, for ONS each KHU is fully redundant to the other without a loss of mitigation capability. Given the KHUs have significantly better reliability compared to a typical EDG, the risk impact of License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 9 KHU unavailability is lower compared to the typical extended EDG outage without back-up power available.

In comparing KHU unavailability to EDG unavailability, the direct numerical comparison is not an accurate view. The major maintenance activities for the EDGs are typically conducted during unit outages when the unavailability of EDGs is not tracked and not reported. These activities can involve EDG outages of up to a week or more, and result in a significant amount of unreported unavailability. On the other hand, major maintenance for the KHUs is typically performed during ONS power operations and is tracked for unavailability. Thus, for a KHU versus EDG comparison, the total EDG hours in maintenance are underreported although the outage risk impact may be similar depending on the outage schedule. If the typical one week duration per EDG per outage is used, the individual EDG unavailability would be higher than an individual KHU.

4.3 Switchyard Reliability and Availability for Oconee compared to other Duke Energy Nuclear site Switchyards.

The Duke Energy Probabilistic Risk Assessment (PRA) measures the Switchyard Reliability and Availability by the Loss of Off-site power initiating event frequency.

A review of the plant specific loss of off-site power initiating events for all of the Duke Energy nuclear switchyards compared to ONS shows that ONS LOOP probability is approximately the same as most of the other sites in the Duke Energy nuclear fleet as shown in the table below:

LOOP with weather LOOP without included weather included Oconee (Units 1, 2, 3) 1.7E-02 1.5E-02 Duke Energy Nuclear Plant 1 1.7E-02 1.3E-02 Duke Energy Nuclear Plant 2 2E-02 1.2E-02 Duke Energy Nuclear Plant 3 2.5E-2 2.1E-2 Duke Energy Nuclear Plant 4 1E-02 8E-03 Duke Energy Nuclear Plant 5 8.1E-02 6.6E-02 An additional consideration is that ONS has considerably more defense-in-depth for large AC power sources than most Duke Energy sites. At ONS there are two different backup power sources (LCT and Jocassee Hydro Unit) capable of powering all ONS safe shutdown loads. The backup sources can be isolated from the grid and dedicated to ONS.

License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 10 5.0 Significant PRA Model Changes and Assumptions The difference between the core damage frequency (CDF) impact provided in 2003 and the current results is caused by differences in schedule and modeling assumptions. A summary list of the important differences is provided below followed by more detailed discussion.

A. Dual KHU outage duration is shorter than 2003 analysis B. Tornado risk effectively eliminated by schedule restrictions C. Reactor Coolant Pump Seal Upgrades D. Oconee PRA Updates and HRA Methodology The 2002 amendment request involved an extension of the TS completion time for the dual KHU outage activities. Thus, the longer duration of the dual KHU portion of the outage is a contributor to the higher 2003 results.

The 2003 CDF results are dominated by tornados and severe weather LOOP events. Although a reduced tornado frequency for scheduling the outage outside of peak tornado season was applied, tornado events were not eliminated in the 2003 dual KHU outage case because the duration was more than a few days. For the current analysis, tornado events were eliminated because of the short duration and administrative controls and risk management plans that require verification of a clear weather forecast to avoid potential impacts of severe weather on the availability of offsite power from the switchyard or the Lee Combustion Turbines. The short duration provides strong confidence in the weather forecast during the outage period.

An important plant change related to Keowee emergency power is the Reactor Coolant Pump (RCP) seal design. ONS Unit 1 has recently upgraded to the Flowserve N9000 seal design. ONS Units 2 and 3 have Bingham RCP seals. All of these seals have similar performance to the Combustion Engineering (CE) plant RCP seals assessed in WCAP-16175-P. In 2003, ONS Unit 1 had just completed an upgrade to a Sulzer seal similar in design to the N9000. Due to a lack of sufficient operating experience, Duke Energy chose to conservatively assume that a loss of seal cooling would result in seal failure consistent with the previous Westinghouse seal design. A sensitivity study was performed in the 2003 analysis using the Westinghouse Owners Group (WOG) 2000 RCP seal model which showed that this provided an additional significant CDF reduction. For the current plant design, the robust seal designs (N9000 & Bingham designs) provide about an order of magnitude further reduction in CDF from seal LOCAs compared to the WOG 2000 model results.

The current PRA results are based on Revision 4 of the Oconee PRA which incorporates a significant number of plant changes and modeling enhancements that have occurred since the completion of the Revision 2 model used in the 2003 analysis. Besides RCP seals, the human reliability analysis (HRA) approach has changed significantly with evolving industry PRA methods and standards. In particular, the Revision 2 model HRA did not directly address human error dependencies and their impact on recovery credit. In general, this change increases overall CDF estimates, but the required dedicated alignment of the Lee CTs to the Standby Buses prior to the outage minimizes this impact on Keowee outage risk impacts.

License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 11 The issue of human error dependency analysis also affects the estimated risk benefit for an alternate onsite power supply. In the 2003 analysis, a sensitivity analysis was conducted for a DG system being installed at Oconee to provide replacement power for the KHU units. However, that analysis assumed that such recovery actions were independent of other operator actions related to the accident scenarios. This significantly overestimates the risk reduction that could be achieved.

The current analysis also considers the option of adding a DG system during the extended KHU outage but uses more realistic assumptions about the maximum benefit that could be achieved.

There are three reasons why the DG recovery action does not provide significant risk reduction.

The ability and probability of success for operators to successfully start and properly load the DG system is low. This is a challenging task to execute even under normal (low stress) conditions because operators must start and parallel, possibly six diesel generators together, and load onto a bus that has been correctly load stripped and then reload the critical loads in the available time. Under high stress and time pressure, this action can be expected to have a high failure probability.

" The diesel generator recovery action is in direct competition with other high priority recovery actions, such as activating and running the SSF, restoring offsite power, restoring a KHU, aligning the standby Lee CT, or aligning a Jocassee Hydro Unit. In an HRA analysis the DG operator action occurs in the same time frame as the other actions, the same operators are involved, and the same cues to initiate the action are used. With these attributes, this new postulated operator action would be assessed as highly or completely dependent upon the existing credited actions. This level of dependency would result in very little if any credit reduction in CDF for the recovery action.

" A temporary onsite DG system is not considered capable of withstanding tornado events and is unlikely to be available following a tornado strike that damages the 230kV switchyard and/or 100kV Fant line. Thus, adding a DG system would provide minimal benefit in reducing the tornado-related CDF associated with the 62 day single KHU outage period.

Although seismic events are a potential cause of a loss of offsite power (LOOP) event, the relative frequency of a seismically-induced LOOP events is significantly lower than from all other causes (e.g., grid-related, switchyard-related, etc.). It is also noted that the basic component fragilities of the switchyard and transmission lines (providing offsite power) are shared in common with the component for the Keowee overhead transmission path. This dependency limits the seismic impact of the Keowee overhead unit maintenance. Thus, it is concluded that the exclusion of seismic events from the analysis does not significantly impact the results and conclusions of this evaluation.

6.0 Standby Shutdown Facility (SSF) Ability to Mitigate Station Blackout The SSF houses stand-alone systems that are designed to maintain the plant in a safe and stable condition following postulated emergency events that are distinct from the design basis accidents for which the plant systems were originally designed. The system provides additional defense-in-depth protection for the health and safety of the public by serving as a backup to existing safety systems. As such, the SSF provides an alternate means to achieve and maintain MODE 3 with an average Reactor Coolant temperature _Ž 525 0F (RCS cold leg temperature

  • 5550F and RCS pressure - 2155 psig) following postulated fire, sabotage, or flooding events, and is designed in accordance with criteria associated with these events.

License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 12 Loss of all other station power does not impact the SSF's capability to mitigate each event. The SSF is also credited as the alternate AC (AAC) power source and the source of decay heat removal required to demonstrate safe shutdown during the required four hour station blackout coping duration. The SSF is capable of maintaining all three ONS units in a safe shutdown condition for a period of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> following a fire, turbine building flood, sabotage, or tornado missile events and station blackout.

7.0 Control of Keowee Rotor Lifts The Keowee generator rotor lift will be controlled in accordance with the Duke Energy Nuclear Lifting Program. The rotor will be lifted straight up off the generator and moved to a stand that is bolted to the floor adjacent to the generator. The lift plan directs minimum moves as necessary while transporting the rotor. If the rotor were dropped while moving it from the operating location to the rotor stand no safety related equipment would be rendered inoperable. The load travel path minimizes interferences and the number of direction movements.

ENCLOSURE 2 REGULATORY COMMITMENTS License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 1 REGULATORY COMMITMENTS The following commitment table identifies those actions committed to by Duke Energy Carolinas, LLC (Duke Energy) in this submittal. Other actions discussed in the submittal represent intended or planned actions by Duke Energy. They are described to the Nuclear Regulatory Commission (NRC) for the NRC's information and are not regulatory commitments.

From Duke Energy letter dated December 14, 2012:

Commitment Completion Date 1

No discretionary maintenance or testing on the offsite power During 62 day CT system (230 kV Switchyard) will be performed for TS 3.8.1 RA C.2.2.5 2

Operability of required offsite circuits should be maintained at all During 62 day CT times.

for TS 3.8.1 RA C.2.2.5 From Duke Energy letter dated May 28, 2013:

Commitment Completion Date 1

Duke Energy will take the necessary steps to ensure the PSW During each KHU tie-in work and the generator pole rewind work will not impact or generator field pole conflict with each other. Note: This does not preclude rewind outage; performing the work concurrently. (As of November 15, 2013, expires on 1/1/2015 PSW tie-in to Keowee is complete.)

2 Duke Energy will use a Critical Activity Plan for the Keowee During each KHU generator pole replacement outages for risk mitigation purposes.

generator field pole This plan will include similar risk mitigation strategies to those rewind outage; that are currently used in the Critical Activity Plans for scheduled expires on 1/1/2015 Dual Unit Outages as described in the response to EEEB RAI 7 in the Enclosure to this letter. The Critical Activity Plan will include requirements to notify the Transmission Control Center (TCC) of plant risk changes that increase the plant's sensitivity to offsite power status and to notify the TCC and System Operating Center to take action to ensure grid reliability and minimize risks.

License Amendment Request No. 2012-01, Supplement 4 November 26, 2013 Page 2 From November 13, 2013, Duke Energy/NRC Meeting and this submittal:

Commitment Completion Date ONS will not start the extended single KHU outage or a dual During KHU KHU outage if severe weather conditions are forecast.

generator pole rewind outages 2

ONS will contact the system load dispatcher once per day to During KHU ensure no significant grid perturbations (high grid loading not generator pole able to withstand a single contingency of line or generation rewind outages outage) are expected during extended TS completion time.

3 ONS will control the steam-driven emergency feedwater pump During KHU on each ONS unit as "protected" equipment during the extended generator pole TS completion time.

rewind outages 4

ONS will continuously staff the SSF during the dual KHU During KHU outages.

generator pole rewind outages 5

Critical Activity Plan will include the following risk reduction During KHU measures:

generator pole a) LCT and Central Switchyard protected rewind outages nd b) 2 LCT protected and available within one hour c) Verify Jocassee Hydro Unit available and can be aligned to the Oconee 230kV Yellow Bus within approximately one hour prior to start of outage d) Temporary DG located at Keowee Hydro Station with capability to restore available KHU unit to operable status within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> from dual KHU outage e) Reduced RCS Inventory not permitted during dual KHU outage f) Temporary diesel-driven pump available to feed each unit's steam generators g) The Protected Service Water (PSW) system is installed and capable of aligning the Fant 100 kV line or a KHU to the SSF should the SSF diesel generator (DG) fail to start and run.

6 Duke Energy will not use the 2nd Completion Time for Required Ongoing until KHU Action C.2.2.5 for planned Keowee work prior to the Keowee generator pole generator pole rewind outage for each KHU.

rewind outages I complete.

ATTACHMENT 1 TECHNICAL SPECIFICATION MARKUP PAGES

AC Sources - Operating 3.8.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C.

KHU or its required overhead emergency power path inoperable due to reasons other than Condition A.

C. 1 Perform SR 3.8.1.3 for OPERABLE KHU.

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> if not performed in previous 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> AND Once per 7 days thereafter AND C.2.1 Restore the KHU and its required overhead emergency power path to OPERABLE status.

OR C.2.2.1 Energize both standby buses from LCT via isolated power path.

AND C.2.2.2 Suspend KHU generation to grid except for testing.

AND adCiti al 96 h rs ic a nn b i d d e d t e r folIo ing co etion ti es. Thi' xpires ugust 2, 2005 058 hours6.712963e-4 days <br />0.0161 hours <br />9.589947e-5 weeks <br />2.2069e-5 months <br />.

-4

-J 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> AND 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from discovery of inoperable KHU 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> AND 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from subsequent discovery of deenergized standby bus 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (6ontinued) 4 OCONEE UNITS 1, 2, & 3 3.8.1-3 Amendment Nos. 347, 340, &

AC Sources - Operating 3.8.1 ACTIONS CONDITIONR REQUIRED ACTION COMPLETION TIME C.

(continued)

NOTE------

Not applicable to remaining KHU and its required underground emergency power path or LCO 3.3.21 when in Condition H to perform generator field pole rewind work.

C.2.2.3 Verify by administrative means that the remaining KHU and its required underground emergency power path and both required offsite sources are OPERABLE and the requirements of LCO 3.8.3, "DC Sources-Operating," LCO 3.8.6, "Vital Inverters-Operating," LCO 3.8.8, "Distribution Systems-Operating," LCO 3.3.17, "EPSL Automatic Transfer Function," LCO 3.3.18, "EPSL Voltage Sensing Circuits," LCO 3.3.19, "EPSL 230 kV Switchyard DGVP,"

and LCO 3.3.21, "EPSL Keowee Emergency Start Function" are met.

AND 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (continued)

OCONEE UNITS 1, 2, & 3 3.8.1-4 Amendment Nos. 353, 35, &3 I

AC Sources - Operating 3.8.1 ACTIONS (continued)

CONDITION R

REQUIRED ACTION COMPLETION TIME C. (continued)

C.2.2.4 Verify alternate power source capability by performing SR 3.8.1.16.

AND C.2.2.5 Restore KHU and its required overhead emergency power path to OPERABLE status.

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> AND Every 31 days thereafter 28 days when Condition due to an inoperable Keowee main step-up transformer AND 1

NOTE------

SNot to exceed 45 days cumulative per rolling 3-year time period for Leach KHU

2. Not applicable during generator field pole rewind work or until 1 year after KHU declared OPERABLE following rewind work.

AND NOTE----

1. No discretionary maintenance or testing allowed on SSF, EFW and essential AC Power Systems.
2. Only applicable one time for each KHU due to generator field pole rewind work and expires on January 1,2015.
3. Only applicable if the SSF and EFW are administratively verified OPERABLE prior to entering the extended Completion Time.

62 days from initial inoperability when Condition due to an inoperable KHU to perform generator field pole rewind work 45 days from discovery of initial inoperability when Condition due to an inoperable KHU I,

(continued)

OCONEE UNITS 1, 2, & 3 ndment Nos. 382, 384, &

ATTACHMENT 2 TECHNICAL SPECIFICATION RETYPED PAGES

AC Sources - Operating 3.8.1 ACTIONS (continued)

CONDITION I

REQUIRED ACTION COMPLETION TIME C.

KHU or its required overhead emergency power path inoperable due to reasons other than Condition A.

C. 1 Perform SR 3.8.1.3 for OPERABLE KHU.

AND C.2.1 Restore the KHU and its required overhead emergency power path to OPERABLE status.

OR C.2.2.1 Energize both standby buses from LCT via isolated power path.

AND C.2.2.2 Suspend KHU generation to grid except for testing.

AND 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> if not performed in previous 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> AND Once per 7 days thereafter 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> AND 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from discovery of inoperable KHU 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> AND 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from subsequent discovery of deenergized standby bus 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (continued)

OCONEE UNITS 1,2, & 3 3.8.1-3 Amendment Nos.

AC Sources - Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION I

COMPLETION TIME C.

(continued)

C.2.2.3 -------

NOTE------

Not applicable to remaining KHU and its required underground emergency power path or LCO 3.3.21 when in Condition H to perform generator field pole rewind work.

Verify by administrative means that the remaining KHU and its required underground emergency power path and both required offsite sources are OPERABLE and the requirements of LCO 3.8.3, "DC Sources-Operating," LCO 3.8.6, "Vital Inverters-Operating," LCO 3.8.8, "Distribution Systems-Operating," LCO 3.3.17, "EPSL Automatic Transfer Function," LCO 3.3.18, "EPSL Voltage Sensing Circuits," LCO 3.3.19, "EPSL 230 kV Switchyard DGVP,"

and LCO 3.3.21, "EPSL Keowee Emergency Start Function" are met.

AND 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (continued)

.1.

L OCONEE UNITS 1,2, & 3 3.8.1-4 Amendment Nos.

AC Sources - Operating 3.8.1 ACTIONS CONDITION R

REQUIRED ACTION COMPLETION TIME C. (continued)

C.2.2.4 Verify alternate power source capability by performing SR 3.8.1.16.

AND C.2.2.5 Restore KHU and its required overhead emergency power path to OPERABLE status.

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> AND Every 31 days thereafter 28 days when Condition due to an inoperable Keowee main step-up transformer AND

.............-NOTE------

1.

Not to exceed 45 days cumulative per rolling 3 year period for each KHU.

2.

Not applicable during generator field pole rewind work or until 1 year after KHU declared OPERABLE following rewind work.

45 days from discovery of initial inoperability when Condition due to an inoperable KHU

.1.

.1.

(continued)

OCONEE UNITS 1, 2, & 3 3.8.1-5 Amendment Nos.

AC Sources - Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME C. (continued)

AND NOTE------

1. No discretionary maintenance or testing allowed on SSF, EFW and essential AC Power Systems.
2. Only applicable one time for each KHU due to generator field pole rewind work and expires on January 1, 2015.
3. Only applicable if the SSF and EFW are administratively verified OPERABLE prior to entering the extended Completion Time.

62 days from initial inoperability when Condition due to an inoperable KHU to perform generator field pole rewind work D.

KHU or its required D.1 Perform SR 3.8.1.4 for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> if not performed underground power OPERABLE KHU.

in previous 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> path inoperable.

AND D.2 Energize either 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> standby bus from LCT via isolated power AND path.

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from subsequent discovery of deenergized required standby bus (continued)

OCONEE UNITS 1, 2, & 3 3.8.1-6 Amendment Nos.

AC Sources - Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME D. (continued)

AND D.3 Restore KHU and its 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> required underground emergency power path AND to OPERABLE status.

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from discovery of inoperable KHU E.

Required Action and E.1 Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> for one unit associated Completion Time not met for AND Required Action D.2.

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> for other unit(s)

AND E.2 Be in MODE 5.

84 hours9.722222e-4 days <br />0.0233 hours <br />1.388889e-4 weeks <br />3.1962e-5 months <br /> F.

Zone overlap protection F.1 Restore zone overlap 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> circuitry inoperable protection circuitry to when overhead OPERABLE status.

electrical disconnects for KHU associated OR with the underground power path are closed.

F.2 Open overhead 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> electrical disconnects for KHU associated with the underground power path.

G.

Both emergency power G.1 Restore one breaker to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> paths inoperable dueto OPERABLE status.

one inoperable E breaker and one inoperable S breaker on the same main feeder bus.

(continued)

OCONEE UNITS 1,2, & 3 3.8.1-7 Amendment Nos.

ATTACHMENT 3 TECHNICAL SPECIFICATION BASES MARKUP PAGES

AC Sources - Operating B 3.8.1 BASES ACTIONS

, or a KHU made inoperable to perform generator field pole rewind work C.1. C.2.1, C.2.2.1. C.2.2.2, C.2.2.3, C.2.2.4, and C.2.2.5 (continued)

If the inoperable KHIU or its required overhead emergency power path are not restored to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> as required by Required Action C.2.1, a controlled shutdown must be initiated as required by the Required Actions for Condition M unless the extended Completion Times of Required Action C.2.2.5 are applicable. The second Completion Time for Required Action C.2.1 establishes a limit on the maximum time allowed fbr a KHU to be inoperable durirg any single contiguous occurrence of having a KHU inoperable. If Condition C is entered as a result of switching an inoperable KHU from the underground to the overhead emergency power path, it may have been inoperable for up to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. This could lead to a total of 144 hours0.00167 days <br />0.04 hours <br />2.380952e-4 weeks <br />5.4792e-5 months <br /> since the initial failure of the KHU. The second Completion Time allows for an exception to the normal "time zero" for beginning the allowed time "clock." This will result in establishing the "time zero" at the time the KHU becom inoperable, instead of at the time Condition C was entered.

The extended Completion Times of Required Action C.2.2.5 ply when the KHU or its required overhead emergency power path inoperable due to an inoperable Keowee main step-up transformer an inoperable KHU (if not used for that KHU in the previous 3 yearsk, In order to use the extended Completion Times, within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> of entering Condition C both standby buses must be energized from an LCT (Required Action C.2.2.1), KHU generation to the grid except for testing must be suspended (Required Action C.2.2.2), the remaining KHU and its required underground emergency power path and both required offsite sources must be verified OPERABLE, the LCOs indicated in Required Action C.2.2.3 must be verified to be met, and alternate power source capability must be verified by performing SR 3.8.1.16.

Required Action C.2.2.5 permits maintenance and repair of a Keowee main step-up transformer which requires longer than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

Transformer replacement is rare but is time extensive. A 28 day Completion Time is permitted by Required Action C.2.2.5 to restore the KHU and its overhead power path to OPERABLE status when inoperable due to an inoperable Keowee main step-up transformer. This allows a reasonable period of time for transformer replacement.

Required Action C.2.2.5 also permits maintenance and repair of a KHU which requires longer than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The primary long term maintenance items are expected to be hydro turbine runner and discharge ring welding OCONEE UNITS 1, 2, & 3 B 3.8.1-9 BASES REVISION DATED 1 GMA 3

AC Sources - Operating B 3.8.1 BASES ACTIONS C.1, C.2.1, C.2.2.1, C.2.2.2, C.2.2.3, C.2.2.4, and C.2.2.5 (continued) repairs which are estimated to be necessary every six to eight years.

Also, generator thrust and guide bearing replacements are necessary.

Other items which manifest as failures are expected to be rare and may be performed during the permitted maintenance periods. The 45 day restoration time of Required Action C.2.2.5 is allowed to be applied cumulatively over a rolling three year period for each KHU. This Completion Time is 45 days from discovery of initial inoperabilityof the The temporary 62-day KHU. This effectively limits the time the KHU can be inoperable to 45 Completion Time of Required days from discovery of initial inoperabilty rather than 45 days from entry Note 1 Action C.2.2.5 is allowed for into Condition C and precludes any additional lime that may be gained as each KHU to perform generator a result of switching an inoperable KH-U from the underground to the field pole rewind work. The 62-overhead emergency power path. The Completion Time is modified by a mdafe y C m lt ion Tie iot s thate indicating it is not to exceed 45 days cum ulative in a rolling 3-year day Completion Time is provide conditions for using the time period for each KHU. For example, if KHU-1 is inoperable for 15 extended outage. Note 1 days, the 45-day Completion Time for KHU-1 is reduced to 30 days for indicates that no discretionary the rolling 3-year time period containing the 15 day inoperability. This maintenance or testing is requires a review of entries for the previous 3 years to determine the allowed on the Standby Shutdown Facility (SSF),

remaining time allowed in the 45-day Completion Time. If the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Emergency Feedwater (EFW),

Completion Time of C.2.1 is not exceeded, the 45-day Completion is not and essential alternating applicable and is not reduced.

current (AC) Power Systems.

Note 2 indicates that the 62-day Required Actions C.2.2.1, C.2.2.2, C.2.2.3, and C.2.2.4 must be met in Completion Time is only order to allow the longer restoration times of Required Action C.2.2.5.

applicable one time for each Required Action C.2.2.1 requires that both standby buses be energized rewind work and expires on using an LCT through the 100 kV transmission circuit. With this January 1,2015. Note 3 arrangement (100 kV transmission circuit electrically separated from the indicates that it is only system grid and all offsite loads), a high degree of reliability for the applicable if the SSF and EFW emergency power system is provided. In this configuration, the LCT is are administratively verified serving as a second emergency power source, however, since the 100 OPe RA L priorde tom p e nteio n

gTm e

kV transm ission circuit is vulnerable to severe w eather a tim e lim it is OPERABLE prior to entering the extended Completion Time.

kVtasisociciisvlealtoserwahratmeiits This increases the probability, imposed. The second Completion Time of Required Action C.2.2.1 even in the unlikely event of an permits the standby buses to be re-energized by an LCT within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> in additional failure, that the risk the event this source is subsequently lost. Required Action C.2.2.2 significant systems will function requires suspension of KHU generation to the grid except for testing.

as required to support their The restriction reduces the number of possible failures which could cause loss of the underground emergency power path.

Required Action C.2.2.3 requires verifying by administrative means that the remaining KHU and its required underground emergency power path and both required offsite sources are OPERABLE. This provides additional assurance that offsite power will be available. In addition, this assures that the KHU and its required underground emergency power path are available.

Required Action C.2.2.3 also requires verifying by administrative means that the requirements of the following LCOs are met:

The 45-day Completion Time is also modified by Note 2 indicating that it is not applicable during generator field pole rewind work or until one year after KHU OCONE declared OPERABLE following rewind work. This note is added to avoid using up 4

the 45-day Completion Time concurrent with the 62-day Completion Time and preserves some time to perform emergent maintenance work should the need arise after a one year waiting period.

AC Sources - Operating B 3.8.1 BASES ACTIONS C.1. C.2.1, C.2.2.1. C.2.2.2, C.2.2.3. C.2.2.4, and C.2.2.5 (continued)

LCO 3.8.3, "DC Sources - Operating;"

LCO 3.8.6, 'Vital Inverters - Operating;"

LCO 3.8.8, "Distribution Systems - Operating;"

LCO 3.3.17, "EPSL Automatic Transfer Function;"

LCO 3.3.18, "EPSL Voltage Sensing Circuits;"

LCO 3.3.19, "EPSL 230 kV Switchyard DGVP;" and Required Action C.2.2.3 is modified by a note indicating that it is not applicable to remaining KHU and its required underground emergency power path or LCO 3.3.21 when in Condition H to perform generator field pole rewind work. This note is needed to allow entry into the 60 hour6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> dual unit outage to reassemble the refurbished KHU and return it to functional condition, as well as perform balance runs and shots, post modification testing, and a commissioning run prior to declaring the refurbished KHU operable. Without this note, entry into Condition L would be required allowing only 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> to restore the KHU and its required underground path and only 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to restore compliance with LCO 3.3.21.

LCO 3.3.21, "EPSL Keowee Emergency Start Function."

This increases the probability, even in the unlikely event of an additional failure, that the DC power system and the 120 VAC Vital Instrumentation power panelboards will function as required to support EPSL, power will not be lost to ES equipment, and EPSL will function as required.

Verifying by administrative means allows a check of logs or other information to determine the OPERABILITY status of required equipment in place of requiring unique performance of Surveillance Requirements. If the AC Source is subsequently determined inoperable, or an LCO stated in Required Action C.2.2.3 is subsequently determined not met, continued operation up to a maximum of four hours is allowed by ACTION L.

Required Action C.2.2.4 requires verifying alternate power source capability by performing SR 3.8.1.16. This confirms that entry into Condition C is due only to an inoperable main step-up transformer or an inoperable KHU, as applicable. If SR 3.8.1.16 is subsequently determined not met, continued operation up to a maximum of four hours is allowed by ACTION L.

OCONEE UNITS 1, 2, & 3 B 3.8.1-11 BASES REVISION DATED=4Wa4

ATTACHMENT 4 TECHNICAL SPECIFICATION BASES RETYPED PAGES

AC Sources - Operating B 3.8.1 BASES ACTIONS C.1, C.2.1, C.2.2.1, C.2.2.2, C.2.2.3, C.2.2.4, and C.2.2.5 (continued)

If the inoperable KHIU or its required overhead emergency power path are not restored to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> as required by Required Action C.2.1, a controlled shutdown must be initiated as required by the Required Actions for Condition M unless the extended Completion Times of Required Action C.2.2.5 are applicable. The second Completion Time for Required Action C.2.1 establishes a limit on the maximum time allowed for a KHU to be inoperable durirg any single contiguous occurrence of having a KHU inoperable. If Condition C is entered as a result of switching an inoperable KHU from the underground to the overhead emergency power path, it may have been inoperable for up to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. This could lead to a total of 144 hours0.00167 days <br />0.04 hours <br />2.380952e-4 weeks <br />5.4792e-5 months <br /> since the initial failure of the KHU. The second Completion Time allows for an exception to the normal "time zero" for beginning the allowed time "clock." This will result in establishing the "time zero" at the time the KHU become inoperable, instead of at the time Condition C was entered.

The extended Completion Times of Required Action C.2.2.5 apply when the KHU or its required overhead emergency power path is inoperable due to an inoperable Keowee main step-up transformer, an inoperable KHU (if not used for that KHU in the previous 3 years), or a KHU made inoperable to perform generator field pole rewind work. In order to use the extended Completion Times, within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> of entering Condition C both standby buses must be energized from an LCT (Required Action C.2.2.1), KHU generation to the grid except for testing must be suspended (Required Action C.2.2.2), the remaining KHU and its required underground emergency power path and both required offsite sources must be verified OPERABLE, the LCOs indicated in Required Action C.2.2.3 must be verified to be met, and alternate power source capability must be verified by performing SR 3.8.1.16.

Required Action C.2.2.5 permits maintenance and repair of a Keowee main step-up transformer which requires longer than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

Transformer replacement is rare but is time extensive. A 28 day Completion Time is permitted by Required Action C.2.2.5 to restore the KHU and its overhead power path to OPERABLE status when inoperable due to an inoperable Keowee main step-up transformer. This allows a reasonable period of time for transformer replacement.

Required Action C.2.2.5 also permits maintenance and repair of a KHU which requires longer than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The primary long term maintenance items are expected to be hydro turbine runner and discharge ring welding OCONEE UNITS 1, 2, & 3 B 3.8.1-9 BASES REVISION DATED

AC Sources - Operating B 3.8.1 BASES ACTIONS C.1. C.2.1, C.2.2.1, C.2.2.2, C.2.2.3, C.2.2.4. and C.2.2.5 (continued) repairs which are estimated to be necessary every six to eight years.

Also, generator thrust and guide bearing replacements are necessary.

Other items which manifest as failures are expected to be rare and may be performed during the permitted maintenance periods. The 45-day Completion Time of Required Action C.2.2.5 is allowed to be applied cumulatively over a rolling three year period for each KHU. This Completion Time is 45 days from discovery of initial inoperability of the KHU. This effectively limits the time the KHU can be inoperable to 45 days from discovery of initial inoperability rather than 45 days from entry into Condition C and precludes any additional time that may be gained as a result of switching an inoperable KHU from the underground to the overhead emergency power path. The Completion Time is modified by Note 1 indicating it is not to exceed 45 days cumulative in a rolling 3-year time period for each KHU. For example, if KHU-1 is inoperable for 15 days, the 45-day Completion Time for KHU-1 is reduced to 30 days for the rolling 3-year time period containing the 15 day inoperability. This requires a review of entries for the previous 3 years to determine the remaining time allowed in the 45-day Completion Time. If the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time of C.2.1 is not exceeded, the 45-day Completion is not applicable and is not reduced. The 45-day Completion Time is also modified by Note 2 indicating that it is not applicable during generator field pole rewind work or until one year after KHU declared OPERABLE following rewind work. This note is added to avoid using up the 45-day Completion Time concurrent with the 62 day Completion Time and preserves some time to perform emergent maintenance work should the need arise after a one year waiting period.

The temporary 62-day Completion Time of Required Action C.2.2.5 is allowed for each KHU to perform generator field pole rewind work. The 62-day Completion Time is modified by three notes that provide conditions for using the extended outage. Note 1 indicates that no discretionary maintenance or testing is allowed on the Standby Shutdown Facility (SSF), Emergency Feedwater (EFW), and essential alternating current (AC) Power Systems. Note 2 indicates that the 62-day Completion Time is only applicable one time for each KHU due to generator field pole rewind work and expires on January 1, 2015. Note 3 indicates that it is only applicable if the SSF and EFW are administratively verified OPERABLE prior to entering the extended Completion Time. This increases the probability, even in the unlikely event of an additional failure, that the risk significant systems will function as required to support their safety function.

Required Actions C.2.2.1, C.2.2.2, C.2.2.3, and C.2.2.4 must be met in order to allow the longer restoration times of Required Action C.2.2.5.

OCONEE UNITS 1, 2, & 3 B 3.8.1-10 BASES REVISION DATED

AC Sources - Operating B 3.8.1 BASES ACTIONS C.1, C.2.1, C.2.2.1, C.2.2.2. C.2.2.3. C.2.2.4, and C.2.2.5 (continued)

Required Action C.2.2.1 requires that both standby buses be energized using an LCT through the 100 kV transmission circuit. With this arrangement (100 kV transmission circuit electrically separated from the system grid and all offsite loads), a high degree of reliability for the emergency power system is provided. In this configuration, the LCT is serving as a second emergency power source, however, since the 100 kV transmission circuit is vulnerable to severe weather a time limit is imposed. The second Completion Time of Required Action C.2.2.1 permits the standby buses to be re-energized by an LCT within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> in the event this source is subsequently lost. Required Action C.2.2.2 requires suspension of KHU generation to the grid except for testing.

The restriction reduces the number of possible failures which could cause loss of the underground emergency power path.

Required Action C.2.2.3 requires verifying by administrative means that the remaining KHU and its required underground emergency power path and both required offsite sources are OPERABLE. This provides additional assurance that offsite power will be available. In addition, this assures that the KHU and its required underground emergency power path are available.

Required Action C.2.2.3 also requires verifying by administrative means that the requirements of the following LCOs are met:

LCO 3.8.3, "DC Sources - Operating;"

LCO 3.8.6, "Vital Inverters - Operating;"

LCO 3.8.8, "Distribution Systems - Operating;"

LCO 3.3.17, "EPSL Automatic Transfer Function;"

LCO 3.3.18, "EPSL Voltage Sensing Circuits;"

LCO 3.3.19, "EPSL 230 kV Switchyard DGVP;" and LCO 3.3.21, "EPSL Keowee Emergency Start Function."

This increases the probability, even in the unlikely event of an additional failure, that the DC power system and the 120 VAC Vital Instrumentation power panelboards will function as required to support EPSL, power will not be lost to ES equipment, and EPSL will function as required.

OCONEE UNITS 1, 2, & 3 B 3.8.1-11 BASES REVISION DATED

AC Sources - Operating B 3.8.1 BASES ACTIONS C.1, C.2.1, C.2.2.1, C.2.2.2. C.2.2.3. C.2.2.4. and C.2.2.5 (continued)

Verifying by administrative means allows a check of logs or other information to determine the OPERABILITY status of required equipment in place of requiring unique performance of Surveillance Requirements. If the AC Source is subsequently determined inoperable, or an LCO stated in Required Action C.2.2.3 is subsequently determined not met, continued operation up to a maximum of four hours is allowed by ACTION L.

Required Action C.2.2.3 is modified by a note indicating that it is not applicable to remaining KHU and its required underground emergency power path or LCO 3.3.21 when in Condition H to perform generator field pole rewind work. This note is needed to all ow entry into the 60 hour6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> dual unit outage to reassem ble the refurbished KH U and return it to functional condition, as well as perform balance runs and shots, post modification testing, and a commissioning run prior to declaring the ref urbished KHU operable. Without this note, entry into Condition L would be required allowing only 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> to restore the KH U and its required underground path and only 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to restore compliance with LCO 3.3.21.

Required Action C.2.2.4 requires verifying alternate power source capability by performing SR 3.8.1.16. This confirms that entry into Condition C is due only to an inoperable main step-up transformer or an inoperable KHU, as applicable. If SR 3.8.1.16 is subsequently determined not met, continued operation up to a maximum of four hours is allowed by ACTION L.

D.1, D.2 and D.3 With the KHU or its required underground emergency power path inoperable, sufficient AC power sources remain available to ensure safe shutdown of the unit in the event of a transient or accident. Operation may continue for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> if the remaining KHU and its required overhead emergency power path are tested using SR 3.8.1.4 within one hour if not performed in the previous 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. SR 3.8.1.4 is only required to be performed when the KHU associated with the overhead emergency power path is OPERABLE. This Required Action provides assurance that no undetected failures have occurred in the overhead emergency power path. Since Required Action D.1 only specifies "perform," a failure of SR 3.8.1.4 acceptance criteria does not result in a Required Action not met. However, if the KHU and its required overhead emergency path fails SR 3.8.1.4, both KHUs and their required emergency power paths are inoperable, and Conditi on I for both KHUs and their emergency power paths inoperable for reasons other than Condition G or H is entered concurrent with Condition D. This OCONEE UNITS 1, 2, & 3 B 3.8.1-12 BASES REVISION DATED

AC Sources - Operating B 3.8.1 BASES ACTIONS D.1, D.2 and D.3 (continued) demonstration is to assure that the remaining emergency power path is not inoperable due to a common cause or due to an undetected failure.

For outages of the KHU and its required underground emergency power path in excess of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, an LCT (using the 100 kV transmission circuit electrically separated from the grid and offsite loads) must energize a standby bus prior to the outage exceeding 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. This ensures the availability of a power source on the standby buses when the KHU and its required underground emergency power path are out of service in excess of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The second Completion Time of Required Action D.2 permits the standby buses to be re-energized by an LCT within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> in the event this source is subsequently lost.

The second Completion Time for Required Action D.3 establishes a limit on the maximum time allowed for a KHU to be inoperable during any single contiguous occurrence of having a KHU inoperable. If Condition D is entered as a result of switching an inoperable KHU from the overhead to the underground emergency power path, it may have been inoperable for up to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. This could lead to a total of 144 hours0.00167 days <br />0.04 hours <br />2.380952e-4 weeks <br />5.4792e-5 months <br /> since the initial failure of the KHU. The second Completion Time allows for an exception to the normal "time zero" for beginning the allowed time "clock." This will result in establishing the "time zero" at the time the KHU become inoperable, instead of at the time Condition D was entered.

E.1 and E.2 If the Required Action and associated Completion Time for Required Action D.2 are not met, the unit must be brought to a MODE in which the LCO does not apply. To achieve this status, the unit must be brought to at least MODE 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> for one Oconee unit and 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> for other Oconee unit(s) and to MODE 5 within 84 hours9.722222e-4 days <br />0.0233 hours <br />1.388889e-4 weeks <br />3.1962e-5 months <br />. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging plant systems.

F.1 and F.2 With the zone overlap protection circuitry inoperable whenthe overhead electrical disconnects for the KHU associated with the underground power path are closed, the zone overlap protection circuitry must be restored to OPERABLE status or the overhead electrical disconnects must be opened within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. In this Condition, both KHUs and their required emergency power paths are OPERABLE, however a single failure could result in the loss of both KHUs.

OCONEE UNITS 1, 2, & 3 B 3.8.1-13 BASES REVISION DATED

AC Sources - Operating B 3.8.1 BASES ACTIONS G..1 (continued)

With both emergency power paths inoperable due to an E breaker and S breaker inoperable on the same main feeder bus, one breaker must be restored to OPERABLE status. In this Condition, both emergency power paths can still provide power to the remaining main feeder bus.

H.1 and H.2 With both KHUs or their required emergency power paths inoperable for planned maintenance or test with both standby buses energized from an LCT via an isolated power path, the KHU must be restored to OPERABLE status within 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br />. Operation with both KHUs and their required power paths inoperable is permitted for 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> provided that both standby buses are energized using an LCT through the 100 kV transmission circuit and the requirements of the Note to the Condition are met. The Note to the Condition indicates that it may only be entered when both offsite sources are verified by administrative means to be OPERABLE and the requirements of the following LCOs are verified by administrative means to be met:

LCO 3.8.3, "DC Sources - Operating;"

LCO 3.8.6, "Vital Inverters - Operating;"

LCO 3.8.8, "Distribution Systems - Operating;"

LCO 3.3.17, "EPSL Automatic Transfer Function;"

LCO 3.3.18, "EPSL Voltage Sensing Circuits;" and LCO 3.3.19, "EPSL 230 kV Switchyard DGVP."

This increases the probability, even in the unlikely event of an additional failure, that the DC power system and the 120 VAC Vital Instrumentation power panelboards will function as required to support EPSL, power will not be lost to ES equipment, and EPSL will function as required.

OCONEE UNITS 1, 2, & 3 B 3.8.1-14 BASES REVISION DATED