Letter Sequence Request |
|---|
|
|
MONTHYEARML12181A3122012-06-27027 June 2012 License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds Project stage: Request ML1221600472012-08-0303 August 2012 License Amendment Request, ME9021, ME9022, & ME9023, Acceptance Review (E-mail) Project stage: Acceptance Review ML12314A4342012-11-13013 November 2012 Request for Additional Information Regarding Amendment Application for a Revision to the Technical Specification on the Emergency Power System Project stage: RAI ML12359A0392012-12-14014 December 2012 Additional Information License Amendment Request for Temporary Tech Spec Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License Amendment Request Project stage: Request ML13077A0192013-03-11011 March 2013 Notification of Registration for Use of General License Spent Fuel Cask Number 127 Project stage: Request ML13094A4312013-04-12012 April 2013 Request for Additional Information Regarding Amendment Application Related to Maintenance on the Onsite Standby Power Sources Project stage: RAI ML13151A0232013-05-28028 May 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Project stage: Request ML13171A2952013-06-26026 June 2013 Request for Additional Information Regarding Amendment Application for a Revision to the Technical Specification on the Emergency Power System Project stage: RAI ML13214A3842013-07-26026 July 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field. Project stage: Request ML13336A5452013-11-13013 November 2013 Presentation Slides from Meeting with Duke Energy Carolinas, LLC, Oconee Nuclear Station Units 1, 2, and 3, Keowee Hydro Unit Generator Field Pole Rewind Project - License Amendment Request Project stage: Meeting ML13326A7212013-11-22022 November 2013 Request for Additional Information - Protected Service Water System Project stage: RAI ONS-2013-029, Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License2013-11-26026 November 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License Project stage: Request ML13338A3742013-12-0303 December 2013 12/3/13 E-mail from R.Guzman to B.Shingleton - Follow-up Request for Additional Information Keowee LAR for Temp TS Change to Support Keowee Generator Pole Rewind Work Project stage: RAI ML13336A5982013-12-0404 December 2013 Summary of Meeting with Duke Energy Carolinas, LLC, to Discuss the Proposed One-time TS Completion Time Change to Perform Khu Generator Field Pole Rewind Maintenance - Oconee Nuclear Station Units 1, 2, and 3 (TAC Nos. ME9021, ME9022, and M Project stage: Meeting ML13346A0202013-12-0606 December 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License.. Project stage: Request ML13349A0022013-12-12012 December 2013 E-mail from B.Shingleton to R.Guzman Revised TS 3.8.1 Markup Pages for License Amendment Request to Extend Khu Allowed Outage Time for Field Pole Rewind Work Project stage: Request ML13351A3172013-12-24024 December 2013 Safety Evaluation Input Regarding Temporary Technical Specification Change Request to Extend the Completion Time for an Inoperable Keowee Hydro Unit Project stage: Approval ML13357A6742014-01-0808 January 2014 Issuance of Amendments Regarding the Temporary Technical Specification Change to Extend the Completion Time for an Inoperable Keowee Hydro Unit Project stage: Approval ML14021A0022014-01-17017 January 2014 1/17/14 E-mail from R.Guzman to B. Shingleton - Minor Comments to Safety Evaluation for Amendment Temporary TS Change Request to Extend the Completion Time for an Inoperable Keowee Hydro Unit (TAC Nos. ME9021/22/23) Project stage: Approval 2013-12-03
[Table View] |
Text
T. PRESTON GILLESPIE, JR.
DEnergy Vice President Oconee Nuclear Station Duke Energy ON01 VP / 7800 Rochester Hwy.
Seneca, SC 29672 10 CFR 72.212 864-873-4478 864-873-4208 fax T. Gillespie@duke-energy. com March 11, 2013 Document Control Desk Director, Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Subject:
Duke Energy Carolinas, LLC Oconee Nuclear Station, Units 1, 2, and 3 Renewed Operating Licenses: DPR-38, DPR-47, and DPR-55 Docket Numbers: 50-269, 50-270, and 50-287 Registration for Use of General License Spent Fuel Cask Number 127 In accordance with 10CFR72.212 (b)(2), Duke Energy Carolinas, LLC, hereby notifies the Commission of storage of dry fuel under Cask Certificate of Compliance 72-1004, Amendment 9. The date of storage was February 24, 2013, and the cask load number was 127. The cask model is the Standardized NUHOMS 24PHB and the dry storage canister identification number is ONS-24PHBL-HZ127. The physical storage location at Oconee Nuclear Station's Independent Spent Fuel Storage Installation is Module W-67.
If there are any questions regarding this registration, please contact Stephen C. Newman, Oconee Regulatory Affairs Group, at (864) 873-4388.
Sincerely, T. Preston Gillespie. Jr.,
Vice President, Oconee Nuclear Station wun4 5502-www. duke-energy, corn
U. S. Nuclear Regulatory Commission March 11, 2013 Page 2 cc:
Mr. John P. Boska, Project Manager (by electronic distribution)
U.S. Nuclear Regulatory Commission One White Flint North, M/S O-8G9A 11555 Rockville Pike Rockville, MD 20852-2746
[Information Only]
C. Haney, Director Office of Nuclear Material Safety and Safeguards U. S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop EBB 1 Rockville, MD 20852-2738 M. D. Waters, Chief - Licensing Branch Office of Nuclear Material Safety and Safeguards U. S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop E3 D2M Rockville, MD 20852-2738 Mr. Victor M. McCree, Administrator, Region II U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Robert P. Carrion, Division of Reactor Safety U. S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 Cecil A. Fletcher II, Division of Reactor Safety U. S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 NRC Senior Resident Inspector Oconee Nuclear Station