Response to NRC Question Regarding Flood Modification Implementation Timeline
ML12354A217
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 12/14/2012
From: Gillespie T
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
TAC ME7970, TAC ME7971, TAC ME7972
Download: ML12354A217 (4)


Text

Duke T.

PRESTON GILLESPIE, Jr.

Vice President Oconee Nuclear Station Duke Energy ON01 VP / 7800 Rochester Hwy.

Seneca, SC 29672 864-873-4478 864-873-4208 fax T. Gillespie@duke-energy. com December 14, 2012 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852

Subject:

Duke Energy Carolinas, LLC (Duke Energy)

Oconee Nuclear Station (ONS), Units 1, 2, and 3 Renewed Facility Operating License Numbers DPR-38, DPR-47, and DPR-55; Docket Numbers 50-269, 50-270, and 50-287; Response to NRC Question Regarding Flood Modification Implementation Timeline

References:

1. Nuclear Regulatory Commission (NRC) letter from Michele Evans to Preston Gillespie (Duke Energy), Oconee Nuclear Station, Units 1, 2, and 3 - Modifications to Address External Flooding Hazards, (TAC Nos. ME7970, ME7971, and ME7972), dated September 20, 2012
2. Nuclear Regulatory Commission (NRC) letter from Luis Reyes to Dave Baxter (Duke Energy), Confirmatory Action Letter - Oconee Nuclear Station, Units 1, 2, and 3 Commitments to address external Flooding Concerns, dated June 22, 2010
3. Duke Energy letter from T. Preston Gillespie to Victor McCree (Nuclear Regulatory Commission), Response to Requests for Additional Information Regarding Necessary Modifications to Enhance the Capability of the ONS Site to Withstand the Postulated Failure of the Jocassee Dam, dated October 17, 2011
4. Safety Evaluation by the Office of Nuclear Reactor Regulation Related to Duke Energy Carolinas, LLC, Confirmatory Action Letter - Commitments to Address External Flooding Concerns, Closure of Inundation Site Results, Oconee Nuclear Station Units 1, 2, and 3 (ONS), dated January 28, 2011 By letter dated September 20, 2012 (Ref. 1), the NRC informed Duke Energy that the Confirmatory Action Letter (CAL) dated June 22, 2010 (Ref 2) will remain active until it can be superseded by regulatory action related to the Fukushima responses. In the same letter, Duke Energy was informed that the NRC's acceptance of the Federal Energy Regulatory Commission (FERC) standards initiates the timeline to have flood modifications installed in A od www. duke-energy. corn

This letter contains security sensitive information Withhold from Public Disclosure under 10CFR 2.390(d)(1)

U.S. Nuclear Regulatory Commission December 14, 2012 Page 2 30 months plus the regulatory review period, which was committed in the Duke Energy letter dated October 17, 2011 (Ref. 3).

The NRC requested that it be advised of Duke Energy's preference as to whether to initiate the timeline now (September 20, 2012) or following the submission of the Flooding Hazard evaluation report.

In response to this request, Duke Energy prefers to initiate the timeline following the NRC approval of the Fukushima Flooding Hazard evaluation report and as requested, will submit the new flood modification design to the NRC and FERC concurrently.

Duke Energy is required to submit the ONS Fukushima Flooding Hazard evaluation report by March 12, 2013 to comply with the NRC 10 CFR 50.54(f Request for Information Regarding Recommendations 2.1, 2.4 and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident. Duke Energy understands that the submission and subsequent NRC approval of the Fukushima Flooding Hazard Report will supersede the current January 28, 2011 Safety Evaluation that addressed external flooding concerns at Oconee Nuclear Station (Ref. 4).

This letter contains no regulatory commitments.

Since this letter contains Security Sensitive information, Duke Energy hereby requests the NRC to withhold it from public disclosure pursuant to 10 CFR 2.390(d)(1), "Public inspections, exemptions, requests for withholding."

Should you have any questions regarding this submittal or require additional information, please contact David Haile of the ONS Regulatory Affairs Group, at (864) 873-4742.

I declare under penalty of perjury that the foregoing is true and correct. Executed on December 14, 2012.

Sincerely, T. Preston Gillespie, Jr.

Vice President Oconee Nuclear Station

This letter contains security sensitive information Withhold from Public Disclosure under 10CFR 2.390(d)(1)

U.S. Nuclear Regulatory Commission December 14, 2012 Page 3 xc:

Mr. Victor McCree, Regional Administrator U. S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257 Mr. John P. Boska, Project Manager (ONS)

(By electronic mail only)

U. S. Nuclear Regulatory Commission One White Flint North, M/S O-8G9A 11555 Rockville Pike Rockville, MD 20852 Senior Resident Inspector Oconee Nuclear Site