Letter Sequence Withdrawal |
---|
TAC:ME0274, Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors (Approved, Closed) TAC:ME0278, Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors (Approved, Closed) |
Results
Other: 3F1109-06, State of Florida Department of Environmental Protection, Conditions of Certification, 3F1209-04, Response to Follow-up to Progress Energy RAI Responses on CR-3 SAMA Evaluation, ML090090233, ML090210171, ML090350657, ML090420362, ML090780840, ML091200415, ML091660559, ML091820465, ML092600889, ML092610309, ML093200023, ML093520079, ML100050166, ML100980517, ML100980519, ML100980520, ML100980523, ML100980524, ML100980525, ML100980526, ML100980528, ML101110235, ML101320401, ML101460577, ML110250183, ML110410597, ML110460629, ML110820185, ML110880294, ML11137A009, ML11140A100, ML11180A275, ML11343A639, ML12117A260, ML12213A058, ML12346A011
|
MONTHYEARHNP-09-016, Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Recombiners and Hydrogen Monitors2009-02-26026 February 2009 Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Recombiners and Hydrogen Monitors Project stage: Request ML0902101712009-02-27027 February 2009 Notice of Opportunity for Hearing Regarding Renewal of Facility Operating License No. DPR-72 for an Additional 20-year Period Florida Power Corporation Corporation Crystal River Unit 3 Nuclear Generating Plant Docket No. 50-302 Project stage: Other ML0900902332009-02-27027 February 2009 Determination of Acceptability and Sufficiency for Docketing, and Opportunity for a Hearing Regarding the Application from Florida Power Corp., for Renewal of the Operating License for Crystal River Unit 3 Nuclear Generating Plant Project stage: Other ML0907808402009-03-31031 March 2009 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for License Renewal for the Crystal River Unit 3 Nuclear Generating Plant (TAC No ME0278) FRN Project stage: Other ML0903506572009-03-31031 March 2009 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for License Renewal for the Crystal River Unit 3 Nuclear Generating Plant Project stage: Other ML0908501762009-04-20020 April 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0913800232009-05-11011 May 2009 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML0912004152009-05-22022 May 2009 Proposed Review Schedule Regarding the Application from Florida Power Corporation for Renewal of the Operating License for Crystal River Unit 3 Nuclear Generating Plant Project stage: Other ML1013204012009-05-31031 May 2009 093-89529, Environmental Support Document South Cooling Tower Laydown Area Citrus County, Florida Project stage: Other ML0904203622009-06-10010 June 2009 Nuclear Generating Plant License Renewal Review Project stage: Other ML0915900062009-07-0202 July 2009 License Amendment, Adoption of Technical Specifications Taskforce (TSTF) Standard Technical Specification Change Traveler TSTF-447, Elimination of Hydrogen Recombiners & Change to Hydrogen & Oxygen Monitors. Project stage: Acceptance Review ML0918204652009-07-0808 July 2009 Plan for the Aging Management Program Regulatory Audit Regarding the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Review Project stage: Other ML0916605592009-07-30030 July 2009 Audit Report Regarding the LRA for the Crystal River, Unit 3 Project stage: Other ML0917400702009-08-0303 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0919700682009-08-10010 August 2009 Request for Additional Information Regarding Severe Accident Mitigation Alternatives for Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0920302082009-08-14014 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0920800452009-08-14014 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0920200122009-08-20020 August 2009 RAI, License Renewal Application Project stage: RAI ML0922507012009-08-20020 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI 3F1109-06, State of Florida Department of Environmental Protection, Conditions of Certification2009-08-28028 August 2009 State of Florida Department of Environmental Protection, Conditions of Certification Project stage: Other ML0923300072009-08-31031 August 2009 RAI for the Review of the Crystal River Unit 3 Nuclear Generating Plant, LRA Project stage: RAI ML0923303432009-08-31031 August 2009 Nuclear Generating Plant, RAI, License Renewal Application Project stage: RAI ML0923308312009-08-31031 August 2009 Request for Additional Information Regarding License Renewal Application Project stage: RAI ML0923309042009-09-0202 September 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0925800952009-09-11011 September 2009 Response to Requests for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC No. ME0274) and Amendment #2 Project stage: Response to RAI ML0921602132009-09-11011 September 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0926008882009-09-11011 September 2009 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML0926008892009-09-11011 September 2009 Areva Np, Inc., 51-9057252-001, Rev. 1, CR3 Reconciliation of 60-Year Fluence Projections Used in Reactor Vessel Beltline Embrittlement Calculations for License Renewal, Enclosure Attachment 3 Project stage: Other ML0926502722009-09-18018 September 2009 Response to Requests for Additional Information for the Review of the License Renewal Application and Amendment #3 Project stage: Response to RAI ML0923706692009-09-22022 September 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Unit Plant, License Renewal Application Project stage: RAI ML0926103092009-09-29029 September 2009 Scoping and Screening Audit Report Regarding the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: Other ML0927901502009-09-30030 September 2009 Response to Requests for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC ME0274) and Amendment #4 Project stage: Response to RAI ML0927901542009-10-0202 October 2009 Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application (TAC No. ME0274) - Sections B.2.37-1, 3.3.2.2, and XI.S8 Project stage: Response to RAI 3F1009-03, Response to Request for Additional Information Regarding Severe Accident Mitigation Alternatives2009-10-0909 October 2009 Response to Request for Additional Information Regarding Severe Accident Mitigation Alternatives Project stage: Response to RAI ML0928901552009-10-13013 October 2009 Response to Request for Additional Information for the Review of Unit 3 Nuclear Generating Plant License Renewal Application and Amendment #5 Project stage: Response to RAI ML0926405542009-10-15015 October 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0930005052009-10-22022 October 2009 Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application (TAC No. ME0274) - and Amendment #6 Project stage: Response to RAI ML0929606602009-10-27027 October 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0929403222009-11-0303 November 2009 Request for Additional Information for the Review of the Crystal River, Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML1009805172009-11-0505 November 2009 License Renewal Revised Environmental Site Audit Needs List Hydrology (Additional Reference 8 Through 16) Project stage: Other ML1009805192009-11-0505 November 2009 Nuclear Generating Plant License Renewal, Revised Environmental Site Audit Needs List, Air, Meteorology, Climate Project stage: Other ML1009805282009-11-0505 November 2009 License Renewal Revised Environmental Site Audit Needs List, Non-Radiological Waste Radiation Protection, Socioeconomics Terrestrial Ecology Project stage: Other ML0931704872009-11-0505 November 2009 Response to Request for Additional Information Re Review of License Renewal Application for Environmental Review Project stage: Response to RAI ML1009805202009-11-0505 November 2009 License Renewal Environmental Site Audit Needs List, Aquatic Ecology (Except AQ-3), Archaeology Project stage: Other ML1009805232009-11-0505 November 2009 License Renewal Environmental Site Audit Needs List, Aquatic Ecology, Additional References, Through AR-3, Page 7 Project stage: Other ML1009805242009-11-0505 November 2009 License Renewal Revised Environmental Site Audit Needs List, Aquatic Ecology AQ-3 Project stage: Other ML1009805182009-11-0505 November 2009 Response to Request for Additional Information Regarding the Review of the License Renewal Application - Revised Environmental Site Audit Needs List Project stage: Response to RAI ML1009805252009-11-0505 November 2009 Plant Operating Manual AI-571, Sea Turtle Rescue and Handling Guidance Project stage: Other ML1009805262009-11-0505 November 2009 License Renewal Revised Environmental Site Audit Needs List, Hydrology (Through Additional Reference 6) Project stage: Other ML1011102352009-11-0505 November 2009 License Renewal Environmental Site Audit Needs List, Aquatic Ecology, AR-3 Page 8 Through AR-6 Project stage: Other 2009-06-10
[Table View] |
|
---|
Category:Federal Register Notice
MONTHYEARML24226B2092024-08-29029 August 2024 Federal Register Notice - Crystal River, Unit 3 Application Withdrawal - LTP Requirements ML24176A2222024-07-12012 July 2024 FRN and Fonsi ML23304A1572023-11-0202 November 2023 Federal Register Notice of Crystal River LTP Public Meeting ML21159A0522021-06-29029 June 2021 VY and CR Indirect License Transfer Order FRN ML21064A1392021-03-29029 March 2021 Nuclear Generating Plant (License DPR-72, Docket Nos. 50-302 and 72-1035) - Notice of Consideration, Request for Indirect License Transfer ML19248C1412019-10-0808 October 2019 FRN Notice of Consideration, Crystal River License Transfer Request ML19140A4562019-05-28028 May 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 06/04/2019 ML18173A1792018-08-0707 August 2018 OEDO-17-00070 - Notice of Issuance of Director'S Decision, 2.206 Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and Japan C NRC-2018-0140, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/20182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML18180A2182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML16355A2612016-12-21021 December 2016 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations; Publication Date: January 3, 2017 NRC-2016-0273, Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations; Publication Date: January 3, 20172016-12-21021 December 2016 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations; Publication Date: January 3, 2017 ML16273A4502016-11-30030 November 2016 Exemption from Record Keeping Requirements NRC-2016-0253, Exemption from Record Keeping Requirements2016-11-30030 November 2016 Exemption from Record Keeping Requirements ML16173A0242016-09-0101 September 2016 Order Approving Transfer of License, Crystal River, Unit 3 NRC-2016-0161, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 20162016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 ML16215A2272016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 ML16084A8912016-03-31031 March 2016 Replacement FRN - Exemption from 10 CFR 50.54(w) (1) for Crystal River, Unit 3 - Federal Register Notice ML16020A4632016-03-16016 March 2016 Exemption from 10 CFR 50.54(w)(1) for Crystal River, Unit 3 - Federal Register notice ML15356A5992015-12-29029 December 2015 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 5, 2016 ML15238B4952015-12-23023 December 2015 FRN Consideration NRC-2011-0024, Crystal River FRN Consideration2015-12-23023 December 2015 Crystal River FRN Consideration ML15121A5982015-05-29029 May 2015 Nuclear Generating Plant - FRN Order Approving Transfer of Licenses and Conforming Amendment ML15146A2912015-05-29029 May 2015 Nuclear Generating Plant - Order Approving Transfer of License and Conforming Amendment ML15121A5702015-05-29029 May 2015 Letter, Safety Evaluation for Order Approving Transfer of Licenses and Conforming Amendments ML14183B3382015-04-27027 April 2015 LTR Exemption from Requirements of 10 CFR 140.11(a)(4), to Allow Reduction in Offsite Primary Liability Insurance and Withdrawal from Participation in Secondary Retrospective Premium Pool for Deferred Premium Charges NRC-2015-0115, FRN, Exemption from Requirements of 10 CFR 140.11(a)(4), to Allow Reduction in Offsite Primary Liability Insurance and Withdrawal from Participation in Secondary Retrospective Premium Pool for Deferred Premium Charges2015-04-27027 April 2015 FRN, Exemption from Requirements of 10 CFR 140.11(a)(4), to Allow Reduction in Offsite Primary Liability Insurance and Withdrawal from Participation in Secondary Retrospective Premium Pool for Deferred Premium Charges ML14183B4772015-04-27027 April 2015 FRN, Exemption from Requirements of 10 CFR 140.11(a)(4), to Allow Reduction in Offsite Primary Liability Insurance and Withdrawal from Participation in Secondary Retrospective Premium Pool for Deferred Premium Charges ML15111A3802015-04-22022 April 2015 Nuclear Generating Plant - Notice of Consideration of Approval of Application for Proposed Merger of Facility Operating License and Conforming Amendment, and Opportunity for a Hearing ML15111A4552015-04-22022 April 2015 Nuclear Generating Plant - Letter and Notice of Consideration of Approval of Application for Proposed Merger of Facility Operating License and Conforming Amendment, and Opportunity for a Hearing NRC-2015-0042, Nuclear Generating Plant - FRN for Exemptions on Emergency Plan and Emergency Action Level Scheme.2015-03-30030 March 2015 Nuclear Generating Plant - FRN for Exemptions on Emergency Plan and Emergency Action Level Scheme. ML15058A9062015-03-30030 March 2015 Letter, Exemptions from Certain Emergency Planning Requirements and Related Safety Evaluation ML15040A0902015-03-30030 March 2015 Nuclear Generating Plant - FRN for Exemptions on Emergency Plan and Emergency Action Level Scheme. ML15013A1812015-02-23023 February 2015 Letter with Environmental Assessment and Finding of No Significant Impact Related to Request for Exemptions from Certain Emergency Planning Requirements ML15013A1732015-02-23023 February 2015 Environmental Assessment and Finding of No Significant Impact Exemptions from Certain Emergency Planning Requirements ML14247A5452015-01-26026 January 2015 Letter, Exemption from the Requirements of 10 CFR Sections 50.75 Related to Use of the Decommissioning Trust Fund for Irradiated Fuel Management and Site Restoration NRC-2015-0010, Crystal River Unit - FRN, Exemption from the Requirements of 10 CFR Sections 50.82 and 50.75 Related to Use of the Decommissioning Trust Fund for Irradiated Fuel Management and Site Restoration2015-01-26026 January 2015 Crystal River Unit - FRN, Exemption from the Requirements of 10 CFR Sections 50.82 and 50.75 Related to Use of the Decommissioning Trust Fund for Irradiated Fuel Management and Site Restoration ML14247A5582015-01-26026 January 2015 Unit - FRN, Exemption from the Requirements of 10 CFR Sections 50.82 and 50.75 Related to Use of the Decommissioning Trust Fund for Irradiated Fuel Management and Site Restoration ML14246A2132015-01-15015 January 2015 FRN, Finding of No Significant Impact and Associated Environmental Assessment Related to Use of the Decommissioning Trust Fund for Irradiated Fuel Management and Site Restoration ML14246A1982015-01-14014 January 2015 Letter, Finding of No Significant Impact and Associated Environmental Assessment Related to Use of the Decommissioning Trust Fund for Irradiated Fuel Management and Site Restoration ML14176B0862014-12-0909 December 2014 Nuclear Generating Plant - FRN, Exemption from Requirements of 10 CFR 73.55(p)(1)(i) and (II) Related to Suspension of Security Measures in an Emergency or During Severe Weather NRC-2014-0266, Nuclear Generating Plant - FRN, Exemption from Requirements of 10 CFR 73.55(p)(1)(i) and (Ii) Related to Suspension of Security Measures in an Emergency or During Severe Weather2014-12-0909 December 2014 Nuclear Generating Plant - FRN, Exemption from Requirements of 10 CFR 73.55(p)(1)(i) and (Ii) Related to Suspension of Security Measures in an Emergency or During Severe Weather ML14205A3142014-07-28028 July 2014 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations- Published July 22, 2014 NRC-2010-0096, G20090690/EDATS:OEDO-2009-0758/Notice of Issuance of Director'S Decision, 2.206 - Enforcement Action Against the Progress Energy Company, Crystal River Nuclear Plant2014-05-0606 May 2014 G20090690/EDATS:OEDO-2009-0758/Notice of Issuance of Director'S Decision, 2.206 - Enforcement Action Against the Progress Energy Company, Crystal River Nuclear Plant ML14097A2202014-05-0606 May 2014 G20090690/EDATS:OEDO-2009-0758/Notice of Issuance of Director'S Decision, 2.206 - Enforcement Action Against the Progress Energy Company, Crystal River Nuclear Plant ML14099A2172014-04-28028 April 2014 FRN on Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI ML13339A6642013-12-22022 December 2013 Nuclear Generating Plant - Federal Register Notice for Post Shutdown Activity Report ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit NRC-2011-0301, Federal Register Notice - Withdrawal of an Amendment Request2013-03-0707 March 2013 Federal Register Notice - Withdrawal of an Amendment Request ML13063A5272013-03-0707 March 2013 Federal Register Notice - Withdrawal of an Amendment Request 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000302/20240012024-09-23023 September 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, NRC Inspection Report No. 05000302/2024001 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24226B2392024-08-27027 August 2024 Application for License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Acknowledgement of Withdrawal ML24179A0702024-07-26026 July 2024 SHPO S106 Completion Crystal River Unit 3 ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commissions Analysis of ADP CR3, LLCs Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan 2024-09-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 February 28, 2013 Mr. Jon A. Franke Vice President Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428
SUBJECT:
CRYSTAL RIVER NUCLEAR PLANT, UNIT 3 - WITHDRAWAL OF APPLICATION FOR RENEWED OPERATING LICENSE (TAC NOS. ME0274 AND ME0278)
Dear Mr. Franke:
By letter dated December 16, 2008, Florida Power Corporation (FPC or the applicant) submitted a license renewal application (LRA) in accordance with Title 10, Part 54, of the Code of Federal Regulations, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," to the U.S. Nuclear Regulatory Commission (NRC or the staff) forCrystal River Nuclear Generating Plant, Unit 3 (CR-3). The applicant requested renewal of the CR-3 operating license (facility operating license number DPR-72) for a period of 20 years beyond the current expiration of midnight, December 3,2016.
The staff completed its "Safety Evaluation Report With Open Items Related to the License Renewal of Crystal River Unit 3 Nuclear Generating Plant" (hereinafter known as the SER), in December 2010 (ADAMS Accession No. ML103490568).
By letter dated February 6,2013, you requested to withdraw the application from NRC review based on your determination to retire CR-3.
Consistent with 10 CFR 54.13(a), "[I]nformation provided to the Commission by an applicant for a renewed license ... must be complete and accurate in all material respects." The staff notes that the SER contains nine open items and two confirmatory items; these items are incomplete in regards to 10 CFR 54.13(a). The staff acknowledges your request to withdraw the application. NRC staff activities on the review have ceased and the associated Technical Assignment Control numbers will be closed by February 28, 2013.
As noted above, the staff's review to date has identified that your application did not provide technical information in sufficient detail to enable the staff to complete its reviews. Therefore, if you decide to re-submit the application, it must include the information identified in our SER.
J. Franke - 2 In accordance with our practice, a Federal Register Notice will be posted regarding this matter.
If you have any questions, please contact the safety project manager, John Daily, at (301) 415-3873 or by email at john.daily@nrc.gov.
. Lubinski, irector Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302 cc: Listserv
February 28, 2013 MEMORANDUM TO: Cindy K. Bladey. Chief Rules, Announcements, and Directives Branch Division of Administrative Services Office of Administration FROM: John Daily, Sr. Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation
SUBJECT:
NOTICE OF WITHDRAWAL FROM DOCKETING OF THE APPLICATION REGARDING RENEWAL OF FACILITY OPERATING LICENSE NUMBER DPR-72 FOR AN ADDITIONAL 20-YEAR PERIOD FOR THE FLORIDA POWER CORPORATION CRYSTAL RIVER NUCLEAR GENERATING PLANT, UNIT 3 (DOCKET NO. 50-302)
Enclosed please find one copy of the supject Federal Register Notice (FRN) for transmittal to the Office of Federal Register for publication.
The Office of Administration, Division of Administrative Services, Rules, Announcements, and Directives Branch (ADM/DAS/RDB) has been given owner's rights to the notice in Agencywide Documents Access and Management System (ADAMS) No. ML13052A655. Publicly available NRC documents referenced in the notice have been finalized in ADAMS and profiled for public release. ADAMS accession numbers for all such documents are provided in the text of the notice.
Copies of this notice and the document(s) being made available to the public have been forwarded to the Office of Information Services (OIS) staff at WEBWORK.Resource@nrc.govfor posting to the NRC public Web site.
Information about this license action has been forwarded to the OIS staff at WEBWORK.Resource@nrc.gov for posting to the NRC public Web site.
Docket No. 50-302 License No. DPR-72
Enclosure:
FRN CONTACT: John Daily, NRR/DLR/RPB1 (301) 415-3873
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-302; NRC-2013-XXXX]
Crystal River Nuclear Generating Plant, Unit 3 Application for Renewal of License to Facility Notice of Withdrawal AGENCY: Nuclear Regulatory Commission, ACTION: License Renewal Application; Withdrawal.
ADDRESSES: Please refer to Docket ID <NRC-201 when contacting the NRC about the availability of information regarding this document. You may access information related to this document, which the NRC possesses and are publicly available, using any of the following methods:
- Federal rulemaking Web site: Go to http://www,regulations,gov and search for Docket ID <NRC-2013-XXXX>, Address questions about NRC dockets to Carol Gallagher; telephone: 301-492-3668; e-mail: CaroI.Galiagher@nrc,gov.
- NRC's Agencywide Documents Access and Management System (ADAMS):
You may access publicly available documents online in the NRC Library at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select "ADAMS Public Documents" and then select "Begin Web-based ADAMS Search," For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or bye-mail to pdr,resource@nrc,gov. The ADAMS accession number for each
-2 document referenced in this notice (if that document is available in ADAMS) is provided the first time that a document is referenced.
- NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room 01-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: John Daily, Senior Project Manager, Projects Branch 1, Division of License Renewal, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, PC 20555; telephone: 301-415-3873; e-mail:
John.Daily@nrc.gov.
SUPPLEMENTARY INFORMATION:
The U.S. Nuclear Regulatory Commission (NRC or the Commission) grants the Florida Power Corporation request to withdraw its application for the renewal of operating license DPR-72, which authorizes Florida Power Corporaton (FPC) to operate the Crystal River Nuclear Generating Plant, Unit 3 (CR3), at 2609 megawatts thermal. FPC stated its decision to withdraw the application is based upon a determination to retire CR3. CR3 is located near Crystal River, FL; the current operating license for CR3 expires on December 3, 2016.
FPC submitted the license renewal application (LRA) by letter dated December 16, 2008, pursuant to Title 10, Part 54, of the Code of Federal Regulations (10 CFR Part 54), to renew operating license DPR-72 for CR3 (ADAMS Accession No. ML090080053). The Commission had previously noticed the acceptance of the application in the Federal Register on March 9, 2009 (74 FR 10099). FPC requested withdrawal of the application by letter dated
- 3 February 6, 2013, based on its determination to retire CR3 (ADAMS Accession No. ML13043A028).
The NRC staff completed its "Safety Evaluation Report With Open Items Related to the License Renewal of Crystal River Unit 3 Nuclear Generating Plant" (hereinafter known as the SER) in December 2010 (ADAMS Accession No. ML103490568). Consistent with 10 CFR 54.13(a), "[I]nformation provided to the Commission by an applicant for a renewed license ... must be complete and accurate in all material respects." The staff noted that the SER contains nine open items and two confirmatory items; these items are incomplete in regards to 10 CFR 54.13(a). Since the staff's review to date has identified that FPC's application did not provide technical information in sufficient detail to enable the staff to complete its reviews, if FPC decides to re-submit the application, it must include this technical information in sufficient detail to allow the staff to continue its evaluations.
The staff also issued a Notice of Issuance for the draft supplemental environmental impact statement (DSEIS) related to the proposed license renewal, which was published in the Federal Register on June 3, 2011 (76 FR 32237). However, since the licensee has withdrawn its application, all comments received on the DSEIS and all of the above Federal Register Notices need not be and will not be resolved.
For further details with respect to this action, see the LRA dated December 16, 2008, and the licensee's letter of withdrawal dated February 6,2013.
th Dated at Rockville, Maryland, this 28 day of FebruaJ 2013.
For the NUctefu. Regulatory Commission.
//~/.
, ski, Director, Di Ision of Li se Renewal, Office of Nuclear Reactor Regulation.
J. Franke - 2 In accordance with our practice, a Federal Register Notice will be posted regarding this matter.
If you have any questions, please contact the safety project manager, John Daily, at (301) 415-3873 or by email at john.daily@nrc.gov.
Sincerely, IRA!
John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302 cc: Listserv ADAMS Accession Nos. ML13052A667 (Package)
ML13052A606 (Incoming)
ML13052A655 (FRN)
ML13052A658 (Memo) *concurred via email DLRI DLRlRPB1/BC DLRI OFFICE DLR/LA RPB1/PM RPB2/BC OGC NLO* DLR/RPB 1/PM NAME IKing JDaily DMorey DWrona LSubin I ~IDaily DATE 2122/13 2/26/13 2/28/13 2/28/13 2/28/13 2/28/13 OFFICIAL RECORD COpy
Letter to J. Franke from J. Lubinski, dated February 28, 2013
SUBJECT:
CRYSTAL RIVER NUCLEAR PLANT, UNIT 3 - WITHDRAWAL OF APPLICATION FOR RENEWED OPERATING LICENSE (TAC NOS. ME0274 AND ME0278)
DISTRIBUTION:
HARD COPY:
DLR R/F E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsOgcMailCenter Resource
..IDaily EKeegan FSaba, DORL AJones,OGC DMclntyre, OPA LLake, RII RReyes, RII TMorrisey, RII