Notification of Inspection and Request for Information
ML12233A635
Person / Time
Site: Harris Duke energy icon.png
Issue date: 08/16/2012
From: Vias S
NRC/RGN-II/DRS/EB3
To: Hamrick G
Carolina Power & Light Co
References
Download: ML12233A635 (8)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 August 16, 2012 Mr. George T. Hamrick Vice President Shearon Harris Nuclear Power Plant Carolina Power and Light Company P.O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

SUBJECT:

SHEARON HARRIS NUCLEAR PLANT - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Hamrick:

On October 22, 2012, the Nuclear Regulatory Commission (NRC) will begin inspection activities for Shearon Harris Nuclear Plant at the NRC Region II office in Atlanta, GA., in accordance with Temporary Instruction (TI) 2515-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks. This in-office inspection is scheduled to be performed from October 22 to October 23, 2012, and will address the inspection requirements for Phase 1 of this TI.

In order to minimize the impact to your on-site resources, and to ensure a productive inspection, we have enclosed a list of documents needed for the preparation and implementation of this inspection. The documents that are requested for this inspection include all relevant documents that will allow the inspector(s) to adequately complete Phase 1 of this inspection.

We have discussed the schedule for this inspection activity with your staff and understand that our licensing contact for this inspection will be Mr. John Doorhy of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector Cecil Fletcher at 404-997-4402 or Cecil.Fletcher@nrc.gov.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its Enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide

G. Hamrick 2 Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/ adams.html (the Public Electronic Reading Room).

Sincerely,

/RA: J. Rivera-Ortiz for/

Steven J. Vias, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 50-400 License No. NPF-63

Enclosure:

Temporary Instruction (TI 2515-182) Inspection Document Request cc w/encl: (See page 3)

_________________________ xG SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE RA RA NAME FLETCHER VIAS DATE 8/16/2012 8/16/2012 8/ /2012 8/ /2012 8/ /2012 8/ /2012 8/ /2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO G. Hamrick 3 cc w/encl: David H. Corlett Brian Bernard Supervisor Manager, Nuclear Services and EP Licensing/Regulatory Programs Nuclear Protective Services Progress Energy Shearon Harris Nuclear Power Plant Electronic Mail Distribution Electronic Mail Distribution David T. Conley Brian C. McCabe Senior Counsel Manager, Nuclear Oversight Legal Department Shearon Harris Nuclear Power Plant Progress Energy Progress Energy Electronic Mail Distribution Electronic Mail Distribution Donna B. Alexander George T. Hamrick Manager, Nuclear Regulatory Affairs Vice President (interim)

Carolina Power and Light Company Progress Energy Shearon Harris Nuclear Power Plant Electronic Mail Distribution Electronic Mail Distribution John H. O'Neill, Jr.

Lara S. Nichols Shaw, Pittman, Potts & Trowbridge Deputy General Counsel 2300 N. Street, NW Duke Energy Corporation Washington, DC 20037-1128 Electronic Mail Distribution Joseph W. Donahue M. Christopher Nolan Vice President Director - Regulatory Affairs Nuclear Oversight Duke Energy Carolinas, LLC Progress Energy Electronic Mail Distribution Electronic Mail Distribution Robert J. Duncan II W. Lee Cox, III Senior Vice President Section Chief Progress Energy Radiation Protection Section Electronic Mail Distribution N.C. Department of Environmental Commerce & Natural Resources Sean T. O'Connor Electronic Mail Distribution Manager, Support Services Shearon Harris Nuclear Power Plant Public Service Commission Electronic Mail Distribution State of South Carolina P.O. Box 11649 Donald L. Griffith Columbia, SC 29211 Training Manager Shearon Harris Nuclear Power Plant Chairman Progress Energy North Carolina Utilities Commission Electronic Mail Distribution Electronic Mail Distribution R. Keith Holbrook Manager, Support Services Shearon Harris Nuclear Power Plant (cc w/encl contd - See page 4)

Electronic Mail Distribution

G. Hamrick 4 (cc w/encl contd)

Terrence E. Slake Manager Nuclear Plant Security Shearon Harris Nuclear Power Plant Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Chair Board of County Commissioners of Wake County P.O. Box 550 Raleigh, NC 27602 Ernest J. Kapopoulos Jr.

Plant General Manager Carolina Power and Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Chair Board of County Commissioners of Chatham County P.O. Box 1809 Pittsboro, NC 27312 Senior Resident Inspector U.S. Nuclear Regulatory Commission Shearon Harris Nuclear Power Plant U.S. NRC 5421 Shearon Harris Rd New Hill, NC 27562-9998

G. Hamrick 5 Letter to George T. Hamrick from Steven J. Vias dated August 16, 2012.

SUBJECT:

SHEARON HARRIS NUCLEAR PLANT - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION Distribution w/encl:

RIDSNRRDIRS PUBLIC RidsNrrPMShearonHarris Resource

TI 2515-182 INSPECTION DOCUMENT REQUEST Inspection Dates: October 22 - 23, 2012 Inspection Procedures: TI 2515-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks Inspector: Cecil Fletcher, Senior Reactor Inspector Information Requested for the Preparation and Completion of the In-Office Inspection

1. The following documents listed below are requested (electronic copy or CD ROM if possible) by October 12, 2012, to facilitate the preparation for the inspection.

A. Site point(s) of contact responsible for the implementation of the underground piping and tanks program; and B. Schedule for completion of the following NEI 09-14, Guideline For The Management of Underground Piping and Tank Integrity, Revision 1, attributes:

Buried Piping

  • Procedures and Oversight
  • Risk Ranking
  • Inspection Plan
  • Plan Implementation
  • Asset Management Plan Underground Piping and Tanks
  • Procedures and Oversight
  • Prioritization
  • Condition Assessment Plan
  • Plan Implementation
  • Asset Management Plan C. Copy of Site Underground Piping and Tanks Program.

D. Self or third party assessments of the Underground Piping and Tanks Program (if any have been performed).

Enclosure

2 E. For any of the NEI 09-14, Revision 1, or subsequent revision attributes identified below which have been completed prior to the NRCs Phase 1 inspection, provide written records that demonstrate that the program attribute is complete.

Buried Piping

  • Procedures and Oversight
  • Risk Ranking
  • Inspection Plan
  • Plan Implementation
  • Asset Management Plan Underground Piping and Tanks
  • Procedures and Oversight
  • Prioritization
  • Condition Assessment Plan
  • Plan Implementation
  • Asset Management Plan Enclosure