WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]
Sent: Monday, August 06, 2012 8:25 AM To: Poole, Justin; Bryan, Robert H Jr Cc: Boyd, Desiree L; Templeton, Pamela J Attachments: 2012-08 WBN Project Plan - Unit 2.pdf Please see attached for todays 9:15 phone call.
Thank you,
~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764 1
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 722 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF307AACC0)
Subject:
Sent Date: 8/6/2012 8:25:22 AM Received Date: 8/6/2012 8:25:29 AM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients:
"Boyd, Desiree L" <dlboyd@tva.gov>
Tracking Status: None "Templeton, Pamela J" <pjtempleton@tva.gov>
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>
Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 255 8/6/2012 8:25:29 AM 2012-08 WBN Project Plan - Unit 2.pdf 219934 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:
Recipients Received:
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 2 of 39 I. SUBMITTAL LOOK-AHEAD Item No. Description Resp. Person Due Date License Amendments / Technical Specifications
- 1. Common Service Station Transformer (CSST) A & B Credit Shea October 12, 2012
- 3. U2 Hydrology FSAR & TS Update Stockton August 26, 2012 SSER Open Item 32:
- 4. Hilmes January 13, 2013 Revise Diesel Generator Frequency Allowable Value. [Commitment 113676066]
SSER Appendix HH Open Items (requiring submittal)
SSER Open Item 1:
Following completion of cable pulls, submit letter to NRC either:
- 1.
- Affirming no power assisted cable pulls were made, or Hilmes TBD
- Documenting any power assisted cable pulls.
[Commitment 113676047]
SSER Open Item 13:
- 2. Submit an ASME Section XI Inservice Test Program for the first ten year interval McDonald / Crouch March 2014 six months before receiving an Operating License. [Commitment NCO080008033:
Item 017 of Enclosure 2 of letter T90 080128 001]
SSER Open Item 25:
- 3. Submit documentation of liability insurance coverage pursuant to 10 CFR 140.11(a)(4). Arent June 2014
[Commitment 113676162]
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 3 of 39 Item No. Description Resp. Person Due Date SSER Open Item 37:
- 4. Submit changes to the Emergency Plan (REP) prior to fuel load. Detchemendy June 2014
[Commitment 111032952]
SSER Open Item 41:
- 5. Update Plant design displays & dose assessment models to provide two unit capability. Hilmes / Koontz December 2013
[Commitment 111033086]
SSER Open Item 43:
- 6. Submit Emergency Plan implementing procedures no less than 180 days before schedule Detchemendy TBD issuance of Operating License. [Commitment ____________]
SSER Open Item 61:
- 7. Fuel Thermal Conductivity Degradation Model (PAD Code) - Note: currently this is a Koontz October 26, 2012 License Condition - tracking PWROG activity to update code. [Commitment 113676152]
SSER Open Item 70:
- 8. McDonald / Crouch September 28, 2012 Submit Pre-Service Inspection program update. [Commitment 113676155]
SSER Open Item 77:
- 9. Provide Electronic Filter Test Results for General Atomic High Range Rad Monitor. Hilmes August 31, 2012
[Commitment 113676079]
SSER Open Item 79:
Perform an EMI survey of the containment high range radiation monitors after they are
- 10. Hilmes March 4, 2014 installed in WBN Unit 2, and submit the results to the NRC within two weeks of the survey being completed. [Commitment 112177753]
SSER Open Item 83:
- 11. Provide Letter verifying completion of data storm test on DCS. Hilmes January 2015
[Commitment 113676093]
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 4 of 39 Item No. Description Resp. Person Due Date SSER Open Item 115:
- 12. Incorporate U1 dose reduction plant changes that 2010 letter said were being done on Unit Arent TBD 2 into FSAR Chapter 12. Engineering to identify change packages showing what is done/planned.
SSER Open Item 117:
- 13. Provide calculational basis for access to vital areas - mission dose and update FSAR. Koontz / Arent August 26, 2012 (Amendment 109) [Commitment 112046729]
SSER Open Item 132:
x Submit letter documenting that plant modifications to add high VCT level alarm to main control room annunciator system have been completed. [Commitment 113111704]
- 14. Arent / Wallace May 24, 2013 x Submit letter documenting that procedure changes associated with limiting the number of operating primary water pumps and isolating potential boron dilution paths have been made. [Commitment 113111704]
SSER Open Item 134:
- 15. Provide resolution of dam stability analysis for Cherokee and Douglas Dams finite element Ray August 31, 2012 analysis.
SSER Open Item 138:
(Amendment 109)
- 16. Bryan August 26, 2012 NRC to verify that the ODCM average annual X/Q & D/Q values have been updated to match the FSAR. [Commitment 113676172]
SSER Open Item 139:
- 17. Include cost benefit analysis in next update to FSAR. (Amend 109) Bryan August 26, 2012
[Commitment 113676181]
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 5 of 39 Item No. Description Resp. Person Due Date Submit a Technical Specification and Bases change package to TVA Licensing to change Table 3.3.3-1, Line item 6 (Reactor Vessel Water Level) to remove the reference to note (g) and bases to show RVLIS as a Type A variable.
- 18. Bryan August 26, 2012 Need calculation WBNO4SG4047 revised PER 488815 [Commitment 113307292]
Submit a FSAR Change Package to TVA Licensing to Amendment 108, Table 7.5-2, Regulatory Guide 1.97 Post Accident Monitoring Variables Lists, will be updated to show RVLIS as a Type A variable.
- 19. Stockton August 26, 2012 Need calculation WBNO4SG4047 revised.
PER 488815 [Commitment 113307350]
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 6 of 39 Item No. Description Resp. Person Due Date Other Submittals
- 1. As-Constructed Fire Protection Report [Commitment 113461862] Hilmes July 2014
- 2. U2 FSAR With As-Constructed Figures [Commitment 112068531] Arent July 2014 Prior to fuel load, a final report will be submitted following certain validation activities as
- 3. Koontz / Enis July 2014 described in the IPEEE Design Report (Enclosure 1). [Commitment 111027893]
TVA will provide the NRC staff an updated [security] classification scheme that reflects
- 4. these changes for WBN Unit 2. [Commitment 111033038: RAI Response 3.r of Reynolds May 2014 Enclosure 2. of Letter T02 100427 001]
- 6. 10 CFR Part 70 License Extension Bryan August 26, 2012
- 7. Two Unit ODCM Woods / Shea September 14, 2012
- 8. As-Constructed PRA Guey / Koontz October 2014
- 9. TMI Commitment Review Letter Licensing January 2014
- 10. Letter to terminate Part 30/40 License after receipt of Part 50 License Licensing January 2015
- 11. ASME Section III N-3 Report Crouch September 2014
- 12. Letter to NRC for notification of Vital Area Boundary Restoration Licensing May 2014
- 13. Unit 2 Completion Letter Licensing December 2014 SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 7 of 39 Item No. Description Resp. Person Due Date Other Submittals
- 14. Fire Protection Report Hilmes / Wiggal September 13, 2012
- 16. Regulatory Framework Update [for status as of 07/31] Elton August 15, 2012 Regional Submittals 1.
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 8 of 39 Item No. Description Resp. Person Due Date Fukushima NRC Order EA-12-049; Mitigating Strategies Order:
Licensees to develop, implement, and maintain guidance and strategies to maintain or restore core
- 1. Williams cooling, containment and SFP cooling capabilities following a beyond-design-basis external event.
Must be implemented in all modes.
NRC Order EA-12-049; Mitigating Strategies Order:
Strategies must be capable of mitigating a simultaneous loss of all alternating current (AC) power and
- 2. Williams loss of normal access to the ultimate heat sink and have adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site.
NRC Order EA-12-049; Mitigating Strategies Order:
Provide reasonable protection for the associated equipment from external events. Such protection
- 3. Williams must demonstrate that there is adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site.
NRC Order EA-12-051; Order:
Licensees to provide instrumentation, able to withstand design-basis natural phenomena and remain
- 4. reliable at temperature, humidity and radiation levels at saturation conditions, to monitor SFP water Hilmes 08/13/2012 level from the control room.
DCN 59683, Spent Fuel Pool Level Indication 10% of package 10 CFR 50.54 F Letter Request for Information:
Licensees to reevaluate the seismic hazards at their sites against current NRC requirements and
- 5. Williams guidance, and if necessary, update the design basis and SSCs important to safety to protect against the updated hazards.
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 9 of 39 Item No. Description Resp. Person Due Date Fukushima 10 CFR 50.54 F Letter Request for Information:
Licensees to reevaluate the flooding hazards at their sites against current NRC requirements and
- 6. Williams guidance, and if necessary, update the design basis and SSCs important to safety to protect against the updated hazards.
10 CFR 50.54 F Letter Request for Information:
- 7. Recommendation 9.3 requires licensees to evaluate communication and staffing needs for multi-unit Williams events.
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 10 of 39 Item No. Description Resp. Person Due Date Waste Confidence
- 1. Follow NRC response to Court Order Vigluicci 10/1/2012 SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 08/06/2012 Page 11 of 39 Item No. Description Resp. Person Due Date Significant New Regulatory Issues New Station Blackout Rule
- 1. Hilmes Ongoing rulemaking 10 CFR 50.46 Rule Change
- 2. Oxidation limits Koontz/Westinghouse Ongoing rulemaking NRC Bulletin 2012-01
- 3. Design Vulnerability in Electric Power Systems Shea 10/25/2012 Fleet Response SOURCE: POD UPDATES, COMMITMENTS