MONTHYEARML24024A0182024-01-24024 January 2024 LTR-23-0216-1 - (E-Mail) Turkey Point Nuclear Plant, Units 3 and 4 - 10 CFR 2.206 Petition -Turkey Point and PWR RPV Embrittlement E-Mail Closure Letter to Petitioner, January 23, 2024 ML24023A0622024-01-10010 January 2024 10 CFR 2.206 Petition - LTR-23-0216-1 - Turkey Point and PWR RPV Embrittlement - E-mail Final Determination Status to Petitioner - 1-10-2024 - L-2023-CRS-0005 IR 05000250/20240102024-01-0505 January 2024 Focused Engineering Inspection 05000250/2024010 and 05000251/2024010 ML23347A0772023-12-13013 December 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Transition to 24-Month Fuel Cycles (L-2023-LLA-00161) ML23341A0602023-12-0707 December 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Exemption Request for Use of Axiom Fuel Cladding (L-2023-LLE-0036) ML23317A3752023-11-0808 November 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Update SFP Criticality Analysis (L-2023-LLA-0142) ML23307A2382023-11-0303 November 2023 10 CFR 2.206 Petition - LTR-23-0216-1 - Initial Assessment; Turkey Point Subsequent License Renewal with Petitioner 11/3/2023 - L-2023-CRS-0005 ML23333A0092023-10-27027 October 2023 Attachment a - NRC Extension of Comment Period-1 ML23265A2692023-09-15015 September 2023 Turkey Point,_Rp Document Request 2023-004 ML23226A0752023-08-14014 August 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23171B0532023-06-20020 June 2023 NRR E-mail Capture - Change in Estimated Review Schedule for Turkey Point Improved Standard Technical Specifications (ITS) LAR (L-2022-LLI-0002) ML23198A0592023-05-22022 May 2023 FPL to Fws, Notification of Doa Crocodile in CCS on 5/22/23 ML23138A0212023-05-17017 May 2023 Telephone Record, Call with Florida Power and Light Regarding Decommissioning Funding Plan Update Dated March 30, 2021 ML23129A8322023-05-0505 May 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23117A2712023-04-11011 April 2023 NRR E-mail Capture - (External_Sender) Updated Data for Doa Turkey Point American Crocodile at 4/10/2023 ML23067A2812023-03-0808 March 2023 NRR E-mail Capture - (External_Sender) Non-causal American Croc Doa Turkey Point ML23038A1892023-02-0303 February 2023 RP RFI April 2023 ML23006A0262023-01-0505 January 2023 NRR E-mail Capture - Audit Plan - Turkey Point Fire Protection Changes to Support RCP Seal Replacement LAR ML22311A4752022-11-0707 November 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - ITS ML22293B6562022-10-18018 October 2022 Request for 45 Day Extension of Comment Period of Turkey Point Subsequent License Renewal Scoping Process, Docket Id NRC-2022-0172 by Natural Resources Defense Council, Miami Waterkeeper and Counsel for Friends of the Earth ML22265A1522022-09-21021 September 2022 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Revise Fire Protection Program (L-2022-LLA-0128) ML22258A1862022-09-15015 September 2022 NRR E-mail Capture - Turkey Point Unit Nos. 3 and 4 - Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Requests to Replace Instrumentation with Digital Systems ML22181A0562022-06-30030 June 2022 NRR E-mail Capture - Request for Additional Information - Turkey Point U3 Sgtir (L-2022-LRO-0070) ML22178A1032022-06-25025 June 2022 NRR E-mail Capture - (External_Sender) Turkey Point Doa American Crocodile 6/25/22 ML22147A0672022-05-19019 May 2022 NRR E-mail Capture - (External_Sender) Turkey Point Doa Crocodile 05/19/2022 ML22095A0162022-04-0505 April 2022 NRR E-mail Capture - Verbal Authorization of Turkey Point Nuclear Plant Unit 3 - Icw Relief Request No. 10-II ML22081A0292022-03-21021 March 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit No. 3 - Request for Additional Information - Icw Alternative ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21302A0052021-12-23023 December 2021 Email to Nextera/Fpl Re Discussion of Availability of Human Factor Validation Information to Support the Planned Turkey Point Digital I&C License Amendment Request ML21307A2882021-11-18018 November 2021 NRC to Fws, Request to Reinitiate Endangered Species Act Section 7 Consultation for Continued Operation of Turkey Point ML21298A0572021-10-25025 October 2021 NRR E-mail Capture - Final: Tpn Request for Additional Information - Round 2 Concerning Relief Request 10 - Extension EPID: L-2021-LLR-0077 ML21291A1272021-10-14014 October 2021 NRR E-mail Capture - Request for Additional Information - Fifth Ten-Year Inservice Inspection Interval Relief Request No.10 - Extension (L-2021-LLR-0077) ML21270A1652021-09-27027 September 2021 NRR E-mail Capture - Turkey Point Request for Additional Information Concerning Full Spectrum LOCA Methodology - EPID L-2021-LLA-0070 ML21266A2602021-09-22022 September 2021 NRR E-mail Capture - (External_Sender) Partial Sea Turtle Carcass at Turkey Point ML21252A2142021-09-0101 September 2021 NRR E-mail Capture - Final: Turkey Point Units 3 and 4 - Request for Additional Information Concerning Relief Requests 8 and 9 ML21207A1212021-06-30030 June 2021 Fws to NRC, Biological Opinion Notifications to Fws Law Enforcement ML21158A2332021-06-0707 June 2021 NRR E-mail Capture - Acceptance Review: Turkey Point Units 3 and 4 Fifth Ten-Year ISI Extension of ISI RPV Welds from 10 to 20 Years (L-2021-LLR-0038) ML21154A0872021-06-0202 June 2021 NRR E-mail Capture - 06/02/2021 Print a Logbook Entry: Turkey Point Endangered Species Report Regarding Injured American Crocodiles ML21154A0862021-05-25025 May 2021 NRR E-mail Capture - Acceptance Review: Turkey Point - Update Listing of Approved LOCA Methodologies to Adopt Full Spectrum LOCA Methodology ML21140A0672021-05-13013 May 2021 NRR E-mail Capture - (External_Sender) Regarding Doa American Crocodile Report 5-13-21 ML21131A1362021-05-0404 May 2021 NRR E-mail Capture - (External_Sender) 5/4/2021 Report Regarding Doa American Crocodile ML21097A1832021-03-30030 March 2021 NRR E-mail Capture - Endangered Species Death Report from Turkey Point Regarding Incident on 03/30/2021 ML21084A1312021-03-18018 March 2021 NRR E-mail Capture - (External_Sender) Deceased American Crocodile Found Outside FPL Property Line ML21056A0002021-02-24024 February 2021 NRR E-mail Capture - Endangered Species - 2/24/2021 Logbook Entry Regarding an American Crocodile ML21029A0172021-01-25025 January 2021 NRR E-mail Capture - 1/25/2021 Logbook Entry Regarding an American Crocodile Reported in the Owner Controlled Area ML21025A4152021-01-25025 January 2021 NRR E-mail Capture - 10 CFR 2.206 Petition Dated January 10, 2021 - Open Phase Condition Implementation ML20346A1022020-12-0808 December 2020 NRR E-mail Capture - Response: September 17, 2020 Submittal to the Nuclear Regulatory Commission ML20218A5502020-08-0505 August 2020 Florida Power & Light Letter L-2020-127: FPL QAPD for 10 CFR 52 Licenses FPL-2 Revision Summary 2024-01-05
[Table view] |
Text
NRR-PMDAPEm Resource From: Tomonto, Bob [Bob.Tomonto@fpl.com]
Sent: Thursday, July 05, 2012 10:05 AM To: Saba, Farideh
Subject:
RE: Follow-up Conference Call with the NRC on the Turkey Point Unit 3 SFP Heat Exchanger Representing FPL:
Bob Tomonto, Licensing Manager Andy Zielonka, EPU Engineering Manager Jaime Delgado, EPU Civil Engineering Supervisor Phil Tiemann, EPU Project Manager David Robinson, EPU Engineer From: Saba, Farideh [1]
Sent: Thursday, July 05, 2012 9:11 AM To: Tomonto, Bob
Subject:
RE: Follow-up Conference Call with the NRC on the Turkey Point Unit 3 SFP Heat Exchanger Thank you. Would you please send the list of FPL participants in this conference call?
NRCs participants:
Chakrapani Basavaraju, NRR/EMCB technical reviewer Farideh Saba, Project manager
- Thanks, Farideh Farideh E. Saba, P.E.
Senior Project Manager NRC/ADRO/NRR/DORL 301-415-1447 Mail Stop O-8G9A Farideh.Saba@NRC.GOV From: Tomonto, Bob [2]
Sent: Thursday, July 05, 2012 8:59 AM To: Saba, Farideh Cc: Zielonka, Andy; Tiemann, Philip; Sluszka, David; Delgado, Jaime
Subject:
Follow-up Conference Call with the NRC on the Turkey Point Unit 3 SFP Heat Exchanger
Background:
By License Amendment 249 for Turkey Point Unit 3 (DPR-31), the NRC specified the following License Condition:
J. Extended Power Uprate Modifications
- 1. Prior to completion of the Cycle 26 refueling outage for Unit 3, the licensee shall provide confirmation to the NRC staff that the design and structural integrity evaluations 1
associated with the modifications related to the spent ful pool supplemental heat exchangers are complete, and that the results demonstrate compliance with appropriate UFSAR and code requirements. As part of the confirmation, the licensee shall provide a summary of the structural qualification results of the piping, pipe supports, supplemental heat exchanger supports, and the inter-tie connection with the existing heat exchange for the appropriate load combinations along with the margins.
Discussion:
By letter dated June 19, 2012 (L-2012-143), FPL provided a response to this requested condition. FPL understood this response satisfied the NRC's request in License Condition 3.J.1.
By email dated July 2, 2012 from Jason Paige (USNRC) to Bob Tomonto (FPL), the NRC requested additional information.
The questions are as follows:
(a) After review of the June 9, 2012, supplement, the staff determined that the nozzle loads for the spent fuel pool heat exchangers, and the valve accelerations are not addressed by the licensee.
Therefore, the staff requests that the licensee provide the summary for (i) nozzle loads for the applicable load combinations along with the allowable nozzle loads, and the margins, and (ii) computed valve accelerations for seismic loading (OBE and SSE) and the allowable limits.
Response: FPL understands that the NRC is requesting a table documenting the nozzle loads for the new spent fuel pool heat exchanger. The specific nozzles are the inlet and oulet nozzles for these new heat exchangers. The valve refered to are the main process isolation valves and cross-tie valves for the same new Unit 3 heat exchangers.
(b) The NRC staff also requests to provide a similar summary described in (a) above for Turkey Point Unit 4 prior to completion of the cycle 27 refueling outage.
Response: FPL agrees to provide a similar report to L-2012-143, as supplemented with the above referenced response for the nozzle loads and valve accelerations, prior to completion of the Unit 4 Cycle 27 refueling outage..
Any questions, please call me.
Bob Tomonto Licensing Manager Turkey Point (work) (305) 246-7327 (cell) (786) 229-5353 2
Hearing Identifier: NRR_PMDA Email Number: 405 Mail Envelope Properties (812C4425A2D74D478462D3F96418489612E497D6FC)
Subject:
RE: Follow-up Conference Call with the NRC on the Turkey Point Unit 3 SFP Heat Exchanger Sent Date: 7/5/2012 10:04:31 AM Received Date: 7/5/2012 10:04:42 AM From: Tomonto, Bob Created By: Bob.Tomonto@fpl.com Recipients:
"Saba, Farideh" <Farideh.Saba@nrc.gov>
Tracking Status: None Post Office: JBXEXVS04.fplu.fpl.com Files Size Date & Time MESSAGE 4043 7/5/2012 10:04:42 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: