Request for Additional Information Email, Relief Request No. A-2, Relief from Inspection Requirements of ASME Code Case N-729-1 Due to Geometric Limitations, 2nd 10-Year Inservice Inspection Interval
ML121240831
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 05/03/2012
From: Balwant Singal
Plant Licensing Branch IV
To: Hope T
Luminant Generation Co
Singal, Balwant, 415-3016, NRR/DORL/LPL4
Shared Package
ML121240816 List:
References
TAC ME7789
Download: ML121240831 (1)


Text

From: Singal, Balwant Sent: Thursday, May 03, 2012 11:42 AM To: 'Hope, Timothy' Cc: 'Jack.Hicks@luminant.com'

Subject:

Request for Additional Information - Relief Request A-2 (TAC ME7789)

Attachments: ME7789_RAI.pdf By letter dated January 5, 2012, as supplemented by letters dated April 16, 2012, Luminant Generation Company, LLC, (the licensee) submitted Relief Request A-2 for the Unit 2 Second 10 Year inservice inspection (ISI) Interval from Title 10 of the Code of Federal Regulations (10 CFR) 50.55a Inspection Requirements Due to Geometric Limitations for Comanche Peak Nuclear Power Station, Unit 2. The U.S. Nuclear Regulatory Commission (NRC) staff has completed initial review of the application and needs additional information described in the attachment to this e-mail to complete its review. You are requested to provide the requested information within 30 days from the date of this e-mail. Please treat this e-mail request as formed request.

A copy of the Draft e-mail was forwarded on April 23, 2012. Jack Hicks of your organization conformed on May 1, 2012 that a clarification conference call is not needed.