ML23145A233

From kanterella
Jump to navigation Jump to search
Email from Mark Yoo (NRC) to Ken Peters (Vistra) - Comanche Peak LRA - Request for Confirmation of Information - Set 2
ML23145A233
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/25/2023
From: Mark Yoo
NRC/NRR/DNRL/NLRP
To: Peters K
Luminant, Vistra Operations Company
References
Download: ML23145A233 (1)


Text

From: Mark Yoo To: ken.peters@luminant.com Cc: RidsNrrDnrl Resource; RidsNrrPMComanchePeak Resource; Jessica Hammock; Lauren Gibson; Brian Smith - NRR; Bernie Thomson; Dennis Galvin; Jennifer Dixon-Herrity; Marcia Carpentier; Ethan Licon; Scott Burnell; Dave McIntyre; Angel Moreno; Neil Day; John Ellegood; Shiattin Makor; Chris Smith; tam Tran; Ted Smith; Todd.Evans@luminant.com; Taylor.Smith@luminant.com; Amit.Kalia@luminant.com

Subject:

Comanche Peak LRA - Request for Confirmation of Information - Set 2 Date: Thursday, May 25, 2023 2:32:00 PM Attachments: Comanche Peak LRA - Request for Confirmation of Information - Set 2.pdf

Mr. Peters,

By letter dated October 3, 2022 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML22276A082), as supplemented by letters dated April 6, 2023 (ADAMS Accession No. ML23096A302) and April 24, 2023 (ADAMS Accession No. ML23114A377), Vistra Operations Company LLC (Vistra or the applicant) submitted an application for license renewal of Facility Operating License Nos.NPF-87 and NPF-89 for Comanche Peak Nuclear Power Plant (CPNPP), Units 1 and 2, to the U.S. Nuclear Regulatory Commission (NRC or staff). Vistra submitted the application pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for license renewal.

The NRC staff is in the process of reviewing your application. Based on our review, the NRC staff has identified the attached requests for confirmation of information (RCIs). The schedule for your response to these RCIs were discussed with Todd Evans of your staff, and a mutually agreeable date for the response is within 30 days from the date of this email.

If you have any questions, please contact me by e-mail at Mark.Yoo@nrc.gov.

Sincerely, Mark Yoo, Senior Project Manager Division of New and Renewed Licenses (DNRL)

Office of Nuclear Reactor Regulation (NRR)

U.S. Nuclear Regulatory Commission (NRC)