MONTHYEARGNRO-2011/00064, License Amendment Request to Revise Technical Specification 2.1.1.22011-10-28028 October 2011 License Amendment Request to Revise Technical Specification 2.1.1.2 Project stage: Request ML11350A0532012-01-0404 January 2012 Plan for the Scoping and Screening Regulatory Audit Regarding the Grand Gulf Nuclear Station, Unit 1 License Renewal Application Review Project stage: Other ML12009A1052012-01-18018 January 2012 Plan for the Aging Management Program Regulatory Audit Regarding the Grand Gulf Nuclear Station, Unit 1, License Renewal Application Review Project stage: Other ML12067A2352012-04-0303 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12068A2332012-04-0404 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12080A1912012-04-11011 April 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Grand Gulf LRA RAI Set 3 Project stage: RAI ML12074A0082012-04-12012 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12076A0142012-04-16016 April 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA Draft RAI Set 5 Project stage: Draft RAI ML12076A0092012-04-17017 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal (TAC ME7493) Grand Gulf LRA Draft RAI Set 6 Project stage: Draft RAI GNRO-2012/00024, Supplemental Information Extended Power Uprate2012-04-18018 April 2012 Supplemental Information Extended Power Uprate Project stage: Request ML12087A0012012-04-18018 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC ME7493)Grand Gulf LRA RAI Set 07 Project stage: RAI ML12094A0092012-04-25025 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nulcear Station Licesne Renewal Application Project stage: RAI ML12101A3602012-04-26026 April 2012 Request for Additional Information for the Review of Th Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 09 Project stage: RAI ML12104A2192012-04-30030 April 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493)LRA RAI Set 10 Project stage: RAI GNRO-2012/00029, Response to Request for Additional Information (RAI) Regarding the License Renewal Application2012-05-0101 May 2012 Response to Request for Additional Information (RAI) Regarding the License Renewal Application Project stage: Response to RAI ML12109A2132012-05-0303 May 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 11 Project stage: RAI ML12115A0902012-05-0909 May 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12115A2762012-05-0909 May 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493)Grand Gulf LRA RAI Set 13 Project stage: RAI GNRO-2012/00036, Response to Request for Additional Information (RAI) Dated April 12, 20122012-05-0909 May 2012 Response to Request for Additional Information (RAI) Dated April 12, 2012 Project stage: Response to RAI ML12117A3832012-05-14014 May 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12118A5392012-05-15015 May 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12125A3732012-05-24024 May 2012 Requests for Additional Information for the Review of the Grant Gulf Nuclear Station License Renewal Application (TAC No. ME7493)Grand Gulf LRA RAI Set 17 Project stage: RAI GNRO-2012/00033, Response to Request for Additional Information (RAI) Dated April 25, 20122012-05-25025 May 2012 Response to Request for Additional Information (RAI) Dated April 25, 2012 Project stage: Response to RAI ML12139A0552012-05-29029 May 2012 LRA RAI Set 19 Project stage: RAI ML12137A2962012-06-0505 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 18 Project stage: RAI GNRO-2012/00056, Response to Request for Additional Information (RAI) Set 13 Dated May 9, 20122012-06-0505 June 2012 Response to Request for Additional Information (RAI) Set 13 Dated May 9, 2012 Project stage: Response to RAI ML12137A2902012-06-0808 June 2012 Aging Management Programs Audit Report Regarding the Grand Gulf Nuclear Station, Unit 1 (TAC No. ME7493) Grand Gulf AMP Audit Report Cover Letter Project stage: Other ML12151A2652012-06-15015 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 20 Project stage: RAI ML12165A3872012-06-20020 June 2012 Scoping and Screening Methodology Audit Report Regarding the Grand Gulf Nuclear Station, Unit 1, License Renewal Application Project stage: Other ML12151A3682012-06-20020 June 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12152A3452012-06-22022 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (Tac No. ME7493) Project stage: RAI ML12152A3932012-06-22022 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI 05000416/LER-2012-004, Regarding Weld Defect Indication Found in Residual Heat Removal System to Reactor Pressure Vessel Boundary Nozzle2012-06-27027 June 2012 Regarding Weld Defect Indication Found in Residual Heat Removal System to Reactor Pressure Vessel Boundary Nozzle Project stage: Request ML12164A1742012-06-27027 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 26 Project stage: RAI ML12157A0562012-06-27027 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493)Grand Gulf LRA RAI Set 24 Project stage: RAI ML12164A7262012-06-27027 June 2012 RAI for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12179A1372012-07-17017 July 2012 Summary of Telephone Conference Call Between NRC and Entergy Operations, Inc., Concerning Requests for Additional Information Pertaining to Grand Gulf License Renewal Application Project stage: RAI ML12180A5412012-07-17017 July 2012 Summary of Telephone Conference Call Held on March 14, 2012, Between NRC and Entergy Operations, Inc., Concerning RAI Pertaining to the Grand Gulf Nuclear Station, LRA Project stage: RAI ML12188A7062012-07-17017 July 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12188A5162012-07-23023 July 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI GNRO-2012/00080, Response to Request for Additional Information (RAI) Set 24 Dated June 27, 20122012-07-25025 July 2012 Response to Request for Additional Information (RAI) Set 24 Dated June 27, 2012 Project stage: Response to RAI ML12200A1382012-07-27027 July 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12201B4762012-07-27027 July 2012 LRA RAI Set 30 Project stage: RAI ML12180A4672012-07-31031 July 2012 LRA RAI Telecon 2012-04-03 Project stage: RAI ML12191A1872012-07-31031 July 2012 LRA RAI Telecon 2012-04-13 Project stage: RAI ML12208A2672012-08-0707 August 2012 RAI for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12193A0712012-08-15015 August 2012 Summary of Telephone Conference Call Held on 5/15/12 Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc., Concerning Requests for Additional Information Pertaining to the Grand Gulf Nuclear Station, LRA Project stage: RAI GNRO-2012/00092, Response to Requests for Additional Information (RAI) Set 28 Dated July 23, 20122012-08-15015 August 2012 Response to Requests for Additional Information (RAI) Set 28 Dated July 23, 2012 Project stage: Response to RAI ML12201B5042012-08-15015 August 2012 Summary of Telephone Conference Call Held on 5/23/12 Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc., Concerning the RAIs Pertaining to the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12202A2142012-08-15015 August 2012 5/30/12 Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc., Concerning Requests for Additional Information Pertaining to the Grand Gulf Nuclear Station, LRA Project stage: RAI 2012-05-24
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 May 14, 2012 Mr. Michael Perito Vice President, Site Entergy Operations, Inc.
P.O. Box 756 Port Gibson, MS 39150
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION (TAC NO. ME7493)
Dear Mr. Perito:
By letter dated October 28, 2011, Entergy Operations, Inc., submitted an application pursuant to Title 10 of the Code of Federal Regulations, Part 54, to renew the operating license for Grand Gulf Nuclear Station, Unit 1 (GGNS) for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information were discussed with Jeff Seiter, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-1045 ore-mail nathaniel.ferrer@nrc.gov.
Sin~_____
Nathaniel Ferrer, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-416
Enclosure:
Requests for Additional Information cc w/encl: Listserv
GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION SET 14 RAI 2.3.3.19-1 LRA Section 2.1.1.2.2(1) indicates that nonsafety-related SSCs attached to safety-related SSCs are within the scope of license renewal for 10 CFR 54.4(a)(2) up to the first seismic anchor past the safety-related/nonsafety-related interface. On the following makeup water treatment system license renewal boundary drawings, the staff could not locate seismic anchors on the 10 CFR 54.4(a)(2) nonsafety-related lines connected to safety-related lines:
License Renewal Application Drawing Number & Location 10 CFR 54.4(a)(2) Pipe Line(s) or Identifier LRA-M-0033B, location E-2 2"-JCD-36 upstream of valve Q1P21F017-A LRA-M-0033B, location E-2 I 2"-JCD-33 downstream of valve Q1 P21 F01B-B LRA-M-0033B, location F-2 4"-JCD-30 downstream of valve Q1 P21 F024 Provide additional information to locate the seismic anchors or anchored components between the safety-related/nonsafety-related interface and the end of the 10 CFR 54.4(a)(2) scoping boundary.
RAI 2.3.3.19-2 Auxiliary steam system license renewal boundary drawing LRA-M-0036C, location D-6, shows line 1"-HBD-110BI-"E" as within the scope of license renewal for 10 CFR 54.4(a)(2). The drawing also shows a portion of the connecting CRW drain line (1-1/2" HBD-110B I-"E" line) as within the scope of license renewal for 10 CFR 54.4(a)(2). However, there is no separation (Le.,
valve) between the in-scope portion of this CRW drain line and the out-of-scope portion of the auxiliary steam system.
Provide additional information to clarify the scoping classification of this pipe section.
RAI 2.3.3.19-3 LRA Section 2.1.1.2.2(1) states that nonsafety-related SSCs attached to safety-related SSCs are within the scope of license renewal for 10 CFR 54.4(a)(2) up to the first seismic anchor past the safety-related/nonsafety-related interface. On reactor water cleanup system license renewal boundary drawing LRA-M-10BOB, location G-4, the staff could not locate a seismic anchor on the nonsafety-related piping downstream of safety related line 4"-HBC-355, where the pipe leaves the auxiliary building.
Provide additional information on the location of the seismic anchors or anchored components between the safety-related/nonsafety-related interface and the end of the 10 CFR 54.4(a)(2) scoping boundary.
ENCLOSURE
-2 RAI 2.3.3.19-4 LRA Section 2.1.1.2.2( 1) states that nonsafety-related SSCs attached to safety-related SSCs are within the scope of license renewal for 10 CFR 54.4(a)(2) up to the first seismic anchor past the safety-related/nonsafety-related interface. On domestic water system license renewal boundary drawing LRA-M-00348, location F-3, the staff could not locate the seismic anchor on the nonsafety-related 3"-HCO-439 line connected to safety-related line 3"-HCC-65.
Provide additional information on the location of the seismic anchors or anchored components between the safety-related/nonsafety-related interface and the end of the 10 CFR 54.4(a)(2) scoping boundary.
RAI 2.3.3.19-5 The containment leak rate test system license renewal boundary drawing LRA-M-1072F, location 8-3 and 8-4, shows the after cooler and refrigerated air dryer as not within the scope of license renewal. However, the lines connecting to these two components are shown as in scope for 10 CFR 54.4(a)(2).
Provide additional information to clarify the scoping classification of the after cooler and refrigerated air dryer.
RAI 2.3.3.19-6 LRA Section 2.1.1.2.2(1) states that nonsafety-related SSCs attached to safety-related SSCs are within the scope of license renewal for 10 CFR 54.4(a)(2) up to the first seismic anchor past the safety-related/nonsafety-related interface. On containment leak rate test system license renewal boundary drawing LRA-M-1111A, locations E-7, 0-7 and C-7, the staff could not locate the seismic anchors on the nonsafety-related lines connected to safety-related lines 1"-HC8-36, 1"-HC8-37, and 1"-HC8-38.
Provide additional information on the location of the seismic anchors or anchored components between the safety-related/nonsafety-related interface and the end of the 10 CFR 54.4(a)(2) scoping boundary.
RAI2.3.3.19-7 LRA Section 2.1.1.2.2(1) states that nonsafety-related SSCs attached to safety-related SSCs are within the scope of license renewal for 10 CFR 54.4(a)(2) up to the first seismic anchor past the safety-related/nonsafety-related interface. On process sampling system license renewal boundary drawing LRA-M-1069 the staff could not locate seismic anchors on the 10 CFR 54.4(a)(2) nonsafety-related line between the safety-related/nonsafety-related interface at location H-8 and the end of the 10 CFR 54.4(a)(2) scoping boundary at valve SV-F572, location H-3.
Provide additional information on the location of the seismic anchors or anchored components between the safety-related/nonsafety-related interface and the end of the 10 CFR 54.4(a)(2) scoping boundary.
- 3 RAI 2.3.3.19-8 The process sampling system license renewal boundary drawing LRA-M-1069D shows the various sampling lines are within the scope of license renewal for 10 CFR 54.4(a){2). However the license renewal boundary of these lines, at locations 8/C-2 and H-3, is shown to end at valves F026 and F031. It is not clear that the piping no longer has the potential to impact safety-related components beyond valves F026 and F031.
Provide additional information to clarify the extent of the license renewal boundary.
RAI 2.3.3.19-9 The process sampling system license renewal boundary drawing LRA-M-10698 shows sampling lines are within the scope of license renewal for 10 CFR 54.4(a){2). The piping sections below are connected to in-scope sampling lines but are not shown as within the scope of license renewal.
Drawing Number & Location Continuation Issue LRA-M-10698, location 8-2 Drip line from valve FA14.
LRA-M-10698, location 8-3 Drip line from valve FA12.
LRA-M-10698, location 8-4 Drip line from valve FA10.
LRA-M-10698, location 8-5/6 Drip line from valve FA08.
LRA-M-10698, location 8-6/7 Drip line from valve FA06.
LRA-M-10698, location 8-7/8 Drip line from valve FA04.
LRA-M-10698, location E-2 Drip line from valve F981.
LRA-M-10698, location E-3 Drip line from valve F979.
LRA-M-10698, location E-4 Drip line from valve F977.
LRA-M-10698, location E-5 Drip line from valve F974.
LRA-M-10698, location E-5/6 Drip line from valve F972.
Provide additional information to clarify the extent of the license renewal boundary.
RAI2.3.3.19-10 The turbine building cooling water system license renewal boundary drawing LRA-M-1044A, location F-6, shows line 1"-~'8D-1342 to be within the scope of license renewal for 10 CFR 54.4(a)(2) with continuation to drawing LRA-M-1062C (location D-1). However, the continuation of this line on drawing LRA-M-1062C is shown as not within the scope of license renewal.
Provide additional information to clarify the scoping classification of this pipe section.
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE GRAND GULF NUCLEAR STATION, LICENSE RENEWAL APPLICATION DISTRIBUTION:
HARD COPY:
DLRRF E-MAIL:
PUBLIC [or NON-PUBLIC, if applicable]
RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource NFerrer DDrucker DWrona DMorey AWang RSmith, RIV BRice, RIV DMclntyre, OPA
M L 12117 a383 OFFICE LA:RPB1:DLR PM:RPB1:DLR BC:RPB1 :DLR PM: RPB1:DLR NAME YEdmonds NFerrer DMorey NFerrer DATE 05/03/12 05/09/12 05 111 112 05/14/12