Letter Sequence Response to RAI |
---|
TAC:ME4679, Clarify Application of Setpoint Methodology for LSSS Functions (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting
Results
Other: GNRO-2012/00150, Final Report for Replacement Steam Dryer, GNRO-2017/00039, Steam Dryer Visual Inspection Results for the First Two Scheduled Refueling Outages, ML102660403, ML111720830, ML112560396, ML12167A257, ML12167A269, ML12177A287, ML13108A217, NRC-2012-0105, Environmental Assessment and Finding of No Significant Impact Related Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt
|
MONTHYEARML1026604002010-08-20020 August 2010 GE-Hitachi Nuclear Energy Americas LLC - Affidavit of Edward Schrull Withholding from Public Disclosure Proprietary Report NEDC-33477P Project stage: Request ML1026603992010-08-31031 August 2010 NEDO-33477, Revision 0, Safety Analysis Report for Grand Gulf Nuclear Station Constant Pressure Power Uprate. Project stage: Request ML1026604032010-09-0808 September 2010 License Amendment Request Extended Power Uprate Project stage: Other GNRO-2010/00056, NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Appendix E Through Appendix G2010-09-30030 September 2010 NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Appendix E Through Appendix G Project stage: Request ML1026604062010-09-30030 September 2010 NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Appendix B Through Appendix D Project stage: Request ML1026604012010-09-30030 September 2010 NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Cover Through Appendix a Project stage: Request ML1030102002010-11-0909 November 2010 Supplemental Information Needed for Acceptance of License Amendment Request, Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Megawatts Thermal Project stage: Acceptance Review GNRO-2010/00071, Supplemental Information, License Amendment Request, Extended Power Uprate2010-11-18018 November 2010 Supplemental Information, License Amendment Request, Extended Power Uprate Project stage: Supplement GNRO-2010/00073, Supplemental Information License Amendment Request, Extended Power Uprate2010-11-23023 November 2010 Supplemental Information License Amendment Request, Extended Power Uprate Project stage: Supplement ML1034201082010-12-16016 December 2010 Request for Withholding Information from Public Disclosure, 9/7/10 Affidavit Executed by E. Schrull, GEH Re NEDC-33601P Project stage: Withholding Request Acceptance ML1034705862011-01-0505 January 2011 Request for Withholding Information from Public Disclosure, 11/19/10 Affidavit Executed by E. Schrull, GE-Hitachi, Regarding NEDC-33621P Project stage: Withholding Request Acceptance ML1102602812011-01-26026 January 2011 E-mail, Request for Additional Information Instrument and Controls, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1102602872011-01-26026 January 2011 E-mail, Request for Additional Information Fire Protection, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1102701872011-01-27027 January 2011 Request for Additional Information, Emcb Non-Steam Dryer Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1103103902011-01-31031 January 2011 E-mail, Request for Additional Information, Vessels and Internal Integrity Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1103901732011-02-0808 February 2011 Email, Request for Additional Information, Nrr/Dci/Csgb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00012, Request for Additional Information Regarding Extended Power Uprate2011-02-23023 February 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request GNRO-2011/00011, Request for Additional Information Regarding Extended Power Uprate2011-02-23023 February 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1105407052011-02-23023 February 2011 E-mail, Request for Additional Information, Nrr/Dirs/Ihpb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1105407122011-02-23023 February 2011 E-mail, Request for Additional Information, Nrr/Dra/Apla Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00013, Request for Additional Information Regarding Extended Power Uprate2011-02-23023 February 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1034200962011-02-25025 February 2011 Request for Withholding Information from Public Disclosure, 8/20/10 Affidavit Executed by E. Schrull, GEH, for NEDC-33477P Project stage: Withholding Request Acceptance ML1106007172011-03-0101 March 2011 Email Request for Additional Information, Round 2, Nrr/Dci/Cvib Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00016, Request for Additional Information Regarding Extended Power Uprate2011-03-0909 March 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1107501322011-03-16016 March 2011 Email, Dose Assessment Branch, Request for Additional Information, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1108202242011-03-23023 March 2011 Email, Request for Additional Information, Nrr/Dss/Srxb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1108202272011-03-23023 March 2011 Request for Additional Information, Nrr/Dss/Srxb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00018, Request for Additional Information Regarding Extended Power Uprate2011-03-30030 March 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request GNRO-2011/00021, Response to Request for Additional Information Regarding Extended Power Uprate2011-03-31031 March 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML1109401362011-04-0404 April 2011 Email, Request for Additional Information, Nrr/Dci/Csgb Review, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1109502722011-04-0505 April 2011 Email, Request for Additional Information, Nrr/De/Eeeb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1109502812011-04-0505 April 2011 Request for Additional Information, Nrr/De/Eeeb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1110301112011-04-12012 April 2011 Email, Request for Additional Information, Nrr/Dss/Snpb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00024, Response to Request for Additional Information Regarding Extended Power Uprate2011-04-14014 April 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML11112A0982011-04-21021 April 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1110401002011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 3/28/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00018 Project stage: Withholding Request Acceptance ML1110401252011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/20/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00013 Project stage: Withholding Request Acceptance ML1110401132011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/20/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00011 Project stage: Withholding Request Acceptance ML1110401072011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/17/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00012 Project stage: Withholding Request Acceptance ML1110401162011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 3/30/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00021 Project stage: Withholding Request Acceptance GNRO-2011/00035, Response to Request for Additional Information Regarding Extended Power Uprate2011-05-0505 May 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML1113001562011-05-10010 May 2011 Email, Request for Additional Information, Nrr/Dss/Scvb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00037, Request for Additional Information Regarding Extended Power Uprate2011-05-11011 May 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1114002992011-05-20020 May 2011 E-mail, Request for Additional Information, Nrr/Dci/Emcb Review, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1113905252011-05-31031 May 2011 Request for Withholding Information from Public Disclosure, 4/21/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00025 Project stage: Withholding Request Acceptance ML1115204582011-06-0101 June 2011 Email, Request for Additional Information, Nrr/Dra/Aadb Review, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1115304392011-06-0606 June 2011 (Redacted) Request for Additional Information from Nrr/De/Emcb Steam Dryer, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00043, Request for Additional Information Regarding Extended Power Uprate2011-06-0808 June 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request GNRO-2011/00046, Response to Request for Additional Information Regarding Extended Power Uprate2011-06-15015 June 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML1117200422011-06-20020 June 2011 Licensee Response Regarding Request for Additional Information on Training for Prnms (TAC No. 4679) Project stage: Request 2011-03-30
[Table View] |
|
---|
Category:Letter type:GNRO
MONTHYEARGNRO-2023/00014, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0606 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GNRO-2023/00015, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-06-0606 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors GNRO-2021/00037, 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 12021-11-30030 November 2021 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 1 GNRO-2021/00017, Notification of Readiness for Supplemental Inspection2021-06-22022 June 2021 Notification of Readiness for Supplemental Inspection GNRO-2021/00014, Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency2021-06-0101 June 2021 Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency GNRO-2021/00015, Annual Radioactive Effluent Release Report2021-04-28028 April 2021 Annual Radioactive Effluent Release Report GNRO-2021/00011, Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 20202021-04-19019 April 2021 Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 2020 GNRO-2021/00012, Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.22062021-04-13013 April 2021 Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.2206 GNRO-2020/00045, 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis2020-12-16016 December 2020 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2020/00034, Notification of Spent Fuel Cask Use2020-10-0808 October 2020 Notification of Spent Fuel Cask Use GNRO-2020/00033, Response to NRC Integrated Inspection Report 05000416/20200022020-09-10010 September 2020 Response to NRC Integrated Inspection Report 05000416/2020002 GNRO-2020/00029, Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 20202020-08-18018 August 2020 Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 2020 GNRO-2020/00022, Report of Technical Specification Bases Changes2020-07-21021 July 2020 Report of Technical Specification Bases Changes GNRO-2020/00027, Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-07-16016 July 2020 Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00023, Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-06-26026 June 2020 Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2020/00020, Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-05-0505 May 2020 Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00018, Annual Radiological Effluent Release Report2020-04-30030 April 2020 Annual Radiological Effluent Release Report GNRO-2020/00016, Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.22062020-04-16016 April 2020 Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.2206 GNRO-2020/00015, Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test2020-04-0707 April 2020 Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test GNRO-2020/00007, Spent Fuel Storage Radioactive Effluent Release Report for 20192020-02-20020 February 2020 Spent Fuel Storage Radioactive Effluent Release Report for 2019 GNRO-2020/00006, License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-02-19019 February 2020 License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2019/00052, Report of Changes and Errors to 10 CFR 50.46 Analysis2019-12-13013 December 2019 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2019/00051, Notification of Readiness of 92723 Inspection2019-12-11011 December 2019 Notification of Readiness of 92723 Inspection GNRO-2019/00045, Emergency Plan, Revision 792019-10-29029 October 2019 Emergency Plan, Revision 79 GNRO-2019/00037, Notification of Spent Fuel Cask Use2019-09-20020 September 2019 Notification of Spent Fuel Cask Use GNRO-2019/00036, Correction to Gnro 2019-00017 Emergency Plan Revision 782019-08-0808 August 2019 Correction to Gnro 2019-00017 Emergency Plan Revision 78 GNRO-2019/00027, Notification of Readiness of 95001 Supplemental Inspections2019-07-0303 July 2019 Notification of Readiness of 95001 Supplemental Inspections GNRO-2019/00031, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report2019-06-25025 June 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report GNRO-2019/00028, Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation.2019-06-13013 June 2019 Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation. GNRO-2019/00026, Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval2019-05-0606 May 2019 Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval GNRO-2019/00024, Annual Radioactive Effluent Release Report2019-04-30030 April 2019 Annual Radioactive Effluent Release Report GNRO-2019/00020, Annual Radiological Operating Report (AREOR)2019-04-30030 April 2019 Annual Radiological Operating Report (AREOR) GNRO-2019/00022, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.22062019-04-22022 April 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 GNRO-2019/00017, Emergency Plan, Revision 782019-03-14014 March 2019 Emergency Plan, Revision 78 GNRO-2019/00014, Snubber Testing Program for Fourth Inspection Interval2019-03-13013 March 2019 Snubber Testing Program for Fourth Inspection Interval GNRO-2019/00012, Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program2019-03-0606 March 2019 Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program GNRO-2019/00016, Spent Fuel Storage Radioactive Effluent Release Report for 20182019-02-21021 February 2019 Spent Fuel Storage Radioactive Effluent Release Report for 2018 GNRO-2019/00003, Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation2019-01-23023 January 2019 Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation GNRO-2018/00057, Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan2018-12-0404 December 2018 Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan GNRO-2018/00055, Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ...2018-11-30030 November 2018 Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ... GNRO-2018/00054, Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval2018-11-30030 November 2018 Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval GNRO-2018/00052, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information2018-10-24024 October 2018 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information GNRO-2018/00051, Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-10-23023 October 2018 Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control GNRO-2018/00046, Submittal of 2018 Report of Changes and Errors to 10CFR50.462018-10-16016 October 2018 Submittal of 2018 Report of Changes and Errors to 10CFR50.46 GNRO-2018/00047, Submittal of 2018 Inservice Inspection Summary Report2018-10-16016 October 2018 Submittal of 2018 Inservice Inspection Summary Report GNRO-2018/00048, Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 62018-10-10010 October 2018 Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6 GNRO-2018/00042, Core Operating Limits Report Cycle 22, Revision 12018-09-18018 September 2018 Core Operating Limits Report Cycle 22, Revision 1 GNRO-2018/00043, Revised Offsite Dose Calculation Manual2018-09-18018 September 2018 Revised Offsite Dose Calculation Manual GNRO-2018/00039, Report of Technical Specification Bases Changes2018-08-20020 August 2018 Report of Technical Specification Bases Changes GNRO-2018/00040, Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 20182018-08-20020 August 2018 Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 2018 2023-06-06
[Table view] |
Text
Entergy Operations, Inc.
P. O. Box 756 Port Gibson, MS 39150 Michael A. Krupa Director, Extended Power Uprate Grand Gulf Nuclear Station Tel. (601) 437-6684 GNRO-2011/00046 June 15, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
Request for Additional Information Regarding Extended Power Uprate Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 License No. NPF-29
REFERENCES:
- 1. Email from A. Wang to F. Burford dated May 20, 2011, GGNS EPU Request for Additional Information Related to Mechanical and Civil Engineering Branch Review Excluding the Steam Dryer (ME4679)
(NRC ADAMS Accession Number ML111400299)
- 2. License Amendment Request, Extended Power Uprate, dated September 8, 2010 (GNRO-2010/00056, NRC ADAMS Accession Number ML102660403)
Dear Sir or Madam:
The Nuclear Regulatory Commission (NRC) requested additional information (Reference 1) regarding certain aspects of the Grand Gulf Nuclear Station, Unit 1 (GGNS) Extended Power Uprate (EPU) License Amendment Request (LAR) (Reference 2). Attachment 1 provides responses to the additional information requested by the Mechanical and Civil Engineering Branch.
No change is needed to the no significant hazards consideration included in the initial LAR (Reference 2) as a result of the additional information provided. There are no new commitments included in this letter.
If you have any questions or require additional information, please contact Jerry Burford at 601-368-5755.
GNRO-2011/00046 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on June 15, 2011.
Sincerely, MAK/FGB/dm Attachments:
- 1. Response to Request for Additional Information, Mechanical and Civil Engineering Branch -
Non-Steam Dryer cc: Mr. Elmo E. Collins, Jr.
Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 612 East Lamar Blvd., Suite 400 Arlington, TX 76011-4005 U. S. Nuclear Regulatory Commission ATTN: Mr. A. B. Wang, NRR/DORL (w/2)
ATTN: ADDRESSEE ONLY ATTN: Courier Delivery Only Mail Stop OWFN/8 B1 11555 Rockville Pike Rockville, MD 20852-2378 State Health Officer Mississippi Department of Health P. O. Box 1700 Jackson, MS 39215-1700 NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150
Attachment 1 GNRO-2011/00046 Grand Gulf Nuclear Station Extended Power Uprate Response to Request for Additional Information Mechanical and Civil Engineering Branch Non-Steam Dryer to GNRO-2011/ 00046 Page 1 of 3 Response to Request for Additional Information Mechanical and Civil Engineering Branch Non-Steam Dryer By letter dated September 8, 2010, Entergy Operations, Inc. (Entergy) submitted a license amendment request (LAR) for an Extended Power Uprate (EPU) for Grand Gulf Nuclear Station, Unit 1 (GGNS). By letter dated February 23, 2011, Entergy submitted responses to the initial request for additional information (RAI) from the Mechanical and Civil Engineering Branch (NRC ADAMS Accession No. ML110540545). Subsequently, the U.S. Nuclear Regulatory Commission (NRC) staff has determined that the following additional information requested by the Mechanical and Civil Engineering Branch is needed for the NRC staff to complete their review of the amendment. Entergys response to each item is also provided below.
RAI # 1 In response to request for additional information (RAI) 1, Reference 1 indicates that the turbine stop valve closure (TSVC) fluid transient loads, used in support of the pipe stress analyses performed for the GGNS EPU, were generated using the STEHAM computer code. Section 3.9.1.2.1.3.3 of the GGNS Updated Final Safety Analysis Report (UFSAR) indicates that the TSVC loads were generated using the TSFOR code, for the current licensed thermal power (CLTP) level. Please provide justification for the use of the STEHAM code in lieu of the TSFOR code, given that the latter is part of the current licensing basis for GGNS. This justification should include results of benchmarking performed to compare the results of the STEHAM code against the TSFOR code, to support the use of the former at GGNS. Additionally, provide any bases for the regulatory acceptance of the STEHAM code, if the STEHAM code has previously been utilized in support of licensing actions which required NRC staff approval.
Response
For the CLTP piping evaluations, TSVC forcing functions were generated using the GE - Hitachi Nuclear Energy Americas, LLC (GEH) proprietary TSFOR code for load development in the piping analyses for the Main Steam (MS) system piping inside containment, as indicated in Section 3.9.1.2.1 of the GGNS UFSAR. For the EPU evaluation, the NRC approved ratio method was applied to MS and associated piping system evaluation (inside containment) as stated in GGNS EPU LAR Attachment 5, Section 2.2.2.2.1.2.
For the CLTP piping evaluations, TSVC forcing functions were generated using a hand calculation method for load development in the piping analyses for the MS system piping outside containment; this is a separate calculation from the analyses for the MS piping inside containment. For the EPU evaluation of the MS piping outside containment, the NRC approved ratio method was applied to MS and associated piping (outside containment) and the loads resulted in some MS piping and supports exceeding code allowable limits, as described in GGNS EPU LAR Attachment 5, Section 2.2.2.2.2.2. As a result, for EPU, the MS piping was re-evaluated using a more detailed analysis using computer code STEHAM to generate the TSVC to GNRO-2011/ 00046 Page 2 of 3 forcing function. The computer based analysis provided more realistic results compared to the original hand calculation, which was very conservative. This EPU analysis using the STEHAM derived forcing function resulted in all MS piping and pipe supports outside containment meeting all code criteria.
The STEHAM computer program is a SHAW Stone and Webster proprietary code used in all steam hammer computerized analyses for all nuclear plant designs including power uprate projects since 1975, including the Point Beach Units 1 & 2 EPU license amendment application recently approved by the NRC (NRC ADAMS Accession No. ML110880039). The program description is provided in the first round response to RAI #1 (NRC ADAMS Accession No. ML110540545). The software is qualified for use in accordance with Shaws QA program requirements.
RAI # 2 In response to RAI 3.c, it was stated in Reference 1 that the GGNS feedwater (FW) piping experiences no percent-increase in stresses as a result of the proposed EPU implementation at GGNS. With respect to the response to RAI 3.c, please address the following:
a) Please confirm that the piping stress analyses performed in support of the proposed EPU implementation at GGNS were carried out at the limiting conditions for operation of these piping systems. This should include a confirmation that the FW system has been evaluated at the highest temperature at which it is expected to operate under EPU conditions (i.e.,
confirm that the proposed EPU at GGNS will be accomplished with no change in the maximum operating temperature).
b) The response to RAI 3.c states that the FW flow at GGNS will increase by approximately 13.1% following EPU implementation. Please provide a quantitative summary of the effects which the higher FW flow has on the occasional loads considered in the FW pipe stress analyses, including water hammer and other transients associated with higher FW flow. As part of this response, please specify which American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code load combinations, for FW pipe stresses and pipe supports, are affected by FW flow transients.
c) Please confirm that these increased occasional loads, discussed in RAI 2.b, above, were considered in the pipe stress re-analyses, including affected pipe supports, in accordance with the provisions of the design code of record applicable to the GGNS FW piping and supports.
d) Please confirm that the increased loading resulting from FW flow transients at EPU conditions were developed in accordance with the methodologies outlined in Section 3.5 of the constant pressure power uprate licensing topical report (CLTR or Reference 2). If these loads were not developed in accordance with the NRC-approved methodologies discussed in the CLTR, please discuss the methodologies used to evaluate the FW flow transients and to GNRO-2011/ 00046 Page 3 of 3 provide the regulatory bases for the acceptance of a methodology which is not described in the CLTR.
Response
a) It is confirmed that the piping stress analyses for the feedwater (FW) system performed in support of the proposed EPU implementation at GGNS were carried out at the limiting conditions for operation. The FW system has been evaluated at the highest operating temperature of 420°F under EPU conditions.
b) The EPU flow rate increase of approximately 13.1% does not affect the reactor FW piping system because water hammer loads were not a design load in the original stress analyses.
Thus, the increased EPU flow rate will not cause any new credible design basis transient loading. For EPU, there will not be any new transient loads for the flow increase.
c) The GGNS design basis results of the occasional and/or transients loadings for the FW systems are not affected by the EPU flow rate change. As indicated in response 2b) above, the water hammer loads were not a design basis load in the original stress analysis calculation.
d) The original design basis FW flow transient loads were not affected by the EPU parameters applicable to the FW system. Therefore, the design basis transient load results remain unchanged for the uprated conditions for the FW system. The FW piping was evaluated in accordance with the methodologies outlined in Section 3.5 of the constant pressure power uprate licensing topical report (CLTR).
REFERENCES
- 1) Letter from M. A. Krupa, Entergy Operations, Inc., to NRC Document Control Desk, Request for Additional Information Regarding Extended Power Uprate - Grand Gulf Nuclear Station, Unit 1 - Docket No. 50-416 - License No. NPF-29, dated February 23, 2011. (ADAMS Accession No.: ML110540545)
- 2) GE Nuclear Energy, Constant Pressure Power Uprate, Licensing Topical Report NEDC-33004P-A, Revision 4, Class III (Proprietary), July 2003; and NEDO-33004, Class I (Non-proprietary), July 2003.