ML111260664

From kanterella
Jump to navigation Jump to search
IR 05000285-11-007, on 01/17/2011 04/15/2011, Fort Calhoun Station, Baseline Inspection Report; Maintenance Effectiveness and Identification and Resolution of Problems
ML111260664
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 05/06/2011
From: Kennedy K
NRC/RGN-IV/DRP
To: Bannister D
Omaha Public Power District
References
EA-11-025 IR-11-007
Download: ML111260664 (35)


See also: IR 05000285/2011007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

May 6, 2011

EA-11-025

Mr. David J. Bannister, Vice President

and Chief Nuclear Officer

Omaha Public Power District

9610 Power Lane

Blair, NE 68008

SUBJECT: NRC INSPECTION REPORT 05000285/2011007; PRELIMINARY YELLOW

FINDING, FORT CALHOUN STATION

Dear Mr. Bannister:

On April 15, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

the Fort Calhoun Station. The enclosed inspection report documents an inspection finding,

which was discussed with you and other members of your staff, on April 15, 2011. The finding is

associated with the June 14, 2010, failure of a reactor trip contactor (M2) in your reactor

protection system. The significance of this finding has preliminarily been determined to be

Yellow, a finding with substantial safety significance that could result in additional NRC

inspections and potentially other NRC action. The specific details of the significance of this

finding are described in Attachment 2 of the enclosed report. This finding was assessed based

on the best available information, using the applicable Significance Determination Process

(SDP). The final resolution of this finding will be conveyed in separate correspondence.

The technical details of the issue and associated NRC risk analysis were discussed with your

staff during the inspection and the exit meeting. Based on the discussions, we understand that

you have the following disagreements regarding our risk assessment: (1) you believe the NRC

did not give sufficient credit to operator actions after the failure of an automatic reactor trip, both

for the manual actions and the timing of those actions; (2) you believe the NRCs generic data

for reliability of the systems Vital Breakers CB-AB and CB-CD was too low; and (3) you believe

the NRC applied a higher common cause probability to Trip Contactor M1 than you determined.

Additionally, we understand you are in the process of performing a failure modes and effects

analysis on the failed contactor to determine if your apparent cause, what we assumed as the

failure mechanism in our analysis, is correct.

Fort Calhoun Station personnel replaced all four of the reactor trip contactors in the reactor

protection system on February 5, 2011, to address this issue. The finding is also an apparent

violation of NRC requirements and is being considered for escalated enforcement action in

Omaha Public Power District -2-

accordance with the Enforcement Policy, which can be found on the NRCs Web site at

http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html.

In accordance with NRC Inspection Manual Chapter (IMC) 0609, we intend to complete our

evaluation using the best available information and issue our final determination of safety

significance within 90 days of the date of this letter. The significance determination process

encourages an open dialogue between the NRC staff and the licensee; however, the dialogue

should not impact the timeliness of the staffs final determination.

Before we make a final decision on this matter, we are providing you with an opportunity (1) to

attend a Regulatory Conference where you can present to the NRC your perspective on the

facts and assumptions the NRC used to arrive at the finding and assess its significance; or.

(2) submit your position on the finding to the NRC in writing. If you request a Regulatory

Conference, it should be held within 30 days of the receipt of this letter and we encourage you

to submit supporting documentation at least one week prior to the conference in an effort to

make the conference more efficient and effective. If a Regulatory Conference is held, it will be

open for public observation. If you decide to submit only a written response, such submittal

should be sent to the NRC within 30 days of your receipt of this letter. If you decline to request

a Regulatory Conference or submit a written response, you relinquish your right to appeal the

final SDP determination, in that by not doing either, you fail to meet the appeal requirements

stated in the Prerequisite and Limitation sections of Attachment 2 of IMC 0609.

Please contact Jeff Clark at (817) 860-8147 and in writing, within 10 days from the issue date of

this letter, to notify the NRC of your intentions. If we have not heard from you within 10 days,

we will continue with our significance determination and enforcement decision. The final

resolution of this matter will be conveyed in separate correspondence.

Because the NRC has not made a final determination in this matter, no Notice of Violation is

being issued for the inspection finding at this time. In addition, please be advised that the

number and characterization of the apparent violation described in the enclosed inspection

report may change as a result of further NRC review.

In accordance with Title of the Code of Federal Regulations 10 CFR 2.390 of the NRC's "Rules

of Practice," a copy of this letter and its enclosure will be made available electronically for public

inspection in the NRC Public Document Room or from the NRCs document system (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/ T. Pruett for

Kriss M. Kennedy

Director, Division of Reactor Projects

Docket: 50-285

License: DPR-40

Omaha Public Power District -3-

Enclosures:

NRC Inspection Report 05000285/2011007

w/attachments: Supplemental Information (A-1); Significance Determination Evaluation (A-2)

Distribution via ListServe

Omaha Public Power District -4-

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

DRP Deputy Director (Troy.Pruett@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

Senior Resident Inspector (John.Kirkland@nrc.gov)

Resident Inspector (Jacob.Wingebach@nrc.gov)

Branch Chief, DRP/E (Jeff.Clark@nrc.gov)

Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)

Project Engineer (Jim.Melfi@nrc.gov)

Project Engineer (Chris.Smith@nrc.gov)

RIV Enforcement, ACES (Ray.Kellar@nrc.gov)

FCS Administrative Assistant (Berni.Madison@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)

Project Manager (Lynnea.Wilkins@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Thomas.Combs@nrc.gov)

OEMail Resource

DRS/TSB STA (Dale.Powers@nrc.gov)

RIV/OEDO ET (Stephanie.Bush-Goddard@nrc.gov)

File located: R:\_REACTORS\_FCS\2011\FCS 2011-007 RP JCK

SUNSI Rev Compl. Yes No ADAMS Yes No Reviewer Initials JCK

Publicly Avail Yes No Sensitive Yes No Sens. Type Initials JCK

SRI:DRP/ RI:DRP/ SPE:DRP/ C:DRS/EB1 C:DRS/EB2

JCKirkland JFWingebach RVAzua TRFarnholtz NFOKeefe

/E-JAClark/ /E-JAClark/ /JMelfi for/ /E-JAClark/ /RA/

4/21/11 4/21/11 4/21/11 4/21/11 4/21/11

DRS/SRA ACES/OE C:DRP/PBE DRP/D

DPLoveless RLKellar JAClark KMKennedy

/RA/ /E-JAClark/ /RA/ /RA/

4/21/11 4/21/11 4/21/11 5/3/11

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 50-285

License: DPR-40

Report Nos.: 05000285/2011007

Licensee: Omaha Public Power District

Facility: Fort Calhoun Station

Location: 9610 Power Lane

Blair, NE 68008

Dates: January 17, 2011 - April 15, 2011

Inspectors: J. Kirkland, Senior Resident Inspector

L. Micewski, Project Engineer

C. Steely, Operations Engineer

J. Wingebach, Resident Inspector

Approved By: Kriss M. Kennedy, Director

Division of Reactor Projects

-1- Enclosure

SUMMARY OF FINDINGS

IR 05000285/2011007; 01/17/2011 - 04/15/2011; Fort Calhoun Station, Baseline Inspection

Report; Maintenance Effectiveness and Identification and Resolution of Problems

The report covered approximately a three month period of inspection by resident inspectors and

two region-based inspectors. One apparent violation of preliminary substantial safety

significance (Yellow) was identified. The significance of most findings is indicated by their color

(Green, White, Yellow, or Red) using Inspection Manual Chapter (IMC) 0609, Significance

Determination Process. The crosscutting aspect is determined using IMC 0310, Components

within the Crosscutting Areas. Findings for which the significance determination process does

not apply may be Green or be assigned a severity level after U.S. Nuclear Regulatory

Commission management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 4, dated December 2006.

A. NRC-Identified Findings and Self-Revealing Findings

Cornerstone: Mitigating Systems

  • TBD. The inspectors identified an apparent violation of Title 10 of the Code of

Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XVI, Corrective

Action, for the licensees failure to ensure that the cause of a significant

condition adverse to quality was determined and corrective actions taken to

preclude repetition. Specifically, the licensee failed to identify the cause and

preclude the shading coils from becoming loose material in the M2 trip contactor

assembly of the reactor protection system that subsequently resulted in a failed

contactor.

The inspectors determined that the licensees failure to preclude shading coils

from repetitively becoming loose material in the M2 reactor trip contactor was a

performance deficiency. The finding is more than minor because it affected the

Mitigating Systems Cornerstone, and it directly affected the cornerstone objective

to ensure the availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences. The inspectors evaluated

the issue using the Significance Determination Process Phase 1 Screening

Worksheet for the Initiating Events, Mitigating Systems, and Barriers

Cornerstones provided in Manual Chapter 0609, Attachment 4, Phase 1 - Initial

Screening and Characterization of Findings. The inspectors determined that the

finding represented the actual loss of a single train (i.e., each of the four

contactors are considered a train) of non-Technical Specification equipment,

designated as risk-significant per 10 CFR 50.65, for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Therefore, the finding was potentially risk significant and a Phase 2 analysis was

required. The inspectors determined that the pre-solved table does not contain a

target suitable for evaluating the finding of interest and informed the regional

senior reactor analyst that use of the risk-informed notebook would be necessary.

The senior reactor analyst completed a Phase 3 analysis using the plant-specific

-2- Enclosure

Standardized Plant Analysis Risk Model for Fort Calhoun, Revision 3.50 modified

to include a detailed modeling of the reactor protection system. The exposure

period of 64 days represented the 63 days from the last verification of contactor

operation, which is most likely the time of failure, until the failure of the quarterly

surveillance plus the 1-day repair time until de-energization of half the reactor

protection system. External events impacting the risk included seismic and

internal fire initiators. The resulting risk was calculated to be 2.6 x 10-5 indicating

that the finding was of preliminarily substantial safety significance (Yellow). The

final significance of this finding is to be determined (TBD). This finding has a

crosscutting aspect in the area of human performance, decision making

component, because the licensee did not use conservative assumptions in the

evaluation of the ongoing problems with the trip contactors

H.1(b)(Section 4OA2).

B. Licensee-Identified Violations

None

-3- Enclosure

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and

Emergency Preparedness

4OA2 Identification and Resolution of Problems (71152)

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency

Preparedness, Public Radiation Safety, Occupational Radiation Safety, and

Physical Protection

.1 Selected Issue Follow-up Inspection

a. Inspection Scope

The inspectors reviewed the failure of a contactor in the clutch power supply system

associated with the reactor protective system. On June 14, 2010, the contacts

associated with the M2 contactor failed to open during performance of a quarterly

surveillance test. The inspectors considered the following during the review of the

licensee's actions:

  • complete and accurate identification of the problem in a timely manner
  • evaluation and disposition of operability/reportability issues
  • consideration of extent of condition, generic implications, common cause, and

previous occurrences

  • classification and prioritization of the resolution of the problem
  • identification of root and contributing causes of the problem
  • identification of corrective actions
  • completion of corrective actions in a timely manner

The clutch power supply system consists of four DC power clutch power supplies, four

contactors (M-contactors), and other relays and contacts which work together to supply

power to control element drive mechanisms (see drawings on next two pages). The

control element assemblies are equipped with magnetic clutches, which couple the

control element assemblies with the control element drive mechanisms. The clutches

are powered from four DC power supplies, PS-1 through PS-4. Power supplies PS-1

and PS-2 supply power to 20 clutches, and power supplies PS-3 and PS-4 supply power

to 17 clutches. All clutches will remain energized if only half of their power supplies are

available. For example, if PS-1 is de-energized, the 20 associated clutches will remain

energized if PS-2 remains energized. Therefore, to de-energize the first 20 clutches,

both PS-1 and PS-2 must be de-energized, and to de-energize the other 17 clutches,

PS-3 and PS-4 must be de-energized. For a complete reactor trip (all 37 clutches), all

four power supplies must de-energize.

-4- Enclosure

Reactor Protection System

Block Diagram

-5- Enclosure

Reactor Protection System

Partial Line Drawing

-6- Enclosure

Power is supplied to the four DC power supplies from 120 Vac instrument busses.

Instrument bus A or B supplies power to PS-1 and PS-3, and instrument bus C or D

supplies power to PS-2 and PS-4. Power from the instrument buses to the dc power

supplies are controlled by one breaker and two sets of contacts in series. For dc power

supplies PS-1 and PS-3, the flow path is from the instrument bus, through breaker

CB-AB, through normally closed contacts M1 then M2, then to the dc power supplies.

Similarly, for power supplies PS-2 and PS-4, through breaker CB-CD, through normally

closed contacts M4 then M3, then to the dc power supplies. This configuration is such

that if power is lost from one instrument bus, the reactor will not trip because the

clutches still have power from the power supplies fed from the other instrument bus.

The M-contacts are controlled through the reactor protective system and the breakers

are controlled from the diverse scram system.

The reactor protective system consists of four channels of instrumentation. Each

channel monitors 12 safety parameters and each parameter input is derived from an

isolated instrument channel. Individual channel trips occur when the measurement

reaches a preselected value, and has input to three of six logic matrices. The logic

matrix trip relays are de-energized when two channels of the same measurement

channel trip.

The clutch power supply and reactor protective systems interface through six normally

closed contacts, in series, in each of four trip paths. The six contacts in each trip path

correspond to the six logic matrices in the reactor protective system. If a logic matrix trip

relay in the reactor protective system is de-energized, it opens the associated contact in

all four trip paths. Opening one of these contacts interrupts power to an interposing

relay, opening a contact which interrupts power to an M-contactor, which in turn opens

the M contacts, interrupting power to two clutch power supplies. Trip path 1 consists of

the M1 contactor and interposing relay 1, trip path 2 consists of the M2 contactor and

interposing relay 2, etc. Initiating a manual reactor trip from control board 4 also

interrupts power to the four interposing relays.

When a valid signal is generated in the diverse scram system, a normally closed contact

will open, interrupting power to a relay associated with the CB-AB and CB-CD breakers,

opening the associated breakers and interrupting power to the clutch power supplies.

Initiating a manual reactor trip from reactor protective system cabinet AI-31 will also

interrupt power to the breaker relays.

In order for the reactor to automatically trip upon a valid signal from the reactor

protective system, the contacts from either M1 or M2 must open (which interrupts power

to PS-1 and PS-3), and the contacts from either M3 or M4 must open (which interrupts

power to PS-2 and PS-4). The M-contacts will not open if power is not interrupted to the

interposing relay or the M-contactors, or the contacts associated with the interposing

relay or M-contactors do not open.

These activities constitute completion of one in-depth problem identification and

resolution sample as defined in Inspection Procedure 71152-05.

-7- Enclosure

b. Findings

Introduction. The inspectors identified an apparent violation of preliminary substantial

safety significance (Yellow) of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective

Action, for the licensees failure to ensure that the cause of a significant condition

adverse to quality was determined and corrective actions taken to preclude repetition.

Specifically, the licensee failed to identify the cause and preclude the shading coils from

becoming loose material in the M2 trip contactor assembly of the reactor protection

system that subsequently resulted in a failed contactor.

Description. On June 14, 2010, the licensee performed a quarterly surveillance test on

the reactor trip contactors of the reactor protective system. During this test, the

M2 contactor failed to open as required. The licensee subsequently determined the

apparent cause was due to a shading coil falling out of its recess, breaking apart, and

lodging in the contactor mechanism such that it bound its contacts in the closed position.

Fort Calhoun Station does not use reactor trip circuit breakers. Instead, the reactor

protective system uses four trip contactors (M1 through M4). For these contactors to

successfully trip the reactor, either M1 and M3 or M4, or M2 and M3 or M4 must open.

Therefore, this is a one out of two, taken twice, coincidence logic. With M2 failed closed,

M1 must open to successfully trip the reactor. The failure of M2 reduced the reliability

and redundancy of the reactor protective system.

The shading coils of the trip contactors do not perform a direct safety function for the

mechanism. They serve to increase the life expectancy and reliability of the contactors.

The shading coils are rectangular strips of metal, not electrically connected to the

device, which produce opposing lines of flux to the main coil. They are maintained in

position, in their recess, by press fit (interference fit) to the contactor pole faces. The

shading coil is used to prevent excess vibration on the single-phase AC magnets that

must be electrically held in a closed position. A shading coil produces a second field to

apply a magnetic force when the primary field force is zero. With no other force present,

an AC magnet will partially open at each current zero. A vibration will develop at twice

the AC frequency. Without a shading coil to help hold the magnet closed during current

zero phase, this vibration could destroy the magnet pole face. Inspectors determined

that the licensee failed to identify that the shading coils being loose within the

mechanism posed a failure mechanism to the safety function of the contactor to open.

The licensee has documented several occurrences of shading coils dislodging from their

recess in the contactor assemblies since 1987. Since 2008, the licensee documented

two such instances of issues with the M2 contactor prior to its failure on June 14, 2010.

On November 3, 2008, after resetting the M2 coil, the AI-3 panel began chattering similar

to an unbalanced fan during performance of quarterly surveillance test IC-ST-RPS-0042,

Rev. 5, Quarterly Functional Test of RPS Trip Logic. The licensee documented this

characterization in Condition Report 2008-6624, and categorized the condition report as

a Level C (an adverse condition that requires a simple cause statement). In analyzing

the initial operability of the contactor, the condition report stated Operating experience

shows that coils and contacts can operate for extended periods making noise. The

-8- Enclosure

licensee concluded that, At this time, the M2 coil would trip and provide the protection it

is designed to provide. Troubleshooting determined the cause of the vibration to be a

shading coil that had fallen out of its recess and was lying across the coil. On

November 5, 2008, the shading coil was re-installed, and the vibration ceased.

The response to Condition Report 2008-6624 recommended that all four contactors be

replaced due to the age of the equipment and identified that the contactor model was

obsolete and no like-for-like parts were available for purchase. However, the licensee

identified a suitable commercially available substitute and initiated an engineering

change to replace all four contactors.

In November 2008, engineering change EC 44745 was sent to design engineering for

approval. It was initially assigned a high priority so that the contactors could be replaced

in the fall 2009 refueling outage. However, the priority was subsequently downgraded

and replacement of the contactor was not included in the 2009 outage. The licensee

inappropriately considered replacement of the contactors to be an enhancement only,

and re-scheduled the activity for the spring 2011 refueling outage. Consequently, review

of EC 44745 was assigned a low priority.

On March 20, 2010, Condition Report 2010-1378 was submitted describing Electrical

noise emanating from AI-3 cabinet has changed in pitch and volume. The inspectors

noted that due to the licensees continued lack of understanding of the potential

contactor problem(s), Condition Report 2010-1378 was cross-referenced to Condition

Report 2008-6624, resulting in Condition Report 2010-1378 being closed with no further

action.

On March 25, 2010, during the performance of quarterly Surveillance Test

IC-ST-RPS-0042, noises from the AI-3 cabinet became louder, which the licensee

documented in Condition Report 2010-1460 and performed an apparent cause analysis.

Troubleshooting again showed that the shading coil had come loose. The condition

report evaluation of safety significance again stated that This is not safety significant as

the contactor was able to remain energized with the contact closed, providing power to

the CEDM [control element drive mechanism] power supplies. The inspectors

concluded this was another missed opportunity for the licensee to identify the potential

negative impact of loose material in the contactor mechanism. On March 31, 2010, the

shading coil was re-installed; however, the vibration was not eliminated, only reduced.

On April 1, 2010, an engineer initiated Condition Report 2010-1586, in an attempt to

elevate the priority so that design engineering would again analyze EC 44745. This

condition report stated there were no spare parts for the contactors, the contactors were

obsolete, and that engineering change request EC 44745 was still in development.

Due to concerns by licensee personnel that the shading coil vibration had not been

eliminated on March 31, 2010, a work request was initiated in order to check the

contactor during a forced outage. On April 8, 2010, the reactor was tripped to enter a

forced outage, which opened the reactor trip contactors. However, the licensee stated in

an apparent cause evaluation for Condition Report 2010-2923, that they did not inspect

the contactors because of a lack of resources due to other work that needed to be

-9- Enclosure

accomplished during the forced outage. The plant was in this outage until startup

commenced on April 10, 2010. At that time the reactor trip contactors were again

closed.

On April 10, 2010, Condition Report 2010-1738 documented that after resetting the

reactor, per Surveillance Test OP-ST-RPS-0008, the M2 contactor started making noise

at the AI-3 cabinet. Electrical maintenance was notified and determined that the M2

shading coil had most likely come loose and was interfering with the normal contactor.

The initial operability basis stated, in part, At this time the M2 coil would trip and provide

the protection it is designed to provide. Work Request 149645 was initiated to address

the condition, which was subsequently assigned to Work Order 374724, which would

again re-install the shading coil, and was scheduled for August 9, 2010.

On June 14, 2010, quarterly Surveillance Test IC-ST-RPS-0042 was performed. During

Step 7.8.5 of Surveillance Test IC-ST-RPS-0042, the system did not perform as required,

in that the M2 coil did not open its associated contacts to drop out clutch power supplies

PS-3 and PS-1. The licensee documented this failure in Condition Report 2010-2923.

The system engineers evaluation of the condition report stated, Troubleshooting

determined that part of one of the shading coils had wedged [itself] between the

contactor and the yoke preventing the contactor from dropping out. The licensee further

concluded that was not safety significant as, The AI-3-M1 contactor would have caused

the power supplies to de-energize in the event of an actual trip signal.

The inspectors postulated that for the shading coil to jam the contactor in the closed

position, the shading coil would have to be out of its recess when the contactor

physically closed. Specifically, a loose shading coil could fall out of its recess when the

contactor is cycled open then jam when subsequently closed. This cycling occurred on

April 8 and 10, 2010. As evidenced by the failure to open on June 14, 2010, the

inspectors concluded the contactor was likely inoperable from April 10 through

June 14, 2010.

In the response to both Condition Reports 2010-1460 and 2010-2923, the licensee

evaluated the significance of a shading coil being out of its recess as not being

significant, as the contactor would still open as required. In these two instances, the

licensee failed to recognize the loose shading coil could adversely affect the safety-

related function of the contactor to open. The licensee also failed to recognize the

importance of the M1 contactor, and the resulting loss of the reactor protection system

reliability, given a failure of M2.

Analysis. The inspectors determined that the failure to identify the cause and preclude

the shading coils from becoming loose material in the M2 trip contactor assembly of the

reactor protection system, that resulted in a failed contactor, was a performance

deficiency. The finding is more than minor because it affected the Mitigating Systems

Cornerstone, and it directly affected the cornerstone objective to ensure the availability,

reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, with M2 failed closed, M1 must open to

successfully trip the reactor. The failure of M2 reduced the reliability and redundancy of

the reactor protection system. The inspectors evaluated the issue using the Significance

- 10 - Enclosure

Determination Process Phase 1 Screening Worksheet for the Initiating Events, Mitigating

Systems, and Barriers Cornerstones provided in Manual Chapter 0609, Attachment 4,

Phase 1 - Initial Screening and Characterization of Findings. The inspectors

determined that the finding represented the actual loss of a single train (i.e., each of the

four contactors are considered a train) of non-Technical Specification equipment,

designated as risk-significant per 10 CFR 50.65, for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Therefore,

the finding was potentially risk significant and a Phase 2 analysis was required. The

inspectors determined that the presolved table did not contain a target suitable for

evaluating the finding of interest and informed the regional senior reactor analyst that

use of the risk-informed notebook would be necessary. Therefore, the senior reactor

analyst completed a Phase 3 analysis using the plant-specific Standardized Plant

Analysis Risk Model for Fort Calhoun, Revision 3.50, modified to include a detailed

modeling of the reactor protection system. The exposure period of 64 days represented

the 63 days from the last verification of contactor operation, which is most likely the time

of failure, until the failure of the quarterly surveillance plus the 1-day repair time until the

M1/M2 half of the reactor protection system was deenergized. External events

impacting the risk included seismic and internal fire initiators. The resulting risk was

calculated to be 2.6 x 10-5 indicating that the finding was of preliminarily substantial

safety significance (Yellow). This finding has a crosscutting aspect in the area of human

performance, decision making component, because the licensee did not use

conservative assumptions in the evaluation of the ongoing problems with the trip

contactors H.1(b).

Enforcement. Title 10 of the Code of Federal Regulations, Part 50, Appendix B,

Criterion XVI, Corrective Action, states, in part, that measures shall be established to

assure that conditions adverse to quality, such as failures, malfunctions, deficiencies,

deviations, defective material and equipment, and non-conformances are promptly

identified and corrected. In the case of significant conditions adverse to quality, the

measures shall assure that the cause of the condition is determined and corrective

action taken to preclude repetition. Contrary to the above, between November 3, 2008,

and June 14, 2010, the licensee failed to preclude shading coils from repetitively

becoming loose material in the M2 reactor trip contactor. Specifically, the shading coils

becoming loose material in the M2 reactor trip contactor assembly was a significant

condition adverse to quality that subsequently resulted in the contactor failing. On

November 3, 2008, the licensee determined that the shading coil in the M2 trip contactor

had fallen out of its recess and had become loose material in the contactor. The

licensee further determined the trip contactors were obsolete and should be replaced.

However, the licensee manually pressed the shading coil back into place and continued

operations. On March 25, 2010, the licensee again identified the shading coil had fallen

out, as evidenced by associated buzzing noise. On March 31, 2010, technicians again

pressed the shading coil back into place during troubleshooting, but the noise

immediately resumed during the postmaintenance testing, indicating the shading coil did

not remain in place. Due to a lack of replacement parts, the licensee determined the

contactor would be left as is and they would continue to operate. On June 14, 2010,

the M2 trip contactor failed to open during a surveillance test because pieces of the

loose shading coil jammed the contactor in the closed position. The licensee failed to

identify that the loose parts in the trip contactor represented a potential failure of the

- 11 - Enclosure

contactor if they became an obstruction; and therefore, failed to preclude repetition of

this significant condition adverse to quality. The licensee has entered this condition into

their corrective action program as Condition Report 2011-0451. The licensee also

replaced all four of the reactor trip contactors in the reactor protection system on

February 5, 2011. Therefore, the NRC no longer has a concern with the potential failure

mechanisms discussed in the report with the previous reactor trip contactors. Pending

completion of the final significance determination, the performance deficiency will be

considered an apparent violation, AV 05000285/2011007-01, Failure to Correct a

Degraded Contactor in the Reactor Protective System.

4OA6 Meetings

Exit Meeting Summary

On April 15, 2011, the inspectors presented the inspection results to you and other members of

your staff. You and your staff acknowledged the issues presented. Your staff also reiterated the

differences they consider in assumptions or analysis in the NRCs risk analysis for this issue.

The inspector asked the licensee whether any materials examined during the inspection should

be considered proprietary. No proprietary information was identified.

- 12 - Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

R. Acker, Station Licensing

M. Bare, System Engineer

J. Bozarth, System Engineer

H. Faulhaber, Division Manager, Nuclear Construction and Projects

M. Ferm, Manager, Systems Engineering

M. Frans, Manager, Engineering Programs

J. Goddell, Division Manager, Nuclear Performance Improvement and Support

D. Guinn, Supervisor Regulatory Compliance

H. Hackerott, Supervisor, Systems Analysis

J. Herman, Division Manager, Nuclear Engineering

T. Nellenbach, Plant Manager

J. Reinhart, Site Vice President

M. Smith, Manager, Operations

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000285/2011007-01 AV Failure to Correct a Degraded Contactor in the Reactor

Protective System

LIST OF DOCUMENTS REVIEWED

Section 4OA2: Identification and Resolution of Problems

CONDITION REPORTS

199600356 2008-6624 2010-1378 2010-1460 2010-1586

2010-1738 2010-2923 2011-0451

WORK ORDERS (WO)

00321729 00372893 00301892

PROCEDURES

NUMBER TITLE REVISION

EM-RR-RPS-0201 Maintenance of M-Contactors for Clutch Power Supplies 6

IC-ST-RPS-0042 Quarterly Functional Test of RPS Trip Logic 5

OP-ST-RPS-0008 Reactor Manual Trip Test 12

A-1 Attachment-1

DRAWINGS

NUMBER TITLE REVISION

E-23866-411-003 Reactor Protective System Functional Diagram 4

ENGINEERING CHANGES (EC)

NUMBER TITLE REVISION

44745 Replacement for AI-3-M1/M2/M3/M4 contactors 1

MISCELLANEOUS DOCUMENTS

NUMBER TITLE REVISION /

DATE

Equipment Reliability (ER) Optimization Project at September 2010

OPPD Fort Calhoun

Meeting Agenda and Package for DNC PRC January 20, 2010

Subcommittee monthly meeting

FCSG-24 Corrective Action Program Guideline 27

STM38 System Training Manual Volume 38, Reactor Protective 20

System and Diverse Scram System

USAR-7.2 Instrumentation and Control - Reactor Protective 14

Systems

A-2 Attachment-1

ATTACHMENT

PRELIMINARY SIGNIFICANCE DETERMINATION

FAILURE TO CORRECT DEFICIENCIES IN THE REACTOR PROTECTION SYSTEM

The seven supplements referred to in this preliminary risk assessment are being

withheld from public disclosure in accordance with Section 2.390(d) of Title 10 of

the Code of Federal Regulations (10 CFR 2.390). These documents will be

provided to the licensee under separate cover.

A. Significance Determination Basis

The senior reactor analyst completed a Phase 3 analysis using the plant-specific

Standardized Plant Analysis Risk (SPAR) Model for Fort Calhoun, Revision 3.50

modified to include a detailed modeling of the reactor protection system. The exposure

period of 64 days represented the 63 days from the last verification of contactor

operation, which is most likely the time of failure, until the failure of the quarterly

surveillance plus the 1-day repair time until deenergization of half the reactor protection

system. External events impacting the risk included seismic and internal fire initiators.

The final change in core damage frequency was calculated to be 2.6 x 10-5 indicating

that the finding was of substantial risk significance (Yellow).

a. Phase 1 screening logic, results and assumptions

In accordance with NRC Inspection Manual Chapter 0612, Appendix B, "Issue

Screening," the team determined that the licensee failed to ensure the

availability, reliability, and capability of safety systems that respond to initiating

events to prevent undesirable consequences of safe shutdown equipment. The

finding is more than minor because it affected the Mitigating Systems

Cornerstone, and it directly affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences.

The team evaluated the issue using the Significance Determination Process

(SDP) Phase 1 Screening Worksheet for the Initiating Events, Mitigating

Systems, and Barriers Cornerstones provided in Manual Chapter 0609,

Attachment 4, "Phase 1 - Initial Screening and Characterization of Findings.

This finding affected the Mitigating Systems Cornerstone. The inspectors

determined that the finding represented the actual loss of a single train (i.e. each

of the four contactors are considered a train) of non-Technical Specification

equipment, designated as risk-significant per 10 CFR 50.65, for greater than

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Therefore, the finding was potentially risk significant and a Phase 2

Estimation was required.

b. Phase 2 Risk Estimation

In accordance with Manual Chapter 0609, Appendix A, Attachment 1, "User

Guidance for Phase 2 and Phase 3 Reactor Inspection Findings for At-Power

Situations," the inspectors evaluated the subject finding using the presolved table

for the Risk-Informed Inspection Notebook for Fort Calhoun Power Station,

Revision 2.01a. The inspectors determined that the presolved table does not

contain a target suitable for evaluating the finding of interest and informed the

A-1 Attachment-2

Regional Senior Reactor Analyst that use of the risk-informed notebook would be

necessary.

The senior reactor analyst used the plant-specific risk-informed notebook to

estimate the risk associated with this finding. The following assumptions were

made:

1. Reactor Protection System Contactor M2 most likely failed on April 10, 2010,

when operators performed surveillance testing of the trip system prior to

restarting the reactor from a midcycle outage. The inspectors determined

that for the shading coil to jam the contactor in the closed position, the event

would have most likely been concurrent with the physical closing of the

contactor with the shading coil out of its recess. The inspectors determined

that vibration of the contactor during operation was insufficient to cause

catastrophic failure of the shading coil.

2. The failure was identified during a test of the system on June 14, 2010. It

took the licensee until June 15, 2010 to deenergize the vital power to the

contactor and confirm a half trip condition existed.

3. In accordance with Manual Chapter 0609, Appendix A, Attachment 2, Site

Specific Risk-Informed Inspection Notebook Usage Rules, Rule 1.1,

Exposure Time, the analyst evaluated the time frame over which the finding

impacted the risk of plant operations. The analyst determined that the

performance deficiency affected plant risk for 64 days. Therefore, the

exposure time used to represent the time that the performance deficiency

affected plant risk in the Phase 2 estimation was greater than 30 days.

4. In accordance with Manual Chapter 0609, Appendix A, Attachment 1,

Step 2.1.3, Find the Appropriate Target for the Inspection Finding in the Pre-

solved Table, the analyst determined that there was no appropriate target for

evaluating this performance deficiency. Therefore, the analyst utilized the

Risk-Informed Notebook for Fort Calhoun Station, Revision 2.01a to perform

the estimation.

5. In accordance with Manual Chapter 0609, Appendix A, Attachment 1,

Step 2.2.1, Select the Initiating Event Scenarios, the analyst determined

that only the anticipated transient without scram (ATWS) was affected.

Therefore, Table 3.9, SDP Worksheet for Fort Calhoun Power Station -

Anticipated Transients Without Scram (ATWS) was used for this estimation.

6. In accordance with Manual Chapter 0609, Appendix A, Attachment 2, Rule

1.2 Inspection Finding (Not Involving a Support System) that Increases the

Likelihood of an Initiating Event, the analyst increased the Initiating Event

Likelihood of the ATWS by one order of magnitude because the increase in

the frequency of the ATWS was not known.

7. The analyst determined that the failure of the M2 contactor did not directly

affect the ability of any other mitigation system to perform its function.

A-2 Attachment-2

8. The analyst gave no operator action credit for recovery of the M2 contactor

as discussed in Manual Chapter 0609, Appendix A, Attachment 1, Table 4,

"Remaining Mitigation Capability Credit." The requirements for such credit

(procedures, available parts and training under similar conditions) were not

met.

The dominant sequences from the notebook are documented in Table 1, and the

worksheet was provided as Supplement 2 to this document.

TABLE 1

Failure Reactor Protection System M2 Contactor

Phase 2 Sequences

Initiating Event Sequence Mitigating Functions Results

Anticipated Transient 1 ATWS-AFW 6

without SCRAM 2 ATWS-BORATE 7

3 ATWS-SRV 7

4 ATWS-TTP 8

Using the site-specific risk-informed notebook, the result from this estimation

indicated that the finding was of low to moderate safety significance (White).

However, the analyst determined that this estimate most likely increased the

initiating event likelihood by more than one order of magnitude and represented a

partial loss of capability of the manual reactor trip. Therefore, in accordance with

the recommendations of the site-specific risk-informed notebook, the finding was

evaluated by the analyst using Phase 3 methods.

c. Phase 3 Analysis

The following assumptions were made to support this Phase 3 analysis:

1. The Fort Calhoun plant-specific SPAR, Revision 3.50, as modified by the

analyst to include a detailed model of the reactor protection system, was the

best tool for quantifying the risk of the subject performance deficiency.

2. The M2 contactor was last cycled on April 10, 2010, when operators

performed surveillance of the trip system prior to restarting the reactor from a

midcycle outage.

3. Using best-available information, the inspectors determined that for the

shading coil to jam the contactor in the closed position, the event would have

most likely been concurrent with the physical closing of the contactor with the

shading coil out of its recess. The inspectors determined that vibration of the

contactor during operation was insufficient to cause catastrophic failure of the

shading coil. Therefore, Reactor Protection System Contactor M2 most likely

failed during the last successful cycle on April 10, 2010, prior to restarting the

reactor from a midcycle outage.

A-3 Attachment-2

4. The failure was identified during a test of the system on June 14, 2010. It

took the licensee until June 15, 2010, to deenergize the vital power to the

contactor and confirm a half trip condition existed.

5. In accordance with Manual Chapter 0609, Appendix A, Attachment 2, Site

Specific Risk-Informed Inspection Notebook Usage Rules, Rule 1.1,

Exposure Time, the analyst evaluated the time frame over which the finding

was reasonably known to have existed. Therefore, the analyst calculated an

exposure time of 64 days which includes the 63 days from April 10, 2010, to

June 14, 2010, plus the 1 day until the vital power to the contactor was

deenergized and a half trip condition confirmed to exist on June 15, 2010.

The 1 day was part of the repair time.

6. The baseline failure rate of an M-Contactor is 1.2 x 10-4/demand (Reference:

NUREG/CR-5500, Volume 10 Reliability Study: Combustion Engineering

Reactor Protection System, 1984 - 1998, Table C-7, Page C-22).

7. The analyst determined that the common cause failure probability should be

adjusted for the contactors. Essentially, there was an increased probability

that the contactors could have both failed in response to the same initiating

event. Common observations existed on both contactors, including: 1) at

least one shading coil would easily come out of its recess; 2) original

installation was during plant construction; 3) there were signs of age-related

fatigue; 4) subparts exhibited significant scratching and indentations; and

5) in November 2008 the licensee determined that the contactors were

obsolete and should have been replaced.

8. The analyst used NUREG 5485, Guidelines on Modeling Common-Cause

Failures in Probabilistic Risk Assessment, November 1998, for the common

cause assessment. The analyst used the alpha-factor method to evaluate

the common cause failure probability. This method is described in

NUREG 5485, Section 5.3. Parametric Representation of Common Cause

Basic Event Probabilities. The analyst used NUREG/CR-5500, Volume 10,

Reliability Study: Combustion Engineering Reactor Protection System,

1984-1998, Table E-6, Page E19 to determine the appropriate 2 factor for

Contactor M1. The 2 factor was 3.59 x 10-2/demand.

9. The analyst determined that the failure of the M2 contactor did not directly

affect the ability of any other mitigation system to perform its function.

10. Other than appropriately modeled manual trip actions, the analyst gave no

operator action recovery credit to restore the M2 contactor because there

was insufficient time to implement these actions before postulated

irrecoverable damage would occur and because parts were not available.

11. The failure to deenergize any 3 or more RPS clutch power supplies will result

in a failure of the automatic scram logic.

12. The failure to deenergize the following combinations of RPS clutch power

supplies will result in a failure of the automatic scram logic: PS1 and PS3;

PS2 and PS3; PS2 and PS4; or PS1 and PS4.

A-4 Attachment-2

13. The failure of either the associated M-contactor or the associated interposing

relay will prevent the trip contacts from opening. Example: If Interposing

Relay 1 fails to open, Contactor M1 will not deenergize. Also, if Contactor M1

fails, its contacts will not open. Therefore, given the failure of Contactor M2,

either Interposing Relay 1 or Contactor M1 failing would result in Clutch

Power Supplies 1 and 3 remaining energized.

14. Should the automatic RPS function fail to deenergize a clutch power supply,

the diverse scram system may cause the power supplies to deenergize by

opening Vital Breakers CB-CD and CB-AB.

15. The diverse scram system will only function to automatically trip the reactor

upon a high pressurizer pressure signal. Therefore, loss of coolant accidents

will not result in the diverse scram system initiating a reactor trip.

16. Manual Trip Pushbutton No. 1 is located on the main reactor control panel

and is designed to trip the reactor by deenergizing each of the M-contactor

coils.

17. Manual Trip Pushbutton No. 2 is located on the reactor protection system

panel and is designed to trip the reactor by deenergizing the holding

solenoids inside Vital Breakers CB-CD and CB-AB.

18. The baseline failure rate of a molded case circuit breaker with a normally

energized holding coil such as Vital Breakers CB-CD and CB-AB was

estimated as 2.5 x 10-3 /demand from binding of the holding coil plunger and

5.0 x 10-3 /demand from all other reasons (Reference EGG-SSRE-8875,

Generic Component Failure Database for Light Water and Liquid Sodium

Reactors, Idaho National Engineering Laboratory, 1990).

19. The probability that a licensed operator failing to manually trip the reactor

using Reactor Trip Pushbutton No. 1 upon failure of the automatic trip

systems is 1.5 x 10-3 /demand (Reference: SPAR-H Human Reliability

Analysis Method Worksheet, Supplement 3).

20. The probability that a licensed operator fails to trip the reactor with Reactor

Trip Pushbutton No. 2 upon failure of the automatic trip systems and the

failure of the reactor to trip upon actuating Manual Trip Pushbutton No. 1 is

5.0 x 10-1/demand based on the high dependency with the failure described

earlier (Reference: SPAR-H Human Reliability Analysis Method Worksheet,

Supplement 3).

21. Because the performance deficiency resulted in at least one shading coil in

both Contactors M1 and M2 being in a condition such that it would easily

come out of its recess, the analyst assumed that a seismic event could result

in the failure of the reactor protection system to initiate an automatic scram at

any time during the 1-year assessment period.

22. Based on analyst judgment, the analyst assumed that the failure described in

Assumption 21 would occur at or above the frequency that would cause a

A-5 Attachment-2

seismically-induced nonrecoverable loss of offsite power. At this frequency,

the offsite power resister stacks have sufficient countermotion in a single

plane that they break. The analyst noted that this level of seismic activity

would also likely fail a contactor with loose shading coils. However, the

analyst determined that the overall analysis was not very sensitive to this

assumption.

23. The analyst assumed that the probability of an anticipated transient without

scram (ATWS) was relatively low, even given the performance deficiency.

Therefore, the probability that a fire would initiate and be severe enough to

cause damage to plant equipment at the same time as an ATWS occurred

would be too low to cause a significant change in the overall analysis of

CDF.

24. Given Assumption 23, the analyst determined that the only fire scenarios that

would be significantly impacted by the subject performance deficiency would

be those that affect ATWS mitigation systems, specifically: emergency

boration; high pressure injection; auxiliary feedwater; shutdown cooling; and

high pressure recirculation.

Exposure Period

As documented in the main control room log, the reactor protection system trips

were tested on April 10, 2010, prior to restarting the reactor from a midcycle

outage. As documented in Assumption 3, this is when the failure of the M2

contactor most likely occurred. A quarterly surveillance of the system on

June 14, 2010, revealed that the contactor had failed. Therefore, the condition

existed 63 days before identification.

As stated in Assumption 4, it took an additional day for the licensee to

deenergize vital power to the contactor and verify that a half trip condition

existed. In accordance with the Risk Assessment of Operational Events

Handbook, Section 2.2, the exposure time for a component failure that was

determined to have occurred when the component was last functionally operated

should be the total time from the last successful operation to the unsuccessful

operation plus the repair time.

The total time from the last successful operation to the unsuccessful operation

was 63 days. The repair time until deenergization was 1 day. Therefore, the

total exposure time was then calculated to be the sum of these two, or 64 days.

Application of Recovery

As stated in the assumptions, other than appropriately modeled manual trip

actions, the analyst gave no operator action recovery credit for recovery of

Contactor M2 failure because there was insufficient time to implement these

actions before postulated irrecoverable damage would occur and because parts

were not available.

A-6 Attachment-2

Adjustment of Common Cause Component Failure Probability

As stated in the assumptions, reactor protection system Contactor M1 was

potentially affected by the performance deficiency. At least one shading coil

would easily come out of its recess, the contactor exhibited signs of age-related

fatigue, parts had significant scratching and indentations and the licensee had

determined in November 2008 that the contactor was obsolete and should have

been replaced.

The Risk Assessment of Operational Events Handbook, Volume 1, Internal

Events, Revision 1.01 stipulates, a component failure should be considered

independent (no common cause failure mechanism exists) ONLY when the

cause is well understood and there is no likelihood that the same components in

other trains or parallel component groups could fail for the same cause. A

presumption of zero common cause potential should be a rare occurrence.

The performance deficiency involved the licensees failure to correct the

degrading conditions of the reactor trip contactors in a timely manner. This

deficiency resulted in the failure of Contactor M2. The same performance

deficiency also applied to the other reactor protection system contactors.

Based on the inspection of Contactor M1, the analyst determined that there was

a likelihood that the same circumstances could exist in this contactor. Therefore,

the analyst determined that the failure probability of the common cause

component group (for Contactors M1 and M2) needed to be increased.

The analyst used NUREG 5485, Guidelines on Modeling Common-Cause

Failures in Probabilistic Risk Assessment, November 1998, for the common

cause assessment. The analyst used the alpha-factor method to evaluate the

common cause failure probability. This method is described in NUREG 5485,

Section 5.3. Parametric Representation of Common Cause Basic Event

Probabilities. The alpha factor model is a multi-parameter model which can

handle any redundancy level and is based on ratios of failures rates which makes

the assessment of its parameters easier when no statistical data are available.

The model has a simpler statistical model, and produces more accurate point

estimates as well as uncertainty distributions when compared to other parametric

models. The alpha factor model develops common cause failure frequencies

from a set of failure ratios and the total component failure rate.

For this specific case, there is a four-component common cause group,

Contactors M1, M2, M3 and M4. Assuming that Contactor M2 failed, the

conditional probability that Contactor M1 fails is of interest. For this particular

problem, the combination of one of M1 and M2 failing together or M3 and M4

failing together, a one-of-two-taken-twice logic scheme, must be evaluated.

There are two out of six such combinations in the group. Mathematically, the

conditional probability of Contactor M1 failing given that Contactor M2 has failed

is as follows:

A-7 Attachment-2

P(M1lM2) = P(M1 M2)

P(M2) (1)

In the basic parameter model, the numerator is given by Q2 if the independent

failures of two components is neglected (because they are negligible), and the

denominator is Qt.

Note: Qk is the probability that a specific group of k components fails from a

shared cause. (Q2 is a specific case of Qk)

Qt is the total component failure probability.

Neglecting independent failures of both components we have:

P(M1lM2) = Q2

Qt

If we assume the components are subject to a staggered-testing scheme, we

have :

Q2 = 2Qt

Substituting into Equation 1 gives:

P(M1lM2) = 2.

Note: k is the probability that when a common cause basic event occurs in a

common cause group it involves failure of k components.

According to NUREG/CR-5500, Volume 10, Reliability Study: Combustion

Engineering Reactor Protection System, 1984-1998, Table E-6, Page E19, the

alpha factor vector for the reactor trip contactors (four like components) is:

1 = 9.52E-1

2 = 3.59E-2

3 = 1.03E-2

4 = 2.20E-3

The common cause failure probability of Contactor M1 given that Contactor M2

has failed can be estimated as the 2 factor from the common cause component

failure group, or 3.59 x 10-2/demand.

The analyst noted that although the common cause failure probability of

Contactors M3 and M4 would also be increased, the impact would be

substantially lower than the impact of M1 failing because both M3 and M4 would

have to fail to cause a failure of the reactor protection system. The probability of

M3 and M4 failing from a common cause given a failure of M2 can be estimated

as 3.70 x 10-4/demand. This is two orders of magnitude less likely than the

failure of Contactor M1 alone and was not considered further in this analysis.

A-8 Attachment-2

Change in Risk from Internal Initiators

The analyst created a more detailed model of the reactor protection system than

that provided in the Fort Calhoun SPAR, Revision 3.50. Idaho National

Laboratories assisted in incorporating this model into the SPAR model and

validating the impact (the associated fault trees are provided as Supplement 4).

The analyst calculated the change in risk related to this performance deficiency

using the following method:

The analyst quantified the new model and reestablished a baseline risk for the

plant (1.24 x 10-5/year).

The analyst set Basic Event RPS-RYT-CF-M12, Common Cause Failure of

Contactors M1 and M2, to 3.59 x 10-2/demand indicating the increased common

cause failure probability derived above. This increase in common cause failure

probability indicated the new failure probability for Contactor M1 given that

Contactor M2 had already failed. The analyst then set Basic

Event RPS-RYT-CC-M2 Contactor M2 Fails to Open upon Demand, to the

house event TRUE, indicating that the contactor had failed to open on demand.

The analyst quantified the model and the results are provided in Table 2 below.

The analyst considered using the modified model in this manner to be the best

estimate of risk.

TABLE 2

Phase 3 Results

SPAR Quantification

Baseline 1.24 x 10-5/year

Case 1.57 x 10-4/year

Difference 1.44 x 10-4/year

64-Day Exposure 1.75 x 10-1 years

CDF (Internal) 2.53 x 10-5

Seismic Initiator 4.40 x 10-7/year

Internal Fires 1.29 x 10-6/year

CDF (External) 6.65 x 10-7

CDF (Total) 2.60 x 10-5

A-9 Attachment-2

Table 3 documents the major internal initiator sequences contributing

93.3 percent of the change in core damage frequency.

TABLE 3

Dominant Core Damage Sequences

Sequence Description CDF  % of Total

Transient 16-12 Plant Transient, Failure of 7.95 x 10-5/yr 55.1

Reactor Protection System*,

Failure of Relief Valves to Limit

Reactor Pressure.

SLOCA 20 Small-Break Loss of Coolant 2.16 x 10-5/yr 15.0

Accident and Failure of the

Reactor Protection System*.

LOMFW 16-12 Loss of Main Feedwater, Failure 9.94 x 10-6/yr 6.9

of Reactor Protection System ,

Failure of Relief Valves to Limit

Reactor Pressure.

LOCHS 16-12 Loss of Condenser Heat Sink, 7.95 x 10-6/yr 5.5

Failure of Reactor Protection

System*, Failure of Relief Valves

to Limit Reactor Pressure.

MLOCA 5 Medium-Break Loss of Coolant 7.21 x 10-6/yr 5.0

Accident and Failure of Reactor

Protection System*.

TRANS 16-10 Plant Transient, Failure of 4.55 x 10-6/yr 3.2

Reactor Protection System ,

Failure of Emergency Boration.

LOOP 23-12 Loss of Offsite Power, Failure of 3.57 x 10-6/yr 2.5

Reactor Protection System ,

Failure of Relief Valves to Limit

Reactor Pressure.

SPURSGIS 16-12 Spurious Steam Generator 3.17 x 10-6/yr 2.2

Isolation Signal, Failure of

Reactor Protection System*,

Failure of Relief Valves to Limit

Reactor Pressure.

TRANS 16-11 Plant Transient, Failure of the 1.14 x 10-6/yr 0.8

Reactor Protection System ,

Failure of Emergency Boration.

SGTR 21 Steam Generator Tube Rupture, 1.14 x 10-6/yr 0.8

Failure of the Reactor Protection

System*.

NOTE: Failure of the Reactor Protection System includes a failure of the reactor

protection system to generate an automatic reactor trip; failure of operator actions

to manually trip the reactor; and failure of the diverse scram system.

The analyst noted that, in accordance with Inspection Manual Chapter 0609,

Appendix A, Determining the Significance of Reactor Inspection Findings for

At-Power Situations, the internal initiators indicated that this performance

deficiency represented a finding of substantial safety significance (Yellow).

A-10 Attachment-2

Change in Risk from External Initiators

Seismic

The analyst used the techniques delineated in the Risk Assessment of Operation

Events Handbook, Volume 2, External Events, Revision 1.01, Section 4.0,

Seismic Event Modeling and Seismic Risk Quantification, to develop a

spreadsheet modeling the Fort Calhoun seismic hazard (Supplement 5). The

analyst then quantified the potential of having a seismically-induced loss of offsite

power with an ATWS (mitigated by a manual reactor trip) over the previous

1-year assessment period as a bounding condition. This was supported by

Assumptions 23 and 24. The results of this analysis are shown in Table 2.

Internal Fire

From the licensees Individual Plant Evaluation of External Events, the analyst

identified six fire areas that contained equipment needed for mitigating an ATWS.

These included fires in the main control room, cable spreading room, Fire

Area 20 (Auxiliary Building general area at ground level), and the charging pump

area. The analyst quantified the change in risk by evaluating the fire ignition

frequency, the nonsuppression probability, and the change in conditional core

damage probability with a known failure of the M2 contactor (See spreadsheet in

Supplement 6). The results of this analysis are shown in Table 2.

Large Early Release Frequency

In accordance with the guidance in Inspection Manual Chapter 0609,

Appendix H, this finding would not involve a significant increase in risk of a large,

early release of radiation because Fort Calhoun has a large, dry containment and

the dominant sequences contributing to the change in the core damage

frequency did not involve either a steam generator tube rupture or an inter-

system loss of coolant accident.

Assessment of Licensees Risk Evaluation

The analyst also reviewed the licensees comments provided on the reactor

protection system fault tree. The following comments were assessed:

1. The human error probability for human failure event RPS-XHE-XM-SCRAM,

Operator Fails to Manually Trip the Reactor, is 1.0E-02. Analysis with

SPAR-H suggests that a more appropriate probability would be 7.5E-04.

The analyst calculated a new human error probability using the SPAR-H

method, derived by the Idaho National Laboratory (documented in

Supplement 3). The new value, representing the best available information

for this failure, was 1.5 x 10-3/demand as documented in Assumption 19.

In addition, the analyst requantified the assessment of this finding using the

licensees value as a sensitivity. The result indicated a change of much less

than 1 percent of the total core damage frequency of the case (See Table 4

A-11 Attachment-2

for results). Therefore, the analyst determined that this evaluation was not

sensitive to the probability of operators failing to manually trip the reactor.

2. The human error probability for human failure event RPS-XHE-ERROR,

Operator Fails to De-energize CEDM power Supply (Recovery Event), is

4.4E-01. Analysis with SPAR-H suggests that a more appropriate probability

would be 1.0E-03.

The analyst calculated a new human error probability using the SPAR-H

method, derived by the Idaho National Laboratory (documented in

Supplement 3). The new value, representing the best available information

for this failure, was 5.0 x 10-1/demand as documented in Assumption 20.

The analyst noted that the licensees analysis did not include the dependency

between this action and Basic Event RPS-XHE-XM-SCRAM. This

dependency is discussed under Assumption 20 and documented in

Supplement 3. The analyst determined that a dependency resulted based on

the action being performed by the same crew, close in time to the previous

action, and only one additional cue being the failure of the first action. After

discussing this with licensee analysts, they stated that there were no

additional cues or indications that could dispute this dependency.

However, the analyst requantified the assessment of this finding using the

licensees value as a sensitivity. The result indicated a change of much less

than 1 percent of the total core damage frequency of the case (See Table 4

for results).

Therefore, the analyst determined that this evaluation was not sensitive to the

probability of operators failing to manually trip the reactor.

3. It appears that there is logic representing test and maintenance, or bypass,

which would prevent an M coil from de-energizing. An example is

Gate RPS-TRIP-PTH1-BYP. These types of activities are not performed

online. Refer to drawing E-23866-411-003. An example of a test that is

performed uses holding coils to prevent the AD contacts from opening if the

RPS 2/4 trip logic is satisfied. However, any of the other 2/4 trip

combinations - AB, AC, BC, CD, or BD - would still de-energize the M coils.

For example, see the logic combinations at drawing coordinate C7.

The analyst noted that the trip and bypass functions are utilized on a trip unit

basis and do not affect the entire trip path. To assess the effect of this

modeling on the final evaluation, the analyst viewed all cutsets that included

the test/maintenance and/or bypass basic events. Only five cutsets were

greater than the 1 x 10-13/year truncation limit and these comprised less than

a tenth of a percent of the final change in core damage frequency.

The appropriate changes to the reactor protection system to reflect placing

trip units in the bypass or trip condition will be made prior to incorporating the

model into the SPAR for unlimited use. As a sensitivity study, the analyst

adjusted appropriate basic events so that all trip and bypass conditions would

A-12 Attachment-2

be removed from the final cutsets. This did not change the first three

significant figures from the best estimate result (See Table 4 for results).

Therefore, the analyst determined that this evaluation was not sensitive to the

trip and bypass fault trees in the modified SPAR model for the reactor

protection system.

4. It is unclear how gate RPS-DSS-NOSGNL would be used. Diverse Scram

System (DSS) is actuated by high pressurizer pressure, so presumably the

purpose of this gate is to disable automatic DSS for initiating events that

cannot result in high pressurizer pressure.

The analyst explained to the licensee analysts that their presumption was

correct. Gate RPS-DSS-NOSGNL was used to model Assumption 15 No

additional licensee comments were made on this subject.

5. Refer to drawing E-23866-411-003. The fault tree appears to be missing the

interposing relays IR-1, IR-2, IR-3, and IR-4. For example, see IR-1 at

drawing coordinate C7.

The analyst agreed with the licensee analysts. The interposing relays were

added to the model for completeness and to add a better understanding of

the risk associated with the performance deficiency. The fault tree was

updated to model the interposing relays as described under Assumption 13.

6. It appears that the fault tree does not contain failure events for the manual trip push buttons and DSS switches. Perhaps those are subsumed into the

human error probabilities.

The analyst agreed with the licensee analysts. The manual trip pushbuttons

and DSS switches were added to the fault tree for completeness. The fault

tree was updated to model the pushbuttons as described under

Assumptions 16, 17, 19, and 20.

7. Generic analyses performed by Combustion Engineering for ATWS scenarios

using best estimate model assumptions and acceptance criteria that was

used to support PRA success criteria indicates that success could be

achieved if only half of the CEDM clutches are de-energized for some

initiators.

The analyst assessed this comment by the licensee and noted that the

generic analyses performed by Combustion Engineering were not

incorporated into the licensees PRA model. The licensees model indicates

that the failure of more than two control rods to insert represents an ATWS.

Sans additional plant specific evaluation and a complete understanding of the

initiators involved in the study, the analyst continued to assume that best

available information indicates that a failure of half the control rods to insert at

Fort Calhoun Station represents an ATWS.

Additionally, the analyst evaluated the probability that a reactor trip signal

would result in only one half of the control rods inserting. The analyst noted

A-13 Attachment-2

that there are no specific active component failures in the reactor protection

system that would result in half the rods falling. For this to occur, the failure

of the M contactors would have to cause 2 of the 5 contacts to fail in the

closed position while an additional 2 would have to open.

Therefore, if this were determined to be a viable failure mechanism, it results

in a one in sixteen probability of the contactors failing such that half the

control rods would fall.

As a sensitivity, the analyst assumed that half the rods falling into the core

would only have a major impact on sequences that did not result in rapid

pressurization of the reactor coolant system. The analyst hand calculated the

worst-case results and determined that the change in risk was approximately

1.8 percent (See Spreadsheet in Supplement 7).

8. In your common cause model, 2 includes six combinations, but only 2 are

involved in the common cause failure of interest for this case. This results in

an overprediction of the failure probability of Contactor M1. We recommend

that the common cause failure probability for Contactor M1 given the failure

of Contactor M2 should be 1/3 2 as opposed to 2.

The use of 2 is clearly delineated in the section Adjustment of Common

Cause Component Failure Probability, above. Had we wanted the

conditional probability of any of the contactors failing (Contactor M1 or

Contactor M3 or Contactor M4), given a failure of Contactor M2, we would

have:

P (M1 M3 M4lM2) = P [(M1 M2) (M3 M2) (M4 M2)]

P (M2) (2)

Equation 2 is a special case of Equation 1. Under the rare event

approximation, and ignoring independent failures, this equation reduces to:

P (M1 M3 M4lM2) = 3Q2

Qt

Therefore, for the more general case suggested by the licensee, using

Equation 2 we would find the result to be:

P (M1 M3 M4lM2) = 3Q2 = 32Qt = 32

Qt Qt

Again, for the specific case of the probability that Contactor M1 fails given

Contactor M2 has failed, this suggests that 2 is the best representation of

this common cause failure probability.

A-14 Attachment-2

Additional Sensitivity Studies

To better understand the impact of the major assumptions on the final change

in core damage frequency and specifically address comments made in the

peer reviews, the analyst evaluated the following scenarios:

  • The probabilities of operators failing to manually trip the reactor using

Pushbuttons 1 and 2, respectively, were replaced with the values

calculated by the licensees risk analysts;

  • Channel trip and bypass terms were set to the house event FALSE,

indicating that they could not affect the failure of the reactor protection

system;

  • The common cause failure probability for Contactors M1 and M2 was

replaced with common cause basic events representing the upper and

lower bounds of the range of probabilities for the failure of

Contactor M1 given that Contactor M2 failed. This probability range

was hand calculated by experts from Idaho National Laboratories;

  • The model was revised to indicate that the diverse scram system

would trip the reactor following a small-break loss of coolant accident;

  • The common cause failure probability for Contactors M1 and M2 was

reset to its original value and the independent failure probabilities of

each of the four contactors were increased as opposed to adjusting

the common cause failure probabilities. The probabilities used were

derived by dividing the one known component failure by the number of

contactor cycles estimated for a 1-year (Higher) and a 12-year

(Lower) period, respectively;

  • The change in risk was hand calculated given that the M contactors

could fail in a manner that would cause 1/2 the control rods to fall into

the core and that 1/2 the rods would appropriately control reactivity for

lower pressure sequences (documented in Supplement 7); and

  • The failure probability for Vital Breakers CB-AB and CB-CD were

replaced with values representing: 1) twice the failure rate, 2) the

failure rate of molded case circuit breakers without holding coils, and

3) the failure rate of reactor trip breaker shunt trips.

The results of these sensitivity studies are shown in Table 4.

A-15 Attachment-2

TABLE 4

Internal Events Sensitivity Study

Sensitivity Basic Event Initial Value Adjusted Baseline Case CDF Change*

Value

(Percent)

-5 -4 -5

Best 1.24 x 10 /yr 1.57 x 10 /yr 2.53 x 10 N/A

Estimate

Manual RPS-XHE- 5.0 x 10-1 1 x 10-3 1.24 x 10-5/yr 1.57 x 10-4/yr 2.53 x 10-5 0.00 %

Trip ERROR

RPS-XHE-XM- 1.5 x 10-3 7.5 x 10-4

SCRAM

Channel RPS-CBI-CF- 7.7 x 10-7 FALSE 1.24 x 10-5/yr 1.57 x 10-4/yr 2.53 x 10-5 0.00 %

Trip and ALL

Bypass RPS-CBI-CF- 1.7 x 10-6 FALSE

4OF6

RPS-CBI-CF- 1.7 x 10-7 FALSE

6OF6

RPS-RYL-CF- 1.6 x 10-8 FALSE

M12BYP

RPS-RYL-CF- 4.3 x 10-8 FALSE

ALL

RPS-RYL-CF- 1.6 x 10-7 FALSE

M12TM

Alpha RPS-RYT-CF- 3.59 x 10-2 4.80 x 10-2 1.24 x 10-5/yr 2.05 x 10-4/yr 3.38 x 10-5 (33.6 %)

Factor M12

Method

(High)

Alpha RPS-RYT-CF- 3.59 x 10-2 1.25 x 10-2 1.24 x 10-5/yr 6.30 x 10-5/yr 8.87 x 10-6 64.9 %

Factor M12

Method

(Low)

Small- Small-Break LOCA actuates Diverse Scram 1.24 x 10-5/yr 1.39 x 10-4/yr 2.22 x 10-5 12.1 %

Break System

LOCA

Higher RPS-RYT-CC-M1 1.2 x 10-4 9.2 x 10-3 1.24 x 10-5/yr 4.95 x 10-5/yr 6.51 x 10-6 97.8 %

Independent

Failure Rate RPS-RYT-CC-M2 1.2 x 10-4 9.2 x 10-3

RPS-RYT-CC-M3 1.2 x 10-4 9.2 x 10-3

(1 year)

RPS-RYT-CC-M4 1.2 x 10-4 9.2 x 10-3

Lower RPS-RYT-CC-M1 1.2 x 10-4 7.6 x 10-4 1.24 x 10-5/yr 1.56 x 10-5/yr 5.61 x 10-7 74.3 %

Independent

RPS-RYT-CC-M2 1.2 x 10-4 7.6 x 10-4

A-16 Attachment-2

Failure Rate RPS-RYT-CC-M3 1.2 x 10-4 7.6 x 10-4

(12 years) RPS-RYT-CC-M4 1.2 x 10-4 7.6 x 10-4

Half Trip Half the Rods Falling would result in 1.22 x 10-5/yr 1.54 x 10-4/yr 2.49 x 10-5 1.7 %

Acceptable acceptable conditions for lower pressure

failures, but would occur only 1 in 16 times.

Circuit RPS-BSN-FO- 5.0 x 10-3 1.0 x 10-2 1.24 x 10-5/yr 2.30 x 10-4/yr 3.81 x 10-5 (50.7 %)

Breaker CBAB

Double RPS-BSN-FO- 5.0 x 10-3 1.0 x 10-2

Failure Rate CBCD

Standard RPS-BSN-FO- 5.0 x 10-3 2.55 x 10-3 1.24 x 10-5/yr 1.21 x 10-4/yr 1.90 x 10-5 24.9 %

Circuit CBAB

Breaker RPS-BSN-FO- 5.0 x 10-3 2.55 x 10-3

CBCD

Reactor RPS-BSN-FO- 5.0 x 10-3 3.29 x 10-4 1.24 x 10-5/yr 8.82 x 10-5/yr 1.33 x 10-5 47.4 %

Trip Shunt CBAB

Trip RPS-BSN-FO- 5.0 x 10-3 3.29 x 10-4

CBCD

  • NOTE: The percent change shown is for combined internal and external events results.

A-17 Attachment-2