UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

)

In the Matter of )

)

AMERENUE ) Docket No. 52-037-COL (Callaway Plant Unit 2) )

)

AP1000 DESIGN CERTIFICATION AMENDMENT ) NRC-2010-0131 (10 C.F.R. Part 52) ) RIN 3150-A18

)

CALVERT CLIFFS NUCLEAR PROJECT, L.L.C. ) Docket No. 52-016-COL (Calvert Cliffs Nuclear Power Plant, Unit 3) )

)

DETROIT EDISON CO. ) Docket No. 52-033-COL (Fermi Nuclear Power Plant, Unit 3) )

)

DUKE ENERGY CAROLINAS, L.L.C. ) Docket Nos. 52-018-COL, (William States Lee III Nuclear Station, Units 1 and 2) ) 52-019-COL

)

ENERGY NORTHWEST ) Docket No. 50-397-LR (Columbia Generating Station) )

)

ENTERGY NUCLEAR GENERATION CO. and ) Docket No. 50-293-LR ENTERGY NUCLEAR OPERATIONS, INC. )

(Pilgrim Nuclear Power Station) )

)

ENTERGY NUCLEAR OPERATIONS, INC. ) Docket Nos. 50-247-LR, (Indian Point Nuclear Generating Station, Units 2 and 3) ) 50-286-LR

)

ESBWR DESIGN CERTIFICATION AMENDMENT ) NRC-2010-0135 (10 C.F.R. Part 52) ) RIN-3150-AI85

)

FIRSTENERGY NUCLEAR OPERATING CO. ) Docket No. 50-346-LR (Davis-Besse Nuclear Power Station, Unit 1) )

)

FLORIDA POWER AND LIGHT CO. ) Docket Nos. 52-040-COL, (Turkey Point, Units 6 and 7) ) 52-035-COL

)

LUMINANT GENERATION CO. L.L.C. ) Docket Nos. 52-034-COL, (Comanche Peak Nuclear Power Plant, Units 3 and 4) ) 52-035-COL

)

NEXTERA ENERGY SEABROOK, L.L.C. ) Docket No. 50-443-LR (Seabrook Station, Unit 1) )

)

PACIFIC GAS AND ELECTRIC CO. ) Docket Nos. 50-275-LR, (Diablo Canyon Power Plant, Units 1 and 2) ) 50-323-LR

)

PPL BELL BEND, L.L.C. ) Docket No. 52-039-COL (Bell Bend Nuclear Power Plant) )

)

PROGRESS ENERGY CAROLINAS, INC. ) Docket Nos. 52-022-COL, (Shearon Harris Nuclear Power Plant, Units 2 and 3) ) 52-023-COL

)

PROGRESS ENERGY FLORIDA, INC. ) Docket Nos. 52-029-COL, (Levy County Nuclear Power Plant, Units 1 and 2) ) 52-030-COL

)

SOUTH CAROLINA ELECTRIC AND GAS CO. and ) Docket Nos. 52-027-COL, SOUTH CAROLINA PUBLIC SERVICE AUTHORITY ) 52-028-COL (also referred to as SANTEE COOPER) )

(Virgil C. Summer Nuclear Station, Units 1 and 2) )

)

SOUTHERN NUCLEAR OPERATING CO. ) Docket Nos. 52-025-COL, (Vogtle Electric Generating Plant, Units 3 and 4) ) 52-026-COL

)

SOUTH TEXAS PROJECT NUCLEAR OPERATING CO. ) Docket Nos. 52-012-COL, (South Texas Project, Units 3 and 4) ) 52-013-COL

)

TENNESSEE VALLEY AUTHORITY ) Docket Nos. 52-014-COL, (Bellefonte Nuclear Power Plant, Units 3 and 4) ) 52-015-COL

)

TENNESSEE VALLEY AUTHORITY ) Docket No. 50-391-OL (Watts Bar, Unit 2) )

)

VIRGINIA ELECTRIC AND POWER CO. ) Docket No. 52-017-COL d/b/a DOMINION VIRGINIA POWER and )

OLD DOMINION ELECTRIC COOPERATIVE )

(North Anna, Unit 3) )

)

ORDER The Commission is in receipt of a petition to suspend adjudicatory, licensing, and rulemaking activities, and requesting other relief, in the captioned matters.1 This order is to set a schedule for further briefing. Any supplements to the petition may be filed no later than 1

See generally Emergency Petition to Suspend All Pending Reactor Licensing Decisions and Related Rulemaking Decisions Pending Investigation of Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident (served in various dockets between April 14, and April 18, 2011) (Petition). The Commission received a corrected petition on April 18, 2011.

Thursday, April 21, 2011.2 Any person may file an answer to the petition, or a brief amicus curiae, no later than Monday, May 2, 2011.

This order is issued pursuant to my authority under 10 C.F.R. §§ 2.346 (a) and (j).

IT IS SO ORDERED.

For the Commission (NRC SEAL)

/RA/

Annette L. Vietti-Cook Secretary of the Commission Dated at Rockville, Maryland, this 19th day of April, 2011 2

See, e.g., Petition at 4 n.2.

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

NEXTERA ENERGY SEABROOK, LLC ) DOCKET NO. 50-443-LR (Seabrook Station, Unit 1) )

)

(License Renewal) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Scheduling Order of the Secretary (regarding petitions to suspend adjudicatory, licensing and rulemaking activities), dated April 19, 2011, have been served upon the following persons by Electronic Information Exchange.

U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Board Panel Office of the General Counsel Mail Stop: T-3F23 Mail Stop: O-15D21 Washington, DC 20555-0001 Washington, DC 20555-0001 Catherine Kanatas Administrative Judge catherine.kanatas@nrc.gov Paul S. Ryerson, Chair Emily Monteith, Esq.

paul.ryerson@nrc.gov emily.monteith@nrc.gov Brian Newell, Paralegal Administrative Judge brian.newell@nrc.gov Michael F. Kennedy David Roth, Esq.

michael.kennedy@nrc.gov david.roth@nrc.gov Maxwell Smith, Esq.

Administrative Judge maxwell.smith@nrc.gov Richard E. Wardwell Mary Spencer, Esq.

richard.wardwell@nrc.gov mary.baty@nrc.gov Edward Williamson, Esq.

Anthony C. Eitreim, Esq. elw2@nrc.gov Chief Counsel Megan Wright, Esq.

ace1@nrc.gov megan.wright@nrc.gov Hillary Cain, Law Clerk OGC Mail Center hillary.cain@nrc.gov OGCMailCenter@nrc.gov U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Office of the Secretary of the Commission Office of Commission Appellate Adjudication Mail Stop: O-16C1 Mail Stop: O-16C1 Washington, DC 20555-0001 Washington, DC 20555-0001 Hearing Docket ocaamail@nrc.gov hearingdocket@nrc.gov

NEXTERA ENERGY SEABROOK, LLC (Seabrook Station Unit 1) - Docket No. 50-443-LR Scheduling Order of the Secretary (regarding petitions to suspend adjudicatory, licensing and rulemaking activities)

NextEra Energy Seabrook, LLC Beyond Nuclear 801 Pennsylvania Avenue, N.W., #220 6930 Carroll Avenue, Suite 400 Washington, DC 20004 Takoma Park, MD 20912 Steven C. Hamrick, Esq. Paul Gunter, Director, Reactor Oversight Project steven.hamrick@fpl.com paul@beyondnuclear.org Kim Bartels, Paralegal kim.bartels@fpl.com New Hampshire Sierra Club 40 N. Main Street NextEra Energy Seabrook, LLC Concord, NH 03870 700 Universe Boulevard Kurt Ehrenberg, Field Organizer Juno Beach, FL 33408 kurtehrenberg@gmail.com William Blair, Esq.

william.blair@fpl.com Seacoast Anti-Pollution League Mitchell S. Ross, Esq. P.O. Box 1136 mitch.ross@fpl.com Portsmouth, NH 03802 Doug Bogen, Executive Director Counsel for the Applicant dbogen@metrocast.net Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, N.W. State of New Hampshire Washington, DC 20037-1122 Office of the Attorney General David R. Lewis, Esq. 33 Capitol Street david.lewis@pillsburylaw.com Concord, NH 03301 K. Allen Brooks, Assistant Attorney General k.allen.brooks@doj.nh.gov Friends of the Coast and Michael A. Delaney, Attorney General New England Coalition (NEC) michael.a.delaney@doj.nh.gov Post Office Box 98 Peter Roth, Assistant Attorney General Edgecomb, ME 04556 peter.roth@doj.nh.gov Raymond Shadis, Pro Se Representative shadis@prexar.com State of Massachusetts Office of the Attorney General Environmental Protection Division One Ashburton Place, 18th Floor Boston, MA 02108 Matthew Brock, Assistant Attorney General matthew.brock@state.ma.us Jennifer Venezie, Paralegal jennifer.venezia@state.ma.us

[Original signed by Linda D. Lewis]

Office of the Secretary of the Commission Dated at Rockville, Maryland this 19th day of April 2011 2