Submittal of Pre-op Test Instruction
ML103610114
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 12/21/2010
From: Bajestani M
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
2-PTI-031B-01
Download: ML103610114 (130)


Text

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 December 21, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391

Subject:

Watts Bar Nuclear Plant (WBN) Unit 2 - Submittal of Pre-op Test Instruction The following approved WBN 2 Pre-op Test Instruction (PTI) is enclosed:

If you have any questions, please contact Pete Olson at (423) 365-3294.

Sincerely, Masoud Baj st ni Watts Bar it Vice President

U.S. Nuclear Regulatory Commission Page 2 December 21, 2010 cc (Enclosure):

U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381

c' WATTS BAR NUCLEAR PLANT UNIT 2 STARTUP TITLE: Incore Instrument Room Air Conditioning System Instruction No: 2-PTI-031 B-01 Revision No: 0000 PREPARED BY: Bethany B Meniman DATE "/o PRIlNT KArlSI G~ RE REVIEWED BY: Keith Jones k*_('L , DATE ?- z-o PRINT NAME/ SIGNATURE INSTRUCTION APPROVAL JTG MEETING 'k, -/0-- 0 JTG CHAIR DATE V3 APPROVED B% x DATE\"V""\yj PREOPERATIONAL STARTUP MANAGER TEST RESULTS APPROVAL JTG MEETING NO:

JTG CHAIRMAN: DATE APPROVED BY: DATE PREOPERATIONAL STARTUP MANAGER

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 2 of 128 Revision Log Revision Affected or Change Effective Page Number Date Numbers Description of RevisionlChange 0 ALL This procedure was written using the Unit I test

.1701 " ~procedure PTI-031 G-01 Rev I as a guide with CN-2 incorporated.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 3 of 128 Table of Contents

1.0 INTRODUCTION

................................................................................................... 5 1.1 Test Objectives ........................................................................................................ 5 1.2 S c o p e .......................................................... ................................................................. 5

2.0 REFERENCES

..................................................................................................... 6 2.1 Performance References ........................................................................................ 6 2.2 Developmental References ...................................................................................... 6 3.0 PRECAUTIONS AND LIMITATIONS ..................................................................... 10 4.0 PREREQUISITE ACTIONS .................................................................................... 12 4.1 Preliminary Actions ................................................................................................. 12 4.2 Special Tools, Measuring and Test Equipment (M&TE), Parts, and S up p lie s ...................................................................................................................... 14 4.3 Field Preparations ....................................... I.......................................................... 15 4.4 Approvals and Notifications ................................................................................... 17 5.0 ACCEPTANCE CRITERIA ....................................... 18 6.0 PERFORMANCE .................................................................................................... 22 6.1 Incore Instrument Room Air Conditioning System Containment Isolation Valves Control Logic ............................................................................................... 23 6.2 Incore Instrument Room Air Conditioning System Containment Isolation Valves Close on Simulated Phase A Containment Isolation ................................... 48 6.3 Incore Instrument Room Air Conditioning System Containment Isolation Valves Close on Loss of Electrical Power ............................................................. 57 6.4 Incore Instrument Room Air Conditioning System Containment Isolation Valves Close on Loss of Control Air ...................................................................... 66 6.5 Incore Instrument Room 2A/2B Pump and Air Handling Unit Local O p e ra tio n .................................................................................................................... 75 6.6 Incore Instrument Room 2A/2B Air Handling Unit, Pump, Chiller, and Damper Normal Operation ...................................................................................... 88 6.7 Incore Instrument Room 2A/2B Air Handling Unit Stop on Simulated Phase A Containment Isolation ............................................................................... 99 6.8 Incore Instrument Room Redundant Unit Start on Low Air Flow ............................... 106

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 4 of 128 Table of Contents (continued) 6.9 Incore Instrument Room 2A/2B Circulation Pump Trip on Low Tank Le v e l ......................................................................................................................... 10 9 7.0 POST PERFORMANCE ACTIVITY .......................................................................... 115 8.0 R E C O R D S ................................................................................................................ 115 Appendix A: TEST PROCEDURES/INSTRUCTIONS REFERENCE R EV IEW ................................................................................................... 116 Appendix B: TEMPORARY CONDITION LOG ............................................................. 117 Appendix C: PERMANENT PLANT INSTRUMENTATION LOG .................................. 118 Table 1: ELECTRICAL LINEUP ............................................................................. 119 Table 2: VA LV E LIN EU P ........................................................................................ 121 Table 3: SW ITC H LINEUP .................................................................................... 127 Appendix D: Background Calculations ....................................................................... 128

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 5 of 128

1.0 INTRODUCTION

1.1 Test Objectives The object of this test is to demonstrate that the Incore Instrument Room Air Conditioning System functions in accordance with design requirements.

1.2 Scope This test demonstrates the operability of the Incore Instrument Room Air Conditioning System to ensure the following:

A. The Incore Instrument Room Air Conditioning System Containment Isolation Valves function in accordance with design requirements.

1. The Incore Instrument Room Air Conditioning System Containment Isolation Valves stroke close time is equal to or less than design requirements.
2. The Incore Instrument Room Air Conditioning System Containment Isolation Valve Control Room alarms and indicators operate in accordance with design requirements.
3. The Incore Instrument Room Air Conditioning System Containment Isolation Valves close on a simulated Phase A Containment Isolation signal and remain closed after a simulated Phase A Containment Isolation signal reset.
4. The Incore Instrument Room Air Conditioning System Containment Isolation Valves fail closed on loss of electrical power.
5. The Incore Instrument Room Air Conditioning System Containment Isolation Valves fail closed on loss of control air.

B. Incore Instrument Room Air Conditioning System Air Handling Units maintain desired air flow.

C. Incore Instrument Room Air Conditioning System controls, interlocks, and alarms function in accordance with design requirements.

D. Essential Raw Cooling Water Supply Valves automatic controls function in accordance with design requirements:

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 6 of 128

2.0 REFERENCES

2.1 Performance References A. SMP-9.0, Conduct of Test B. GTM-05, HVAC Air Balance 2.2 Developmental References A. Final Safety Analysis Report

1. FSAR, Amendment 100
a. SubSection 6.2.4, Containment Isolation System
b. Table 6.2.4-1, Pgs 38-39, Watts Bar Nuclear Plant Containment Penetrations and Barriers
c. SubSection 9.2.1, Essential Raw Cooling Water (ERCW)
d. SubSection 9.4.7, Containment Air Cooling System
e. Table 14.2-1, Sheets 4/5, Essential Raw Cooling Water System Test Summary
f. Table 14.2-1, Sheets 38/39, Containment Ventilation System Test Summary
g. Table 14.2-1, Sheet 83, Containment Isolation System Test Summary B. Drawings
1. Flow Diagrams
a. 2-47W866-1, Rev 2, Flow Diagram Heating and Ventilation Air Flow
b. 2-47W865-5, Rev 0, Flow Diagram Air Conditioning Chilled Water, DRAs 53763-030, -032 Rev 1, and -034 Rev 0 DRAs 53764-002 & -031 Rev 0, DRAs 54923-027 & -028 Rev 0, -061 thru -066 Rev 0
c. 2-47W845-2, Rev 0, Flow Diagram Essential Raw Cooling Water System

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 7 of 128 2.2 Developmental References (continued)

d. 2-47W848-9, Rev 1, Mechanical Flow Diagram Control Air, DRA 53340-001 Rev 0
2. Electrical
a. 2-45B655-5C, Rev 0, Main Control Room Annunciator Inputs Window Box XA-55-5C
b. 2-45B655-E5C, Rev 0, Electrical Annunciator Window Box XA-55-5C Engraving
c. 45N2635-15, Rev 11, Local Instrument Panels Connection Diagrams, DRAs 54172-314 & -315 Rev 0
d. 45N2648-2, Rev 6, Unit Control Board Panel 2-M-9 Connection Diagrams
e. 45N2648-3, Rev 7, Unit Control Board Panel 2-M-9 Connection Diagrams
f. 45N2648-4, Rev 13, Unit Control Board Panel 2-M-9 Connection Diagram
g. 45N2676-4, Rev 16, Solid State Protection Sys Train A Connection Diagram
h. 45N2676-5, Rev 10, Solid State Protection Sys Train A Connection Diagram
i. 45N2677-4, Rev 18, Solid State Protection Sys Train B Connection Diagram
j. 45N2677-5, Rev 9, Solid State Protection Sys Train B Connection Diagram
k. 45W2766-6, Rev 11, 480V Reactor MOV Board 2A1 -A Connection Diagram, DRA 54172-310, Rev 0
1. 45B2766-16A, Rev 8, 480V Reactor MOV Board 2A1 Conn Diag -

Compt 16A

m. 45B2766-18C, Rev 4, 480V Reactor MOV Board 2A1 Conn Diag -

Compt 18C

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 8 of 128 2.2 Developmental References (continued)

n. 45W2768-9, Rev 5, 480V Reac MOV Board 2B1-B Connection Diagram, DRA 54172-311, Rev 0
o. 45B2768-16A, Rev 8, 480V Reac MOV BD 2B1-B Conn Diag - Compt 16A
p. 45B2768-18C, Rev 3, 480V Reac MOV BD 2B1-B Conn Diag - Compt 18C
q. 2-45W600-31-1, Rev 0, Air Conditioning System Schematic Diagrams
r. 2-45W600-57-1 1, Rev 0, Separation and Misc Aux Relays Schematic Diagrams
s. 45W703-7, Rev 19, 125V Vital Battery Board III Panel 4 Connection Diagram
t. 45W703-8, Rev 20, 125V Vital Battery Board IV Panel 4 Connection Diagram
u. 2-45W751-1, Rev 1, 480V Reac MOV BD 2A1-A Single Line
v. 2-45W751-7, Rev 1, 480V Reac MOV BDS 2B1-B Single Line, DRA 53292-092 Rev 0
w. 2-45W760-31-6, Rev 0, Air Conditioning System Schematic Diagrams, DRAs 53287-086 & -088 Rev 0, DRAs 53292-081 & -089 Rev 0
x. 45W2766-7, Rev 7, 480V Reactor MOV BD 2A1-A Connection Diagram
y. 2-47B601-55-3, [LATER], Electrical Instrument Tabulation, DRA 52453-006 Rev 0
z. 2-47B601-55-4, [LATER], Electrical Instrument Tabulation, DRA 52453-007 Rev 0
3. Mechanical
a. 2-47W600-198, Rev 0, Electrical Instruments and Controls
b. 2-47W600-221, Rev 0, Electrical Instruments and Controls

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 9 of 128 2.2 Developmental References (continued)

4. Logic/Control
a. 2-47W610-31-5, Rev 2, Electrical Control Diagram Air Conditioning System
b. 2-47W611-31-7, Rev 1, Electrical Logic Diagram Air Conditioning System
c. 2-47W610-67-3, Rev 3, Electrical Control Diagram ERCW System
d. 2-47W611-67-3, Rev 1, Electrical Logic Diagram Essential Raw Cooling Water C. Vendor Documents
1. D02207-1, Rev 0, Schematic Wiring Diagram For PWC120S3-T4-Z (Contract Number 43993)

D. Documents

1. WBN2-30RB-4002, Rev 1, System Description - Reactor Building Ventilation System
2. WBN2-67-4002, Rev 1, Essential Raw Cooling Water System, System 67
3. WBNP Technical Specifications, Unit 2, SubSection 3.6.3, Containment Isolation Valves
4. 2-SOI-30.04, [DRAFT]
5. 2-TSD-31 B-01, Rev 1, Containment Instrument Room Cooling System (31)
6. 2-TSD-88-05, Rev 1, Containment Isolation System
7. G-37, Rev 4, General Engineering Specification for Testing and Balancing of HVAC Systems During Installation, Modification, and Maintenance
8. 2-PTI-067-03, ERCW Valve Logic Test [LATER]

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 10 of 128 3.0 PRECAUTIONS AND LIMITATIONS A. Standard precautions shall be followed for working around energized electrical equipment in accordance with TVA Safety Procedure 1021.

B. Steps may be repeated if all components cannot be tested in a step. However, if the test has been exited, prerequisite steps must be re-verified and a Chronological Test Log (CTL) entry made.

C. Component tags and labels may differ slightly (abbreviations, punctuation, letter case, etc.) from the description given in this test. If this situation occurs, it shall not be considered a test deficiency or procedure deviation. It shall be documented in the CTL and reconciled by way of a plant labeling request, drawing discrepancy, or pen and ink procedure change, as appropriate.

D. All wires removed/lifted from a terminal shall be identified, grouped together, and taped or covered with an insulator to prevent personnel or equipment hazard and possible spurious initiations. The wires should be labeled with the work implementing document number that required them to be lifted if left unattended.

E. All open problems (including non Tech Spec testing acceptance criteria) are to be tracked by a corrective action document and entered on the appropriate system punchlist.

F. Problems identified during the test shall be annotated on the Chronological Test Log (CTL) from SMP-9.0 including a description of the problem, the procedure step when/where the problem was identified, corrective action steps taken to resolve the problem, and the number of the corrective action document, if one was required.

G. Observe all Radiation Protection (RP) requirements when working, in or near contaminated areas.

H. All terminal points and connections are to be considered energized.

Instrumentation must be used to determine if the circuits are de-energized.

I. Retermination of lifted leads requires that their restored bend radius is equal to or greater than the as found condition.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 11 of 128 3.0 PRECAUTIONS AND LIMITATIONS (continued)

J. Transients include pump starts and stops, water hammers or other fluid transients. Check valves should be observed for abnormal slam during startup or shutdown of pumps. Verification that transient conditions are NOT causing excessive vibration may be accomplished by observation during the transient or verification subsequent to the transient that resultant damage has NOT occurred.

K. Steady-state conditions include verification that flow control valves and orifices do NOT produce excessive cavitation induced vibrations. Verification that excessive vibration from other flow induced phenomena does NOT occur is also required.

L. The instrument room chilled water system expansion tank water level shall be inspected periodically. Water level should be above the tank midpoint. To prevent possible overpressurization of the chilled water pump discharge piping, makeup should NOT be added to the system when the chilled water pumps are running.

M. During the performance of this procedure visual observation of piping and components is required. This includes steady-state and transient operations with visual confirmation that vibration is NOT excessive.

N. Ifvibration is determined to be excessive, the Startup Test Engineer (STE) shall initiate a Test Deficiency Notice (TDN).

0. Portions of this test will simulate a high ambient room temperature using an electric heat gun. This activity shall be performed slowly to prevent damage to the temperature switch sensing bulb.

P. During the performance of this procedure, ensure no adverse impacts to the operation of Unit 1 systems, structures, or components.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 12 of 128 Data Package: Page - of Date 4.0 PREREQUISITE ACTIONS NOTE Prerequisite steps may be performed in any order unless otherwise stated and should be completed as close in time as practicable to the start of the instruction subsection to which they apply.

4.1 Preliminary Actions

[1] VERIFY the test/performance copy of this Preoperational Test Instruction (PTI) is the current revision and as needed, each test person assisting in this test has the current revision.

[2] OBTAIN copies of the applicable forms from the latest revision of SMP-9.0, AND ATTACH to this PTI for use during the performance of this PTI.

[3] ENSURE changes to the references listed on "Test Procedures/Instructions Reference Review", Appendix A, have been reviewed, and determined NOT to adversely affect the test performance.

[4] VERIFY current revisions and change papers for referenced drawings have been reviewed and determined NOT to adversely affect the test performance, AND ATTACH documentation of current drawing revision numbers and change papers that were reviewed to data package.

[5] EVALUATE open items in Watts Bar Integrated Task Equipment List (WITEL), AND ENSURE that they will NOT adversely affect the test performance.

[6] ENSURE required Component Testing has been completed prior to start of test.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 13 of 128 Data Package: Page _ of Date 4.1 Preliminary Actions (continued)

[7] ENSURE outstanding Design Change Notices (DCNs),

Engineering Document Construction Releases (EDCRs), or Temporary Alterations (TAs) do NOT adversely impact testing, AND ATTACH documentation of DCNs, EDCRs, and TAs that were reviewed to the data package.

[8] ENSURE a review of outstanding Clearances has been coordinated with U2 Operations for impact to the test performance, AND IF items are found, THEN RECORD in Appendix B, Temporary Condition Log.

[9] ENSURE GTM-05, HVAC Air Balance, has been submitted to the JTG for concurrence that it adequately satisfies the requirements of this instruction.

JTG Meeting:

[10] ATTACH completed GTM-05, HVAC Air Balance package for System 31B.

[11] VERIFY system cleanness as required for the performance of this test has been completed in accordance with SMP-7.0.

[12] ENSURE components contained within the boundaries of this test are under the jurisdictional control of Preoperational Startup Engineering (PSE) and/or Plant Operations.

[13] PERFORM a pretest walkdown on equipment to be tested to ensure no conditions exist that will impact test performance.

[14] CONDUCT a pretest briefing with Test and Operations personnel in accordance with SMP-9.0.

[15] ENSURE that communications are available for areas where testing is to be conducted.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 14 of 128 Data Package: Page - of Date 4.1 Preliminary Actions (continued)

[16] REVIEW preventative maintenance for systems/components covered by this test, AND VERIFY no conditions exist that will impact test performance.

4.2 Special Tools, Measuring and Test Equipment (M&TE), Parts, and Supplies

[1] OBTAIN the following M&TE, or equivalent, AND COMPLETE the following table:

Digital Stopwatches 60 minutes NA 0-60 min

[2] +/-0.1 sec NA Pocket Thermometer 0-100OF +/- 20F Ultrasonic Flowmeter and Transducers for 0-100 gpm + 3% of reading 2 inch Sch 40 pipe

[2] VERIFY M&TE calibration due dates will support the completion of this test performance.

[3] OBTAIN the following items:

A. electric heat gun (Subsections 6.5 and 6.6)

B. cardboard, approximately 3 ft x 6 ft (Subsection 6.8)

C. electrical jumper (Subsection 6.9)

D. plastic five gallon bucket (Subsection 6.9)

[4] ENSURE an ice bath is available for use.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 15 of 128 Data Package: Page - of ____Date 4.3 Field Preparations

[1] ENSURE the following systems are operable and have been placed in service to the extent necessary to perform this test:

A. System 32, Control Air - Provides control air to valves, dampers, and controllers.

B. System 67, Essential Raw Cooling Water - Provides cooling water to Incore Instrument Room Chillers.

C. System 213, 480V AC Reactor MOV Boards - Provides electrical power to Incore Instrument Room Cooler Fans, Circulation Pumps, and Chiller Compressors.

D. System 235, 120V AC Vital Power System - Provides power to instrumentation and controls.

E. System 236, 125V DC Vital Power System - Provides power to isolation valves and dampers.

[2] ENSURE System 55, Annunciator and Sequential Events Recording System applicable TBK switches are ON, the applicable Master Switches are ON, and window software input(s) are ENABLED for the following Annunciator Windows:

A. 2-XA-55-5C/103-E, INSTR RM COOLER A/B FLOW LO B. 2-XA-55-5C/104-E, INSTR RM COOLING SURGE TANK A/B LEVEL LO

[3] PERFORM Electrical Lineup, Table 1.

[4] PERFORM Valve Lineup, Table 2.

[5] PERFORM Switch Lineup, Table 3.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 16 of 128 Data Package: Page -of Date 4.3 Field Preparations (continued)

[6] VERIFY system piping is properly filled and vented in accordance with 2-SOI-30.04.

A. Subsection 6.5 B. Subsection 6.6 C. Subsection 6.7 D. Subsection 6.8 E. Subsection 6.9

[7] ENSURE required scaffold is in place.

[8] VERIFY Incore Instrument Room Chilled Water Surge Tank Level is greater than or equal to 75% for the following:

A. 2-LG-31-304, INCORE INSTRUMENT ROOM SURGE TANK 2A LEVEL [Pen Rm, EL 692, Col A12W]

B. 2-LG-31-325, INCORE INSTRUMENT ROOM SURGE TANK 2B LEVEL [Pen Rm, EL 692, Col A12W]

[9] ENSURE M&TE required for test performance has been (as required) filled, vented and placed in service, AND RECORD data on Appendix E of SMP-9.0.

[10] ENSURE plant instruments required for test performance, listed on Appendix C, Permanent Plant Instrumentation Log, have been (as required) filled, vented and placed in service, and are within their calibration interval, AND RECORD data on Appendix C.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 17 of 128 Data Package: Page - of Date 4.4 Approvals and Notifications

[1] OBTAIN permission of the Preoperational Startup Manager to start the test.

Preoperational Startup Manager Date Signature

[2] OBTAIN the Unit 2 Supervisor's (US/SRO) or Shift Manager's (SM) authorization.

U2 US/SRO/SM Signature Date

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 18 of 128 5.0 ACCEPTANCE CRITERIA Refer to Appendix D, Backup Calculations, for discussion of instrumentation uncertainties.

A. Incore Instrument Room Air Conditioning System Containment Isolation Valves:

Stroke close Control Room Close on a Remain closed time is leql te or equal alarms and indicators simulated Phase A afterPhase a simulated A Fail theclosed loss ofon Fail theclosed loss ofon than operate in Containment Containment electrical control air 10 seconds accordance Isolation Isolation signal power with design signal reset 2-FCV-31-305, 6.1.2[3],

INCORE INSTR RM 6.1.2[5] 6.1.2[4], 6.2.2[3] 6.2.2[5] 6.3.2[2] 6.4.2[3]

AHU 2A CWR ISOL 6.1.2[7],

6.1.2[8]

2-FCV-31-306, 6.1.3[3],

INCORE INSTR RM 6.1.3[5] 6.2.3[3] 6.2.3[5] 6.3.3[22 6.4.3[3]

AHU 2A CW 6.1.3[7],

PUMP 2A ISOL 6.1.3[8]

2-FCV-31-308, 6.1.4[3],

INCORE INSTR RM 6.1.4[5] 6.1.4[4], 6.2.4[3] 6.2.4[5] 6.3.4[2] 6.4.4[3]

AHU 2A CWS ISOL 6.1.4[7],

6.1.4[8]

2-FCV-31-309, 6.1.5[3],

INCORE INSTR RM 6.1.5[5] 6.1.5[4], 6.2.5[3] 6.2.5[5] 6.3.5[2] 6.4.5[3]

AHU 2A CWS ISOL 6.1.5[7],

6.1.5[8]

2-FCV-31-326, 6.1.6[3],

INCORE INSTR RM 6.1.6[5] 6.1.6[7], 6.2.6[3] 6.2.6[5] 6.3.6[2] 6.4.6[3]

AHU 2B CWR ISOL 6.1.6[8],

6.1.6[8]

2-FCV-31-327, 6.1.7(3],

INCORE INSTR RM 6.1.7[5] 6.1.7[4], 6.2.7[3] 6.2.7[5] 6.3.7[2] 6.4.7[3]

AHU 2B CWR ISOL 6.1.7[7],

6.1.7(8]

2-FCV-31-329, 6.1.8(3],

INCORE INSTR RM 6.1.8[5] 6.1.8[4] 6.2.8[3] 6.2.8[5] 6.3.8[2] 6.4.8[3]

AHU 2B CWS ISOL 6.1.8(7],

6.1.898]

2-FCV-31-330, 6.1.9(3],

INCORE INSTRRM 6.1.9(5] 6.1.9[7], 6.2.9[3] 6.2.9[5] 6.3.9[2] 6.4.9[3]

AHU 2B3 CWS ISL 6.1.9[8]

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 19 of 128 5.0 ACCEPTANCE CRITERIA (continued)

B. Incore Instrument Room Air Conditioning System Air Handling Units Maintain Desired Air Flow:

1. Air Handling Unit 2.-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, 5,200 CFM (minimum 4,680) (Step 6.5.4[6])
2. Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, 5,200 CFM (minimum 4,680) (Step 6.5.5[6])

C. Incore Instrument Room Air Conditioning System Chillers Recieve Desired Water Flowrate:

1. Chiller 2-CHR-31-303, INCORE INSTR ROOM CHILLER 2A, minimum 22 GPM (Step 6.6.2[5])
2. Chiller 2-CHR-31-324, INCORE INSTRUMENT ROOM CHILLER 2B, minimum 22 GPM (Step 6.6.3[5])

D. Incore Instrument Room Air Conditioning System Manual Controls Function In Accordance With Design Requirements:

1. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A (Subsection 6.5.2)
2. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B (Subsection 6.5.3)
3. Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A (Subsection 6.5.4)
4. Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B (Subsection 6.5.5)

E. Incore Instrument Room Air Conditioning System Automatic Controls Function In Accordance With Design Requirements:

1. Damper 2-FCO-31-263, INCORE INSTR RM AHU 2ADISCHARGE (Subsection 6.6.2)
2. Damper 2-FCO-31-264, INCORE INSTR RM AHU 2A DISCHARGE (Subsection 6.6.2)
3. Damper 2-FCO-31-268, INCORE INSTR RM AHU 2B DISCHARGE (Subsection 6.6.3)

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 20 of 128 5.0 ACCEPTANCE CRITERIA (continued)

4. Damper 2-FCO-31-269, INCORE INSTR RM AHU 2B DISCHARGE (Subsection 6.6.3)
5. Temperature Control Valve 2-TCV-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL (Subsection 6.5.6)
6. Temperature Control Valve 2-TCV-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL (Subsection 6.5.7)
7. Pump 2-PMP-31-303/1,.INCORE INSTR ROOM CW PUMP 2A (Subsection 6.6.2)
8. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B (Subsection 6.6.3)
9. Compressor 2-COMP-31-303B, INCORE INSTR RM CHILLER A COMPRESSOR (Subsection 6.6.2)
10. Compressor 2-COMP-31-324B, INCORE INSTR RM CHILLER B COMPRESSOR (Subsection 6.6.3)
11. Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A (Subsection 6.6.2)
12. Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B (Subsection 6.6.3)

F. Incore Instrument Room Air Conditioning System Interlocks and Alarms Function In Accordance With Design Requirements:

1. Air Handling Unit 2A Stop on Simulated Phase A Containment Isolation (Subsection 6.7.2)
2. Air Handling Unit 2B Stop on Simulated Phase A Containment Isolation (Subsection 6.7.3)
3. Redundant Unit Start on Low Air Flow (Subsection 6.8)
4. Circulation Pump 2A Trip on Low Tank Level (Subsection 6.9.2)
5. Circulation Pump 2B Trip on Low Tank Level (Subsection 6.9.3)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 21 of 128 5.0 ACCEPTANCE CRITERIA (continued)

G. Essential Raw Cooling Water Supply Valves Automatic Controls Function In Accordance With Design Requirements:

1. Temperature Control Valve 2-TCV-67-115, INSTR RM WATER CLR 2A ERCW SUP TEMP CNTL (Subsection 6.6.2)
2. Temperature Control Valve 2-TCV-67-118, INSTR RM WATER CLR 2B ERCW SUP TEMP CNTL (Subsection 6.6.3)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 22 of 128 6.0 PERFORMANCE NOTES

1) Subsection 6.1 shall be performed first. Subsections 6.2, 6.3, 6.4, and 6.5 may be performed in any order after completion of subsection 6.1. Subsection 6.6 may be performed after completion of subsections 6.1 and 6.5. Subsections 6.7, 6.8, and 6.9 may be performed after completion of subsections 6.1, 6.5, and 6.6. Subsections of 6-,1 this test shall be performed per the flow diagram below:

46.5 6.6

2) When manipulating Contaiment Isolation Valve Handswitches, handswitches must be held in the OPEN position until valve is fully OPEN.

Refer to the following sketch depicting the respective open and closed orientations of Containment Isolation Valves:

1777"F7

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 23 of 128 Data Package: Page - of Date 6.1 Incore Instrument Room Air Conditioning System Containment Isolation Valves Control Logic 6.1.1 Preliminary Actions

[1] VERIFY prerequisites listed in Section 4.0 for SubSection 6.1 have been completed.

NOTES

1) Subsections 6.1.2 thru 6.1.9 may be performed in any order. Steps within these subsections must be performed in the order written.
2) Containment Isolation Valves will be stroke timed locally at the valve, and remotely at the control switch, in the close direction. Local stroke timing begins with the initiating signal, and is concluded with the completion of limit switch actuator movement.

Remote stroke timing begins with the initiating signal, and is concluded with the position indication lights status change on 2-M-9. Stroke time acceptance criteria will be based on the movement to the safety function final position of the valve.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 24 of 128 Data Package: Page - of Date 6.1.2 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, Control Logic

[1] ENSURE 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL [Annulus, EL 736, AZ 64], is CLOSED (local observation).

[2] PLACE Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A [2-M-9], to the OPEN position, AND VERIFY Valve 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

[3] VERIFY status lights on Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, are:

A. Red Light ON, 2-M-9 (Acc Crit)

B. Green Light OFF, 2-M-9 (Acc Crit)

[4] VERIFY status lights on 2-XX-55-6F, Window 19, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-B),

FCV-31-305 [2-M-6], are:

A. Red Light ON, 2-M-6 (Acc Crit)

B. Green Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 25 of 128 Data Package: Page - of Date 6.1.2 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, Control Logic (continued)

NOTE The following step requires stroke timing both locally and in the Main Control Room. All M&TE (stopwatches) should be readied and personnel should agree on a countdown method.

[5] PLACE Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, to the CLOSE position, AND RECORD:

A. Stroke CLOSE time of Valve 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL (local observation) seconds M&TE:

Acc Crit: < 10 sec B. Stroke CLOSE time of Valve 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL (indication lights) seconds M&TE:

Acc Crit: _<10 sec

[6] VERIFY Valve 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, is CLOSED (local observation).

[7] VERIFY status lights on Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[8] VERIFY status lights on 2-XX-55-6F, Window 19, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-B),

FCV-31-305, are:

A. Green Light ON, 2-M-6 (Acc Crit)

B. Red Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 26 of 128 Data Package: Page - of Date 6.1.2 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, Control Logic (continued)

[9] PLACE Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, to the OPEN position, AND VERIFY 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 27 of 128 Data Package: Page __ of__ Date 6.1.3 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL, Control Logic

[1] ENSURE 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL [Inst Rm, EL 716, AZ 60], is CLOSED (local observation).

[2] PLACE Handswitch 2-HS-31-306, CIRC PMP A SUCT ClV-PHASE A [2-M-9], to the OPEN position, AND VERIFY Valve 2-FCV-31-306, INCORE INSTR RM AHU .2A CW PUMP 2A ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

[3] VERIFY status lights on Handswitch 2-HS-31-306, CIRC PMP A SUCT ClV-PHASE A, are:

A. Red Light ON, 2-M-9 (Acc Crit)

B. Green Light OFF, 2-M-9 (Acc Crit)

[4] VERIFY status lights on 2-XX-55-6E, Window 19, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-A),

FCV-31-306 [2-M-6], are:

A. Red Light ON, on 2-M-6 (Acc Crit)

B. Green Light OFF, on 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 28 of 128 Data Package: Page - of Date 6.1.3 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL, Control Logic (continued)

NOTE The following step requires stroke timing both locally and in the Main Control Room. All M&TE (stopwatches) should be readied and personnel should agree on a countdown method.

[5] PLACE Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, to the CLOSE position, AND RECORD:

A. Stroke CLOSE time of Valve 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL (local observation) seconds M&TE:

Acc Crit: _<10 sec B. Stroke CLOSE time of Valve 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL (indication lights) seconds M&TE:

Acc Crit: _<10 sec

[6] VERIFY Valve 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL, is CLOSED (local observation).

[7] VERIFY status lights on Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 29 of 128 Data Package: Page - of Date 6.1.3 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL, Control Logic (continued)

[8] VERIFY status lights on 2-XX-55-6E, Window 19, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-A),

FCV-31-306, are:

A. Green Light ON, on 2-M-6 (Acc Crit)

B. Red Light OFF, on 2-M-6 (Acc Crit)

[9] PLACE Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, to the OPEN position, AND VERIFY 2-FCV-31-306, INCORE INSTR RM-AHU 2A CW PUMP 2A ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 30 of 128 Data Package: Page _ of Date 6.1.4 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, Control Logic

[1] ENSURE 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL [Inst Rm, EL 716, AZ 65], is CLOSED (local observation).

[2] PLACE Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A [2-M-9], to the OPEN position, AND VERIFY Valve 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

[3] VERIFY status lights on Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, are:

A. Red Light ON, 2-M-9 (Acc Crit)

B. Green Light OFF, 2-M-9 (Acc Crit)

[4] VERIFY status lights on 2-XX-55-6E, Window 20, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-A),

FCV-31-308 [2-M-6], are:

A. Red Light ON, on 2-M-6 (Acc Crit)

B. Green Light OFF, on 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 31 of 128 Data Package: Page _ of Date 6.1.4 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, Control Logic (continued)

NOTE The following step requires stroke timing both locally and in the Main Control Room. All M&TE (stopwatches) should be readied and personnel should agree on a countdown method.

[5] PLACE Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, to the CLOSE position, AND RECORD:

A. Stroke CLOSE time of Valve 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL (local observation) seconds M&TE:

Acc Crit: < 10 sec B. Stroke CLOSE time of Valve 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL (indication lights) seconds M&TE:

Acc Crit: _ 10 sec

[6] VERIFY Valve 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, is CLOSED (local observation).

[7] VERIFY status lights on Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[8] VERIFY status lights on 2-XX-55-6E, Window 20, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-A),

FCV-31-308, are:

A. Green Light ON, 2-M-6 (Acc Crit)

B. Red Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument. Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 32 of 128 Data Package: Page - of Date 6.1.4 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, Control Logic (continued)

[9] PLACE Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, to the OPEN position, AND VERIFY 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 33 of 128 Data Package: Page - of Date 6.1.5 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, Control Logic

[1] ENSURE 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL [Annulus, EL 737, AZ 65], is CLOSED (local observation).

[2] PLACE Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A [2-M-9], to the OPEN position, AND VERIFY Valve 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

[3] VERIFY status lights on Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, are:

A. Red Light ON, 2-M-9 (Acc Crit)

B. Green Light OFF, 2-M-9 (Acc Crit)

[4] VERIFY status lights on 2-XX-55-6F, Window 20, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-B),

FCV-31-309 [2-M-6], are:

A. Red Light ON, 2-M-6 (Acc Crit)

B. Green Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 34 of 128 Data Package: Page - of Date 6.1.5 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, Control Logic (continued)

NOTE The following step requires stroke timing both locally and in the Main Control Room. All M&TE (stopwatches) should be readied and personnel should agree on a countdown method.

[5] PLACE Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, to the CLOSE position, AND RECORD:

A. Stroke CLOSE time of Valve 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL (local observation) seconds M&TE:

Acc Crit: _<10 sec B. Stroke CLOSE time of Valve 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL (indication lights) seconds M&TE:

Acc Crit: < 10 sec

[6] VERIFY Valve 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, is CLOSED (local observation).

[7] VERIFY status lights on Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[8] VERIFY status lights on 2-XX-55-6F, Window 20, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-B),

FCV-31-309, are:

A. Green Light ON, 2-M-6 (Acc Crit)

B. Red Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 35 of 128 Data Package: Page - of Date 6.1.5 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, Control Logic (continued)

[9] PLACE Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, to the OPEN position, AND VERIFY 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 36 of 128 Data Package: Page - of _ Date 6.1.6 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, Control Logic

[1] ENSURE 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL [Annulus, EL 737, AZ 104], is CLOSED (local observation).

[2] PLACE Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A [2-M-9], to the OPEN position, AND VERIFY Valve 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

[3] VERIFY status lights on Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, are:

A. Red Light ON, 2-M-9 (Acc Crit)

B. Green Light OFF, 2-M-9 (Acc Crit)

[4] VERIFY status lights on 2-XX-55-6E, Window 21, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-A),

FCV-31-326 [2-M-6], are:

A. Red Light ON, on 2-M-6 (Acc Crit)

B. Green Light OFF, on 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 37 of 128 Data Package: Page - of Date 6.1.6 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, Control Logic (continued)

NOTE The following step requires stroke timing both locally and in the Main Control Room. All M&TE (stopwatches) should be readied and personnel should agree on a countdown method.

[5] PLACE Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, to the CLOSE position, AND RECORD:

A. Stroke CLOSE time of Valve 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL (local observation) seconds M&TE:

Acc Crit: _<10 sec B. Stroke CLOSE time of Valve 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL (indication lights) seconds M&TE:

Acc Crit: _<10 sec

[6] VERIFY Valve 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, is CLOSED (local observation).

[7] VERIFY status lights on Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[8] VERIFY status lights on 2-XX-55-6E, Window 21, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-A),

FCV-31-326, are:

A. Green Light ON, 2-M-6 (Acc Crit)

B. Red Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 38 of 128 Data Package: Page - of Date 6.1.6 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, Control Logic (continued)

[9] PLACE Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, to the OPEN position, AND VERIFY 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 39 of 128 Data Package: Page - of Date 6.1.7 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, Control Logic

[1] ENSURE 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL [Inst Rm, EL 716, AZ 104], is CLOSED (local observation).

[2] PLACE Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A [2-M-9], to the OPEN position, AND VERIFY Valve 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

[3] VERIFY status lights on Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, are:

A. Red Light ON, 2-M-9 (Acc Crit)

B. Green Light OFF, 2-M-9 (Acc Crit)

[4] VERIFY status lights on 2-XX-55-6F, Window 21, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-B),

FCV-31-327 [2-M-6], are:

A. Red Light ON, 2-M-6 (Acc Crit)

B. Green Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 40 of 128 Data Package: Page - of Date 6.1.7 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, Control Logic (continued)

NOTE The following step requires stroke timing both locally and in the Main Control Room. All M&TE (stopwatches) should be readied and personnel should agree on a countdown method.

.[5] PLACE Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, to the CLOSE position, AND RECORD:

,J A. Stroke CLOSE time of Valve 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL (local observation) seconds M&TE:

Acc Crit: _<10 sec B. Stroke CLOSE time of Valve 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL (indication lights) seconds M&TE:

Acc Crit: _<10 sec

[6] VERIFY Valve 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, is CLOSED (local observation).

[7] VERIFY status lights on Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[8] VERIFY status lights on 2-XX-55-6F, Window 21, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-B),

FCV-31-327, are:

A. Green Light ON, 2-M-6 (Acc Crit)

B. Red Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 41 of 128 Data Package: Page - of Date 6.1.7 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, Control Logic (continued)

[9] PLACE Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, to the OPEN position, AND VERIFY 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

'A

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 42 of 128 Data Package: Page - of Date 6.1.8 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, Control Logic

[1] ENSURE 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL [Inst Rm, EL 716, AZ 105], is CLOSED (local observation).

[2] PLACE Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A [2-M-9], to the OPEN position, AND VERIFY Valve 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

[3] VERIFY status lights on Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, are:

A. Red Light ON, 2-M-9 (Acc Crit)

B. Green Light OFF, 2-M-9 (Acc Crit)

[4] VERIFY status lights on 2-XX-55-6F, Window 31, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-B),

FCV-31-329 [2-M-6], are:

A. Red Light ON, 2-M-6 (Acc Crit)

B. Green Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 43 of 128 Data Package: Page -of Date 6.1.8 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, Control Logic (continued)

NOTE The following step requires stroke timing both locally and in the Main Control Room. All M&TE (stopwatches) should be readied and personnel should agree on a countdown method.

[5] PLACE Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, to the CLOSE position, AND RECORD:

A. Stroke CLOSE time of Valve 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL (local observation) seconds M&TE:

Acc Crit: _<10 sec B. Stroke CLOSE time of Valve 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL (indication lights) seconds M&TE:

Acc Crit: _<10. sec

[6] VERIFY Valve 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, is CLOSED (local observation).

[7] VERIFY status lights on Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[8] VERIFY status lights on 2-XX-55-6F, Window 31, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-B),

FCV-31-329, are:

A. Green Light ON, 2-M-6 (Acc Crit)

B. Red Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 44 of 128 Data Package: Page - of Date 6.1.8 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, Control Logic (continued)

[9] PLACE Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, to the OPEN position, AND VERIFY 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 45 of 128 Data Package: Page - of Date 6.1.9 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, Control Logic

[1] ENSURE 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL [Annulus, EL 738, AZ 105], is CLOSED (local observation).

[2] PLACE Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A [2-M-9], to the OPEN position, AND VERIFY Valve 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

[3] VERIFY status lights on Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, are:

A. Red Light ON, 2-M-9 (Acc Crit)

B. Green Light OFF, 2-M-9 (Acc Crit)

[4] VERIFY status lights on 2-XX-55-6E, Window 31, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-A),

FCV-31-330 [2-M-6], are:

A. Red Light ON, 2-M-6 (Acc Crit)

B. Green Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 46 of 128 Data Package: Page - of Date 6.1.9 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, Control Logic (continued)

NOTE The following step requires stroke timing both locally and in the Main Control Room. All M&TE (stopwatches) should be readied and personnel should agree on a countdown method.

[5] PLACE Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, to the CLOSE position, AND RECORD:

A. Stroke CLOSE time of Valve 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL (local observation) seconds M&TE:

Acc Crit: < 10 sec B. Stroke CLOSE time of Valve 2-FCV-31.-330, INCORE INSTR RM AHU 2B CWS ISOL (indication lights) seconds M&TE:

Acc Crit: _<10 sec

[6] VERIFY Valve 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, is CLOSED (local observation).

[7] VERIFY status lights on Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[8] VERIFY status lights on 2-XX-55-6E, Window 31, CONTAINMENT ISOLATION STATUS PANEL (TRAIN-A),

FCV-31-330, are:

A. Green Light ON, 2-M-6 (Acc Crit)

B. Red Light OFF, 2-M-6 (Acc Crit)

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 47 of 128 Data Package: Page - of Date 6.1.9 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, Control Logic (continued)

[9] PLACE Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, to the OPEN position, AND VERIFY 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, OPENS (local observation), THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 48 of 128 Data Package: Page - of Date 6.2 Incore Instrument Room Air Conditioning System Containment Isolation Valves Close on Simulated Phase A Containment Isolation 6.2.1 Preliminary Actions

[1] VERIFY prerequisites listed in Section 4.0 for SubSection 6.2 have been completed.

NOTE Subsections 6.2.2 thru 6.2.9 may be performed in any order. Steps within these subsections must be performed in the order written.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 49 of 128 Data Package: Page - of _ Date 6.2.2 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, Simulated Phase A

[1] ENSURE status lights on Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A [2-M-9], are:

A. Green Light OFF, 2-M-9 B. Red Light ON, 2-M-9

[2] LIFT Wire VBK5 from Terminal Point 8 on TB 637 in 2-R-51 to simulate a Phase A Containment Isolation.

1st CV

[3] VERIFY status lights on Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[4] LAND Wire VBK5 on Terminal Point 8 on TB 637 in 2-R-51 to simulate a Phase A Containment Isolation reset.

1st CV

[5] VERIFY status lights on Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[6] PLACE Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 50 of 128 Data Package: Page - of Date 6.2.3 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL, Simulated Phase A

[1] ENSURE status lights on Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A [2-M-9], are:

A. Green Light OFF, 2-M-9 B. Red Light ON, 2-M-9

[2] LIFT Wire VBL5 from Terminal Point 8 on TB 637 in 2-R-48 to simulate a Phase A Containment Isolation.

1st CV

[3] VERIFY status lights on Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[4] LAND Wire VBL5 on Terminal Point 8 on TB 637 in 2-R-48 to simulate a Phase A Containment Isolation reset.

1st CV

[5] VERIFY status lights on Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[6] PLACE Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 51 of 128 Data Package: Page - of Date 6.2.4 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, Simulated Phase A

[1] ENSURE status lights on Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A [2-M-9], are:

A. Green Light OFF, 2-M-9 B. Red Light ON, 2-M-9

[2] LIFT Wire VBN5 from Terminal Point 10 on TB 637 in 2-R-48 to simulate a Phase A Containment Isolation.

1st Cv

[3] VERIFY status lights on Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[4] LAND Wire VBN5 on Terminal Point 10 on TB 637 in 2-R-48 to simulate a Phase A Containment Isolation reset.

1st Cv

[5] VERIFY status lights on Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[6] PLACE Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 52 of 128 Data Package: Page - of Date 6.2.5 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, Simulated Phase A

[1] ENSURE status lights on Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A [2-M-9], are:

A. Green Light OFF, 2-M-9 B. Red Light ON, 2-M-9

[2] LIFT Wire VBM5 from Terminal Point 10 on TB 637 in 2-R-51 to simulate a Phase A Containment Isolation.

1st CV

[3] VERIFY status lights on Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[4] LAND Wire VBM5 on Terminal Point 10 on TB 637 in 2-R-51 to simulate a Phase A Containment Isolation reset.

1st CV

[5] VERIFY status lights on Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[6] PLACE Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 53 of 128 Data Package: Page __ of__ Date 6.2.6 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, Simulated Phase A

[1] ENSURE status lights on Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A [2-M-9], are:

A. Green Light OFF, 2-M-9 B. Red Light ON, 2-M-9

[2] LIFT Wire VHG5 from Terminal Point 12 on TB 637 in 2-R-48 to simulate a Phase A Containment Isolation.

1st CV

[3] VERIFY status lights on Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[4] LAND Wire VHG5 on Terminal Point 12 on TB 637 in 2-R-48 to simulate a Phase A Containment Isolation reset.

1st CV

[5] VERIFY status lights on Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[6] PLACE Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 54 of 128 Data Package: Page - of Date 6.2.7 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, Simulated Phase A

[1] ENSURE status lights on Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A [2-M-9], are:

A. Green Light OFF, 2-M-9 B. Red Light ON, 2-M-9

[2] LIFT Wire VHH5 from Terminal Point 12 on TB 637 in 2-R-51 to simulate a Phase A Containment Isolation.

1st CV

[3] VERIFY status lights on Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[4] LAND Wire VHH5 on Terminal Point 12 on TB 637 in 2-R-51 to simulate a Phase A Containment Isolation reset.

1st CV

[5] VERIFY status lights on Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[6] PLACE Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 55 of 128 Data Package: Page - of Date 6.2.8 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, Simulated Phase A

[1] ENSURE status lights on Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A [2-M-9], are:

A. Green Light OFF, 2-M-9 B. Red Light ON, 2-M-9

[2] LIFT Wire VHK5 from Terminal Point 2 on TB 638 in 2-R-51 to simulate a Phase A Containment Isolation.

1st CV

[3] VERIFY status lights on Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[4] LAND Wire VHK5 on Terminal Point 2 on TB 638 in 2-R-51 to simulate a Phase A Containment Isolation reset.

1st CV

[5] VERIFY status lights on Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[6] PLACE Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 56 of 128 Data Package: Page - of _ Date 6.2.9 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, Simulated Phase A

[1] ENSURE status lights on Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A [2-M-9], are:

A. Green Light OFF, 2-M-9 B. Red Light ON, 2-M-9

[2] LIFT Wire VHJ5 from Terminal Point 2 on TB 638 in 2-R-48 to simulate a Phase A Containment Isolation.

1 st Cv

[3] VERIFY status lights on Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[4] LAND Wire VHJ5 on Terminal Point 2 on TB 638 in 2-R-48 to simulate a Phase A Containment Isolation reset.

1st Cv

[5] VERIFY status lights on Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, are:

A. Green Light ON, 2-M-9 (Acc Crit)

B. Red Light OFF, 2-M-9 (Acc Crit)

[6] PLACE Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 57 of 128 Data Package: Page _ of Date 6.3 Incore Instrument Room Air Conditioning System Containment Isolation Valves Close on Loss of Electrical Power 6.3.1 Preliminary Actions

[1] VERIFY prerequisites listed in Section 4.0 for SubSection 6.3 have been completed.

CAUTION Work in 125V DC Vital Battery Boards III and IV involves energized circuits.

NOTES

1) Subsections 6.3.2 thru 6.3.9 may be performed in any order. Steps within these subsections must be performed in the order written.
2) Removal of fuses in this section will disable handswitch indication (Red & Green Lights).
3) Each fuse in this section has a blown fuse indicator which must be oriented towards the annunciator circuit.
4) While working in 125V DC Vital Battery Boards III and IV, proceed with caution as to not impact U1 structures, systems, or components.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 58 of 128 Data Package: Page - of Date 6.3.2 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, Loss of Electrical Power

[1] ENSURE 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL [Annulus, EL 736, AZ 64], is OPEN (local observation).

[2] PULL Fuse 0-FU-236-4/C3, INSTR RM COOLANT UNIT A VLV [125V DC Vital Batt Bd IV, Ckt C3, EL 757 A12/Q], AND VERIFY Valve 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, CLOSES (local observation) (Acc Crit).

1 st CV

[3] INSTALL Fuse 0-FU-236-4/C3, INSTR RM COOLANT UNIT A VLV.

1st CV

[4] PLACE Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 59 of 128 Data Package: Page - of Date 6.3.3 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL, Loss of Electrical Power

[1] ENSURE 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL [Inst Rm, EL 716, AZ 60], is OPEN (local observation).

[2] PULL Fuse 0-FU-236-3/C3, INSTR RM COOLANT UNIT A VLV [125V DC Vital Batt Bd III, Ckt C3, EL 757 Al1/Q], AND VERIFY Valve 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL, CLOSES (local observation) (Acc Crit).

1st CV

[3] INSTALL Fuse 0-FU-236-3/C3, INSTR RM COOLANT UNIT A VLV.

1st CV

[4] PLACE Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 60 of 128 Data Package: Page - of Date 6.3.4 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, Loss of Electrical Power

[1] ENSURE 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL [Inst Rm, EL 716, AZ 65], is OPEN (local observation).

[2] PULL Fuse 0-FU-236-3/C4, INSTR RM COOLANT UNIT A VLV [125V DC Vital Batt Bd Ill, Ckt C4], AND VERIFY Valve 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, CLOSES (local observation) (Acc Crit).

1st CV

[3] INSTALL Fuse 0-FU-236-3/C4, INSTR RM COOLANT UNIT A VLV.

1 st CV

[4] PLACE Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 61 of 128 Data Package: Page - of Date 6.3.5 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, Loss of Electrical Power

[1] ENSURE 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL [Annulus, EL 737, AZ 65], is OPEN (local observation).

[2] PULL Fuse 0-FU-236-4/C4, INSTR RM COOLANT UNIT A VLV [125V DC Vital Batt Bd IV,Ckt C4], AND VERIFY Valve 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, CLOSES (local observation) (Acc Crit).

1st CV

[3] INSTALL Fuse 0-FU-236-4/C4, INSTR RM COOLANT UNIT A VLV.

1st CV

[4] PLACE Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 62 of 128 Data Package: Page - of Date 6.3.6 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, Loss of Electrical Power

[1] ENSURE 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL [Annulus, EL 737, AZ 104], is OPEN (local observation).

[2] PULL Fuse 0-FU-236-3/C5, INSTR RM COOLANT UNIT B VLV [125V DC Vital Batt Bd Ill, Ckt C5], AND VERIFY Valve 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, CLOSES (local observation) (Acc Crit).

1st CV

[3] INSTALL Fuse 0-FU-236-3/C5, INSTR RM COOLANT UNIT B VLV.

1st CV

[4] PLACE Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 63 of 128 Data Package: Page - of Date 6.3.7 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, Loss of Electrical Power

[1] ENSURE 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL [Inst Rm, EL 716, AZ 104], is OPEN (local observation).

[2] PULL Fuse 0-FU-236-4/C5, INSTR RM COOLANT UNIT B VLV [125V DC Vital Batt Bd IV, Ckt C5], AND VERIFY Valve 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, CLOSES (local observation) (Acc Crit).

1st CV

[3] INSTALL Fuse 0-FU-236-4/C5, INSTR RM COOLANT UNIT B VLV.

1st CV

[4] PLACE Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 64 of 128 Data Package: Page - of Date 6.3.8 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, Loss of Electrical Power

[1] ENSURE 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL [Inst Rm, EL 716, AZ 105], is OPEN (local observation).

[2] PULL Fuse 0-FU-236-4/C6, INSTR RM COOLANT UNIT B VLV [125V DC Vital Batt Bd IV, Ckt C6], AND VERIFY Valve 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, CLOSES (local observation) (Acc Crit).

1st CV

[3] INSTALL Fuse 0-FU-236-4/C6, INSTR RM COOLANT UNIT B VLV.

1st CV

[4] PLACE Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 65 of 128 Data Package: Page - of Date 6.3.9 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, Loss of Electrical Power

[1] ENSURE 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL [Annulus, EL 738, AZ 105], is OPEN (local observation).

[2] PULL Fuse 0-FU-236-3/C6, INSTR RM COOLANT UNIT B VLV [125V DC Vital Batt Bd III, Ckt C6], AND VERIFY Valve 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, CLOSES (local observation) (Acc Crit).

1st CV

[3] INSTALL Fuse 0-FU-236-3/C6, INSTR RM COOLANT UNIT B VLV.

1st CV

[4] PLACE Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 66 of 128 Data Package: Page - of Date 6.4 Incore Instrument Room Air Conditioning System Containment Isolation Valves Close on Loss of Control Air 6.4.1 Preliminary Actions

[1] VERIFY prerequisites listed in Section 4.0 for SubSection 6.4 have been completed.

NOTE Subsections 6.4.2 thru 6.4.9 may be performed in any order. Steps within these subsections must be performed in the order written.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 67 of 128 Data Package: Page - of Date 6.4.2 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL, Loss of Control Air

[1] ENSURE Valve 2-FCV-31-305, INCORE INSTR RM AHU 2A CWR ISOL [Annulus, EL 736, AZ 64], is-OPEN (local observation).

[2] CLOSE the Control Air Valve 2-ISV-32-3492, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-305 [Annulus, EL 736, AZ 64].

[3] SLOWLY OPEN the petcock on the bottom of Pressure Regulator 2-PREG-31-305, CONTROL AIR PRESSURE REG FOR 2-FCV-31-305 [Annulus, EL 736, AZ 64], AND VERIFY Valve 2-FCV-31-305 INCORE INSTR RM AHU 2A CWR ISOL, CLOSES (local observation) (Acc Crit).

[4] CLOSE the petcock on the bottom of Pressure Regulator 2-PREG-31-305, CONTROL AIR PRESSURE REG FOR 2-FCV-31-305.

[5] SLOWLY OPEN the Control Air Valve 2-ISV-32-3492, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-305, AND ENSURE there is no leakage from the petcock on the bottom of Pressure Regulator 2-PREG-31-305, CONTROL AIR PRESSURE REG FOR 2-FCV-31-305.

[6] PLACE Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-305, CIRC PMP A SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 68 of 128 Data Package: Page - of Date 6.4.3 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL, Loss of Control Air

[1] ENSURE Valve 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL [Inst Rm, EL 716, AZ 60], is OPEN (local observation).

[2] CLOSE the Control Air Valve 2-ISV-32-3637, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-306 [Inst Rm, EL 716, AZ 60].

[3] SLOWLY OPEN the petcock on the bottom of Pressure Regulator 2-PREG-31-306, CONTROL AIR PRESSURE REG FOR 2-FCV-31-306 [Inst Rm, EL 716, AZ 60], AND VERIFY Valve 2-FCV-31-306, INCORE INSTR RM AHU 2A CW PUMP 2A ISOL, CLOSES (local observation) (Acc Crit).

[4] CLOSE the petcock on the bottom of Pressure Regulator 2-PREG-31-306, CONTROL AIR PRESSURE REG FOR 2-FCV-31-306.

[5] SLOWLY OPEN the Control Air Valve 2-ISV-32-3637, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-306, AND ENSURE there is no leakage from the petcock on the bottom of Pressure Regulator 2-PREG-31-306, CONTROL AIR PRESSURE REG FOR 2-FCV-31-306.

[6] PLACE Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-306, CIRC PMP A SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 69 of 128 Data Package: Page of Date 6.4.4 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, Loss of Control Air

[1] ENSURE Valve 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL [Inst Rm, EL 716, AZ 65], is OPEN (local observation).

[2] CLOSE the Control Air Valve 2-ISV-32-3638, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-308 [Inst Rm, EL 716, AZ 65].

[3] SLOWLY OPEN the petcock on the bottom of Pressure Regulator 2-PREG-31-308, CONTROL AIR PRESSURE REG FOR 2-FCV-31-308 [Inst Rm, EL 716, AZ 65], AND VERIFY Valve 2-FCV-31-308, INCORE INSTR RM AHU 2A CWS ISOL, CLOSES (local observation) (Acc Crit).

[4] CLOSE the petcock on the bottom of Pressure Regulator 2-PREG-31-308, CONTROL AIR PRESSURE REG FOR 2-FCV-31-308.

[5] SLOWLY OPEN the Control Air Valve 2-ISV-32-3638, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-308, AND ENSURE there is no leakage from the petcock on the bottom of Pressure Regulator 2-PREG-31-308, CONTROL AIR PRESSURE REG FOR 2-FCV-31-308.

[6] PLACE Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-308, CIRC PMP A DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 70 of 128 Data Package: Page -of Date 6.4.5 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, Loss of Control Air

[1] ENSURE Valve 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL [Annulus, EL 737, AZ 65], is OPEN (local observation).

[2] CLOSE the Control Air Valve 2-ISV-32-3493, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-309 [Annulus, EL 737, AZ 65].

[3] SLOWLY OPEN the petcock on the bottom of Pressure Regulator 2-PREG-31-309, CONTROL AIR PRESSURE REG FOR 2-FCV-31-309 [Annulus, EL 737, AZ 65], AND VERIFY Valve 2-FCV-31-309, INCORE INSTR RM AHU 2A CWS ISOL, CLOSES (local observation) (Acc Crit).

[4] CLOSE the petcock on the bottom of Pressure Regulator 2-PREG-31-309, CONTROL AIR PRESSURE REG FOR 2-FCV-31-309.

[5] SLOWLY OPEN the Control Air Valve 2-ISV-32-3493, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-309, AND ENSURE there is no leakage from the petcock on the bottom of Pressure Regulator 2-PREG-31-309, CONTROL AIR PRESSURE REG FOR 2-FCV-31-309.

[6] PLACE Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-309, CIRC PMP A DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 71 of 128 Data Package: Page - of Date 6.4.6 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, Loss of Control Air

[1] ENSURE Valve 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL [Annulus, EL 737, AZ 104], is OPEN (local.

observation).

[2] CLOSE the Control Air Valve 2-ISV-32-3666, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-326 [Annulus, EL 737, AZ 104].

[3] SLOWLY OPEN the petcock on the bottom of Pressure Regulator 2-PREG-31-326, CONTROL AIR PRESSURE REG FOR 2-FCV-31-326, Annulus, Elev 737, AZ 104, AND VERIFY Valve 2-FCV-31-326, INCORE INSTR RM AHU 2B CWR ISOL, CLOSES (local observation) (Acc Crit).

[4] CLOSE the petcock on the bottom of Pressure Regulator 2-PREG-31-326, CONTROL AIR PRESSURE REG FOR 2-FCV-31-326.

[5] SLOWLY OPEN the Control Air Valve 2-ISV-32-3666, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-326, AND ENSURE there is no leakage from the petcock on the bottom of Pressure Regulator 2-PREG-31-326, CONTROL AIR PRESSURE REG FOR 2-FCV-31-326.

[6] PLACE Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-326, CIRC PMP B SUCT CIV-PHASE A, Green Light OFF-and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 72 of 128 Data Package: Page - of Date 6.4.7 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, Loss of Control Air

[1] ENSURE Valve 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL [Inst Rm, EL 716, AZ 104], is OPEN (local observation).

[2] CLOSE the Control Air Valve 2-ISV-32-3646, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-327 [Inst Rm, EL 716, AZ 104].

[3] SLOWLY OPEN the petcock on the bottom of Pressure Regulator 2-PREG-31-327, CONTROL AIR PRESSURE REG FOR 2-FCV-31-327 [Inst Rm, EL 716, AZ 104], AND VERIFY Valve 2-FCV-31-327, INCORE INSTR RM AHU 2B CWR ISOL, CLOSES (local observation) (Acc Crit).

[4] CLOSE the petcock on the bottom of Pressure Regulator 2-PREG-31-327, CONTROL AIR PRESSURE REG FOR 2-FCV-31-327.

[5] SLOWLY OPEN the Control Air Valve 2-ISV-32-3646, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-327, AND ENSURE there is no leakage from the petcock on the bottom of Pressure Regulator 2-PREG-31-327, CONTROL AIR PRESSURE REG FOR 2-FCV-31-327.

[6] PLACE Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-327, CIRC PMP B SUCT CIV-PHASE A, Green Light OFF and Red Light ON, THEN

  • RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 73 of 128 Data Package: Page - of Date 6.4.8 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, Loss of Control Air

[1] ENSURE Valve 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL [Inst Rm, EL 716, AZ 105], is OPEN (local observation).

[2] CLOSE the Control Air Valve 2-ISV-32-3647, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-329 [Inst Rm, EL 716, AZ 105].

[3] SLOWLY OPEN the petcock on the bottom of Pressure Regulator 2-PREG-31-329, CONTROL AIR PRESSURE REG FOR 2-FCV-31-329 [Inst Rm, EL 716, AZ 105], AND VERIFY Valve 2-FCV-31-329, INCORE INSTR RM AHU 2B CWS ISOL, CLOSES (local observation) (Acc Crit).

[4] CLOSE the petcock on the bottom of Pressure Regulator 2-PREG-31-329, CONTROL AIR PRESSURE REG FOR 2-FCV-31-329.

[5] SLOWLY OPEN the Control Air Valve 2-ISV-32-3647, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-329, AND ENSURE there is no leakage from the petcock on the bottom of Pressure Regulator 2-PREG-31-329, CONTROL AIR PRESSURE REG FOR 2-FCV-31-329.

[6] PLACE Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-329, CIRC PMP B DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 74 of 128 Data Package: Page of _ Date 6.4.9 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, Loss of Control Air

[1] ENSURE Valve 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL [Annulus, EL 738, AZ 105], is OPEN (local observation).

[2] CLOSE the Control Air Valve 2-ISV-32-3667, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-330 [Annulus, EL 738, AZ 105].

[3] SLOWLY OPEN the petcock on the bottom of Pressure Regulator 2-PREG-31-330, CONTROL AIR PRESSURE REG FOR 2-FCV-31-330 [Annulus, EL 738, AZ 105], AND VERIFY Valve 2-FCV-31-330, INCORE INSTR RM AHU 2B CWS ISOL, CLOSES (local observation) (Acc Crit).

[4] CLOSE the petcock on the bottom of Pressure Regulator 2-PREG-31-330, CONTROL AIR PRESSURE REG FOR 2-FCV-31-330.

[5] SLOWLY OPEN the Control Air Valve 2-ISV-32-3667, CONTROL AIR ISOLATION VALVE TO 2-FCV-31-330, AND ENSURE there is no leakage from the petcock on the bottom of Pressure Regulator 2-PREG-31-330, CONTROL AIR PRESSURE REG FOR 2-FCV-31-330.

[6] PLACE Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, to the OPEN position, AND VERIFY status lights on Handswitch 2-HS-31-330, CIRC PMP B DISCH CIV-PHASE A, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 75 of 128 Data Package: Page - of Date 6.5 Incore Instrument Room 2A/2B Pump and Air Handling Unit Local Operation 6.5.1 Preliminary Actions

[1] VERIFY prerequisites listed in Section 4.0 for SubSection 6.5 have been completed.

NOTE

1) Electrical power to Incore Instrument Room Chillers 2A and 2B was disconnected in Step 4.3[3] to prevent excessive chiller cycling.
2) Equipment status is to be visually verified from the field location.
3) Train A and Train B subsections may be performed in any order as shown in the flow diagram below:

Train A Train B 6.5.2 6.5.4 6.5.3 6.5.5 6.5.6 6.5.7 Pump and Air Handling Unit testing for each respective Train must be completed before performing Temperature Control Valve testing for that Train. Steps within each subsection must be performed in the order written.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 76 of 128 Data Package: Page -of Date 6.5.2 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, Local Operation

[1] PRESS and HOLD START pushbutton on Handswitch 2-HS-31-303, INCORE INSTR ROOM CW PUMP 2A [Pen Rm, EL 692, Col A12W], in 2-JB-292-835, AND VERIFY:

A. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A [Pen Rm, EL 692, Col A12W], STARTS.

B. Status light on Handswitch 2-HS-31-303, INCORE INSTR ROOM CW PUMP 2A, Red Light ON.

C. Status light on Handswitch 2-HS-31-303, INCORE INSTR ROOM CW PUMP 2A, Green Light OFF.

[2] PRESS and HOLD STOP pushbutton on Handswitch 2-HS-31-303, INCORE INSTR ROOM CW PUMP 2A, AND VERIFY:

A. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, STOPS.

B. Status light on Handswitch 2-HS-31-303, INCORE INSTR ROOM CW PUMP 2A, Green Light ON.

C. Status light on Handswitch 2-HS-31-303, INCORE INSTR ROOM CW PUMP 2A, Red Light OFF.

[3] RELEASE STOP pushbutton on Handswitch 2-HS-31-303, INCORE INSTR ROOM CW PUMP 2A, AND VERIFY Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, STARTS.

[4] RELEASE START pushbutton on Handswitch 2-HS-31-303, INCORE INSTR ROOM CW PUMP 2A, AND VERIFY Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, STOPS.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 77 of 128 Data Package: Page - of Date 6.5.2 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, Local Operation (continued)

[5] VERIFY successful completion of this Subsection 6.5.2.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 78 of 128 Data Package: Page - of Date 6.5.3 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, Local Operation

[1] PRESS and HOLD START pushbutton on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B

[Pen Rm, EL 692, Col A12W], in 2-JB-292-835, AND VERIFY:

A. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B [Pen Rm, EL 692, Col A12W], STARTS.

B. Status light on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B, Red Light ON.

C. Status light on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B, Green Light OFF.

[2] PRESS and HOLD STOP pushbutton on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B, AND VERIFY:

A. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, STOPS.

B. Status light on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B, Green Light ON.

C. Status light on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B, Red Light OFF.

[3] RELEASE STOP pushbutton on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B, AND VERIFY Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, STARTS.

[4] RELEASE START pushbutton on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B, AND VERIFY Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, STOPS.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 79 of 128 Data Package: Page _ of Date 6.5.3 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, Local Operation (continued)

[5] VERIFY successful completion of this Subsection 6.5.3.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 80 of 128 Data Package: Page - of Date 6.5.4 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, Local Operation NOTE The electrical circuit for Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, contains a 50 second Time Delay Relay.

[1] PRESS and HOLD START pushbutton on Handswitch 2-HS-31-265B, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A [Inst Rm, EL 730, AZ 57], in 2-JB-293-806, AND VERIFY Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A [Inst Rm, EL 730, AZ 57], STARTS.

[2] PRESS and HOLD STOP pushbutton on Handswitch 2-HS-31-265B, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, AND VERIFY Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, STOPS.

[3] RELEASE STOP pushbutton on Handswitch 2-HS-31-265B, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, AND VERIFY Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, STARTS.

[4] RELEASE START pushbutton on Handswitch 2-HS-31-265B, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, AND VERIFY Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, STOPS.

[5] ENSURE Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, air flow measurement has been performed using GTM-05, AND ATTACH completed GTM-05 data sheets.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 81 of 128 Data Package: Page _ of _ Date 6.5.4 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, Local Operation (continued)

[6] RECORD the air flow measurement below:

CFM Acc Crit: 5,200 CFM (min. 4,680)

AND VERIFY the air flow measurement meets acceptance criteria.

[7] VERIFY successful completion of this Subsection 6.5.4.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 82 of 128 Data Package: Page __ of__ Date 6.5.5 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, Local Operation NOTE The electrical circuit for Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, contains a 50 second Time Delay Relay.

[1] PRESS and HOLD START pushbutton on Handswitch 2-HS-31-266B, INCORE INSTRUMENT ROOM CHILLER 2B

[Inst Rm, EL 730, AZ 112], in 2-JB-293-804, AND VERIFY Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B [Inst Rm, EL 730, AZ 112], STARTS.

[2] PRESS and HOLD STOP pushbutton on Handswitch 2-HS-31-266B, INCORE INSTRUMENT ROOM CHILLER 2B, AND VERIFY Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, STOPS.

[3] RELEASE STOP pushbutton on Handswitch 2-HS-31-266B, INCORE INSTRUMENT ROOM CHILLER 2B, AND VERIFY Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, STARTS.

[4] RELEASE START pushbutton on Handswitch 2-HS-31-266B, INCORE INSTRUMENT ROOM CHILLER 2B, AND VERIFY Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, STOPS.

[5] ENSURE Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, air flow measurement has been performed using GTM-05, AND ATTACH completed GTM-05 data sheets.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 83 of 128 Data Package: Page - of Date 6.5.5 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, Local Operation (continued)

[6] RECORD the air flow measurement below:

CFM Acc Crit: 5,200 OFM (min. 4,680)

AND VERIFY the air flow measurement meets acceptance criteria.

[7] VERIFY successful completion of this Subsection 6.5.5.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 84 of 128 Data Package: Page _ of _ Date 6.5.6 2-TCV-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL, Operation NOTE The determination of position for three-way Temperature Control Valves is:

  • "0" indicates OPEN (air applied and spring retracted), or full flow through bypass.
  • "S"indicates SHUT (air off and spring extended), or full flow through cooling coil.

[1] PRESS START pushbutton on Handswitch 2-HS-31-303, INCORE INSTR ROOM CW PUMP 2A [Pen Rm, EL 692, Col A12W], in 2-JB-292-835, AND VERIFY Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A [Pen Rm, EL 692, Col A12W], STARTS.

[2] APPLY heat to the Temperature Indicating Controller 2-TIC-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL

[Inst Rm, EL 730, AZ 70], sensing bulb with a heat gun.

[3] WHEN Valve 2-TCV-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL [Inst Rm, EL 730, AZ 70], moves fully to the "S" position, THEN STOP applying heat to the Temperature Indicating Controller 2-TIC-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL, sensing bulb.

[4] COOL the Temperature Indicating Controller 2-TIC-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL, sensing bulb with an ice bath.

[5] WHEN Valve 2-TCV-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL, moves fully to the "0" position, THEN REMOVE the ice bath.

[6] APPLY heat to the Temperature Indicating Controller 2-TIC-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL, sensing bulb with a heat gun.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 85 of 128 Data Package: Page - of Date 6.5.6 2-TCV-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL, Operation (continued)

[7] WHEN Valve 2-TCV-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL, moves AWAY from the "0"position, allowing normal coil flow, THEN STOP applying heat to the Temperature Indicating Controller 2-TIC-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL, sensing bulb.

[8] PRESS STOP pushbutton on Handswitch 2-HS-31-"303, INCORE INSTR ROOM CW PUMP 2A, AND VERIFY Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, STOPS.

[9] VERIFY successful completion of this Subsection 6.5.6.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 86 of 128 Data Package: Page _ of -Date 6.5.7 2-TCV-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL, Operation NOTE The determination of position for three-way Temperature Control Valves is:

  • "0"indicates OPEN (air applied and spring retracted), or full flow through bypass.
  • "S" indicates SHUT (air off and spring extended), or full flow through cooling coil.

[1] PRESS START pushbutton on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B [Pen Rm, EL 692, Col A12W], in 2-JB-292-835, AND VERIFY Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B [Pen Rm, EL 692, Col A12W], STARTS.

[2] APPLY heat to the Temperature Indicating Controller 2-TIC-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL [Inst Rm, EL 731, AZ 116], sensing bulb with a heat gun.

[3] WHEN Valve 2-TCV-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL [Inst Rm, EL 731, AZ 116], moves fully to the "S"position, THEN STOP applying heat to the Temperature Indicating Controller 2-TIC-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL, sensing bulb.

[4] COOL the Temperature Indicating Controller 2-TIC-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL, sensing bulb with an ice bath.

[5] WHEN Valve 2-TCV-31-328 INCORE INSTR RM AHU 2B CW TEMP CONTROL, moves fully to the "0"position, THEN REMOVE the ice bath.

[6] APPLY heat to the Temperature Indicating Controller 2-TIC-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL, sensing bulb with a heat gun.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 87 of 128 Data Package: Page - of _ Date 6.5.7 2-TCV-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL, Operation (continued)

[7] WHEN Valve 2-TCV-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL, moves AWAY from the "0" position, allowing normal coil flow, THEN STOP applying heat to the Temperature Indicating Controller 2-TIC-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL, sensing bulb.

[8] PRESS STOP pushbutton on Handswitch 2-HS-31-324, INCORE INSTRUMENT ROOM CW PUMP 2B, AND VERIFY Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, STOPS.

[9] VERIFY successful completion of this Subsection 6.5.7.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 88 of 128 Data Package: Page _ of Date 6.6 Incore Instrument Room 2A/2B Air Handling Unit, Pump, Chiller, and Damper Normal Operation 6.6.1 Preliminary Actions

[1] VERIFY prerequisites listed in Section 4.0 for SubSection 6.6 have been completed.

NOTES

1) Subsections 6.6.2 and 6.6.3 may be performed in any order. Steps within these subsections must be performed in the order written.
2) Equipment status is to be visually verified from the field location.

[2] PLACE the following breakers in CLOSED:

A. Breaker 2-BKR-31-303B, INCORE INSTR RM CHLR 2A COMPR (2-COMP-303/2) [480V Rx MOV Bd 2A1 -A, Compt 16F2, EL 772 A12/T]

B. Breaker 2-BKR-31-324B, INSTR RM A/C COMPR 2B (2-COMP-31-324/2) [480V Rx MOV Bd 2B1 -B, Compt 17F2, EL 772 A12/T]

[3] ENSURE the following valves are CLOSED:

A. Valve 2-TCV-67-115, INSTR RM WATER CLR 2A ERCW SUP TEMP CNTL [Pen Rm, EL 692, Col A12W]

B. Valve 2-TCV-67-118, INSTR RM WATER CLR 2B ERCW SUP TEMP CNTL [Pen Rm, EL 692, Col A12W]

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 89 of 128 Data Package: Page _ of Date 6.6.2 Incore Instrument Room 2A Air Handling Unit, Pump, Chiller, and Damper Normal Operation

[1] INSTALL ultrasonic flowmeter onto 2 inch chilled water piping (Schedule 40 carbon steel, 2.38 inch OD, 0.15 inch wall thickness) immediately downstream of 2-CHR-31-303, INCORE INSTR ROOM CHILLER 2A [Pen Rm, EL 692, Col A12W].

NOTES

1) Temperature Indicating Controller 2-TIC-31-307, INCORE INSTR RM AHU 2A CW TEMP CNTL, sensing bulb is to be kept above 85 0 F to indirectly maintain chiller operation throughout the performance of this section.
  • Use heat guns as needed to maintain temperature.
  • Use pocket thermometer as needed to verify temperature.
2) The electrical circuit for Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, contains a 50 second Time Delay Relay.

NOTE During the performance of Steps 6.6.2[2] and 6.6.2[3] visual observation of transient and steady state vibrations is required.

[2] PLACE Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW [2-M-9], to START, AND VERIFY Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A [Inst Rm, EL 730, AZ 57], STARTS, AND RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 90 of 128 Data Package: Page - of Date 6.6.2 Incore Instrument Room 2A Air Handling Unit, Pump, Chiller, and Damper Normal Operation (continued)

[3] VERIFY:

A. Pump 2-PMP-31-303/1, INCORE INSTR ROOM OW PUMP 2A [Pen Rm, EL 692, Col A12W], STARTS.

B. Compressor 2-COMP-31-303B, INCORE INSTR RM

.CHILLER A COMPRESSOR [Pen Rm, EL 692, Col Al2W], STARTS.

C. Damper 2-FCO-31-263, INCORE INSTR RM AHU 2A DISCHARGE [Inst Rm, EL 730, AZ 57], is OPEN.

D. Damper 2-FCO-31-264, INCORE INSTR RM AHU 2A DISCHARGE [Inst Rm, EL 730, AZ 57], is OPEN.

E. Valve 2-TCV-67-115, INSTR RM WATER CLR 2A ERCW SUP TEMP CNTL [Pen Rm, EL 692, Col A12W], is OPEN.

F. Red Light ON, at Breaker 2-BKR-31-265, INCORE INSTR RM COOLER FAN 2A (2-MTR-31-265) [480V Rx MOV Bd 2A1-A, Compt 16A].

G. Red Light ON, at Breaker 2-BKR-31-303A, INCORE INSTR RM CW PMP 2A (2-PMP-31-303/1) [480V Rx MOV Bd 2A1 -A, Compt 18C].

H. Red Light ON, at Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW.

1. Green Light OFF, at Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW.

J. Red Light ON, Status Indication Window, 2-XI-31-263, INCORE INST RM A/C ISOL DMPR STATUS [2-M-9].

K. Green Light OFF, Status Indication Window, 2-XI-31-263, INCORE INST RM A/C ISOL DMPR STATUS.

L. Red Light ON, Status Indication Window, 2-XI-31-264, INCORE INST RM A/C ISOL DMPR STATUS [2-M-9].

M. Green Light OFF, Status Indication Window, 2-XI-31-264, INCORE INST RM A/C ISOL DMPR STATUS.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 91 of 128 Data Package: Page - of _ Date 6.6.2 Incore Instrument Room 2A Air Handling Unit, Pump, Chiller, and Damper Normal Operation (continued)

[4] WAIT approximately 15 minutes before performing next step.

[5] RECORD the chilled water flow rate from the ultrasonic flow meter:

GPM Acc Crit: min. 22 GPM AND VERIFY the chilled water flow rate meets acceptance criteria.

[6] RECORD chilled water inlet/return temperature setpoint from local control panel of 2-CHR-31-303, INCORE INSTR ROOM CHILLER 2A:

Inlet/Return OF Temp. Setpoint

[7] RAISE chilled water inlet/return temperature setpoint on local control panel of 2-CHR-31-303, INCORE INSTR ROOM CHILLER 2A, ABOVE current chilled water inlet/return temperature UNTIL Compressor 2-COMP-31-303B, INCORE INSTR RM CHILLER A COMPRESSOR, STOPS.

[8] WAIT approximately 15 minutes before performing next step.

[9] RETURN chilled water inlet/return temperature setpoint on local control panel of 2-CHR-31-303, INCORE INSTR ROOM CHILLER 2A, to the setpoint recorded in Step 6.6.2[6].

[10] VERIFY Compressor 2-COMP-31-303B, INCORE INSTR RM CHILLER A COMPRESSOR, STARTS.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 92 of 128 Data Package: Page -of Date 6.6.2 Incore Instrument Room 2A Air Handling Unit, Pump, Chiller, and Damper Normal Operation (continued)

NOTE During the performance of Step 6.6.2111] visual observation of transient and steady state vibrations is required.

[11] PLACE Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW, to STOP (PULL TO LOCK), AND VERIFY:

A. Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, STOPS.

B. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, STOPS.

C. Compressor 2-COMP-31-303B, INCORE INSTR RM CHILLER A COMPRESSOR, STOPS.

D. Damper 2-FCO-31-263, INCORE INSTR RM AHU 2A DISCHARGE, CLOSES.

E. Damper 2-FCO-31-264, INCORE INSTR RM AHU 2A DISCHARGE, CLOSES.

F. Valve 2-TCV-67-115, INSTR RM WATER CLR 2A ERCW SUP TEMP CNTL, CLOSES.

G. Red Light OFF, at Breaker 2-BKR-31-265, INCORE INSTR RM COOLER FAN 2A (2-MTR-31-265).

H. Red Light OFF, at Breaker 2-BKR-31-303A, INCORE INSTR RM CW PMP 2A (2-PMP-31-303/1).

1. Green Light ON, at Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW.

J. Red Light OFF, at Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW.

K. Green Light ON, Status Indication Window, 2-XI-31-263, INCORE INST RM A/C ISOL DMPR STATUS.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 93 of 128 Data Package: Page - of Date 6.6.2 Incore Instrument Room 2A Air Handling Unit, Pump, Chiller, and Damper Normal Operation (continued)

L. Red Light OFF, Status Indication Window, 2-XI-31-263, INCORE INST RM A/C ISOL DMPR STATUS.

M. Green Light ON, Status Indication Window, 2-XI-31-264, INCORE INST RM A/C ISOL DMPR STATUS.

N. Red Light OFF, Status Indication Window, 2-XI-31-264, INCORE INST RM A/C ISOL DMPR STATUS.

[12] VERIFY no excessive vibration of the piping system and components associated with the performance of this subsection was observed.

[13] REMOVE ultrasonic flowmeter from 2 inch chilled water piping immediately downstream of 2-CHR-31-303, INCORE INSTR ROOM CHILLER 2A.

[14] VERIFY successful completion of this Subsection 6.6.2.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 94 of 128 Data Package: Page _ of _ Date 6.6.3 Incore Instrument Room 2B Air Handling Unit, Pump, Chiller, and Damper Normal Operation

[1] INSTALL ultrasonic flowmeter onto 2 inch chilled water piping (Schedule 40 carbon steel, 2.38 inch OD, 0.15 inch wall thickness) immediately downstream of 2-CHR-31-324, INCORE INSTRUMENT ROOM CHILLER 2B [Pen Rm, EL 692, Col A12W].

NOTES

1) Temperature Indicating Controller 2-TIC-31-328, INCORE INSTR RM AHU 2B CW TEMP CONTROL, sensing bulb is to be kept above 85 0F to indirectly maintain chiller operation throughout the performance of this section.
  • Use heat guns as needed to maintain temperature.
  • Use pocket thermometer as needed to verify temperature.
2) The electrical circuit for Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, contains a 50 second Time Delay Relay.

NOTE During the performance of Steps 6.6.3[2] and 6.6.3[3] visual observation of transient and steady state vibrations is required.

[2] PLACE Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW [2-M-9], to START, AND VERIFY Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B [Inst Rm, EL 730, AZ 112], STARTS, AND RELEASE to A AUTO.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 95 of 128 Data Package: Page - of Date 6.6.3 Incore Instrument Room 2B Air Handling Unit, Pump, Chiller, and Damper Normal Operation (continued)

[3] VERIFY:

A. Pump 2-PMP-31.-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B [Pen Rm, EL 692, Col A12W], STARTS.

B. Compressor 2-COMP-31-324B, INCORE INSTR RM CHILLER B COMPRESSOR [Pen Rm, EL 692, Col A12W], STARTS.

C. Damper 2-FCO-31-268, INCORE INSTR RM AHU 2B DISCHARGE [Inst Rm, EL 730, AZ 112], is OPEN.

D. Damper 2-FCO-31-269, INCORE INSTR RM AHU 2B DISCHARGE [Inst Rm, EL 730, AZ 112], is OPEN..

E. Valve 2-TCV-67-118, INSTR RM WATER CLR 2B ERCW SUP TEMP CNTL [Pen Rm, EL 692, Col A12W], is OPEN.

F. Red Light ON, at Breaker 2-BKR-31-266, INCORE INSTR RM AHU 2B (2-AHU-31-266-B) [480V Rx MOV Bd 2B1 -B, Compt 16A].

G. Red Light ON, at Breaker 2-BKR-31-324A, INCORE INSTR RM CW PMP 2B (2-MTR-31-324/1) [480V Rx MOV Bd 2B1 -B, Compt 18C].

H. Red Light ON, at Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW.

1. Green Light OFF, at Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW.

J. Red Light ON, Status Indication Window, 2-XI-31-268, INCORE INST RM A/C ISOL DMPR STATUS [2-M-9].

K. Green Light OFF, Status Indication Window, 2-XI-31-268, INCORE INST RM A/C ISOL DMPR STATUS.

L. Red Light ON, Status Indication Window, 2-XI-31-269, INCORE INST RM A/C ISOL DMPR STATUS [2-M-9].

M. Green Light OFF, Status Indication Window, 2-XI-31-269, INCORE INST RM A/C ISOL DMPR STATUS.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 96 of 128 Data Package: Page - of _ Date 6.6.3 Incore Instrument Room 2B Air Handling Unit, Pump, Chiller, and Damper Normal Operation (continued)

[4] WAIT approximately 15 minutes before performing next step.

[5] RECORD the chilled water flow rate from the ultrasonic flow meter:

GPM Acc Crit: min. 22 GPM AND VERIFY the chilled water flow rate meets acceptance criteria.

[6] RECORD chilled water inlet/return temperature setpoint from local control panel of 2-CHR-31-324, INCORE INSTRUMENT ROOM CHILLER 2B:

Inlet/Return OF Temp. Setpoint

[7] RAISE chilled water inlet/return temperature setpoint on local control panel of 2-CHR-31-324, INCORE INSTRUMENT ROOM CHILLER 2B, ABOVE current chilled water inlet/return temperature UNTIL Compressor 2-COMP-31-324B, INCORE INSTR RM CHILLER B COMPRESSOR, STOPS.

[8] WAIT approximately 15 minutes before performing next step.

[9] RETURN chilled water inlet/return temperature setpoint on local control panel of 2-CHR-31-324, INCORE INSTRUMENT ROOM CHILLER 2B, to the setpoint recorded in Step 6.6.3[6].

[10] VERIFY Compressor 2-COMP-31-324B, INCORE INSTR RM CHILLER B COMPRESSOR, STARTS.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 97 of 128 Data Package: Page _ of _ Date 6.6.3 Incore Instrument Room 2B Air Handling Unit, Pump, Chiller, and Damper Normal Operation (continued)

NOTE During the performance of Step 6.6.3[1 1] visual observation of transient and steady state vibrations is required.

[11] PLACE Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW, to STOP (PULL TO LOCK), AND VERIFY:

A. Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, STOPS.

B. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, STOPS.

C. Compressor 2-COMP-31-324B, INCORE INSTR RM CHILLER B COMPRESSOR, STOPS.

D. Damper 2-FCO-31-268, INCORE INSTR RM AHU 2B DISCHARGE, CLOSES.

E. Damper 2-FCO-31-269, INCORE INSTR RM AHU 2B DISCHARGE, CLOSES.

F. Valve 2-TCV-67-118, INSTR RM WATER CLR 2B ERCW SUP TEMP CNTL, CLOSES.

G. Red Light ON, at Breaker 2-BKR-31-266, INCORE INSTR RM AHU 2B (2-AHU-31-266-B).

H. Red Light ON, at Breaker 2-BKR-31-324A, INCORE INSTR RM CW PMP 2B (2-MTR-31-324/1).

1. Green Light ON, at Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW.

J. Red Light OFF, at Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW.

K. Green Light ON, Status Indication Window, 2-XI-31-268, INCORE INST RM A/C ISOL DMPR STATUS.

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 98 of 128 Data Package: Page - of Date 6.6.3 Incore Instrument Room 2B Air Handling Unit, Pump, Chiller, and Damper Normal Operation (continued)

L. Red Light OFF, Status Indication Window, 2-XI-31-268, INCORE INST RM A/C ISOL DMPR STATUS. .

M. Green Light ON, Status Indication Window, 2-XI-31-269, INCORE INST RM A/C ISOL DMPR STATUS.

N. Red Light OFF, Status Indication Window, 2-XI-31-269, INCORE INST RM A/C ISOL DMPR STATUS.

[12] VERIFY no excessive vibration of the piping system and components associated with the performance of this subsection was observed.

[13] REMOVE ultrasonic flowmeter from 2 inch chilled water piping immediately downstream of 2-CHR-31-324, INCORE INSTRUMENT ROOM CHILLER 2B.

[14] VERIFY successful completion of this Subsection 6.6.3.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 99 of 128 Data Package: Page _ of Date 6.7 Incore Instrument Room 2A/2B Air Handling Unit Stop on Simulated Phase A Containment Isolation 6.7.1 Preliminary Actions

[1] VERIFY prerequisites listed in Section 4.0 for SubSection 6.7 have been completed.

NOTES

1) Subsections 6.7.2 and 6.7.3 may be performed in any order. Steps within these subsections must be performed in the order written.
2) Equipment status is to be visually Verified from the field location.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 100 of 128 Data Package: Page - of _ Date 6.7.2 Incore Instrument Room 2A Air Handling Unit Stop on Simulated Phase A Containment Isolation

[1] PLACE Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW [2-M-9], to START, AND VERIFY Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A [Inst Rm, EL 730, AZ 57], STARTS, AND RELEASE to A AUTO.

[2] VERIFY:

A. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A [Pen Rm, EL 692, Col A12W], STARTS.

B. Damper 2-FCO-31-263, INCORE INSTR RM AHU 2A DISCHARGE [Inst Rm, EL 730, AZ 57], is OPEN.

C. Damper 2-FCO-31-264, INCORE INSTR RM AHU 2A DISCHARGE [Inst Rm, EL 730, AZ 57], is OPEN.

[3] LIFT Wire 16A6 from Terminal Point 6 on TB 612 in 2-R-48

[U2 Aux Inst Room] to simulate a Phase A Containment Isolation.

1 st CV

[4] VERIFY:

A. Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, STOPS.

B. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, STOPS.

C. Damper 2-FCO-31-263, INCORE INSTR RM AHU 2A DISCHARGE, CLOSES.

D. Damper 2-FCO-31-264, INCORE INSTR RM AHU 2A DISCHARGE, CLOSES.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 101 of 128 Data Package: Page -of Date 6.7.2 Incore Instrument Room 2A Air Handling Unit Stop on Simulated Phase A Containment Isolation (continued)

[5] LAND Wire 16A6 on Terminal Point 6 on TB 612 in 2-R-48 to simulate a Phase A Containment Isolation reset.

1st Cv

[6] VERIFY:

A. Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, is OFF.

B. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, is OFF.

C. Damper 2-FCO-31-263, INCORE INSTR RM AHU 2A DISCHARGE, is CLOSED.

D. Damper 2-FCO-31-264, INCORE INSTR RM AHU 2A DISCHARGE, is CLOSED.

[7] PLACE Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW, to START, AND VERIFY Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, STARTS, AND RELEASE to A AUTO.

[8] VERIFY:

A. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, STARTS.

B. Damper 2-FCO-31-263, INCORE INSTR RM AHU 2A DISCHARGE, is OPEN.

C. Damper 2-FCO-31-264, INCORE INSTR RM AHU 2A DISCHARGE, is OPEN.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 102 of 128 Data Package: Page - of Date 6.7.2 Incore Instrument Room 2A Air Handling Unit Stop on Simulated Phase A Containment Isolation (continued)

[9] PLACE Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW, to STOP (PULL TO LOCK), AND VERIFY:

A. Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A, STOPS.

B. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, STOPS.

C. Damper 2-FCO-31-263, INCORE INSTR RM AHU 2A DISCHARGE, CLOSES.

D. Damper 2-FCO-31-264, INCORE INSTR RM AHU 2A DISCHARGE, CLOSES.

[10] VERIFY successful completion of this Subsection 6.7.2.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 103 of 128 Data Package: Page of _ Date 6.7.3 Incore Instrument Room 2B Air Handling Unit Stop on Simulated Phase A Containment Isolation

[1] PLACE Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW [2-M-9], to START, AND VERIFY Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B [Inst Rm, EL 730, AZ 112], STARTS, AND RELEASE to A AUTO.

[2] VERIFY:

A. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B [Pen Rm, EL 692, Col A12W], STARTS.

B. Damper 2-FCO-31-268, INCORE INSTR RM AHU 2B DISCHARGE [Inst Rm, EL 730, AZ 112], is OPEN.

C. Damper 2-FCO-31-269, INCORE INSTR RM AHU 2B DISCHARGE [Inst Rm, EL 730, AZ 112], is OPEN.

[3] LIFT Wire 16A6 from Terminal Point 6 on TB 612 in 2-R-51

[U2 Aux Inst Room] to simulate a Phase A Containment Isolation.

1 st CV

[4] VERIFY:

A. Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, STOPS.

B. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, STOPS.

C. Damper 2-FCO-31-268, INCORE INSTR RM AHU 2B DISCHARGE, CLOSES.

D. Damper 2-FCO-31-269, INCORE INSTR RM AHU 2B DISCHARGE, CLOSES.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 104 of 128 Data Package: Page - of Date 6.7.3 Incore Instrument Room 2B Air Handling Unit Stop on Simulated Phase A Containment Isolation (continued)

[5] LAND Wire 16A6 on Terminal Point 6 on TB 612 in 2-R-51 to simulate a Phase A Containment Isolation reset.

1st Cv

[6] VERIFY:

A. Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, is OFF.

B. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, is OFF.

C. Damper 2-FCO-31-268, INCORE INSTR RM AHU 2B DISCHARGE, is CLOSED.

D. Damper 2-FCO-31-269, INCORE INSTR RM AHU 2B

, DISCHARGE, is CLOSED.

[7] PLACE Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW, to START, AND VERIFY Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, STARTS, AND RELEASE to A AUTO.

[8] VERIFY:

A. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, STARTS.

B. Damper 2-FCO-31-268, INCORE INSTR RM AHU 2B DISCHARGE, is OPEN.

C. Damper 2-FCO-31-269, INCORE INSTR RM AHU 2B DISCHARGE, is OPEN.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 105 of 128 Data Package: Page of _ Date 6.7.3 Incore Instrument Room 2B Air Handling Unit Stop on Simulated Phase A Containment Isolation (continued)

[9] PLACE Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW, to STOP (PULL TO LOCK), AND VERIFY:

A. Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, STOPS.

B. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, STOPS.

C. Damper 2-FCO-31-268, INCORE INSTR RM AHU 2B DISCHARGE, CLOSES.

D. Damper 2-FCO-31-269, INCORE INSTR RM AHU 2B DISCHARGE, CLOSES.

.[10] VERIFY successful completion of this Subsection 6.7.3.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 106 of 128 Data Package: Page - of Date 6.8 Incore Instrument Room Redundant Unit Start on Low Air Flow

[1] VERIFY prerequisites listed in Section 4.0 for SubSection 6.8 have been completed.

[2] PLACE Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW [2-M-9], to START, AND VERIFY status lights on Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW, Green Light OFF and Red Light ON, THEN RELEASE to A AUTO.

[3] ENSURE Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B [Inst Rm, EL 730, AZ 112], is OFF (local observation).

[4] VERIFY Annunciator Window 2-XA-55-5C/103-E, INSTR RM COOLER A/B FLOW LO, is CLEAR.

NOTE In the following step, if difficulties are encountered, the Air Handling Unit should be STOPPED immediately.

[5] COMPLETELY COVER air inlet to Fan 2-FAN-31-265, INCORE INSTR RM AHU 2A FAN, Incore Inst Rm, Elev 730, AZ 57, with cardboard, AND VERIFY:

A. Air Handling Unit 2-AHU-31-266, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2B, STARTS (local observation).

B. Annunciator Window 2-XA-55-5C/1 03-E, INSTR RM COOLER A/B FLOW LO, ALARMS.

C. Unit 2 Alarm Events Display Screen indicates 103-E INSTR RM COOLER A/B FLOW LO (FS-31-263) is in ALARM (Red).

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 107 of 128 Data Package: Page - of Date t 6.8 Incore Instrument Room Redundant Unit Start on Low Air Flow (continued)

[6] REMOVE cardboard from air inlet installed in Step 6.8[5].

[7] VERIFY:

A. Annunciator Window 2-XA-55-5C/1 03-E, INSTR RM COOLER A/B FLOW LO, CLEARS.

B. Unit 2 Alarm Events Display Screen indicates 103-E, INSTR RM COOLER A/B FLOW LO (FS-31-263), is NORMAL (Green).

[8] PLACE Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW, to STOP, AND VERIFY status lights on Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW, Green Light ON and Red Light OFF, THEN RELEASE to A AUTO.

[9] VERIFY Annunciator Window 2-XA-55-5C/1 03-E, INSTR RM COOLER A/B FLOW LO, is CLEAR.

NOTE In the following step, if difficulties are encountered, the Air Handling Unit should be STOPPED immediately.

[10] COMPLETELY COVER air inlet to Fan 2-FAN-31-266, INCORE INSTR RM AHU 2B FAN, Incore Inst Rm, Elev 730, AZ 112, with cardboard, AND VERIFY:

A. Air Handling Unit 2-AHU-31-265, INCORE INSTRUMENT ROOM AIR HANDLING UNIT 2A [Inst Rm, EL 730, AZ 57], STARTS (local observation).

B. Annunciator Window 2-XA-55-5C/103-E, INST RM COOLER A/B FLOW LO, ALARMS.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 108 of 128 Data Package: Page - of Date 6.8 Incore Instrument Room Redundant Unit Start on Low Air Flow (continued)

C. Unit 2 Alarm Events Display Screen indicates 103-E INST RM COOLER A/B FLOW LO (FS-31-263) is in ALARM (Red).

[11] REMOVE cardboard from air inlet installed in Step 6.8[10].

[12] VERIFY:

A. Annunciator Window 2-XA-55-5C/103-E, I NST RM COOLER A/B FLOW LO, CLEARS.

B. Unit 2 Alarm Events Display Screen indicates 103-E INSTR RM COOLER A/B FLOW LO (FS-31-263) is in NORMAL (Green).

[13] PLACE Handswitch, 2-HS-31-266A, INCORE INST RM A/C B SW [2-M-9], to STOP (PULL TO LOCK), AND VERIFY status lights on Handswitch 2-HS-31-266A, INCORE INST RM A/C B SW, Green Light ON and Red Light OFF.

[14] PLACE Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW, to STOP (PULL TO LOCK), AND VERIFY status lights on Handswitch 2-HS-31-265A, INCORE INST RM A/C A SW, Green Light ON and Red Light OFF.

[15] VERIFY successful completion of this Subsection 6.8.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 109 of 128 Data Package: Page - of Date 6.9 Incore Instrument Room 2A/2B Circulation Pump Trip on Low Tank Level 6.9.1 Preliminary Actions

[1] VERIFY prerequisites listed in Section 4.0 for SubSection 6.9 have been completed.

CAUTION Work in 2-JB-292-835 involves energized circuits.

6.9.2 Incore Instrument Room Circulation Pump 2A Trip on Low Tank Level

[1] ENSURE 2-LG-31-304, INCORE INSTRUMENT ROOM SURGE TANK 2A LEVEL [Pen Rm, EL 692, Col A12W],

indicates 75-100% full.

[2] INSTALL jumper at terminal block TA, across wire numbers 18CX and 18CLS2, in 2-JB-292-835 [Pen Rm, EL 692, Col Al 2W], to simulate the air handling unit fan starting.

1st CV

[3] VERIFY 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A [Pen Rm, EL 692, Col A12W], STARTS.

[4] VERIFY Annunciator Window 2-XA-55-5C/104-E, INSTR RM COOLING SURGE TANK A/B LEVEL LO, is CLEAR.

[5] CLOSE the following valves:

A. 2-RTV-31-1102A, 2-LS-31-303 ROOT [Pen Rm, EL 692, Col A12W]

B. 2-RTV-31-1103A, 2-LS-31-303 ROOT [Pen Rm, EL 692, Col A12W]

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 110 of 128 Data Package: Page _ of Date 6.9.2 Incore Instrument Room Circulation Pump 2A Trip on Low Tank Level (continued)

[6] DISCONNECT the top test port connection between 2-RTV-31-1102A, 2-LS-31-303 ROOT, and 2-LS-31-303, INCORE INSTR ROOM SURGE TANK 2A [Pen Rm, EL 692, Col AI2W].

1st CV NOTES

1) Step 6.9.2[7] requires a 5 gallon bucket to capture drain water from Level Switch instrument lines.
2) During the performance of Steps 6.9.2[7] and 6.9.2[8], moniter Level Gauge 2-LG-31-304, INCORE INSTRUMENT ROOM SURGE TANK 2A LEVEL, to prevent pump operation under dry conditions. If the level gauge indicates less than 25%, the pump should be STOPPED immediately.

[7] DISCONNECT the bottom test port connection between 2-RTV-31-1103A, 2-LS-31-303 ROOT, and 2-LS-31-303, INCORE INSTR ROOM SURGE TANK 2A, (to drain line).

1st CV

[8] VERIFY:

A. Pump 2-PMP-31-303/1, INCORE INSTR ROOM CW PUMP 2A, STOPS.

B. Annunciator Window, 2-XA-55-5C/104-E, INSTR RM COOLING SURGE TANK A/B LEVEL LO, ALARMS.

C. Unit 2 Alarm Events Display Screen indicates 104-E INSTR RM COOLING SURGE TANK A LEVEL LO (LS-31-303) is in ALARM (Red).

[9] REMOVE jumper from terminal block TA, across wire numbers 18CX and 18CLS2, in 2-JB-292-835, to simulate the air handling unit fan stopping. 1st CV

Incore Instrument Room Air 2-PTI-031B-01 Conditioning System Rev. 0000 Page 111 of 128 Data Package: Page _ of Date 6.9.2 Incore Instrument Room Circulation Pump 2A Trip on Low Tank Level (continued)

[10] RECONNECT the following:

A. Bottom test port connection between 2-RTV-31-1103A, 2-LS-31-303 ROOT, and 2-LS-31-303, INCORE INSTR ROOM SURGE TANK 2A 1st CV B. Top test port connection between 2-RTV-31-1102A, 2-LS-31-303 ROOT, and 2-LS-31-303, INCORE INSTR ROOM SURGE TANK 2A 1 st CV

[11] OPEN 2-RTV-31-1102A, 2-LS-31-303 ROOT.

[12] SLOWLY OPEN 2-RTV-31-1103A, 2-LS-31-303 ROOT, to refill 2-LS-31-303, INCORE INSTR ROOM SURGE TANK 2A.

[13] ENSURE 2-LG-31-304, INCORE INSTRUMENT ROOM SURGE TANK 2A LEVEL, indicates 75 - 100% full.

[14] VERIFY the following:

A. Annunciator Window, 2-XA-55-5C/104-E, INSTR RM COOLING SURGE TANK A/B LEVEL LO, CLEARS.

B. Unit 2 Alarm Events Display Screen indicates 104-E INSTR RM COOLING SURGE TANK A LEVEL LO (LS-31-303) is NORMAL (Green).

[15] VERIFY successful completion of this Subsection 6.9.2.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 112 of 128 Data Package: Page -of Date 6.9.3 Incore Instrument Room Circulation Pump 2B Trip on Low Tank Level

[1] ENSURE 2-LG-31-325, INCORE INSTRUMENT ROOM SURGE TANK 2B LEVEL [Pen Rm, EL 692, Col A12W]

indicates 75-100% full.

[2] INSTALL jumper at terminal block TB, across wire numbers 18CX and 18CLS2, in 2-JB-292-835, to simulate the air handling unit fan starting.

1st CV

[3] VERIFY 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B [Pen Rm, EL 692, Col A12W], STARTS.

[4] VERIFY Annunciator Window, 2-XA-55-5C/1 04-E, INSTR RM COOLING SURGE TANK A/B LEVEL LO, is CLEAR.

[5] CLOSE the following valves:

A. 2-RTV-31-1112, INCORE INST RM CHILL B SURG TK LEVEL [Pen Rm, EL 692, Col A12W]

B. 2-RTV-31-1113A, 2-LS-31-324 ROOT [Pen Rm, EL 692, Col A12W]

[6] DISCONNECT the top test port connection between 2-RTV-31-1112, INCORE INST RM CHILL B SURG TK LEVEL, and 2-LS-31-324, INCORE INSTRUMENT ROOM SURGE TANK 2B LEVEL [Pen Rm, EL 692, Col Al 2W].

1 st CV

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 113 of 128 Data Package: Page - of Date 6.9.3 Incore Instrument Room Circulation Pump 2B Trip on Low Tank Level (continued)

NOTES

1) Step 6.9.3[7] requires a 5 gallon bucket to capture drain water from Level Switch instrument lines.
2) During the performance of Steps 6.9.3[7] and 6.9.3[8], moniter Level Gauge 2-LG-31-304, INCORE INSTRUMENT ROOM SURGE TANK 2A LEVEL, to prevent pump operation under dry conditions. If the level gauge indicates less than 25%, the pump should be STOPPED immediately.

[7] DISCONNECT the bottom test port connection between 2-RTV-31-1113A, 2-LS-31-324 ROOT, and 2-LS-31-324, INCORE INSTRUMENT ROOM SURGE TANK 2B LEVEL, (to drain line).

1st CV

[8] VERIFY:

A. Pump 2-PMP-31-324/1, INCORE INSTRUMENT ROOM CW PUMP 2B, STOPS.

B. Annunciator Window, 2-XA-55-5C/104-E, INSTR RM COOLING SURGE TANK A/B LEVEL LO, ALARMS.

C. Unit 2 Alarm Events Display Screen indicates 104-E INST RM COOLING SURGE TANK B LEVEL LO (LS-31-324) is in ALARM (Red).

[9] REMOVE jumper from terminal block TB, across wire numbers 18CX and 18CLS2, in 2-JB-292-835, to simulate the air handling unit fan stopping.

1st CV

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 114 of 128 Data Package: Page _ of Date 6.9.3 Incore Instrument Room Circulation Pump 2B Trip on Low Tank Level (continued)

[10] RECONNECT the following:

A. Bottom test port connection between 2-RTV-31-1113A, 2-LS-31-324 ROOT, and 2-LS-31-324, INCORE INSTRUMENT ROOM SURGE TANK 2B LEVEL 1st CV B. Top test port connection between 2-RTV-31-1112, INCORE INST RM CHILL B SURG TK LEVEL, and 2-LS-31-324, INCORE INSTRUMENT ROOM SURGE TANK 2B LEVEL 1 st CV

[11] OPEN 2-RTV-31-1112, INCORE INST RM CHILL B SURG TK LEVEL ISOL VLV.

[12] SLOWLY OPEN 2-RTV-31-1113A, 2-LS-31-324 ROOT, to refill 2-LS-31-324, INCORE INSTRUMENT ROOM SURGE TANK 2B LEVEL.

[13] ENSURE 2-LG-31-325, INCORE INSTRUMENT ROOM SURGE TANK 2B LEVEL, indicates 75 - 100% full.

[14] VERIFY the following:

A. Annunciator Window, 2-XA-55-5C/1 04-E, INSTR RM COOLING SURGE TANK A/B LEVEL LO, CLEARS.

B. Unit 2 Alarm Events Display Screen indicates 104-E INSTR RM COOLING SURGE TANK B LEVEL LO (LS-31-324) is NORMAL (Green).

[15] VERIFY successful completion of this Subsection 6.9.3.

(ACC CRIT)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 115 of 128 Data Package: Page - of Date 7.0 POST PERFORMANCE ACTIVITY

[1] VERIFY that post-test calibration of the M&TE used to record quantitative acceptance criteria has been satisfactorily performed, AND RECORD the results on Measuring and Test Equipment Log, Appendix E in SMP-9.0

[2] VERIFY that post-test calibration of permanent plant instruments used to record quantitative acceptance criteria has been satisfactorily performed (as required), AND RECORD the results on Appendix C, Permanent Plant Instrumentation Log.

[3] NOTIFY the Unit 2 US/SRO of the test completion and system alignment.

8.0 RECORDS A. QA Records Completed Test Package B. Non-QA Records None

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 116 of 128 Appendix A (Page 1 of 1)

TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW Data Package: Page - of Date NOTES

1) Additional copies of this table may be made as necessary.
2) Initial and date indicates review has been completed for impact.

PROCEDURE/ IMPACT INITIAL AND DATE INSTRUCTION REVISIONICHANGES Yes/No (N/A for no change)

SMP-9.0 FSAR SubSection 6.2.4 Table 6.2.4-1, Pgs 38-39 SubSection 9.2.1 and 9.4.7 Table 14.2-1, Sheets 4/5, 38/39, and 83 WBN2-30RB-4002 WBN2-67-4002 WBNP Tech Specs, Unit 2, SubSection 3.6.3 2-SOI-30.04 2-TSD-31 B-01 2-TSD-88-05 G-37 2-PTI-067-03

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 117 of 128 Appendix B (Page 1 of 1)

TEMPORARY CONDITION LOG Data Package: Page - of Date NOTES

1) Additional copies of this table may be made as necessary.
2) These steps will be N/A'd if no temporary condition existed.

ITEM TEMPORARY CONDITION PERFORMED RETURNED TO NORMAL No. DESCRIPTION Step Performed By/Date Step Returned By/Date No. CV By/Date No. CV By/Date

)

Incore Instrument Room Air 2-PTI-031 B-01 Conditioning System Rev. 0000 Page 118 of 128 Appendix C (Page 1 of 1)

PERMANENT PLANT INSTRUMENTATION LOG Data Package: Page of Date POST-TEST FILLED AND PLACED IN CALIBRATION SERVICE' USED FOR QUANTITATIVE ACC CRIT ACCEPTABLE2 INSTRUMENT OR VENTED1 INSTRUMENT POST-TEST2 CAL LOOP # CAL DUE DATE INITIDATE INIT/DATE YES NO DATE INIT/DATE 2 2-TIC-31-307 X NA NA 2-FS-31-263 X NA NA 2-LS-31-303 X NA NA 2-TIC-31-328 X NA NA 2-FS-31-268 X NA NA 2-LS-31-324 X NA NA 4 4 f + * -t 4 I t t T I L I L ..-

1 These items may be initialed and dated by personnel performing the task. Instrumentation NOT required to be filled and vented may be identified as Not Applicable (NA).

2 May be identified as NA if instrument was NOT used to verify/record quantitative acceptance criteria data.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 119 of 128 Table 1 (Page 1 of 2)

ELECTRICAL LINEUP Data Package: Page of Date COMPONENT COMPONENT COMP. VERIFIED IDENTIFICATION NOMENCLATURE POSITION BY INITIAL 2-BKR-31-265-A INCORE INSTR RM AHU 2A Unit 2 480V RX MOV BD 2A1-A, CLOSED (2-AHU-31-265) Compt. 16A 2-BKR-31-303A-A INCORE INSTR RM CW Unit 2 480V RX MOV BD 2A1-A, CLOSED PMP 2A (2-PMP-31-303/1) Compt. 18C 2-BKR-31-303B-A INCORE 2A COMPRINSTR RM CHLR Unit 2 480V RX MOV BD 2A1-A, (2-COMP-303/2) Compt. 16F2 OPEN 2-BKR-31-266-B INCORE INSTR RM AHU 2B Unit 2 480V RX MOV BD 2B1-B, CLOSED (2-AHU-31-266) Compt. 16A 2-BKR-31-324A-B INCORE INSTR RM CW Unit 2 480V RX MOV BD 2B1-B, CLOSED PMP 2B (2-PMP-31-324/1) Compt. 18C 2-BKR-31-324B-B INSTR RM A/C COMPR 2B Unit 2 480V RX MOV BD 2B1-B, OPEN (2-COMP-31-324/2) Compt. 17F2 2 -BKR- 235-1/07-D AUX RELAY RACK 2-R-76 BABk7CLOSED 120V AC Vital Inst Power Bd 2-1 BUS A Bkr 7 I

2-BKR-235-1/19-D SYS 31 TR A ASSOCIATED 120V AC Vital Inst Power Bd 2-1 CLOSED FLOW SWITCHES Bkr 19 2-BKR-235-2/06-E AUX RELAY RACK 2-R-76 BSBkr6CLOSED 120V AC Vital Inst Power Bd 2-11 BUS B Bkr 6 2-BRK-235-2/14-E SYS FLWSICE 31 TR B ASSOCIATED 120V AC Vital kInst 4CLOSED Power Bd 2-11 FLOW SWITCHES Bkr 14 O-FU-236-3/C3 INSTR RM COOLANT UNIT 125V VITAL BATT BD III, CKT# INSTALLED A VLV C/3 0-FU-236-3/C4 INSTRUMENT ROOM 125V VITAL BATT BD III, CKT# INSTALLED COOLANT UNIT A VLV C/4 0-FU-236-3/C5 INSTRUMENT ROOM 125V VITAL BATT BD III, CKT# INSTALLED COOLANT UNIT B VLV C/5 0-FU-236-3/C6 INSTRUMENT ROOM 125V VITAL BATT BD III, CKT# INSTALLED COOLANT UNIT B VLV C/6

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 120 of 128 Table 1 (Page 2 of 2)

ELECTRICAL LINEUP Data Package: Page -of Date COMPONENT COMPONENT COMP. VERIFIED IDENTIFICATION NOMENCLATURE POSITION BY INITIAL 0-FU-236-4/C3 INSTR RM COOLANT UNIT 125V VITAL BATT BD IV, CKT# INSTALLED A VLV C/3 0-FU-236-4/C4 INSTR RM COOLANT UNIT 125V VITAL BATT BD IV, CKT# INSTALLED A VLV C/4 0-FU-236-4/C5 INSTR RM COOLANT UNIT 125V VITAL BATT BD IV, CKT# INSTALLED B VLV C/5 0-FU-236-4/C6 INSTR RM COOLANT UNIT 125V VITAL BATT BD IV, CKT# INSTALLED B VLV C/6

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 121 of 128 Table 2 (Page 1 of 6)

VALVE LINEUP Data Package: Page - of Date VALVE NOMENCLATURE LATIO POITO BYRINITA VALVE NUMBER TLOCATION POSITION BY INITIALS TRAIN A 2-DRV-31-3422 INCORE INSTR RM CW AIR SEPARATOR 692 Al2W CLOSED 2A DRAIN 2-DRV-31-3981 INCORE INSTR ROOM DAN692 SURGE TANK 2A A12W CLOSED DRAIN 2-VTV-31-3426 INCORE INSTR ROOM SURGE TANK 2A 692 A12W CLOSED VENT 2-RTV-31-3977A 2-LG-31-304 ROOT 692 A12W OPEN 2-RTV-31-3978A 2-LG-31-304 ROOT 692 A12W OPEN 2-RTV-31-1102A 2-LS-31-303 ROOT 692 A12W OPEN 2-RTV-31-1103A 2-LS-31-303 ROOT 692 A12W OPEN 2-ISV-31-3425 INCORE INSTR RM CHLR 2ACW MU 692 A12W CLOSED CHECK 2-VTV-31-3423 INCORE INSTR ROOM AIR SEPARATOR 2A 692 A12W CLOSED VENT 2-ISV-31-342 17 INCORE INSTR ROOM CW PUMP 2A 692 Al2W OPEN SUCTION 2-RTV-31-1101A 2-PI-31-302 ROOT 692 A12W OPEN 2-DRV-31-3428 INCORE INSTR ROOM CW PUMP 2A 692 A12W CLOSED DRAIN 2-RTV-31-1100A 2-PI-31-301 ROOT 692 A12W OPEN 2-ISV-31-3430 INCORE INSTR ROOM CW PUMP 2A 692 A12W OPEN DISCHARGE 2-VTV-31-3441 INCORE INSTR RM CHLR 2ACW IN VENT 692 A12W CLOSED 2-ISV-31-3431 INCORE INSTR ROOM CHLR 2A CW IN 692 A12W OPEN ISOL 2-RTV-31 -3432A INCORE INSTR RM CHLR 2ACW PRESS 692 Al2W CLOSED TEST

WBN Incore Instrument Room Air 2-PTI-031 B-01 Unit 2 Conditioning System Rev. 0000 Page 122 of 128 Table 2 (Page 2 of 6)

VALVE LINEUP Data Package: Page - of__ Date VALVE VALVE VERIFIED BYRINITA VALVE NUMBER VALVE NOMENCLATURE LATIO POITO LOCATION POSITION BY INITIALS 2-DRV-31-3414 INCORE INSTR RM CHLR 2ACW DRAIN 692 A12W CLOSED 2-RTV-31-1104A 2-PI-31-313 ROOT 692 A12W OPEN 2-ISV-31-3413 INCORE INSTR RM CHLR 2ACW OUT ISOL 692 A12W OPEN 2-RTV-31-3999A 2-FIS-31-311 ROOT 692 A12W OPEN 2-RTV-31-4000A "2-FIS-31-311 ROOT 692 A12W OPEN 2-FCV-31-305 INCORE INSTR RM AHU 2A CWR ISOL OC 730 AZ 70 CLOSED 2-VTV-31-3440 INCORE INSTR RM AHU 2A CWR VENT OC 737 Q4 CLOSED 2-FCV-31-309 INCORE INSTR RM AHU 2A CWS ISOL OC 730 AZ 70 CLOSED 2-VTV-31-3446 INCORE INSTR RM AHU 2A CWS VENT OC 737 Q4 CLOSED INCORE INSTR RM AHU 2A CW PUMP 2A 2-FCV-31-3.06 ISOL 730 AZ 70 CLOSED 2-TV-31-3451 INCORE INSTR RM AHU 2A CWR TEST 716 AZ 120 CLOSED VENT 2-VTV-31-3435 INCORE INSTR RM AHU 2A CWR VENT 716 AZ 120 CLOSED 2-DRV-31-3447 INCORE INSTR RM AHU 2A CWR DRAIN 716 AZ 119 CLOSED 2-BYV-31-3416 INCORE INSTR RM AHU 2A CW BYPASS 716 AZ 119 OPEN INCORE INSTR RM AHU 2A CW 2-ISV-31-3417 NCV-31ST07 TCV-31-307 U/SUISOL 2A 716 AZ 119 OPEN 2-BYV-31-3418 INCORE INSTR RM AHU 2A CW 716 AZ 122 CLOSED TCV-31-307 BYPASS INCORE INSTR RM AHU 2A CW 2-ISV-31-3419 NCVRE INT-307RM TCV-31 D/S ISOL 716 AZ 121 OPEN

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 123 of 128 Table 2 (Page 3 of 6)

VALVE LINEUP Data Package: Page - of Date VALVE VALVE POITO VERIFIED BYRINITA VALVE NUMBER VALVE NOMENCLATURE LATIO LOCATION POSITION BY INITIALS 2-TCV-31-307 INCORE INSTR RM AHU 2A CW TEMP 730 AZ 70 OPERABLE CNTL 2-FCV-31-308 INCORE INSTR RM AHU 2A CWS ISOL 730 AZ 70 CLOSED 2-TV-31-3450 INCORE INSTR RM AHU 2A CWS TEST 716 AZ 120 CLOSED VENT 2-VTV-31-3436 INCORE INSTR RM AHU 2A CWS VENT 716 AZ 120 CLOSED 2-DRV-31-3445 INCORE INSTR RM AHU 2A CWS DRAIN 716 AZ 118 CLOSED 2-DRV-31-3404 INCORE INSTR RM AHU 2A CWS DRAIN 716 AZ 120 CLOSED 2-ISV-31-3405 INCORE INSTR RM AHU 2A CWS ISOL 716 AZ 119 OPEN TRAIN B 2-DRV-31-3393 INCORE INSTR ROOM AIR SEPARATOR 2B 692 A12W CLOSED DRAIN 2-DRV-31-3982 INCORE INSTR ROOM SURGE TANK 2B 692 Al2W CLOSED DRAIN 2-VI-V-31-3397 INCORE INSTR ROOMVET692SURGE TANK 2B 6 Al12W CLOSED.

VENT 2-RTV-31-3979A 2-LG-31-325 ROOT 692 A12W OPEN 2-RTV-31-3980A 2-LG-31-325 ROOT 692 A12W OPEN 2-RTV-31-1112 2-LS-31-324 ROOT 692 A12W OPEN 2-RTV-31-1113A 2-LS-31-324 ROOT 692 A12W OPEN 2-ISV-31-3396 INCORE INSTR RM CHLR 2BCW MU 692 A12W CLOSED 2-VTV-31-3394 INCORE INSTR ROOM AIR SEPARATOR 2B 692 Al2W CLOSED VENT

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 124 of 128 Table 2 (Page 4 of 6)

VALVE LINEUP Data Package: Page __ of Date VALVE VALVE VERIFIED VALVE NUMBER VALVE NOMENCLATURE LOCATION POSITION BY INITIALS 2-ISV-31-3398 INCORE INSTR ROOM CW PUMP 2B 692 A12W OPEN SUCTION 2-RTV-31-1111A 2-PI-31-323 ROOT 692 A12W OPEN 2-DRV-31-3399 INCORE INSTR ROOM CW PUMP 2B 692 A12W CLOSED DRAIN 2-RTV-31-111OA 2-PI-31-322 ROOT 692 A12W OPEN 2-ISV-31-3401 INCORE INSTR ROOM CW PUMP 2B 692 A12W OPEN DISCH 2-VTV-31-3438 INCORE INSTR RM CHLR 2BC3W IN VENT 692 A12W CLOSED 2-ISV-31-3402 INCORE INSTR ROOM CHLR 2B CW IN 692 A12W OPEN ISOL 2-RTV-31-3403A INCORE INSTR RM CHLR 2BC3W IN TEST 692 A12W CLOSED -'

POINT 2-DRV-31-3385 INCORE INSTR RM CHLR 2BC3W DRAIN 692 A12W CLOSED 2-RTV-31-1114A 2-PI-31-334 ROOT 692 A12W OPEN 2-ISV-31-3384 INCORE INSTIR RM CHLR 2BCW OUT ISOL 692 A12W OPEN 2-RTV-31-3997A 2-FIS-31-332 ROOT ( 692 A12W OPEN 2-RTV-31-3998A 2-FIS-31-332 ROOT 692 A12W OPEN 2-FCV-31-326 INCORE INSTR RM AHU 2B CWR ISOL OC 735 AZ 104 CLOSED 2-VTV-31-3437 INCORE INST RM AHU 2B CWR VENT OC 737 Q4 CLOSED 2-FCV-31-330 INCORE INSTR RM AHU 2B CWS ISOL OC 734 AZ 105 CLOSED 2-VTV-31-3434 INCORE INSTR RM AHU 2B CWS VENT OC 737 Q4 CLOSED

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 125 of 128 Table 2 (Page 5 of 6)

VALVE LINEUP Data Package: Page - of Date VALVE VALVE POITO VERIFIED BYRINITA VALVE NUMBER VALVE NOMENCLATURE LATIO LOCATION POSITION BY INITIALS 2-FCV-31-327 INCORE INST RM AHU 2B CWR ISOL 731 AZ 107 CLOSED 2-TV-3-3449 INCORE INSTR RM AHUI 2B CWR TEST 73AZ12 COE VENT 2-DRV-31-3444 INCORE INSTR RM AHU 2B CWR DRAIN 731 AZ 120 CLOSED 2-BYV-31-3387 INCORE INSTR RM AHU 2B CW BYPASS 735 AZ 90 OPEN 2-ISV-31-3388 INCORE INSTR RM AHU 2B OW 731 AZ 120 OPEN TCV-31-328 U/S ISOL 2-BYV-31-3389 INCORE INSTR RM AHU 28 CW 731 AZ 120 CLOSED TCV-31-328 BYPASS 2-ISV-31-3390 INCORE INSTR RM/ISL731 TV3-2 AHU 2B CW Q2 OPEN TCV-31-328 D/S ISOL 2-TCV-31-328 INCORE INSTR RM AHU 2B CW TEMP 731 AZ 116 OPERABLE CONTROL 2-VTV-31-3439 INCORE INSTR RM AHU 2B CWR VENT 731 AZ 123 CLOSED 2-FCV-31-329 INCORE INSTR RM AHU 2B CWS ISOL 731 AZ 102 CLOSED 2-TV-31-3433 INCORE INSTR RM AHU 2B CWS TEST 731 AZ 112 CLOSED VENT INCORE INSTR RM AHU 2B CWS TEST 2-TV-31-3448 VENT 731 AZ 112 CLOSED 2-DRV-31-3442 INCORE INSTR RM AHU 2B CWS DRAIN 731 AZ 117 CLOSED 2-DRV-31-3375 INCORE INSTR RM AHU 2B CWS DRAIN 731 AZ 123 CLOSED 2-ISV-31-3376 INCORE INSTR RM AHU 2B CWS ISOL 731 Q2 OPEN COMMON 2-ISV-31-3986 INCORE INSTR ROOM CHEM TRTMT TANK 692 Al2W CLOSED A ISOL

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 126 of 128 Table 2 (Page 6 of 6)

VALVE LINEUP Data Package: Page - of__ Date VALVE VALVE VERIFIED BYRINITA VALVE NUMBER VALVE NOMENCLATURE LO T POITO LOCATION POSITION BY INITIALS 2-ISV-31-3987 INCORE INSTR ROOM CHEM TRTMT TANK 692 Al2W CLOSED A ISOL 2-VTV-31-3408 INCORE INSTR RM CW CHEM TRTMT 692 A12W CLOSED TANK 2A VENT 2-1SV-31-3409 INCORE INSTR RM CW CHEM TRTMT 692 A12W CLOSED TANK 2A OUT 2-DRV-31-341 0 INCORE INSTR RM CW CHEM TRTMT TNK 692 Al2W CLOSED 2A DRAIN 2-ISV-31-341 1 INCORE INSTR RM, CW CHEM TRTMT 692 A12W CLOSED TANK 2A FILL 2-ISV-31-3412 INCORE INSTR RM CW CHEM TRTMT TNK 692 Al2W CLOSED 2A INLET N.

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 127 of 128 Table 3 (Page 1 of 1)

SWITCH LINEUP

, Data Package: Page _ of Date SWITCH SWITCH SWITCH VERIFIED BY NUMBER LOCATION POSITION INITIAL 2-HS-31-265A 2-M-9 INCORE INST RM A/C A SW STOP (PULL-TO-LOCK) 2-M-9 INCORE INST RM A/C B SW STOP 2-HS-31-266A (PULL-TO-LOCK) 2-HS-31-305 2-M-9 CIRC PMP A SUCT CIV-OA CLOSE return to A AUTO 2-HS-31-306 2-M-9 CIRC PMP A SUCT CIV-0A AUTO CLOSE return to A 2-HS-31-308 2-M-9 CIRC PMP A DISCH CIV-OA Auto CLOSE return to A AUTO 2-HS-31-309 2-M-9 CIRC PMP A DISCH CIV-OA AUTO CLOSE return to A 2-HS-31-326 2-M-9 CIRC PMP B SUCT CIV-OA CLOSE return to A AUTO 2-HS-31-327 2-M-9 CIRC PMP B SUCT CIV-OA AUTO CLOSE return to A 2-HS-31-3 2-M-9 CIRC PMP B DISCH CIV-AAUTO CLOSE return to A 2-HS-31-329 2-M-9 CIRC PMVP B DISCH CIV-0A CLOSE return to A AUTO Chiller 2A CHILLER 2A CONTROL PANEL POWER ON 2-CHR-31-303 Panel SWITCH (GREEN LIGHT ON)

Chiller 2B CHILLER 2B CONTROL PANEL POWER ON Panel SWITCH (GREEN LIGHT ON)

WBN Incore Instrument Room Air 2-PTI-031B-01 Unit 2 Conditioning System Rev. 0000 Page 128 of 128 Appendix D (Page 1 of 1)

Background Calculations A. Water Flow Instrument Uncertainties Design Flow Rate = 21 ,OPM Flowmeter Uncertainty = + 3% of reading 21 GPM

  • 1.03 - 21.63 GPM = 22 GPM B. Air Flow Instrument Uncertainties Air Flow Uncertainties are covered within GTM-05 and are not required to be calculated within this PTI.

C. Valve Stroke Timing Instrument Uncertainties Design Valve Stroke Timing = 10 sec Stopwatch Uncertainty = +/- 0.1 sec Uncertainty is negligible compared to the human error factor involved with use of a stopwatch.