ML103000225
ML103000225 | |
Person / Time | |
---|---|
Site: | Sequoyah |
Issue date: | 10/26/2010 |
From: | NRC/RGN-II/DRS/OLB |
To: | Tennessee Valley Authority |
References | |
50-327/10-302, 50-328/10-302 | |
Download: ML103000225 (7) | |
See also: IR 05000327/2010302
Text
ENCLOSURE 5
Substantive Comments
Note: There were two substantive comments made by applicants following the written
examination, with explanations concerning why the comments were accepted.
September 2010 Written examination comments.
The following substantive comments are being submitted for consideration during the grading of
the Licensing exam that was administered at the Sequoyah Nuclear Station on September 29,
2010.
The first comment is submiffed by candidate
Question #41, Which ONE of the following ice condenser temperatures is within the optimal
range in accordance with 0-S0-61-1, Ice Condenser Cooling, and one of the potential adverse
affects of being outside this range?
A. 19°F; excessive concrete expansion
B. 19°F; operation outside technical specification limit
C. 27°F; excessive concrete expansion
D. 27°F; operation outside technical specification limit
Comment; The question has two parts, (1) the optimal temperature range and (2) one of the
potential adverse affects of being outside this range.
Since the optimal temperature range is 18°F to 20°F, then either A or B has the correct
temperature, however, since the candidate wasnt sure how far outside the optimal temperature
limit they could be, then they assumed that once temperature was greater than 27°F, you would
be outside the technical specification limit and that would have an adverse affect on operation,
since the plant would be in an LCO and may have to shutdown. Also from 1-SO-OPS-000-
002.0, Daily Shift Log, 3.0 Precautions and Limitations, C. The Ice condenser may be
operated at a temperature outside the optimum range, provided technical specifications limits
are maintained, in accordance with Engineering recommendations to support system
maintenance or planned outages. Thus the plant could operate outside the optimal limit as
long as the technical specification limit was not exceeded. Based on this criterion, this would
make B also a correct answer.
Site Recommendation:
It was intended that the adverse affects of operating outside the optimal range was physical in
nature, testing the candidates knowledge of the potential adverse affects of not maintaining the
ice condenser temperature within established optimal limit, (as indentified in the distractor
analysis the Final safety Analysis Report (FSAR) 6.5.7.2 identifies 19°F to be the optimal
temperature range to minimize the condition of concrete expansion, floor heaving and frost
buildup.) However, since the adverse affect asked for in the question was not limited to a
physical condition or a physical affect, then it would be reasonable that an adverse
administrative affect (operating outside the technical specification limit, thus rending the ice
condenser bed inoperable) could also be assumed. This would make both A and B correct.
Since either an adverse affect could be interpreted as physical or administrative, Sequoyah
station concludes that both A and B are considered as correct answers.
Additionally the following comment was submitted by (applicant
- 95. Given the following:
Unit-i outage schedule logic changes for a planned 28-day refueling outage are being reviewed
by an SRO to determine if they are safety significant in accordance with SPP-7.2, Outage
Management, Appendix E, Outage Schedule Logic Change Control.
In accordance with Appendix E, which ONE of the following proposed logic changes would meet
the criteria for a Safety Significant change?
A. Reschedule the Unit-i loop #2 MSIV seat inspection from the core empty mid-loop
period to the time period during core reload while SG secondary manways are removed for
inspection.
B. Increase the cavity level from 711 feet to 712 feet elevation to minimize dose while
unlatching control rods.
C. Add a 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> activity to perform preventative maintenance on the turbine driven
auxiliary feedwater pump before entry into Mode 4.
D. Change the window for a contract diver to enter the CCW pump intake bay from the end
of the outage (before starting CCW pumps) to the beginning of the outage (after securing CCW
pumps.)
Comment: Since the Condenser Circulating Water system (CCW) intake bay is common to both
units, diving operations could affect both units. As per SPP-7.2, Appendix E, (provided as a
reference) the SRO is to evaluate if the activity would meet any of the listed criteria. Item 15
asks if the activity will affect the non-outage unit and if so then that item would be considered a
safety significant change and would require additional evaluation. Since diving could affect the
non-outage unit then D is a correct answer.
Response: After evaluating the question and choices against the criteria of SPP-7.2, Appendix
E, and industry OE associated with diving operations, it is plausible that an SRO could
reasonably conclude that a diving operation, in the vicinity of the CCW pumps, could (and
would) have an impact on the operation of the non-outage unit. Thus per the direction of SPP
7.2, Appendix E, which was provided to the SRO candidates evaluating the events, we agree
with the comment and consider A and D as correct answers.
SQN ICE CONDENSER COOLING 0-SO-61-1
0 Rev. 30
Page 8 of 131
3.0 PRECAUTIONS AND LIMITATIONS (Continued)
B. Trapping cold glycol solution between two isolated valves must
be avoided. When isolating a component, close one valve
only, until fluid warms up to ambient, or open a vent between
the two closed valves.
C. Raw cooling water header pressure should normally be maintained
greater than 40 psig to glycol chiller packages. if available, the
standby RCW booster pump should be started in accordance with
0-SO-24-1 as necessary to maintain system pressure.
If NO RCW booster pump can be started, 0-SO-24-1 provides
guidance on raising ROW header pressure to allow short-term
operation of a few glycol chiller packages while restoring a ROW
booster pump.
D. During cooldown, the differential temperature between the glycol
supply temperature and the averaged measured floor surface
temperature (Appendix G), should not exceed 20°F.
E. in order to minimize sublimation, frost buildup, and ice condenser door
binding problems, the Ice Condenser temp should be maintained within
the optimum range of 18°F to 20°F. [C.1J
F. if glycol flow is left on the shutdown chiller unit, the bypass valve
around the temperature control valve in the cooling water flow path
must be left open at all times to prevent freezing.
G. The following apply to the AHUs:
1. Heat tracing on the AHU defrost drains must be maintained
continuously while plenum temperature is below freezing. If
power is lost to both heating circuits for any length of time, the
drain pipes must be inspected for signs of damage due to
freezing.
2. If isolation of an AHU is necessary, use the odd numbered
isolation valves if possible. Even numbered return valves are
used for flow balance, and they should be returned to their
previous position if closure is necessary.
3. When removing an AHU from service for maintenance, open
circuit breaker CB #1, so it will not unnecessarily add its defrost
heat to the ice condenser during the normal defrost cycle.
4. Do not operate any AHU that is not completely assembled.
When air bypasses the coils due to the front or side panels
being removed, it is adding warmer air to the wall panels. All
sheetmetal panels must be installed on the front and sides of the
AHUs. Open CB #1, unless all sheetmetal panels are installed.
CONTAINMENT SYSTEMS
3/46.5 ICE CONDENSER
ICE BED
LIMITING CONDITION FOR OPERATION
3.6.51. The ice bed shall be OPERABLE with:
a. The stored ice having a boron concentration of 1800 ppm and 2500 ppm boron as
sodium tetraborate and a pH of 9.0 to 9.5,
b. Flow channels through the ice condenser,
c. A maximum ice bed temperature of less than or equal 27° F,
d. A total ice weight of at least 2,225,880 pounds at a 95% level of confidence, and
e. 1944 ice baskets.
APPLICABILITY: MODES 1, 2, 3 and 4.
ACTION:
With the ice bed inoperable, restore the ice bed to OPERABLE status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> or be in at least
HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
SURVEILLANCE REQUIREMENTS 4.6.5.1 The ice condenser shall be determined OPERABLE:
a. At least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying that the maximum ice bed temperature is less than or
equal to 27° F.
b. At least once per 18 months by verifying, by visual inspection, accumulation of ice on
structural members comprising flow channels through the ice bed is 15 percent blockage
of the total flow area for each safety analysis section.
September 30, 2002
SEQUOYAH - UNIT 1 3/4 6-26 Amendment No. 4, 126, 131, 224, 267, 269,
277, 279
4
Outage Management SPP-7.2
NPG Standard Rev. 0020
Programs and Page 35 of 45
Processes
Appendix E
(Page 1 of 2)
Outage Schedule Logic Change Control
IOSR was
ty Review (IOSR) or issuance of Rev. C if an
Subsequent to the Independent Outage Safe of logic relation
dule changes which involve the modification
not performed, all significant outage sche
d by the following process.
between outage activities will be controlle
ted on the Outage Schedule Logic Change Form
A. The proposed schedule change is documen
edure.
(OSLCF) SPP-7.2-2, Attachment 1 of this proc
ge
individual each time a logic change to the outa
An OSLCF is initiated by the responsible of the OSL CF.
plete items A through D
schedule is required. The initiator must com
ates
change documented on the OSLCF and evalu
B. A licensed SRO reviews the requested logic proc eed. This revie w by a
should be approved and
whether the change to the outage schedule t with the initia l
ges receive a review consisten
SRO is to ensure safety significant chan criteria
ge schedule. The SRO should consider the
-
independent outage safety review of the outa
ld be approved: If the answer to any of these
below when determining If the change shou safety
appropriate actions are taken to minimize the
questions is yes, the reviewer should ensure chan ge requ ires a
ge prior to approval. If the logic
risk resulting from incorporating the logic chan h strat egy with
nt a challenge to the defense in dept
major system window change, or could prese pend ent
will be consulted to convene an Inde
safety significance, the Unit Outage Manager should
tional expert opinions on whether the change
Outage Safety Review team to provide addi ed safety
nee, will approve a schedule change, deem
be approved. The plant manager, or desig
significant via the following questions.
SRO review questions for consideration:
, pressure, temperature, etc.) and other
1. Perturb the stability of RHR parameters (flow
eres, etc.)?
operational parameters (operating pump amp
value
t RCS temperature below the minimum
2. Alter plant configurations that would resul in
used to analyze reactor shutdown margin?
inventory?
3. Reduce the reactor cavity or reactor vessel
enge SF Cooling redundancy?
4. Reduce the spent fuel pit inventory or chall
vessel
ort systems required to provide reactor
5. Reduce the availabihty of systems or supp
heat generation load?
makeup water consistent with the decay
injection?
6. Minimize the availability of ow pressure
istent with
ces of reactor vessel makeup water cons
7. Reduce the availability of alternate sour
the decay heat generation rate?
ce
installed temporary equipment that could redu
8. Increase the probability of jeopardizing
safety system availability?
?
9. Isolate of the operable boration flow path
t
.t.
NPG Standard Outage Management SPP-7.2
Programs and Rev. 0020
Processes Page 36 of 45
Appendix E
(Page 2 of 2)
Outage Schedule Logic Change Control
10. Cause leakage of water into the RCS or spent fuel pit which would dilute the boron
concentration to a value below the minimum required?
11. Affect bus outages or switchyard outages?
12. Reduce the availability of onsite or offsite electrical power supplies or support systems?
13. Increase the probability of fuel or other core component mishandling or damage?
14. Reduce the ability to isolate containment when required?
15. Affect the non-outage unit?
After reviewing the above questions, the SRO signs the OSLCF for approval if warranted. If
the SRO rejects the change, the OSLCF is returned to the originator with an explanation of
why it was rejected for enhancement or cancellation as appropriate.
C. Following SRO approval of an OSLCF, the Outage Manager reviews the OSLCF for
on
completeness and determines if additional reviews are required. This determination is based
the following criteria:
1. Logic changes for work activities within a system window which change the sequence of
scheduled work and do not pose a potential challenge to the defense in depth strategy can
be approved by the Outage Manager.
2. Logic changes which move a work activity scheduled in Modes 5 or 6 (PWR only) to the
empty reactor vessel period can be approved by the Outage Manager.
3. Logic changes for work activities on the equipment and systems affecting system
e
operations require review and concurrence by the Operations Management representativ
logic change
in the 0CC, in addition to the original SROs approval. As an example: jf the
the
moves the activity out of its scheduled work window OR has the potential to challenge
stations defense in depth strategy, Operations management concurrence in 0CC is
required, as well as Outage Manager and Plant Manager, or outage shift designees.
can be
4. Logic changes for work activities on equipment and systems not identified above
approved by the Outage Manager.
outage schedule in
D. Following approval of the OSLCF, the Outage Manager directs changing the
Manager. OSLCFs
accordance with the OSLCF. Approved OSLCFs are retained by the Outage
for cancellation or further processing.
that are not approved are returned to the originator
and to other outage
E. Copies of approved OSLCFs should be distributed to the Outage Manager
participants that will be affected by the change as deemed necessary.