ML103000225

From kanterella
Jump to navigation Jump to search
10-302,05000328-10-302 Post Exam Comments
ML103000225
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 10/26/2010
From:
NRC/RGN-II/DRS/OLB
To:
Tennessee Valley Authority
References
50-327/10-302, 50-328/10-302
Download: ML103000225 (7)


See also: IR 05000327/2010302

Text

ENCLOSURE 5

Substantive Comments

Note: There were two substantive comments made by applicants following the written

examination, with explanations concerning why the comments were accepted.

September 2010 Written examination comments.

The following substantive comments are being submitted for consideration during the grading of

the Licensing exam that was administered at the Sequoyah Nuclear Station on September 29,

2010.

The first comment is submiffed by candidate

Question #41, Which ONE of the following ice condenser temperatures is within the optimal

range in accordance with 0-S0-61-1, Ice Condenser Cooling, and one of the potential adverse

affects of being outside this range?

A. 19°F; excessive concrete expansion

B. 19°F; operation outside technical specification limit

C. 27°F; excessive concrete expansion

D. 27°F; operation outside technical specification limit

Comment; The question has two parts, (1) the optimal temperature range and (2) one of the

potential adverse affects of being outside this range.

Since the optimal temperature range is 18°F to 20°F, then either A or B has the correct

temperature, however, since the candidate wasnt sure how far outside the optimal temperature

limit they could be, then they assumed that once temperature was greater than 27°F, you would

be outside the technical specification limit and that would have an adverse affect on operation,

since the plant would be in an LCO and may have to shutdown. Also from 1-SO-OPS-000-

002.0, Daily Shift Log, 3.0 Precautions and Limitations, C. The Ice condenser may be

operated at a temperature outside the optimum range, provided technical specifications limits

are maintained, in accordance with Engineering recommendations to support system

maintenance or planned outages. Thus the plant could operate outside the optimal limit as

long as the technical specification limit was not exceeded. Based on this criterion, this would

make B also a correct answer.

Site Recommendation:

It was intended that the adverse affects of operating outside the optimal range was physical in

nature, testing the candidates knowledge of the potential adverse affects of not maintaining the

ice condenser temperature within established optimal limit, (as indentified in the distractor

analysis the Final safety Analysis Report (FSAR) 6.5.7.2 identifies 19°F to be the optimal

temperature range to minimize the condition of concrete expansion, floor heaving and frost

buildup.) However, since the adverse affect asked for in the question was not limited to a

physical condition or a physical affect, then it would be reasonable that an adverse

administrative affect (operating outside the technical specification limit, thus rending the ice

condenser bed inoperable) could also be assumed. This would make both A and B correct.

Since either an adverse affect could be interpreted as physical or administrative, Sequoyah

station concludes that both A and B are considered as correct answers.

Additionally the following comment was submitted by (applicant

  1. 95. Given the following:

Unit-i outage schedule logic changes for a planned 28-day refueling outage are being reviewed

by an SRO to determine if they are safety significant in accordance with SPP-7.2, Outage

Management, Appendix E, Outage Schedule Logic Change Control.

In accordance with Appendix E, which ONE of the following proposed logic changes would meet

the criteria for a Safety Significant change?

A. Reschedule the Unit-i loop #2 MSIV seat inspection from the core empty mid-loop

period to the time period during core reload while SG secondary manways are removed for

inspection.

B. Increase the cavity level from 711 feet to 712 feet elevation to minimize dose while

unlatching control rods.

C. Add a 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> activity to perform preventative maintenance on the turbine driven

auxiliary feedwater pump before entry into Mode 4.

D. Change the window for a contract diver to enter the CCW pump intake bay from the end

of the outage (before starting CCW pumps) to the beginning of the outage (after securing CCW

pumps.)

Comment: Since the Condenser Circulating Water system (CCW) intake bay is common to both

units, diving operations could affect both units. As per SPP-7.2, Appendix E, (provided as a

reference) the SRO is to evaluate if the activity would meet any of the listed criteria. Item 15

asks if the activity will affect the non-outage unit and if so then that item would be considered a

safety significant change and would require additional evaluation. Since diving could affect the

non-outage unit then D is a correct answer.

Response: After evaluating the question and choices against the criteria of SPP-7.2, Appendix

E, and industry OE associated with diving operations, it is plausible that an SRO could

reasonably conclude that a diving operation, in the vicinity of the CCW pumps, could (and

would) have an impact on the operation of the non-outage unit. Thus per the direction of SPP

7.2, Appendix E, which was provided to the SRO candidates evaluating the events, we agree

with the comment and consider A and D as correct answers.

SQN ICE CONDENSER COOLING 0-SO-61-1

0 Rev. 30

Page 8 of 131

3.0 PRECAUTIONS AND LIMITATIONS (Continued)

B. Trapping cold glycol solution between two isolated valves must

be avoided. When isolating a component, close one valve

only, until fluid warms up to ambient, or open a vent between

the two closed valves.

C. Raw cooling water header pressure should normally be maintained

greater than 40 psig to glycol chiller packages. if available, the

standby RCW booster pump should be started in accordance with

0-SO-24-1 as necessary to maintain system pressure.

If NO RCW booster pump can be started, 0-SO-24-1 provides

guidance on raising ROW header pressure to allow short-term

operation of a few glycol chiller packages while restoring a ROW

booster pump.

D. During cooldown, the differential temperature between the glycol

supply temperature and the averaged measured floor surface

temperature (Appendix G), should not exceed 20°F.

E. in order to minimize sublimation, frost buildup, and ice condenser door

binding problems, the Ice Condenser temp should be maintained within

the optimum range of 18°F to 20°F. [C.1J

F. if glycol flow is left on the shutdown chiller unit, the bypass valve

around the temperature control valve in the cooling water flow path

must be left open at all times to prevent freezing.

G. The following apply to the AHUs:

1. Heat tracing on the AHU defrost drains must be maintained

continuously while plenum temperature is below freezing. If

power is lost to both heating circuits for any length of time, the

drain pipes must be inspected for signs of damage due to

freezing.

2. If isolation of an AHU is necessary, use the odd numbered

isolation valves if possible. Even numbered return valves are

used for flow balance, and they should be returned to their

previous position if closure is necessary.

3. When removing an AHU from service for maintenance, open

circuit breaker CB #1, so it will not unnecessarily add its defrost

heat to the ice condenser during the normal defrost cycle.

4. Do not operate any AHU that is not completely assembled.

When air bypasses the coils due to the front or side panels

being removed, it is adding warmer air to the wall panels. All

sheetmetal panels must be installed on the front and sides of the

AHUs. Open CB #1, unless all sheetmetal panels are installed.

CONTAINMENT SYSTEMS

3/46.5 ICE CONDENSER

ICE BED

LIMITING CONDITION FOR OPERATION

3.6.51. The ice bed shall be OPERABLE with:

a. The stored ice having a boron concentration of 1800 ppm and 2500 ppm boron as

sodium tetraborate and a pH of 9.0 to 9.5,

b. Flow channels through the ice condenser,

c. A maximum ice bed temperature of less than or equal 27° F,

d. A total ice weight of at least 2,225,880 pounds at a 95% level of confidence, and

e. 1944 ice baskets.

APPLICABILITY: MODES 1, 2, 3 and 4.

ACTION:

With the ice bed inoperable, restore the ice bed to OPERABLE status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> or be in at least

HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REQUIREMENTS 4.6.5.1 The ice condenser shall be determined OPERABLE:

a. At least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying that the maximum ice bed temperature is less than or

equal to 27° F.

b. At least once per 18 months by verifying, by visual inspection, accumulation of ice on

structural members comprising flow channels through the ice bed is 15 percent blockage

of the total flow area for each safety analysis section.

September 30, 2002

SEQUOYAH - UNIT 1 3/4 6-26 Amendment No. 4, 126, 131, 224, 267, 269,

277, 279

4

Outage Management SPP-7.2

NPG Standard Rev. 0020

Programs and Page 35 of 45

Processes

Appendix E

(Page 1 of 2)

Outage Schedule Logic Change Control

IOSR was

ty Review (IOSR) or issuance of Rev. C if an

Subsequent to the Independent Outage Safe of logic relation

dule changes which involve the modification

not performed, all significant outage sche

d by the following process.

between outage activities will be controlle

ted on the Outage Schedule Logic Change Form

A. The proposed schedule change is documen

edure.

(OSLCF) SPP-7.2-2, Attachment 1 of this proc

ge

individual each time a logic change to the outa

An OSLCF is initiated by the responsible of the OSL CF.

plete items A through D

schedule is required. The initiator must com

ates

change documented on the OSLCF and evalu

B. A licensed SRO reviews the requested logic proc eed. This revie w by a

should be approved and

whether the change to the outage schedule t with the initia l

ges receive a review consisten

SRO is to ensure safety significant chan criteria

ge schedule. The SRO should consider the

-

independent outage safety review of the outa

ld be approved: If the answer to any of these

below when determining If the change shou safety

appropriate actions are taken to minimize the

questions is yes, the reviewer should ensure chan ge requ ires a

ge prior to approval. If the logic

risk resulting from incorporating the logic chan h strat egy with

nt a challenge to the defense in dept

major system window change, or could prese pend ent

will be consulted to convene an Inde

safety significance, the Unit Outage Manager should

tional expert opinions on whether the change

Outage Safety Review team to provide addi ed safety

nee, will approve a schedule change, deem

be approved. The plant manager, or desig

significant via the following questions.

SRO review questions for consideration:

, pressure, temperature, etc.) and other

1. Perturb the stability of RHR parameters (flow

eres, etc.)?

operational parameters (operating pump amp

value

t RCS temperature below the minimum

2. Alter plant configurations that would resul in

used to analyze reactor shutdown margin?

inventory?

3. Reduce the reactor cavity or reactor vessel

enge SF Cooling redundancy?

4. Reduce the spent fuel pit inventory or chall

vessel

ort systems required to provide reactor

5. Reduce the availabihty of systems or supp

heat generation load?

makeup water consistent with the decay

injection?

6. Minimize the availability of ow pressure

istent with

ces of reactor vessel makeup water cons

7. Reduce the availability of alternate sour

the decay heat generation rate?

ce

installed temporary equipment that could redu

8. Increase the probability of jeopardizing

safety system availability?

?

9. Isolate of the operable boration flow path

t

.t.

NPG Standard Outage Management SPP-7.2

Programs and Rev. 0020

Processes Page 36 of 45

Appendix E

(Page 2 of 2)

Outage Schedule Logic Change Control

10. Cause leakage of water into the RCS or spent fuel pit which would dilute the boron

concentration to a value below the minimum required?

11. Affect bus outages or switchyard outages?

12. Reduce the availability of onsite or offsite electrical power supplies or support systems?

13. Increase the probability of fuel or other core component mishandling or damage?

14. Reduce the ability to isolate containment when required?

15. Affect the non-outage unit?

After reviewing the above questions, the SRO signs the OSLCF for approval if warranted. If

the SRO rejects the change, the OSLCF is returned to the originator with an explanation of

why it was rejected for enhancement or cancellation as appropriate.

C. Following SRO approval of an OSLCF, the Outage Manager reviews the OSLCF for

on

completeness and determines if additional reviews are required. This determination is based

the following criteria:

1. Logic changes for work activities within a system window which change the sequence of

scheduled work and do not pose a potential challenge to the defense in depth strategy can

be approved by the Outage Manager.

2. Logic changes which move a work activity scheduled in Modes 5 or 6 (PWR only) to the

empty reactor vessel period can be approved by the Outage Manager.

3. Logic changes for work activities on the equipment and systems affecting system

e

operations require review and concurrence by the Operations Management representativ

logic change

in the 0CC, in addition to the original SROs approval. As an example: jf the

the

moves the activity out of its scheduled work window OR has the potential to challenge

stations defense in depth strategy, Operations management concurrence in 0CC is

required, as well as Outage Manager and Plant Manager, or outage shift designees.

can be

4. Logic changes for work activities on equipment and systems not identified above

approved by the Outage Manager.

outage schedule in

D. Following approval of the OSLCF, the Outage Manager directs changing the

Manager. OSLCFs

accordance with the OSLCF. Approved OSLCFs are retained by the Outage

for cancellation or further processing.

that are not approved are returned to the originator

and to other outage

E. Copies of approved OSLCFs should be distributed to the Outage Manager

participants that will be affected by the change as deemed necessary.