Letter Sequence Response to RAI |
---|
|
|
|
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24250A0532024-09-0606 September 2024 LRA - Requests for Additional Information - Set 1 ML24184C0422024-07-0202 July 2024 NRR E-mail Capture - Request for Additional Information Diablo Canyon 50.69 risk-informed Categorization ML24065A1312024-03-20020 March 2024 ISFSI Renewal RAI Transmittal Letter ML24065A1332024-03-20020 March 2024 Enclosure- Diablo Canyon ISFSI Renewal Request for Additional Information ML24024A2072024-01-24024 January 2024 Inservice Inspection Request for Information IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) ML23249A2782023-09-0606 September 2023 Inservice Inspection Request for Information ML23159A2372023-07-25025 July 2023 ISFSI Renewal RAI Transmittal Letter Enclosure ML23159A2382023-07-25025 July 2023 Request for Additional Information for the Technical Review of the Application for Renewal of the Diablo Canyon Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2022-RNW-0007) ML23096A1792023-04-0606 April 2023 NRR E-mail Capture - Request for Additional Information Diablo Canyon Exemption Request Regarding Senior Reactor Operator License Application ML23047A0062023-02-21021 February 2023 Request for Additional Information Alternative Security Measures for Early Warning System (EPID: L-2022-LLA-0029) (Public Version) ML23041A1862023-02-17017 February 2023 Request for Information Regarding Diablo Canyon Power Plant, Units 1 and 2 - December 8, 2022, Public Meeting ML22258A1112022-09-14014 September 2022 2022 Diablo Canyon PIR Request for Information ML22200A2572022-07-19019 July 2022 Notification of In-service Inspection (Inspection Report 05000323/2022004) and Request for Information ML22187A2652022-07-0606 July 2022 NRR E-mail Capture - Request for Additional Information: Diablo Canyon Exemption Request for Part 73 force-on-force Training Due to COVID-19 ML22152A1502022-06-21021 June 2022 Request for Additional Information Regarding License Amendment Request for Technical Specifications and Revised License Conditions for the Permanently Defueled Condition ML22122A1412022-05-0505 May 2022 .02 Doc Request ML22068A2312022-03-17017 March 2022 Notification of NRC Design Bases Assurance Inspection (Team) 05000275/2022011 and 05000323/2022011 and Initial Request for Information ML22061A2192022-03-0202 March 2022 NRR E-mail Capture - Request for Additional Information - Diablo Canyon Proposed Changes to Emergency Plan for post-shutdown and Permanently Defueled Condition ML21363A1692021-12-29029 December 2021 Inservice Inspection Request for Information ML22019A0412021-12-29029 December 2021 RFI ML21215A3432021-08-0303 August 2021 NRR E-mail Capture - Request for Additional Information - Diablo Canyon Request to Revise Technical Specification 3.8.1, AC Sources - Operating to Support Diesel Fuel Oil Transfer System Component Planned Maintenance ML21130A3642021-06-21021 June 2021 DC 2021401 Information Request ML21104A3642021-04-14014 April 2021 NRR E-mail Capture - Request for Additional Information - Diablo Canyon Proposed Technical Specifications and Revised License Conditions for the Permanently Defueled Condition ML21062A0642021-03-0202 March 2021 NRR E-mail Capture - Request for Additional Information for Diablo Canyon Generic Letter 2004-02 Submittal (L-2017-LRC-0000) ML20329A0692020-11-23023 November 2020 NRR E-mail Capture - Request for Additional Information: Diablo Canyon COVID-19 Exemption Request to Extend force-on-force Exercise ML20323A4532020-11-18018 November 2020 NRR E-mail Capture - Request for Additional Information: Diablo Canyon COVID-19 Exemption Request to Extend Firearms Requalification ML20301A2212020-10-27027 October 2020 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000275/2021010 and 05000323/2021010) and Request for Information ML20261H4232020-09-17017 September 2020 NRR E-mail Capture - Request for Additional Information: Diablo Canyon Unit 2 Fall 2019 Steam Generator Tube Inspection Report ML20231A2372020-08-17017 August 2020 NRR E-mail Capture - Diablo Canyon Additional Request for Additional Information: Exigent License Amendment Request for Application to Provide a New Technical Specification 3.7.5, Auxiliary Feedwater System, Condition G EPID: L-2020-LLA-017 ML20230A0732020-08-14014 August 2020 NRR E-mail Capture - Diablo Canyon Request for Additional Information: Exigent License Amendment Request for Application to Provide a New Technical Specification 3.7.5, Auxiliary Feedwater System, Condition G ML20280A5432020-06-0303 June 2020 DC 2020 PIR Request for Information ML20041E6012020-02-10010 February 2020 NRR E-mail Capture - Diablo Canyon Nuclear Power Plant, Units 1 and 2 - Request for Additional Information for Post -Shutdown Decommissioning Activities Report (PSDAR) ML19262G7482019-08-0909 August 2019 Request for Information ML19149A6012019-05-28028 May 2019 NRR E-mail Capture - Request for Additional Information (Supplemental) - License Amendment Request (LAR) to Revise Emergency Plan Response Organization Staffing and Augmentation ML19123A2162019-05-0202 May 2019 NRR E-mail Capture - Diablo Canyon Nuclear Power Plant -Request for Exemption from Operator Written Examination and Operating Test - Request for Additional Information ML19084A2572019-03-21021 March 2019 NRR E-mail Capture - Request for Additional Information - License Amendment Request (LAR) to Revise Emergency Plan Response Organization Staffing and Augmentation ML19043A9452019-02-20020 February 2019 Notification of Inspection (NRC Inspection Report 05000275/2019002, 05000323/2019002 and Request for Information ML17306A9382017-11-0202 November 2017 NRR E-mail Capture - Request for Additional Information - Request for Approval for Application of Full Weld Overlay REP-RHR-SWOL, Diablo Canyon Power Plant, Units 1 and 2 ML17152A3192017-06-0101 June 2017 NRR E-mail Capture - Request for Additional Information (RAI)- Relief Requests NDE-SLH U2, NDE-LSL U2, NDE-LHC U2, NDE-LHM U2, and NDE-ONV U2 (CAC Nos. MF9386 Through MF9390) ML17102B6072017-04-12012 April 2017 NRR E-mail Capture - Request for Additional Information (RAI) - Revised Emergency Action Level Schemes Pursuant to Nuclear Energy Institute (NEI) 99-01, Revision 6 ML16347A0032016-12-0909 December 2016 NRR E-mail Capture - Request for Additional Information (RAI) - Diablo Canyon Power Plant License Amendment Request for Adoption of NEI 94-01 ML16326A3562016-11-21021 November 2016 NRR E-mail Capture - Request for Additional Information - License Amendment Request to Adopt Nuclear Energy Institute (NEI) 94-01, Revision 2-A for Diablo Canyon Power Plant, Units 1 and 2 - CAC Nos. MF7731 and MF7732 ML16048A2322016-02-17017 February 2016 NRR E-mail Capture - Diablo Canyon 1 and 2 - Met Data Second Round of Requests for Additional Information for License Amendment Request 15-03 to Adopt the Alternative Source Term Per 10 CFR 50.67 (TAC Nos. MF6399 and MF640 ML16011A3652016-02-0202 February 2016 Requests for Additional Information for the Review of the Diablo Canyon Power Plant, Units 1 and 2, License Renewal Application - Set 39 (TAC Nos. ME2896 and ME2897) ML16011A3172016-01-11011 January 2016 NRR E-mail Capture - Diablo Canyon 1 and 2 - Requests for Additional Information for License Amendment Request 15-03 to Adopt the Alternative Source Term Per 10 CFR 50.67 ML15358A0022015-12-23023 December 2015 Request for Additional Information Email (Follow-up Pra), Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML15357A3822015-12-23023 December 2015 Request for Additional Information, Round 4 - Amendment Request to Replace Digital Process Protection System for Reactor Protection System and Engineered Safety Features Actuation System Functions ML15295A3732015-11-0505 November 2015 Requests for Additional Information Related to the Diablo Canyon LRA Environmental Review ML15287A1652015-10-23023 October 2015 Requests for Additional Information Related to the Diablo Canyon LRA Environmental Review - SAMA 2024-09-06
[Table view] |
Text
Draft Response to general justification for "EMERGENCY":
DCPP entered LCO 3.8.1 as a result of compensatory measures taken in response to discovery of a nonconservative TS SR 3.3.5.3. The nonconservative TS was concluded based on inspectors insisting our design should consider worst case degraded voltage and timing even if it is non-mechanistic. When these worst case scenarios were postulated, permanently connected class 1E loads such as auxiliary saltwater pumps and component cooling water pumps were determined to trip on overcurrent prior to the second level undervoltage relay time delay transferring them to EDGs.
Detailed timeline is pending.
Other stations have been challenged on similar scenarios but have treated these as URI's.
- 1. Provide a detailed list and descriptions of all compensatory measures being used during this extended Allowed Outage Time (AOT) for the Offsite Circuit. This list shall include demonstrated operability of remaining offsite circuit(s), demonstrated operability of all site Emergency Diesel Generators (EDGs), demonstrated operability of all safety busses and the necessary circuits which provide them power from the offsite sources and the EDGs, demonstrated operability of all supporting vital DC systems, demonstrated functionality of both switchyards (230 kV and 500 kV) to support output of both main generators and provide stable offsite power to the plant safety systems, controls in place to prevent maintenance, testing of and protect the aforementioned systems and components during the extended AOT as well as avoid possible plant transients or abnormal plant evolutions, details of plans made with the Transmission Operator for oversight of transmission system operation during this AOT to ensure continued availability and reliability.
Draft Response:
Compensatory Measures:
The compensatory measure taken for the non-conservative Technical Specification was to cut out the auto transfer to the standby offiste circuit (Startup power) for one vital 4 kv bus. The bus was selected based on which Auxiliary Saltwater (ASW) pump and which Component Cooling Water (CCW) pumps are running. If the transfer to Startup is disabled for a bus, then the running ASW and CCW pumps would not be exposed to the postulated degraded Startup voltage and would not trip on overcurrent.
Cutting out the auto transfer to Startup places the affected unit in Technical Specification 3.8.1, "AC Source - Operating". In this configuration, there is no need for any procedure revisions, as a bus transfer to emergency diesel generator (EDG) is already covered by the Emergency Operating Procedure (EOP) set. If the EDG fails to start or load, operators would re-energize the bus from offsite power in accordance with EOP ECA-0.3 "Restore 4kV Buses". Operators are already trained on ECA-0.3. If an overcurrent does occur, operators would respond in accordance with Operations policy B-2, "Electrical Alarm Relay Response". B-2 allows the operators to attempt one reset of an inverse time overcurrent trip if the equipment is needed to stabilize the plant. Resetting the relay is accomplished by turning the pump control
switch to the left on the main control boards. This is a simple manipulation and the operators are currently trained on this topic.
Operability of Remaining Offsite Circuits:
The remaining offsite circuit - 500 kV is in operation with all three lines connecting the 500 kV switchyard to the Pacific Intertie in normal service. Both units are at 100 percent power and connected to the 500 kV switchyard. Should the units go offline and both 230 and onsite power was unavailable, this 500 kV source would provide power to ESF loads as a delayed source of power, following operators opening of the motor operated disconnect and initiating backfeed. Procedure AD7.DC6 implements protective measures for all these systems.
Operability of all onsite EDGs:
All onsite EDGs remain operable. During the FLUR setpoint modification the risk status is elevated resulting in additional protective measures such as postings Operability of all safety buses and necessary circuits:
Operability of all supporting vital DC systems:
Functionality of both switchyards:
- 2. Provide detailed information concerning ability of the offsite circuits to also provide the necessary power and voltage for starting of all required 1E loads as a result of the scenarios which caused the problems with the running 1E loads.
Draft Response:
Relays prevent loading the offsite circuit when voltage is below 85%.
- 3. Provide a description of and describe whether training has been completed for any procedures required for the configuration of the plant during the extended AOT. For example, a procedure for restarting a 1E pump that would happen to trip on overload.
Draft Response:
The compensatory measure taken for the non-conservative Technical Specification was to cut out the auto transfer to the standby offiste circuit (Startup power) for one vital 4 kv bus. The bus was selected based on which Auxiliary Saltwater (ASW) pump and which Component Cooling Water (CCW) pumps are running. If the transfer to Startup is disabled for a bus, then the running ASW and CCW pumps would not be exposed to the postulated degraded Startup voltage and would not trip on overcurrent.
Cutting out the auto transfer to Startup places the affected unit in Technical Specification 3.8.1, "AC Source - Operating". In this configuration, there is no need for any procedure revisions, as a bus transfer to emergency diesel generator (EDG) is already covered by the Emergency Operating Procedure (EOP) set. If the EDG fails to start or load, operators would re-energize the
bus from offsite power in accordance with EOP ECA-0.3 "Restore 4kV Buses". Operators are already trained on ECA-0.3. If an overcurrent does occur, operators would respond in accordance with Operations policy B-2, "Electrical Alarm Relay Response". B-2 allows the operators to attempt one reset of an inverse time overcurrent trip if the equipment is needed to stabilize the plant. Resetting the relay is accomplished by turning the pump control switch to the left on the main control boards. This is a simple manipulation and the operators are currently trained on this topic.
- 4. Provide a detailed description of the maintenance plan and the post maintenance operability testing required to implement compensatory measures for the purpose of justifying the 24-hour AOT extension.
See schedule attached to e-mail. Post Mod Test is accomplished by STP M-75, "4KV Vital Bus Undervoltage Relay Calibration "
- 5. Provide a detailed discussion about the affects on plant operations under the current configuration with the automatic transfers being disabled.
Draft Response: See Response to #3.
- 6. Confirm that a dual unit trip is part of the Diablo Canyon Power Plant (DCPP) licensing basis in addition to being required by the Transmission Provider.
Draft Response:
The dual unit trip is also a licensing basis in accordance with the NRC's 12/14/2009 letter. DCPP's design is capable of handling the worst case of dual unit trip or accident in one with a spurious SI in the other unit.