February 17, 2023 Ms. Paula Gerfen Senior Vice President, Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Nuclear Power Plant P.O. Box 56 Mail Code 104/6 Avila Beach, CA 93424

SUBJECT:

REQUEST FOR INFORMATION REGARDING DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - DECEMBER 8, 2022, PUBLIC MEETING

Dear Ms. Gerfen:

During the December 8, 2022, public meeting Pacific Gas & Electric Company (PG&E) described plans to review and/or revise the existing aging management programs (AMPs) and to reconsider the timing of AMP-required activities, such as one-time inspections. In order to facilitate U.S. Nuclear Regulatory Commission inspection planning for the final Unit 1 outage before entering the Period of Extended Operations (PEO) in October 2023, the staff requests the following:

  • the AMP-required commitments (including but not limited to inspections) that PG&E was committed to perform by the withdrawn license renewal application (dated November 23, 2009) prior to entering the PEO; and
  • the current schedule for AMP-related activities in the October 2023 Unit 1 refueling outage.

If you have any questions, please contact me at 301-415-2277 or via email at Brian.Harris2@nrc.gov.

Sincerely,

/RA/

Brian K, Harris, Senior Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323

ML23041A186 *via email NRR-106 OFFICE NRR/DNRL/NLRP/PM NRR/ DNRL/NLRP/LA NRR/DNRL/NLRP/BC NAME BHarris SGreen LGibson: BHarris for DATE 2/08/2022 02/15/2023 02/17/2023