ML100630115

From kanterella
Jump to navigation Jump to search

Additional Information Regarding Environmental Review
ML100630115
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 02/25/2010
From: Bajestani M
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
TAC MD8203
Download: ML100630115 (146)


Text

Tennessee Valley Authority, Post Office Box 2000, Spring City, TN 37381-2000 February 25, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop: OWFN P1-35 Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391

Subject:

WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - ADDITIONAL INFORMATION REGARDING ENVIRONMENTAL REVIEW (TAC NO. MD8203)

References:

1. NRC letter dated December 3, 2009, "Watts Bar Nuclear Plant, Unit 2 -

Request for Additional Information Regarding Environmental Review (TAC No. MD8203)"

2. TVA letter dated February 15, 2008, 'Watts Bar Nuclear Plant (WBN) -

Unit 2 - Final Supplemental Environmental Impact Statement for the Completion and Operation of Unit 2"

3. TVA letter dated July 2, 2008, 'Watts Bar Nuclear Plant (WBN) - Unit 2 -

Final Supplemental Environmental Impact Statement - Request for Additional Information (TAC No. MD8203)"

4. TVA letter dated January 27, 2009, 'Watts Bar Nuclear Plant (WBN) Unit 2 -

Final Supplemental Environmental Impact Statement - Severe Accident Management Alternatives (TAC No. MD8203)"

5. TVA letter dated December 23, 2009, 'Watts Bar Nuclear Plant (WBN) Unit 2

- Additional Information Regarding Environmental Review (TAC No.

MD8203)"

The purpose of this letter is to provide additional information in support of NRC's environmental review of WBN Unit 2 as requested by NRC in Reference 1 subsequent to a site audit in October 2009.

Printed on recycled paper

U.S. Nuclear Regulatory Commission Page 2 February 25, 2010 The WBN Unit 2 Final Supplemental Environmental Impact Statement (June 2007) was submitted to NRC on February 15, 2008 (Reference 2). By letter dated July 2, 2008 (Reference 3), TVA responded to an NRC request for additional information. By letter dated January 27, 2009 (Reference 4), TVA provided the Severe Accident Management Alternatives analysis report for WBN Unit 2. By letter dated December 23, 2009 (Reference 5), TVA provided additional information in support of NRC's environmental review of WBN Unit 2. provides the NRC environmental review requests for additional information and TVA's responses as of February 12, 2010. Attached to the Enclosure is an Optical Storage Media (OSM #1) with additional supporting documents. Additional supporting documents not suited to electronic submission are also attached. TVA expects to provide the remaining information by March 12, 2010.

If you have any questions, please contact me at (423) 365-2351.

Sincerely, Masou(

ajestani Watts J ar Unit 2 Vice President

Enclosures:

1. Additional Information Environmental Review
2. List of commitments Attachments to Enclosure 1:
1. OSM #1 Additional information
2. Other additional information cc (Enclosures):

U. S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381 Additional Information Environmental Review

Additional Information Regarding Environmental Review Land Use L-1. Verify that current land use at the site and in the vicinity is the same as described in the 1978 FES-OL. Provide a map of the Watts Bar site and vicinity with detail on current land-use coverage categories. This map should reproduce clearly in black and white for use in hardcopy and website versions of the Nuclear Regulatory Commission (NRC) EIS.

A map of the WBN site and vicinity showing current land use is attached.

L-2. As discussed at the site audit, provide land acreage estimates of major coverage type categories (e.g., forested, built-up, etc.) within the site and boundary and within the vicinity of the site.

Attached is a spreadsheet that provides the land acreage estimates for the land use classes shown on the map (see L-1).

Transmission Lines TL-1. As discussed at the site audit, provide a map of the Watts Bar transmission system within the site and to the nearest substations. Include corresponding description of relevant dimensions (e.g., length and width of the corridors) and land-use coverage type in transmission corridor. This map should reproduce clearly in black and white for use in hardcopy and website versions of the NRC EIS.

Attached are plot figures that show the dimensions of the transmission corridors and the transmission line numbers associated with the plot. The numbers at the bottom are estimated brush acres to be mowed, or herbicide acres, and total easement acres, along with plot dimensions.

Socioeconomics S-6. Provide data on the capacity and average usage for regional (i.e., Rhea and Meigs Counties) water and sewer utilities (including DecatUr Water Department, Dayton Water Department and Wastewater Treatment, Spring City Water System and Waste Treatment, and Watts Bar Utility District).

The following data was obtained for regional water and sewer utilities:

Utility Capacity Average Daily Usage

-Dayton Wastewater Treatment Plant 2.67 million gallons/day 1.8 MGD (MGD)

Decatur Water Department -

wastewater 0.34 MGD Not provided Decatur Water Department 1 MGD Not provided Spring City Water 1.5 MGD 0.51 MGD Spring City Sewage 1.1 MGD 0.6 MGD Watts Bar Utility District 1.8 MGD 0.89 MGD E1-1

Benefit-Cost BC-2. Provide an estimate of levelized operating (i.e., delivered cost) costs associated with power generation from Watts Bar Unit 2 and describe relevant assumptions, including assumed capacity factor. Indicate the amount (either as a percent or in cents/kWh) attributable to fuel costs, decommissioning expenses, and waste disposal costs.

An estimate of the operating costs associated with the operation of WBN Unit 2 is attached.

Hydrology H-5. In order to better understand the impact of plant operations on site groundwater, provide information on the stage fluctuation of the yard holding pond during a recent year of operations. How are those fluctuations expected to change when WBN Unit 2 begins operation?

A plot of the actual water surface elevation (WSEL) measured for the yard holding pond (YHP) is given in Figure 1 for the year 2001. This year is close to normal in terms of the overall summer hydrology and meteorology in the Eastern Tennessee Valley. Also shown is the expected WSEL in the YHP for the same year based on a simulation of WBN with the operation of both Unit 1 and Unit 2. The computer code and output files for the simulation are provided in the response for RAI H-15.

The following general comments are provided in terms of the operation of WBN with two units versus one unit:

The average WSEL in the pond is expected to be higher with the operation of two units. This is because with two units, the blowdown discharge will be larger, requiring more storage in the YHP when the flow cannot be released from Outfall 101 (i.e., when the release from Watts Bar Dam is less than 3,500 cfs). Based on the results shown in Figure 1, the average WSEL in the YHP is expected to be about 1.75 feet higher with the operation of two units.

Due to the larger blowdown flowrate, the WSEL in the pond with two units will both rise and fall faster than with the operation of one unit.

The YHP is not expected to exceed the overflow elevation with normal operation of two units.

H-6. The ARCADIS report reviewed at the site audit showed the impact on the water table of a French drain surrounding the power block. How much water is pumped from the French drain annually?

Approximately 2.6 x10 8 gallons per year are pumped from the French drain.

H-9. Provide a current table of dilution factors and travel times for downstream water users within an 80-kilometer (50-mile) radius of the WBN Plant.

El -2

Have any of the users listed in the 1995 EIS ceased water withdrawal? Are there new users to be considered? Have any changes occurred that result in changes to the dilution factors reported.

The following users have ceased withdrawal:

U.S. Army Volunteer Ammunition Plant Rock-Tennessee Mill Dixie Sand and Gravel Chattanooga Missouri Portland Cement Signal Mountain Cement (TRM 433.3R)

Note: The water users down river of Tennessee-American Water are outside of the 50-mile radius.

There are no new users to be considered. However, the following user name changes have occurred:

E.I. DuPont Company is now Invista-Dupont Company Signal Mountain Cement (TRM 454.2R) is now BUZZI UNICEM USA Mead Corporation is now Smurfit Stone Reference information for the cited table indicates that the computations for the dilution factors were performed based on a rectangular channel of 1100 feet in width and 30 feet in depth, a river flow of 27,800 cfs, and a diffuser discharge of 62 cfs. The channel width of 1,100 feet is representative of the width of the Tennessee River in the upper portion of Chickamauga Reservoir, and the depth of 30 feet is roughly representative of the average depth of the main channel in reservoir for winter pool conditions, when river velocities are high. The flow of 27,800 cfs is the approximate average annual flow past WBN, and 62 cfs is the average annual flowrate from the plant diffusers for normal operation of the plant with two units. The latter is as anticipated by TVA in the original work to estimate the dilution factors. Between the time these computations were performed and now, the geometry of Tennessee River and the expected average annual flow past the plant have not changed.

The most recent TVA analyses for the plant water balance, summarized in response to RAI H-14, suggests a flowrate for the plant diffusers (Outfall 101) of about 64 cfs for operation with two units. This is not considered a material change from the conditions of original computations. As such, at this time, TVA feels that there is no need to update values for the dilution factors in the table.

With the above responses, a current update of dilution factors and travel times is given below:

E1-3

Dilution Factors and Travel Times for Downstream Water Users Within an 80-Kilometer (50-Mile) Radius of the WBN Plant Water Users Location Travel Time (days)

Dilution Factor Watts Bar Nuclear Plant TRM 528.8 R(a)

N/A N/A Dayton, TN TRM 503.8 R 1.8 204 Soddy-Daisy Falling Water U.D.

TRM 487.2 R 3.0 272 Soddy OK 4.0 Sequoyah Nuclear Plant TRM 483.6 R 3.3 282 East Side Utility TRM 473.0 4.0 307 Chickamauga Dam TRM 471.0 4.2 (C)

Invista-Dupont Company TRM 469.9 R 4.2 (c)

Tennessee-American Water TRM 465.3 L(b)

.4.6 (c)

(a) Right bank (b) Left bank (c) River is assumed to be fully mixed downstream of the Chickamauga Dam; dilution factor equals 448.

H-IO. Table 2.3 of the Final Environmental Statement related to the operation of Watts Bar Nuclear Plant Units Nos. 1 and 2 (1978) (NUREG 0498) summarized water quality in Chickamauga Reservoir adjacent to the Watts Bar site. Identify any changes to water quality since publication of that table.

This information was provided in TVA's letter dated December 23, 2009, "Watts Bar Nuclear Plant (WBN) Unit 2 - Additional Information Regarding. Environmental Review (TAC NO.

MD8203)".

Based on the NRC staff further request, the following additional data for September 2009 is provided:

Sep-09 pH 7.4 Specific Conductance, at 218 25°C, mmhos Alkalinity, "P" 0

as CaCO 3, ppm Alkalinity, "M" 81 as CaCO 3, ppm Sulfur, Total, as S04, ppm 17.5 Chloride, as Cl, ppm 8.2 Hardness, Total, 96 as CaCO 3, ppm Calcium Hardness, Total, 67 as CaCO 3, ppm Magnesium Hardness, Total, 29 as CaCO 3, ppm Copper, Total, as Cu, ppm

<0.05 Iron, Total, as Fe, ppm 0.25 E1-4

Sodium, as Na, ppm 7.7 Zinc, Total, as Zn, ppm

<0.01 Manganese, Total, as Mn, 0.09 ppm Phosphate, Total,

<0.4 as P041 ppm Phosphate, Total Inorganic,

<0.2 as P0 4, ppm Phosphate, Filtered Ortho,

<0.2 as P0 4, ppm Silica, Total, as Si0 2, ppm 5.5 H-11. Provide through screen velocities for water entering the Intake Pumping Station under normal operating conditions with WBN Units 1 and 2 operating. Provide a diagram of the intake pumping station that includes dimensions of intake openings, location, and characteristic of trash racks and traveling screens to allow staff to validate the velocity provided.

Computations for the velocity of water entering the Intake Pumping Station under normal maximum mode of operation are provided in the attached file entitled:

H-i1_lntakePumpingStationVelocityRevl.

Drawings and related information for the Intake Pumping Station, trashracks, and traveling water screens are provided in the PDF reference files entitled:

WBN 31 N220-1.pdf WBN 31 N220-2.pdf WBN 31 N221-1.pdf WBN 31N221-2.pdf WBN 31N221-3.pdf WBN 31N221-4.pdf WBN 31N221-5.pdf WBN 31N221-6.pdf WBN 34N210.pdf WBN 38N200.pdf WB-DC-20-20.pdf H-12. Provide through screen velocities for water entering the Supplemental Condenser Cooling Water (SCCW) system under normal operating conditions with WBN Units 1 and 2 operating. Provide a diagram of the SCCW intake structure that includes the dimensions of intake openings, location, and characteristics of trash racks and traveling screens to allow staff to validate the velocity provided.

Computations for the velocity of water entering the SCCW system under normal operation of Watts Bar Reservoir are provided in the attached file entitled:

H-12_SCCW_Velocity.

E1-5

Drawings and related information about the SCCW intake, trashracks, and traveling water screens are provided in the PDF reference files entitled:

WBH 41 N515 (cal).pdf WBH 48N202 (cal).pdf WBF 44N203.pdf Calc MDN1027-98006.pdf H-13. Provide a description of how the cooling system will be operated under normal winter and summer operations. Provide a copy of the TVA procedure for operations of the cooling systems to make sure National Pollutant Discharge Elimination System (NPDES) permit conditions are not exceeded.

For hydrothermal compliance, the WBN cooling system contains three outfalls to the Tennessee River. Outfall 101 is the diffuser, Outfall 102 is the emergency overflow from the YHP, and Outfall 113 is discharge structure for the SCcW system. The current NPDES status for hydrothermal compliance for each outfall is available to WBN operators in the control room via the display shown in Figure 1. In addition, the TVA River Forecast Center (RFC) in Knoxville has a continuous display on a large-panel screen that summarizes the current hydrothermal status of all TVA thermal plants that usually require NPDES attention,

-including WBN. An example of the RFC display is shown in Figure 2. With this introduction, a discussion of each WBN outfall relative to the requested information is provided herein.

E1-6

Figure 1. WBN Computer Display for NPDES Hydrothermal Compliance E1-7

Hydrothermall Status Summary 0!I1iI!0i0'i5:50 PRant.

C~ai'acreniic:

Peijod

' JoinSe'ierF6ssil

.PDES Intale ThIAX.

iDaiv..vg".

BunlRunFossil.

tNDEN Intake ThLkX Daily.Axg:

Jai~o Fsi NPDES.3,Itak4114'AX

~

~

iyi UHS IntaLke ThLAX Intanutaneous NPDES'Ambient Rive.TrMP Rmunng.*-H Avg i NDI*ES SCCWV Donsti'eamn ThAL*X Riuunng -%H-A-g

  • Vatts B~u: I'¢~le' IqNPDES SCCWV DELTA.T Runingi-Hr Avg.

NPI)ES SCUW Dowvnstreatm TROC Rmunng i-,H Avg NPDES SCCW h'IUZ TMALX Rmmiingl -h. Avg.

.NPDES Diffuser Discharge T'AX, Dail. Avg,,

Y a'd H61ding Pond Elevation htitanta*einu 9,

HSIntake, TNAX Lamaios

...NPIDESIAjnbient River TFhiP Rinming 24:41r Avg 1l

.;*e~ioy~alt b~iide~.

NPDES Doionstrearn TIAX-Rumnig24Hr Avg WEDES DowunsteamThMAX.

Runing IjiHr Avg-NPDESINMLTAT

'Running.4-R6HiAvg '

NPDES DowstreamTROC' RnnnihgT-if,'Av-,,"

WVidoivs Creek Fossdl, N'IDEN'Intake TIA.X Dnily'Avg; I.)DES'iAmbienteRiver.TEMP

.Running 2-Hi"A-g Hi owns Fe *fn~ Kcl!e mK

INiDE D ownstb ea nvT.if.AX-Running 24*BHr*A:gr

'N]'DES DoivunoteawnThIXRung rvg N"PDES.DELTAT Running 24hAvg"

  • Celbei tFossil NPDES Intake TMIAX Daily Avg.-

G'llatinFozsil, NIDES Intake.TMLX Daily.Avg.

Ciunbefland Fossl NPDES Iut ake. TAX

.Dabily, Avg, S68.3 PE

$ 6.9PF S3.6 0F1lu, S92.3 PF S95.0?F

=j707.02,'

_j, 85.S;OF 86.9-F 29.0 OF"

3. 8S.0IF S92'%9F 90.q?0

'-85.6

-OF

~*76.0iF' Figure 2. TVA River Forecast Center Display for NPDES Hydrothermal Compliance Outfall 101 The operation of Outfall 101 depends on the release of water from Watts Bar Dam. Based on the NPDES requirements, if the release is less than 3,500 cfs, Outfall 101 is automatically removed from service by an interlock circuit. When flow from the dam is resumed at levels above 3,500 cfs, the interlock is released and an annunciator in the control room sounds to indicate "RIVER FLOW LO DISCHARGE TERMINATED." In response to the alarm, operators confirm the status of the flow control valves and the operation of the SCCW system (see page 27 of TVA WBN ARI-159-165, 2006). If desired, the diffuser flow control valves can be opened at this time. Depending on other operating requirements of the plant, the plant may choose to continue to keep the diffuser/Outfall 101 out of service. Since the operation of the diffuser is linked to the operation of Watts Bar Dam, it is possible for the diffusers to be cycled closed and open several times a day depending on the schedule for hydro peaking at the dam. That is, under normal winter and summer operating conditions, Outfall 101 can be closed and opened daily.

The NPDES temperature limit for Outfall 101 is a daily average value of 95°F. Plant instrumentation is provided to measure the Outfall 101 temperature continuously. If an instantaneous value of the measurement reaches 950F, an annunciator in the control room sounds to indicate "DIFFUSER TEMP HI." In response to the alarm, operators open the E1-8

flow control valve for the YHP (if it is closed), close the flow control valves-for the diffuser, confirm proper operation of the Condenser Cooling Water (CCW) System, and notify site environmental personnel to evaluate NPDES compliance (see page 44 of TVA WBN ARI-159-165, 2006). The immediate impact of this operation terminates releases to the river and routes the cooling tower blowdown to the YHP, thereby preventing exceedances of the NPDES temperature limit. For normal winter and summer operating conditions, the flow control valve for the YHP is open, so termination of flow to the river usually only involves closing the flow control valves for the diffuser. It is important to emphasize that this operation occurs based on an instantaneous measurement of 950F, whereas the NPDES limit is based on a daily average measurement. In this manner, WBN is notified of encroaching conditions well in advance of a genuine threat to the NPDES limit. Since the startup of the plant, events have occurred in the late afternoon of hot, humid days in warm summers where the instantaneous temperature for Outfall 101 has reached 95 0F and triggered the annunciator. When this occurs, site environmental personnel consult with pertinent staff to evaluate hydrothermal conditions, and if needed, implement changes in the operation of WBN and/or the river to protect the NPDES limit. With this strategy, since the startup of the plant, the daily average discharge temperature for Outfall 101 has never reached 950F.

Outfall 102 The overflow from the YHP is for emergency situations only. As such, under normal winter and summer operations there is no discharge from Outfall 102. Under normal winter and summer operations, filling of the YHP occurs when Outfall 101 is out of service (i.e., when the release from Watts Bar Dam is below 3,500 cfs). To ensure that no unexpected overflow occurs from the YHP, the WSEL in the YHP is monitored continuously. The WSEL measurement is available to operators in the WBN control room via the display shown in Figure 1. The overflow elevation of the YHP is 707 feet msl. Currently, a computer-generated alarm is issued in the control room if the WSEL in the YHP reaches 705.8 feet msl. For a blowdown rate of about 28,700 gpm, which is expected to be typical for the combined operation of Unit 1 and Unit 2 (see response to RAI H-14, Table 21), this provides a notification of about 51/2 hours before the pond WSEL will reach the overflow elevation, if flow into the pond is not terminated. There presently is no formal operating procedure specifying a required response to the YHP alarm. The current practice is for the control room to informally contact the TVA RFC in Knoxville and request an evaluation of the scheduled releases from Watts Bar Dam, and if needed, to implement changes in the releases so that Outfall 101 can be returned to service (i.e., allow the YHP to drain through the diffuser).

In addition to the computer-generated alarm in the WBN control room, there are two other systems that issue alarms for a high WSEL in the YHP. The first is a callout computer that monitors the WBN Environmental Data Station (EDS). The EDS callout computer continuously monitors the status of the WBN hydrothermal data and automatically issues telephone notifications if hydrothermal parameters reach or exceed established administrative limits. The callout computer also issues notifications if the hydrothermal data fails-to pass certain validation tests, or if the hydrothermal instrumentation does not respond to data requests (i.e., identifies potential instrumentation problems). Currently, the callout computer issues a notification to the TVA RFC in Knoxville when the YHP WSEL reaches 705.9 feet msl. The second system is the hydrothermal compliance display in the TVA RFC (i.e., Figure 2). When the YHP WSEL reaches 705.9 feet ms I, the background color for the current value of the YHP WSEL changes from green to yellow (caution). If the YHP WSEL E1-9

reaches 706.4 feet msl, the background color changes from yellow to red (action). When an EDS callout notification or a yellow or red alarm is obtained in the TVA RFC, pertinent staff in TVA River Operations is contacted informally to perform evaluations and develop options for preventing an overflow of the YHP. Thus far, the duplicity in monitoring and alarming of the YHP water level has been successful in ensuring that an unexpected overflow of the YHP does not occur (i.e., computer-generated alarm in the WBN control room, EDS callout notification, and hydrothermal compliance display in the TVA RFC).

Outfall 113 The operation of Outfall 113 is restricted by the NPDES water temperature limits summarized in Table 1. In addition, the NPDES permit also specifies that there shall be a release of at least 3,500 cfs from Watts Bar Dam whenever there is a change in operation of the SCCW system.

Table 1. NPDES Temperature Limits for SCCW Discharge/Outfall 113 Parameter Sample Period NPDES Limit Temperature at Downstream End of Running 1-Hr Avg 86.9°F Mixing Zone Temperature Rise from Ambient to Downstream End of Mixing Zone Temperature-Rate-of-Change at Downstream End of Mixing Zone Running 1-Hr Avg

+/-3.6 FO/hr Temperature at Bottom of Receiving Running 1-Hr Avg 92.3 0F Stream Bottom The basic operation of the SCCW system is described in Section 2.2.2 of the 2007 Final Supplemental Environmental Impact Statement (FSEIS) (TVA, 2007). In general, there are three modes of operation of the SCCW system-out of service, in service with bypass closed (summer mode), and in service with bypass open (winter mode). The different modes of operation are provided primarily for maintaining compliance with the NPDES temperature limits given in Table 1. Other objectives in operating the plant, however, can dictate the mode of operation of the SCCW system. Under normal winter and summer operating conditions, the SCCW system will be summer mode. In infrequent events where the meteorology and hydrothermal conditions of the river do not provide adequate dilution of the effluent from Outfall 113 (i.e., when the temperature limits summarized in Table 1 are threatened), the SCCW system will be moved from summer mode to winter mode, and in the most extreme events, removed entirely from service.

System Operating Instruction (SOI) 27.03 provides the formal requirements for operating the SCCW system (TVA SOI-27.03, 2007). In terms of NPDES requirements, however, SOI-27.03 includes steps only to ensure that any change in operation of the SCCW system is accompanied by a river flow of at least 3,500 cfs. Guidance on how to operate the SCCW system with respect to the NPDES requirements in Table 1 currently relies on informal procedures tied to real-time monitoring of the NPDES temperatures and in performing river temperature forecasts.

El-10

All the NPDES temperature parameters in Table 1 are available to operators in'the WBN control room via the display shown in Figure 1. The same is true for the TVA RFC in.

Knoxville via the display shown in Figure 2. The EDS callout computer also monitors these temperature parameters. Each of these monitoring systems have alarm levels-those in the WBN control room issued by a computer-generated alarm, those by the EDS callout computer issued by a telephone notification, and those in the TVA RFC by changes in the screen colors. For each monitoring system, Table 2 provides a summary of the current alarm levels for each of the NPDES parameters listed in Table 1. As before, there presently are no formal operating procedures specifying a required response to these alarms. In response to an alarm, the current practice is for the WBN control room to informally contact the TVA RFC in Knoxville and request an evaluation of the SCCW system to determine if changes in operation should be implemented. Independently, when an alarm is obtained in the TVA RFC in Knoxville, pertinent staff in TVA River Operations is contacted to perform evaluations and develop options for preventing an NPDES exceedance for the SCCW system.

Table 2. Current Alarm Levels for Outfall 113 NPDES Temperature Parameters EDS TVA RFC Control Room Clo DsA C

Parameter Computer-Generated Callout Display Color AlrsComputer Alarms Alarms Yellow Red Temperature at Downstream 85.4 0F 85.40F 83.90F 85.40F End of Mixing Zone Temperature Rise from Ambient to Downstream 4.4 F0 4.4 F0 4.4 F0 4.9 F0 End of Mixing Zone Temperature-Rate-of-Change at Downstream

+/-2.6 F°/hr

+/-2.6 F°/hr

+/-2.6 F°/hr

+/-3.1 F°/hr End of Mixing Zone Temperature at Bottom of Receiving Stream 90.80F 90.8 0F 90.8 0F 91.8 0F Bottom In addition to the alarms summarized above, a WBN water temperature forecast is performed to evaluate the expected thermal impact in the river of the SCCW operation.

Using a hydrothermal model for the WBN cooling system, the forecast is performed by staff in the TVA RFC. Based on the expected conditions of the river (ambient water temperature and flow), the forecast meteorology, and the expected operation of WBN, the hydrothermal model provides a prediction of the hourly river temperature at the downstream end of the Outfall 113 mixing zone. The prediction is used to provide a recommendation to WBN for the operation of the SCCW system. The forecast is issued by email almost every day. An example email is shown in Figure 3.

Again, the duplicity in monitoring and alarming of the real-time temperature measurements, along with the routine hydrothermal forecast, thus far has been successful in ensuring that' the impact of the SCCW system does not exceed NPDES water temperature limits.

El-11

From:

roht@tva.gov Sent:

Sunday, January 24,2010 5:08 PM To:

RO HT WBN; RO HT Nuclear; RO HT Common

Subject:

WBN hydrothermal forecast for Sunday, January 24, 2010.

Recommendation - Monday 1125110 Based on current forecast meteorology and forecast river flow, it is safe to operate the SCCW system in summer mode.

Outlook - Tuesday 1126110 and beyond The current forecastsuggests that it will be safe to operate.the SCOW system in sumimer mode through Sunday, January 31, 2010.

Forecast Notes The next forecast will be issued Monday, 1/25/10, unless actual conditions stray apprediably from predicted conditions, in which case the next forecast will be issued sooner.

Figure 3. Example Hydrothermal Forecast for Operation of WBN SCOW System H-14. Provide a water balance and heat balance for the operation of WBN Units 1 and 2.

Indicate where incremental increases in water use will occur as a result of initiating operation of Unit 2. Provide this information for normal summer and winter operation and for the operational mode which has the greatest impact on the receiving water body (effluent temperature, instream temperature, and instream temperature rate of change).

Since completing the FSEIS in 2007, TVA has a fuller understanding of the expected operation of the SCOW system. The hydrothermal model used to estimate the thermal impact of the plant on the receiving waterbody (i.e., Tennessee River) has been updated to reflect this understanding. However, to provide an expeditious response to this RAI, analyses with the updated model had to be limited to steady-state evaluations. That is, in the FSEIS of 2007, an unsteady model was run with an hourly time step to simulate the hourly operation of the plant over a period of 30 years. The average and extreme (e.g.,

maximum and minimum) impacts in the river were then determined based on statistical properties of the hourly model results. In the analyses summarized herein, the time histories of the hydrologic and meteorological data were first analyzed to determine average and extreme hourly values for each month of the year. These were then used as input in the steady-state model to estimate the thermal impacts for the cases specified in this RAI.

In addition to updating the model for the operation of the SCOW system, other updates were made to capture better the range of operation of the Intake Pumping Station (IPS). The following discussions provide summaries of the model changes, the hydrologic and meteorological data used in the model simulations, and the model results. To respond to the requested information for normal summer and winter operation, simulations were performed based on the statistical characteristics of the expected hydrology and meteorology for each month of the year. To respond to the requested information for the greatest impact on the receiving waterbody, model simulations were performed for five specific cases with extreme hydrology and meteorology.

E1-12

SCCW System Section 2.2.2 of the 2007 FSEIS provides a description of the WBN heat dissipation system.

In this section TVA states (page 26), "If WBN Unit 2 is completed, the current plan is to supply the SCCW to both the Unit 1 and the Unit 2 CCW systems." This is again emphasized in Section 3.1.1 where TVA states (page 37), "With the combined operation of Unit 1 and Unit 2, the SCCW system would serve both units." At the time of the 2007 FSEIS, it was anticipated that-any modifications to the SCCW system associated with the addition of Unit 2 would not require changes in the design capacity of the plant outfalls to the Tennessee River. These include the diffuser (Outfall 101), the emergency overflow for the YHP (Outfall 102), and the SCCW discharge structure (Outfall 113). This was emphasized in Section 3.1.1 where TVA states (page 34), "For the combined operation of Unit 1 and Unit 2, the control structures that regulate the amount of flow between and out of the cooling tower basins would need to be modified to preserve the original design bases for all three outfalls." Based on this assumption, the hydrothermal analyses summarized in Section 3.1.1 of the FSEIS specified the inflow and outflow of the SCCW system for the combined operation of Unit 1 and Unit 2 to be the same as that for the current operation of Unit 1. As a gravity-driven system, this was accomplished by assuming the water levels in the cooling tower basins remained unchanged for both cases. It also was assumed that the SCCW system would serve only Unit 2 (page 37).

The operation of the SCCW system for the combined operation of Unit 1 and Unit 2 is expected to resemble that shown schematically in Figure 1. With this, the hydrothermal model was updated to provide a better estimate of the flows entering and exiting the cooling tower basins. This was accomplished by incorporating in the model the hydraulic characteristics of the key inflow and outflow structures for the basins, and computing the expected water levels in the basins. In contrast to the hydrothermal analyses of the 2007 FSEIS, this allows an estimate of the potential magnitude of changes in the inflow and outflow of the SCCW system due to the combined operation of Unit 1 and Unit 2 versus the current operation of Unit 1. The same is true for the blowdown.

Furthermore, to better estimate impacts for the combined operation of Unit 1 and Unit 2, and again in contrast to the 2007 FSEIS, model simulations for this RAI were performed for the SCCW system serving both units rather than solely Unit 2.

IPS Table 1 provides a summary of assumed operating conditions of the IPS for this RAI. The IPS includes pumps for the ERCW system, the RCW system, the Screen Wash System, and the Fire Protection System. The screen wash pumps and fire protection pumps are operated only intermittently, and thus are not significant in representing normal operation of the plant. A configuration representing the typical annual average water use of the IPS (+/-

10 percent) is given by the operation of two ERCW pumps and four RCW pumps. For this configuration, the combined flow delivered to the plant by the ERCW and RCW systems is about 39,500 gpm. With the operation of both Unit 1 and Unit 2, the operation of the plant is expected to vary between a normal configuration represented by two ERCW pumps and six RCW pumps and a normal max configuration represented by four ERCW pumps and six RCW pumps. For the former, the combined flow delivered to the plant by the ERCW and RCW systems is about 52,100 gpm. For the latter, the combined flow delivered to the plant by the ERCW and RCW systems is about 78,200 gpm. This is similar to a flow as high as an accident condition. This RAI is concerned with the water and heat balance for the operation of both Unit 1 and Unit 2. For this case, in order to bound the potential order of El-13

magnitude of the plant thermal impacts, the plant is assumed to operate in the normal maximum mode as defined in Table 1. This represents an update from the hydrothermal analyses summarized in the 2007 FSEIS, which were performed assuming the operation of the IPS with four ERCW pumps and four RCW pumps, delivering a combined flow to the plant of about 68,700 gpm.

Basic Hydrologic and Meteorolo-gical Data River Flow The river flow used in the analyses included the hourly release from Watts Bar Dam for years 1976 through 2009. For years 1976 through 2004, the hourly release is based on a simulation of the upstream portion of the TVA river system using historical runoff for 1976 through 2004, and assuming operation of the river system consistent with the policy established by the TVA Reservoir Operations Study (ROS) of 2004 (http://www.tva.gov/environment/reports/ros eis/index.htm). For years 2005 through 2009, actual hourly releases from Watts Bar Dam were used in the analyses, since the river system was operated in accordance with the ROS operating policy in these years. The basic monthly statistics for the hourly river flow are summarized in Table 2.

Ambient River Temperature The ambient river temperature used in the analyses included the hourly release temperature from Watts Bar Dam for years 1976 through 2009. For years 1976 through 2004, the hourly release temperature is based on a simulation of the upstream portion of the TVA river system using historical runoff and meteorology for 1976 through 2004, and assuming operation of the river system consistent with the policy established by the ROS. For years 2005 through 2009, actual hourly release temperatures from Watts Bar Dam were used in the analyses, since the river system was operated in accordance with the ROS operating policy in these years. Note that the NPDES permit for the plant specifies that the hourly release temperature from Watts Bar Dam as the ambient temperature for monitoring compliance to permit limits for river temperature. The basic monthly statistics for the hourly ambient river temperature are summarized in Table 3.

Wetbulb and Drybulb Air Temperature The drybulb and wetbulb air temperatures used in the analyses were obtained from measurements at the Chattanooga airport for years 1976 through 2009. The basic monthly statistics for the hourly drybulb and wetbulb temperatures are summarized in Table 4 and Table 5, respectively.

Difference between Wetbulb Temperature and Ambient River Temperature The difference between the wetbulb temperature and ambient river temperature provides a measure of the expected difference between the plant effluent temperature and the ambient river temperature. This is because the effluent discharge temperature from the hyperbolic draft cooling towers tends to track in parallel with the wetbulb temperature. Data for the difference between the wetbulb temperature and ambient river temperature is used to estimate the hydrologic conditions that are likely to produce the largest plant-induced water E1-14

temperature impacts. Using the data sources summarized above, the basic monthly statistics for the difference between the hourly wetbulb and hourly ambient river temperature are summarized in Table 6.

Water Surface Elevations in Watts Bar Reservoir and Chickamauga Reservoir Since the WBN SCCW system is a gravity-fed system, the amount of flow entering the SCCW system depends on the WSEL in Watts Bar Reservoir. Furthermore, the depth of water in the river below Watts Bar Dam influences the dilution of the plant effluent for the diffuser discharge (Outfall 101) and for the SCCW discharge (Outfall 113). This depth is controlled by the WSEL in Chickamauga Reservoir. For the simulations summarized herein, the assumed WSELs for Watts Bar Reservoir and the upper end of Chickamauga Reservoir are summarized in Table 7. These elevations correspond to the approximate seasonally normal levels for these reservoirs based on the current operating policy for the TVA river system.

Model Simulations Operation of Unit I and Unit 2 for Normal Winter and Summer Conditions To capture the potential variation in thermal impact between winter and summer conditions, model simulations of the plant were performed for each month of the year. The basic operating assumptions for each month are summarized in Table 8. Monthly average hourly values were used for the river flow, river temperature, drybulb temperature, and wetbulb temperature (i.e., from Table 2, Table 3, Table 4, and Table 5). Each unit was assumed to be operating at full power with four CCW pumps. The cooling towers were assumed to have a capability of 105 percent, and the IPS was assumed to be providing flow with four ERCW pumps and six RCW pumps. Water levels in Watts Bar Reservoir and Chickamauga Reservoir were based on the information provided in Table 7. On an average annual basis there is no net storage in the YHP, thus no outflow was assumed to occur from the pond. In the model simulations this is accomplished by assuming a pond WSEL of 698 feet msl, which is the elevation of the pond outlet structure. For conditions based on monthly average hourly river flows, releases from Watts Bar Dam are high enough to allow the operation of the SCCW system in summer mode for each case. With these assumptions, simulation results for the heat balance are given in Table 9. Results for the water balance and thermal impacts for each of the plant outfalls are given in Table 10. It is emphasized that with the YHP WSEL at 698 feet msl, there is no overflow for pond (i.e., Outfall 102). Overflow from the YHP currently is not expected for any normal operating conditions of the plant. It again is emphasized that this version of the hydrothermal model provides estimates only for a steady-state snapshot of the prevailing operating conditions. Temperature rate-of-change events due to variations in meteorology and river flow would be of the same order of magnitude as that determined by the 30-year dynamic simulations presented in Section 3.1.1 of the 2007 FSEIS.

Operation of Unit I and Unit 2 Yielding the Greatest Impact on the Receiving Waterbody The operational modes yielding the greatest impact on the receiving waterbody have been captured in five cases. These are summarized in Table 11. The basic operating assumptions for these cases are summarized in Table 12. Each unit was assumed to be operating at full power with four CCW pumps. The cooling towers were assumed to have a capability of 105 percent, and the IPS was assumed to be providing flow with four ERCW El-15

pumps and six RCW pumps. With the above assumptions, simulation results for the heat balance are given in Table 13. Results for the water balance and thermal impacts for each of the plant outfalls are given in Table 14. Other comments regarding each case include the following:

Case 1: The case producing a maximum instream temperature rise for Outfall 101 would occur during low river flow in the late winter/early spring months of the year, when the river temperature is cool but meteorology can produce days with high drybulb and wetbulb temperatures. The minimum river flow for which releases can be provided from Outfall 101 is 3,500 cfs, which is assumed for this case. Per the plant NPDES permit, releases cannot be made from Outfall 101 below this value. A control system between Watts Bar Dam and WBN is provided to close automatically the WBN diffuser when the release from the Watts Bar hydroplant drops below 3,500 cfs. In reality, for this case, a flow of 3,500 cfs is considered conservative because the minimum flow for a single hydroturbine at Watts Bar Dam is about 4,500 cfs. To produce the maximum discharge from Outfall 101, the YHP was assumed to be at the maximum level (no overflow) and draining to Outfall 101. The WSEL in the YHP corresponding to this condition is 707 feet msl. For the assumed conditions of the river and meteorology, the plant could operate with the SCCW system in summer mode.

Case 2: The case producing a maximum instream temperature rise for Outfall 113 also would occur during low river flow in the late winter/early spring months of the year, when the river temperature is cool but meteorology can produce days with high drybulb and wetbulb temperatures. The SCCW can operate with a river flow of 0 cfs, which was assumed for this case. For this flow, and for the reason cited above, there would be no discharge from Outfall 101 to the river-all the flow exiting the Unit 1 cooling tower basin by the blowdown weir would be diverted to the YHP. As such, for this case, the WSEL in the YHP is irrelevant. To be consistent with all the cases of Table 11, a YHP WSEL of 707 feet msl was assumed. For these conditions, the plant could operate with the SCCW system in winter mode. However, the results of the Case 2 simulation indicate that with this mode of operation, the temperature rise for Outfall 113 would be equivalent to the maximum allowable NPDES temperature rise for this outfall, 5.40F. For this reason it needs to be emphasized that whereas the plant could operate at this condition from a theoretical standpoint, because of the uncertainty of hourly variations in river flow and meteorology, such would never occur in practice. Procedures for monitoring thermal compliance would dictate changes in the operation of the river and/or WBN if the temperature rise were to reach about 4.90F. If the SCCW system were already operating in winter mode, and if there was not enough water in the river system to increase the release from Watts Bar Dam, the SCCW system would be removed from service. These procedures are discussed in more detail in the TVA response for RAI number H-13.

Case 3: The case producing a maximum combined instream temperature rise at Outfall 101 and Outfall 113 is the same as Case 1.

Case 4: The case producing a maximum instream temperature for Outfall 101 would occur during low river flow in the summer, when the river temperature is warm and the meteorology produces days with high drybulb and wetbulb temperatures. For this case the minimum river flow for the operation of Outfall 101 was again assumed, 3,500 cfs.

As for Case 1, a flow of 3,500 cfs is considered conservative because the minimum flow for a single hydroturbine at Watts Bar Dam is about 4,500 cfs. An extreme combination E1-16

of the drybulb and wetbulb temperatures was assumed, based on the historical meteorology. Similarly, an extreme value of the ambient river temperature also was assumed. To produce the maximum discharge from Outfall 101, the YHP again was assumed to be at the maximum WSEL, 707 feet msl (no overflow), and draining to Outfall 101. For the assumed conditions of the river and meteorology, the plant could operate with the SCCW system in summer mode.

Case 5: The case producing a maximum instream temperature for Outfall 113 is the same as Case 4, except for a river flow of 0 cfs rather than 3,500 cfs. There would be no discharge from Outfall 101 to the river-all the flow exiting the Unit 1 cooling tower basin by the blowdown weir would be diverted to the YHP. As before, the WSEL in the YHP is irrelevant, and a value of 707 feet msl was assumed for consistency. For these conditions, the plant could operate with the SCCW system in summer mode. However, the results of the Case 5 simulation indicate that with this mode of operation, the instream temperature for Outfall 113 would be equivalent to the maximum allowable NPDES temperature for this outfall, 86.90F. As for the temperature rise for Case 2, whereas the plant could operate at this condition from a theoretical standpoint, because of the uncertainty of hourly variations in river flow and meteorology, such would never occur in practice. Procedures for monitoring thermal compliance would dictate changes in the operation of the river and/or WBN if the temperature were to reach about 86.4°F.

If it were not possible to provide cooler releases from Watts Bar Dam, the operation of the SCCW system would be shifted from summer mode to winter mode.

To provide a basis for comparison of the above results, model simulations also were performed for the current operation of Unit 1. This includes both the normal winter and summer conditions and the cases yielding the greatest impact on the receiving waterbody.

For the IPS, the model simulations were performed for the case in Table 1 considered representative of Unit 1 operating experience.

Operation of Unit 1 for Normal Winter and Summer Conditions The basic operating assumptions for each month are summarized in Table 15. Simulation results for the heat balance are given in Table 16, and results for the water balance and thermal impacts for each of the plant outfalls are given in Table 17.

Operation of Unit 1 Yielding the Greatest Impact on the Receiving Waterbody The operational modes yielding the greatest impact on the receiving waterbody are the same cases summarized in Table 11. The basic operating assumptions for each case are summarized in Table 18. Simulation results for the heat balance are given in Table 19, and results for the water balance and thermal impacts for each of the plant outfalls are given in Table 20.

Comparison of Flow for Unit 1 Operation Versus Combined Operation Of Unit 1 and Unit 2 Based on averages of the results for each month as present in Table 10 and Table 17, a comparison of the estimated average plant inflows and outflows for the sole operation of Unit 1 versus the operation of both Unit 1 and Unit 2 is given in Table 21. These flows are only for the plant waste heat dissipation, although this encompasses the vast majority of the plant water use. The following items are emphasized:

E1-17

(i) Plant Inflow Because of the greater number of pumps in service, the inflow from the IPS is higher for the operation of Unit 1 and Unit 2. Recall that simulations for the operation of Unit 1 assumed two ERCW pumps and four RCW pumps in service, whereas simulations for the operation of Unit 1 and Unit 2 assumed four ERCW pumps and six RCW pumps in service.

The SCCW inflow estimated for the operation of Unit 1 and Unit 2 is about 9 cfs (3 percent) lower than that for the operation of Unit 1. This is because for the operation of Unit 1 and Unit 2, the water level in the Unit 2 cooling tower basin is higher, which reduces slightly the head for delivering SCCW flow from Watts Bar Reservoir.

(ii) Plant Outflow Cooling tower evaporation for the operation of Unit 1 and Unit 2 is about twice that for the operation of Unit 1, obviously because the former case includes two rather than one tower in service.

The outflow through the diffuser/Outfall 101 for the operation of Unit 1 and Unit 2 is about 11 cfs (21 percent) higher than that for the operation of Unit 1.

The outflow through the SCCW discharge/Outfall 113 for the operation of Unit 1 and Unit 2 is about 35 cfs (13 percent) higher than that for the operation of Unit 1.

(iii)

Distribution of Plant Discharge Among the Outflow Points The fraction of the total plant discharge evaporated into the atmosphere by the cooling towers increases from about 8 percent for the operation of Unit 1 to about 14 percent for the operation of Unit 1 and Unit 2.

For the operation of Unit 1 and Unit 2, the fraction of the total plant discharge released to the river via the diffuser/Outfall 101 remains roughly the same as that for the operation of Unit 1, about 15 percent.

The fraction of the total plant discharge released to the river via the SCCW/Outfall 113 decreases from about 76 percent for the operation of Unit 1 to about 71 percent for the operation of Unit 1 and Unit 2.

H-15. Thermal Description and Physical Impacts. Provide the calculation package for all runs that support the application (CORMIX or other models). Include electronic copies of all input and output files.

The response presented herein focuses exclusively on the calculation package supporting the results summarized in Section 3.1.1 of the FSEIS (TVA, 2007). The calculations were made using a hydrothermal model developed by TVA that simulates the unsteady, combined operation of the plant and Tennessee River over an extended period of time. In this case, the simulations were performed over a period of 30 years, corresponding to recorded hydrology and meteorology from 1976 through 2005. Other basic aspects of the simulations are presented in the FSEIS. It is emphasized that the plant is assumed to operate in a normal mode throughout the simulations. For this operation, thermal impacts El-18

occur in the Tennessee River for the discharge from the diffusers (Outfall 101) and for the discharge from the SCCW system (Outfall 113). Mixing of thermal effluent from Outfall 101 is estimated based on the behavior of the thermal effluent observed in a physical model study of the discharge diffusers (TVA 1977a; TVA 1997b). Mixing of thermal effluent from Outfall 113 is estimated using CORMIX. In terms of the CORMIX simulations, the following additional comments are provided:

CORMIX Version 3.1 was used in modeling the mixing from the SCCW/Outfall 113. The original runs were made in 1997 and updated in 2004. This version of CORMIX accepted input only via keyboard entry. The desire, however, was to examine the thermal impact of the SCCW based on multiyear simulations with hourly variations in river conditions and meteorology. Hourly computations, however, could not be performed in a reasonable manner with a keyboard-entry model. To overcome this issue, CORMIX simulations were performed for a limited number of cases encompassing the expected range of conditions for the river and plant. The results of these simulations then were used in an interpolation scheme wherein the hourly instream river temperature rise due to the discharge from the SCCW system was computed based on the prevailing hourly conditions of the river and plant. The interpolation scheme was based on five key parameters: river depth, river flow, ambient river temperature, SCCW discharge, and SCCW discharge temperature rise above ambient river temperature.

A rectangular shoreline surface discharge into a rectangular river channel was assumed for the SCCW outfall for all cases. In order to preserve the initial momentum of the flow from the outfall, the height and width of the modeled outfall were varied such that the depth of the discharge was equal to the difference between the river elevation and the elevation of the outfall invert (665 feet msl), with the width adjusted so that the cross sectional area of the outfall was equal to that of the 15-foot wide by 10-foot deep rectangular outfall. The modeled outfall depth thus varied from 10 feet to 18 feet, with corresponding widths of 15 feet and 8.3 feet, respectively.

" Values of the five key parameters for the interpolation scheme are as follows:

River Depth (Elevation)

1. El: River depth 3.3528 m (11 feet, corresponding to WSEL 675 feet msl)

River width 365.76 m (1200 feet)

SCCW outfall depth 3.048 m (10 feet)

SCCW outfall width 4.572 m (15 feet)

2. E2: River depth 5.7912 m (19 feet, corresponding to WSEL 683 feet msl)

River width 365.76 m (1200 feet)

SCCW outfall depth 5.4864 m (18 feet)

SCCW outfall width 2.54 m (8.3 feet)

River Flow

1. R1:28cms(989cfs)
2. R2:113 cms (3990 cfs)
3. R3:226 cms (7980 cfs)
4. R4:1300 cms (45900 cfs)

El-19

Ambient River Tem,

1. T1: 4.0000C (39.2°F)
2. T2: 15.5560C (60'F)
3. T3: 28.3330C (83°F)

SCCW Discharge

1. Q1:9.472 cms (334 cfs)
2. Q2:7.634 cms (270 cfs)

SCCW Discharge Temperature Rise above Ambient River Temp

1. D1:3.0°C (5.4°F)
2. D2:6.5°C (11.7°F)
3.

D3:11.50C (20.7°F)

4. D4:24.0°C (43.2°F)

Support materials in response to this RAI are found in the following attached electronic folders:

H-15_CORMIXSimulations: Input and output files for CORMIX simulations that were performed to implement the interpolation scheme described above.

H-15_HTSimulationsFSEISJune_2007: Code for the hydrothermal model used to perform the multiyear simulations presented in the FSEIS, and the appropriate input and output files.

References (previously submitted)

TVA, 2007. Completion and Operation of Watts Bar Nuclear Plant Unit 2, Final Supplemental Environmental Impact Statement. Tennessee Valley Authority, June 2007.

TVA, 1977a. Effects of Watts Bar Nuclear Plant and Watts Bar Steam Plant Discharges on Chickamauga Lake Water Temperatures. Tennessee Valley Authority, Division of Water Management, Water Systems Development Branch, Report No. WM28-1-85-100, February 1977.

TVA, 1977b. Results of Hydrothermal Model Test of the Multiport Diffuser System Watts Bar Nuclear Plant. Tennessee Valley Authority, Division of Water Management, Water Systems Development Branch, Report No. 9-2013, May 1977.

H-18. What is the current expectation for blowdown discharge for operating WBN Units I and 2? The 2007 TVA EIS states "For the original heat dissipation system, the maximum discharge from the plant diffusers due solely from blowdown from the cooling towers was expected to be about 50 cfs for the operation of one unit and 85 cfs for the operation of both units (TVA 1977b)."

The results of model simulations presented in Table 10 of the response for H-14 provide the current expectations for blowdown for the combined operation of Unit 1 and Unit 2. In these simulations, the blowdown from the cooling towers is given by the discharge from El-20

Outfall 101. Depending on seasonal conditions, the results suggest that the blowdown will vary between about 54 cfs and 70 cfs.

H-21. The ER states (p. 52) "Operation of Unit 2 along with Unit 1 would result in an increase of raw water intake usage at the IPS by an estimated 33 percent compared to sole operation of Unit 1." Why does water withdrawn at the IPS only increase 33 percent for a doubling of the amount of cooling needed?

TVA's original estimate of a 33-percent increase was based on the best understanding of heat loads and system flows in 2007 with the expectation of the need for 4 ERCW pumps and 2 RCW pumps for two-unit operation. Based on modeling and actual calculations, TVA now estimates that dual unit operation will require 2 ERCW pumps and 6 RCW pumps, representing a 44 percent increase in raw water intake usage. Attached is a more detailed analysis of the cooling water requirements.

H-25, What is the concentration of total dissolved solids in the water discharged from the cooling tower basins through the diffuser? How does this compare to the concentration in the intake water Attached is an Excel data sheet with the total suspended solids (TSS).values for the water discharged from WBN via the diffuser or Outfall 101 (H-25 Discharge TSS), The data provides the date collected, date analyzed, time collected, time analyzed, the TSS value and if the TSS value is an excursion. TSS at the outfall is monitored per WBN's NPDES permit.

Attached is an Excel data sheet with the raw water turbidity (H-25 Raw water Turbidity) at the IPS. TVA does not sample for TSS in the intake water and has no way of comparing the intake water data with the diffuser discharge TSS.

H-26, On one of the tours during the site audit, we visited the onsite landfill and were told it is not currently being used. How will solid waste from operation of WNB Unit 2 be disposed of?

Solid waste (excluding radioactive and mixed waste) from the TVA WBN Unit 2 operations will be disposed of at the Rhea County Municipal landfill. Disposal of solid waste at the Rhea County Municipal landfill at the time of this response is more economically favorable to TVA; however, regardless of economics, TVA reserves the right to utilize the onsite landfill.

The landfill is operated in accordance with Watts Bar Nuclear Plant, Unit 0, Environmental Compliance Manual, Chapter 11, Non-Radioactive Solid Waste and Demolition Waste Landfill, Revision 0006. TVA maintains an active permit from Tennessee Department of Environment and Conservation (TDEC) Division of Solid Waste Management for the onsite landfill, Demolition Waste Landfill Registration No. DML 72-103-0025.

H-28, Provide an update of Table 3-10 of the 2007 EIS that reflects changes in chemical use and site operations since closure of the sewage treatment plant and change in chemical use at the site documented in the April 2009 letter, "Watts Bar Nuclear Plant (WBN) - National Pollutant Discharge Elimination System (NPDES) Permit No. TNO020168-Request For Raw Water Treatment Modification." Letter from Darin Hutchison to Mr. Vojin Janjic.

E1-21

Table 3-8.

History of Betz Chemical Treatment of Raw Water at WBN 1996-Present Chemicals Chemical Start.Year

.End Year Syste Clamtrol CT1300*

1996 1998 ERCW/RCW Spectrus NX1104*

1998 Present ERCW/RCW CopperTrol CU-1 1996 1998 ERCW/RCW Biotrol 88P 1996 1998 ERCW/RCW

  • Vendor global chemical name change from Clamtrol CT1 300 to Spectrus NX1 104 in 1998
    • ERCW = Essential Raw Cooling Water; RCW = Raw Cooling Water Table 3-9.

History of Nalco Chemical Treatment of Raw Water at WBN 1996-Present1 Chemical Start Year End Yearstem H-901G 1996 2009 ERCWO/RCW Coppertrol 1996 1999 ERCW/RCW PCL-10Z 1996 2002 ERCW/RCW PCL-60K 1996 2002 ERCW/RCW PCL-401 1996 2007 ERCW/RCW Towerbrom 960 1999 2009 Cooling Tower H-130M2 2002

.2002 ERCW/RCW MSW-.109 (vendor changed 2003 2010 ERCW/RCW chemical name to C9 in 2010)

H-130M.

2004 2004 ERCW/RCW Coagulant Aid-35 2004 Present ERCW/RCW H150M 2005 Present ERCW/RCW Liquid Bleach(alternati 2007 Present ERCW/RCW ve for H-901G)

Nalco 73200 2007 2009 ERCW/RCW (replace PCL-,

401)

Flogard MS62095' 6 (alternative 2009

-2009 ERCW/RCW MSW-109)

Depositrol PY5200 5, 6 (replaces 2009 Present ERCW/RCW Nalco 73200)

Inhibitor AZ8100 5, 6 (replaces Nalco 2009 Present ERCW/RCW 1336)

Spectrus BD1500QQ 6

(replaces Nalco 2009 Present ERCW/RCW 73551)

Towerbrom 60m5, 6 (replaces 2009 Present ERCW/RCW Towerbrom 960)

Spectrus OX12005, 6 E1-22

(replaces Nalco 2009 Present ERCW/RCW 901G)

Spectrus DT1404' 6 (replaces Nalco 2009 Present ERCW/RCW CA-35)

Spectrus CT1 300f" (replaces H 150M) 2009 Present ERCW/RCW

-OR-Spectrus NX1 1045" (replaces Spectrus 2009 Present ERCW/RCW NX104)

Bentonite Clay5.6 2009 Present ERCW/RCW C91-1 (vendor changed 2010 Present ERCW/RCW chemical name from MSW-109, 2010) 1 Known as Calgon Corporation, 1996-2001; Ondeo-Nalco, 2001-2003; Nalco, 2003-present 2 H-130M used with no detoxification in 2002 3 ERCW = Essential Raw Cooling Water 4 RCW = Raw Cooling Water 5GE Betz 2009-present. TVA chemical vendor change with the new suppliers products being "similar" products containing "essentially the same chemical" as previously approved by the Tennessee Department of Environment & Conservation (TDEC). April 15, 2009 letter from WBN to TDEC, Vojin Janic, Watts Bar Nuclear Plant System - NPDES Permit #TNO020168 - Request for Raw Water Treatment Modification Chemicals previously approved under the former vendor may continue to be used. April 15, 2009 letter from WBN to TDEC, Vojin Janic, Watts Bar Nuclear Plant System - NPDES Permit #TN0020168 - Request for Raw Water Treatment Modification Table 3-10. Potential Chemical Discharge to NPDES Outfalls at WBN 101 Diffuser Discharge Ammonium Hydroxide, Ammonium Chloride, Alpha Cellulose, Boric Acid, Sodium Tetraborate, Bromine, Chlorine, Copolymer Dispersant, Ethylene Glycol, Hydrazine, Laboratory Chemical Wastes, Lithium, Molybdate, Monoethanolamine, Molluscicide H150M, Oil and Grease, Phosphates, Phosphate Cleaning Agents, Paint Compounds, Sodium Hydroxide, Surfactant -

Dimethylamide and Alcohol, Tolyltriazole, Zinc Sulfate, Zinc Acetate Dihydrate, LCS-60.

Post-Oct 2008, Potable Water (Cooling Tower at Training Center), Superior SWS 4550.

102 1 YHP Overflow Weir Alternate discharge path for Outfall 101 Ammonium Hydroxide, Ammonium Chloride, 103 LVWTP Boric Acid, Sodium Tetraborate, Bromine, Chlorine, Copolymer Dispersant, Ethylene E1-23

Glycol, Hydrazine, Laboratory Chemical Wastes, Molybdate, Monoethanolamine, Molluscicide H150M, Oil and Grease, Phosphates, Phosphate Cleaning Agents, Paint Compounds, Sodium Hydroxide, Surfactant - Dimethylamide and Alcohol, Tolyltriazole, Zinc Sulfate Metals - Iron and Copper, Acids and Caustics, Ammonium Hydroxide, Ammonium Chloride, Boric Acid, Sodium Tetraborate, Bromine, Chlorine, Copolymer Dispersant, 107 LP and ULP Hydrazine, Laboratory Chemical Wastes, Molybdate, Monoethanolamine, Molluscicide H150M, Oil and Grease, Phosphates, Phosphate Cleaning Agents, Sodium, Sodium Hydroxide, Surfactant - Dimethylamide and Alcohol, Tolyltriazole, Zinc Sulfate Chlorine, Organic Matter, Laboratory Chemical Wastes, Paint Compounds (pre-Plant 2008). WBN connected to the Spring City POTW in August 2008 and the Outfall was completely decommissioned in Oct 2008.

Chlorine, Organic Matter, Paint Compounds, Potable Water (Cooling Tower at Training Center), High Pressure Fire Protection flushes. Post-Oct 2008, this outfall no longer received OSN 111 effluent. Potable water and Superior SWS 4550 were re-routed to 112 Runoff Holding Pond OSN 101. Internal study of time for de-toxification of quaternary amine residue found in High Pressure Flushes yielded immediate de-toxification when the water made contact with soil prior to reaching the receiving stream feeding into the pond. In April 2009, WBN petitioned TDEC for TMSP coverage only.

Severe Accidents SA-1. As discussed at the site audit, provide MACCS input and output files for Watts Bar Unit 2 that include analyses for all severe accident release classes including the release class or classes in which radionuclides are released to reactor containment and containment remains intact.

Attached is the report for the Loss of Coolant Accident with containment intact. The MACCS files are also attached. The report concluded that overall the risk results are small.

SA-2. As discussed at the site audit, provide a discussion of the potential risks associated with external initiating events and accidents that might occur when the reactor is not at power and the relative frequency of such events and accidents.

E1-24

WBN has not performed a low-power shutdown Probabilistic Risk Assessment (PRA).

Currently for Unit 1, risk during low power and shutdown conditions is controlled by an outage risk management program based upon the qualitative defense in depth guidance given in NUMARC 91-06. WBN uses EPRI's ORAM-Sentinel program to track the safety function requirements prescribed in NUMARC 91-06.

Risk during shutdown from external events is bounded by the at power Individual Plant Examination of External Events (IPEEE) model. WBN performed an IPEEE for Unit 1 operation to identify any vulnerabilities to severe accidents from these events. The IPEEE for Unit 2 is currently in progress.

To address seismic events, WBN performed a Seismic Margins Assessment in accordance with EPRI NP-6041-SL for Unit 1. This analysis did not identify any adverse spatial interactions or components with a seismic capacity below the reference level of the Review Level Earthquake which is 0.3g. Only 4 components types had High Confidence Low Probability of Failure values below 0.4g. WBN expects that when reviewed Unit 2 components will also meet this standard.

TVA performed an analysis of internal fires using the Fire Induced Vulnerability Evaluation methodology for Unit 1. The evaluation results determined that core damage frequency (CDF) for fire areas would be below 1 E-06. WBN expects that when reviewed the CDF for Unit 2 fire areas will also be below 1 E-06.

WBN performed the screening review described in Supplement 4 to Generic Letter 88-20 and NUREG-1407 for Unit 1. A review was performed to determine if any changes around and at WBN had taken place since the issuance of the Unit 1 operating license in November 1995. The evaluation at the time revealed that the plant met the Standard Review Plan criteria and only one recommendation for plant improvement resulted. This recommendation was to modify an Auxiliary Building concrete canopy to provide additional protection against tornado missiles. This modification has been completed. This modification was to the Unit 2 side of the plant and is effective for both units.

The status of high winds, transportation and nearby facilities accidents remains similar to when the original review was performed. Since the time of the original IPEEE evaluation for external flooding an issue has been identified that resulted in an increase in the calculated Probable Maximum Flood (PMF) level for WBN. There has been a project underway to widen the locks at the Chickamauga Dam downstream of WBN. The temporary configuration during this construction period has resulted in some of the spillways credited in the flooding analysis being unavailable. The reduction in the number of spillways has caused the PMF level to be increased to 738.8 ft. This has been documented in the WBN corrective action program in Problem Evaluation Reports 211722 and 154477. The corrective action is implemented in AOI-7.01, "Maximum Probable Flood," which invokes the performance of MI-17-004, "Movement of Equipment Flood Mode Preparation." This MI installs temporary flood barriers around the Unit 1 thermal barrier booster pumps in accordance with temporary alteration TACF 1-09-0006-070. The issue will be examined in the Unit 2 IPEEE with a similar expected outcome.

E1-25

Severe Accident Mitiaation Alternatives (SAMA)

SAMA-1. As discussed at the site audit, provide a discussion of the extent to which the January 2009 assessment considers the risks (core damage frequencies) associated externally initiated events and events that might occur when the reactor is shut down.

As stated in the submittal the SAMA PRA model used is an internal events including internal flooding, at power model. A multiplication factor of 2 was applied to the internal events results to account for the contribution to core damage from other events. The factor of 2 was based on a review of the SAMA submittals for a number of plants and previous practice at WBN when preparing submittals involving risk applications such as Technical Specification (TS) Completion time changes. The NRC accepted this methodology for these submittals.

SAMA-2. As discussed at the site audit, provide a discussion of the bases for estimating the costs of implementing design alternatives for the January 2009 document.

The costs of design alternatives were determined by estimating various parameters including but not limited to the cost of the equipment and materials, potential cost of shipping, costs of engineering, labor costs, cost of operation personnel support, cost of procedure changes, cost of training, cost of Radcon personnel support, cost of security support, taxes and contingencies. Costs were estimated by upgrading previous Unit 1 estimates, completing new cost estimates by the WBN Engineering/Construction organization, or by using cost estimates from similar studies at other plants.

SECPOP2000 V3.12 was used for the MACCS2 Site Data File for Watts Bar. To account for inflation, economic values were escalated (1990 to 2007) using the following method.

The year 1990 was assumed to be the benchmark of all dollar input values, the CHRONC input file was compared with sample data that references NUREG/CR-4691, and the values were identical.

All of these input values are in units of dollars per human or land unit. The original data was assumed to be based on 1990 values. To adequately project the dollar values to the year 2007, an inflation factor of 1.555 was used to multiply each of these values.

U.S. Department of Labor annual consumer price index (CPI) values per year from 1990 to 2007 for the Midwest region was used to calculate the inflation factor. The 2008 annual value was not available due to this analysis being performed before the end of the calendar year 2008. A CPI is a measure of the average price of consumer goods and services purchased by households. The percent change in the CPI is commonly used for inflation.

The CPI can be used to index (i.e., adjust for the effects of inflation) wages, salaries, pensions, or regulated or contracted prices.

To find the correct multiplier to represent the cost increase from 1990 in 2007:

Annual CPI 2007 / Annual CPI 1990 = 198.12 / 127.4 = 1.555. The multiplier 1.555 was then applied to all costs that needed to be updated from 1990 to 2007. For example, the value of the input variable CHEVACST001 was updated as follows, CHEVACST001 in 1990

27.00 dollars/person-day, 27.00xl.5551 = 41.9877, therefore, CHEVACST001 in 2007

42.00 dollars/person-day. All other identified costs were updated in this manner.

E1-26

Terrestrial Ecology TE-1. As discussed at the site audit, provide a map of terrestrial habitats on the WBN site, including wetlands and streams.

A map showing wetlands and streams is attached.

TE-2. As discussed at the site audit, provide an updated list of federal-and state-listed species that may occur on or within 1/2 mile of the WBN site and transmission corridors.

Attached is an Excel file that lists protected species within 3 miles of each of the 500-kV lines that originate at WBN.

TE-3. Provide updated distribution and abundance information describing known occurrences of federal-and state-listed species within 1/2 mile of the transmission corridors that service the WBN site from the site to the first substation.

Attached is an Excel file that lists protected species within 3 miles of each of the 500-kV lines that originate at WBN.

TE-4. As discussed at the site audit, provide a list of and distribution information on exotic invasive species that may occur on the WBN site, within the transmission corridors, and within 1/2 mile of the WBN site and the transmission corridors.

Field reviews have noted the presence of the following non-native invasive species: Autumn olive, Chinese privet, Japanese stilt grass, Japanese honeysuckle, and multiflora rose.

These species along with other commonly occurring invasive plants such as kudzu, mimosa, princess tree, and tree of heaven could be present around the WBN reservation.

Radiological Protection RP-2. As discussed at the site audit, dose to biota was calculated in the 1978 NUREG-0478.

However, this analysis cannot be validated using the current guidance. The following information is needed to meet the intent of NUREG-1555, ESRP 5.4.4 (1) Identify the representative biota for the area (see ESRP 5.4.4).

(2) Identify the pathways of exposure to the biota (3) Based on the above, perform dose calculations to biota using the radioactive source term used for the human dose calculations As discussed during a phone call between NRC and TVA on January 7, 2010, NRC staff will use information previously submitted by TVA to complete this analysis.

E1-27

Transportation TR-2. In Section 3.16 of the TVA 2007 EIS, the applicant refers frequently to "tons" of new fuel.

Confirm that the unit is "MTU".

This is tons of new fuel assemblies including the slightly enriched uranium fuel and the nozzles, guide thimbles and grids that support the fuel. There is about 1,014 Ibm (460 Kg) of uranium in a single fuel assembly. Each fuel assembly weighs about 1,500 Ibm (or 680 kg).

E1-28 TVA Watts Bar Nuclear Plant Unit 2 List of Files File Name File Size - Bytes TVAWBN-2_Files H-11Files 001_H-1 WTVAWBN-DC-20-20 (Travling Water Screens) 117,388 012_H-1 T-VAWBN U2 RAIH-1 lIntakePumpingStation VelocityRev1 75,312 Total 192,700 H-12_File 002 H-12 TVA WBN SCCW Velocity 72,484 Total 72,484 H-13_Files 001 H-13 TVA WBN ARI 159 165 R34 103,063 001 H-13 TVA WBN SOI-27.03 R25 180,043 Total 283,106 H-14 File 001 H-14 TVA WBN TABLES 88,523 Total 88,523 H-15_Files 001 H-15 TVA WBN Cormix nonruns 25,897 002 RAI H-15 TVA WBN CORMIX SIMULATION Files Not PDF 003 RAI H-15 TVA WBN HT Simulations FSEIS-June 2007 Files Not PDF Total 25,897 H-25_Files 001 TVA WBN H-25 discharge TSS 49,076 002WTVAWBNH-25_WBN Raw Water Turbidity 68,889 Total 117,965 SA-1_File 001WTVAWBNSA-1_Final-WBN-DBA LOCA Analysis-January-10 197,294 Total 197,294 Page 1 of 2 TVA Watts Bar Nuclear Plant Unit 2 List of Files File Name File Size - Bytes TL-1_Files 001 TVA WBN TL-1 BULL RUN-WATTS BAR KX 6059 37,589 002_TVAWBN TL-1 SEQUOYAH-WATTS BAR HP CL 5047 31,529 003_TVAWBNTL-1 WATTS BAR HP-GREAT FALLS KX 5173 31,884 004 TVA WBN TL-1 WATTS BAR HP-ROCKWOOD KX 5791 32,831 005 TVA WBN TL-1 WATTS BAR HP-SPRING CITY KX 5733 28,984 006 TVA WBN TL-1 WATTS BAR HP-WATTS BAR 1 CL 5127 30,158 007 TVA WBN TL-1 WATTS BAR NP-SEQUOYAH 1 CL 6080 31,444 008WTVAWBNTL-1 WATTS BAR NP-SEQUOYAH NP 2 CL 6081 27,211 009WTVAWBNTL-1 WATTS BAR-ATHENS CL 5645 32,070 010 TVA WBN TL-1 WATTS BAR-ROANE KX 6084 33,225 011 WTVAWBNTL-1 WATTS BAR-VOLUNTEER KX 6092 -

44,309 012 TVA WBN TL-1 WINCHESTER-WATTS BAR FP GF 5167 28,881 Total 390,115 BC-2 H-5 H-21 L-1_ L-2_ TE-1_ ANDTE-2 Files 001_-VAWBNBC-2 WBN2 Operating Annual Estimates 2008 62,249 001 WTVAWBNH-5PondWSEL_2001 456,174 001 TVA WBN H-21 Plant water Flow Info 170,944 001WTVAWBNL-1 LULC 11 7 2009 Final 30,464,887 001WTVAWBNL-2 WBNLULCAcres 51,658 001WTVAWBN TE-1 Wetlands Streams 30,381,462 TE-2 and 3 BLN500KVTLs ProtectedElements_3miradius (2)

Excel Spread Sheet Total 61,587,374 Total 124,585,496 Page 2 of 2 TVA Watts Bar Nuclear Plant Unit 2 List of Hard Copies File Name Number of Pages H-11_Files 002 H-11 TVA WB WBN 31N220-1 1

003 H-11 TVA WBN 31N220-2 1

004 H-11 TVA WBN 31N221-1 1

005 H-11 TVA WBN 31N221-2 1

006 H-1 WTVA WBN 31N221-3 I

007 H-1 WTVA WBN 31N221-4 1

008 H-1 WTVA WBN 31N221-5 1

009 H-11 TVA WBN 31N221-6 1

010 H-11 TVA WBN 34N210 1

011 H-11 TVA WBN 38N200 1

Total 10 H-12_Files 001 H-12 TVA WBN Calc MDN1027-980006 93 003 H-12 TVA WBN WBF 44N203 1

004_H-12WTVAWBNWBH41N515 (Cal) 1 005_H-12WTVAWBNWBH 48N202 (Cal) 1 Total 96 H-14_File 001_H-14WTVAWBNFigure I

4.

Page 1 of 1

H-li Figures

I

~-OZZNS I'

SECTION A2-AZ IM'T TI/IS CPA IV/ND WATER SUPPLY UNITS IA Z INTAKE FUMPING STATION CONCRETE GENERAL OUTLINE FEATURES SHEET 2 WATTS BAR NUCLEAR PLANT TENNESSEE VALLEY AUTHORITY I Tp-o7.-wT-I - I - 1,awý,, I I T" 7

'M J31 I

I i*

i I

i i

i*,-. i

  • I **

0-1 LI

ý I NA*ce E -

f F

EM UTY.

V I

FF17 I

Gzz.z 3 8 -13I202n I

I.TFe T~l-ANP I

J00I I.

1 I

. 19ý0-Rgsu:

I-IZZNIE 1 4-I Iso r-s l~ !l--.-

"I' z'is t'-,

"',* i

~~y1/4I s4v

-all RIVs'

~ '~

~-

S ofees~A~~ M-s,7

-O6,

\\1Aon.

I.-

M z!

aa~ncs 0= 'StAt'!

jsd "SCOe'Oe5S 0055555 nea i~5 &

I z'r

,~

eorm COrd-'

5*555500.

atAri

osen, j~'O9O

~'PAN

  • S n,~ j45V J.

W~A' n-SObS-'

~~MflC5C OC CiCOSfl'Ov, vo vs,.notm.

Caner An, rn-COres' nosy I

A A00V& 055/059 BflC*C 5W557t7Wt 405 SW Cs, STCersOAt SVSACOCT,.

flsSeAvyCvs SW SW bOSSeS CA-AS I YJ I~ t r

\\H4 snse t sssssse on esen Co sor PLAN EL 728. 0 8 L754.0

/5;K DETAIL cI

[FTI ancovAsi CO* SW05C SW a asstz ~

54590 WeSt 590 SACCOC SOT, 075905751V0.t o syvon ow 005555-sW 500 SWc'vvc.v swAts C5755'SCO vs vCrss-mCio

,srrarosOtm,'ssc. 5'ssFvsneC Er 555#555'v055v00 tO 155 555.5555 s,.sr-swcscm SWC ACvrev a SC CSSWSDASC COCasy 0' AOS ocr sActsSMAcvo 55,40 CO5,fl55501T CC 'SOS 00W StMvs'Avse 055C9 055 0C5S5Wv59T 555 OtisrsffC 0905 on,- 55 o90avrv-CC 95555ev nOv A5*55s5 a' vs's 05-C.

08.555W met a, CZCAASO 09051 5055 inS ices,-

555tn'cvs CiSC 5*00050.

455FF vA, it* is. 520

-Se an,,

1 I

I Eon?

i s,

- io

  • I
  • =:*..*..-..*(.,,*.gm
  • .m.,*r*

I hIve'

'500.'

I" t"'

z*

r"*

c t.

, r*

Cs

-*5 COO

.I

~"It e

°"

7,47"7 el a*:;;',%;

sos','!'.

5 CSSC lsCn'C 55'dSCvAS 555 55095-MA CA,05,'C S5PXT5t5C AC5CCW!

AMiss At L5Aa SCAS 000 SW SAT, flit iMP cites o' CO tints. SWIC5Cv5 SW Asses ASCOt ft rite SCAtSS5 asS A avAs sCes A-s vsv ns,5.CC,.

CvCCOCCS Ate ACOOCS COCts 1-eseta' on"Coves,,ssSCC.

toss (MACDOSS XCCCO ACOCAC 005 APSXeCCCC 50/550 ACI7S OCt MOS5OCACSSAC5I5 C55.e5555.

A 555 WaCO ACit COrOnA SAC SAPS5SCA 550W/CO AsIAN.

C /55 CCOeCC550 non'. sea, sA COeSSeSS.

Ass ststeaMOt 0750, viCCisvs5 CC aeCvcSas 05555£ v ens.'svse CC PXAsrSss es 55710 5056. SW 055,5000 CC A'SSCCSSCS SOC 5~5A5 tAOS SW 05004.

A SW 05550 CO 5555 esC SpOts AS SPAS ASCO 45*'ASSA-5.

a SW eaveas oCOC7,tCCOce' Anevovy, $55 OviSt.

en OAsvseee MA" OC 5-555,5 90 Ct 7555 CCSOO vs 550500 sMCLOCi assla am a no,-CO CCC AvesevnC a00 Ce Cse.5.. eon ASS CLCCCS5eA P500 Pe Cees P55 CCC wnenn=ess.sse>

viCsCS5AeoOsCsiCe TCCO.AOA COO

'0 OtisS 055CC s.C seAr *C SQOAYCeIeC5 Sc-SPA tee avisSCo'Ae UNIT 1 ONLY I

AWS' As-C 0

WOTES SCC9Cv'

,So 6.

St 5-A....A..

JA*

!S..

.i4I05 II C O !1-

'IC 090 1

C; Steel

~ ~

~

~

-A

-'I'~

~

'e e

C/

c 090"' [ "

.f,;:an.-o r47-I -A. Ave*'-,-,,-A o,-o,

.5.,

" *T IL c/

191" a/

1.

Af-t

" 'C' ret r.si

Ate,

<Ce teeAIesevet tCC.C' aeAAvSPPC roan

~

oAStA~.e's ff1-PA NI-hO aieC,p~c,-

MACE 5, e's Ce ~

2000905 CAIrO evEns, no RI-A'!

WATER*1 SUm*_y UNMTS I&Z CONCRETE INTAKE PUMPING STATION OUTLINE WATTS BAR NUCLEAR PLANT TENNESSEE VALLEY AUTHORSTYI

Al-/,l MS-SI JI-d/

0/-0/

-i

-s~

IZ~Ze'* 6-LI I

I It 1srsAtCe

.ev 151 I. I 3iNZ~li v

I

,L L*J i

i

..-.--.5

-~AS ~S~UCTE11~

.-1

  • ~tS'.--s.-'S.--

90

  • ~=~s~£e.-~

~

I

.1 CZS...7.,Z

-'e.

'mn"Y'e-,v-0 e.

I-OGZNIS I,'I-I" 4rC 1 Ia aSI~fnraV tA!Fý F71W.

~

~

£4atVa

.U n

rs I~

,all.

I

~ ~

,,I F-1 I~ F

,j II PLAN E1 728.0 9 EL 741.0 SETONA PLAN Al -Al 00NT S HI RAII WATER SUPPLY UNITS I2 INTAKE PUMPING STATION CONCRETE GENERAL OUTLINE FEATLRES SHEET I WATTS BAR NUCLEAR PLANT TENNESSEE VAULEY AUTHORrTY LJ~

FSAR FIG 3 a 4-50 XNQ-7 931 C 141 31N220-1 n

I e-Io(2.NIL VI'1'I 5055 00500500'CAcj SOSfIMO d-IddNIL I" - 1 1 ýI A";

000o3005

,.-.0 05.050,0 OS£550 050 O3Ota os i~ ~*Zr~

Ot tO

~~~

~ctSov Ti1.000]500

'1 I

I-Il-05 I

F

-I 0005

,O~

A'050

-o 1

$000 I-7 FT.

-P CON$7ý's e-t

~rt&~

s U

Zr-r00

-c 50 o

84oa fS

o.

r 00 IV 1:1'.-

csctoos ly~

-v55 50 SOSZO05

,~ {

L ' o~t tt S 0 005 5 5------0----------0CAS S 5 05 W0,5

[

00 5

45 1S S005

-St tOO 0

-i-i-

&S~O/I_-

T j T

1.

7 O~Lfo~0,55

.50 05'S OStOSO I

tote

-'--007-070

&oAS2StXt D2_______

o~otoo I

atoo,00V017 jt~t~t j

OW~t20taWOsL AZ0 h ~

t

.~-

zt cel StOtcOoOttA' -

~

005 ostt-ctL

  • 0,0 (Stotot)-, ~

.. t4o....J 00055 S~L0 5000 K050t. OSLO' Cososot)

DETAIL AZ 8 82 05000 f.otO 5

.4~t 0000005 OtALek. (-0'.

0000," OW SECTIONAL PLAN A2-A2 L

o,

-0 A42-A22 4

~00.-

If F Re RI 00 SO If'"711 -11 1 jc 000005014]

14-L 11o1_

[~ ~ Lii0/0.1 0002 I*,-OW-It-.-

.I r'I J

I*:

I" 00000

.0.0.

O"tt.

I T-70, OS0tO000500 o7010 DFT41L 0t?

02.* $5 "0DZ0000.

¢*¢r~urte S*-'*W.-IO 0,ATOO SUO0LY ONTO I 02 2.I

~tooc~tt 0271 5-OO~c-A 011Ooco

,1110r, Lo ol zz-EZ S

CONCRETE iNTAKE PUMPING STATION OUTLINE WATTS BAR NUCLEAR PLANT TENNESSEE VALLEY AUTHORITY NTER ETEPLY 0

0 0 t.~0'SO0St-cO-

.'--0,0SSS 00/ ocOtccOSIO-'

5 5) s-p -. so.,'s-- ~ 000 500 gA{2oLo4.- 0~

I 81-8z 7,Z,ý

=

'Z7 L

KNO-El ~ ~ ~ ~

7 4-1-4 I,

,I N21-I r~

r r

I AS CONSTRUCTED c'

':Vý I'D F2 r

r I

oSO~or.-----

-AAA ZNli:

L so-sos a-c owr B11..o

£ C "w

1 i"

_coward.,

0-f srj r

cO:,

L,,:,

r, N

aL/C/A /0000CT n~m N. 0/

SHOW tCM L4 II o,*-* v a. *..

OrLO~ I P/TCLOEji 00400011 cowad FI Aor~no)-5 4A4 row4 A3'sT]

~O'/tO~p

  • ~

~

~

~

~

~

~

F Arro-IO r*

po o

wK I-a oo-wreds

/4 Alsas-towr L*oMA~s TA/Ot

/ l: "

"If 0007 0000r 00#

E0700000ON SP OLOOEOCFON aowoor 0/wo Ot £oo, SEE EOo~sr~ocrOOO OOEMOEOCATON C-,a R P/O

4-I I

ON A*a

-w OP0NO N

TLO---

Mors w-r---

~04oO-

[*. ~C L:

V d/~ /i

$T*f I

00I AlI owrr

:, 4... EAL.S,

i II-II 0000-7 L 0&L 3-L3 1.UNIT 1 ONt

  • ~I V

N 13 -. 13 CONCRETE

~INTAKE PUMPING STATION..

  • OUTLINE co~* c*w,:*,*t-,vas WATTS BAR NUCLEAR PLANT TE-NNES.*SEE.

VALLEY AUTHORIT m

-_w K340 $ Z3-L3 JS-'S A4tL

ý11,1 I0C/CLP000.

M 0M4 5p0.p 3

Byfl C3

'F---3--1

'3" a'..""

"I 7

" : "II

  • /

I~l*l. :1:

l'%Z

~1ZZi 2400/dr A4 10*-4

-- S M -S MCO'.40400P0 MR4 f.__i "I -

r

/OP i

ý __ý _ý.

\\\\

i

-C3 PLAN EL 663. 0 r3l-,'

~ ~~........

M-7f I.

I g ZXsw7Vqql

- jo I

I AS UUNMI*UUILU I

k-I~~NIE I' I' I~I C2 831 e

I Il

"° *

-a - ---..

F- I-..

II A4 A4

, % - --- '-T

-- -4 "r--; z IA 84 I",

2 C41 rEt 7550 1

s,'S "

L-3/4

,C45SThrEc 74.c-.-sj

~~0~I~.

i4-Du Ll

]

II

'Q\\Ji s 1I'

~

't ri V

~

ts I--

V\\..

- ~

II.*

r.s-

'I

[. L D4.c

,55 4

45,-

5.

'ExI I

55*...

re PtAN Et 652.0-mr-C

  • t S-Ii

~

5550 ii' 50 ill-G4 Z5 4 5 j]\\q Ji 45,5 G#-G4~~~~

--q'H

~"

-6

".C; I 45-5.5,15 (311.555) 51 If j4 -aJ I "

A : iao

&I

[

.I---.2, *

/- " " * *

  • ---*:*-s-*=--=--=-*-s---*

=

-- /

AI-

~

i~_

-5S~Oc44 555l

/*\\"

L1 d e, /\\

I I /

I 5

I I

,\\

',d I

I Vi \\V: V N o

  • 'HssAV N ' V" Ntl=

-I l~*

I-,

1 % I*.

.:J "-J*l II I

5.-

5o 4555 I

  • ~~.*

4,

-' o77 I1..

5,5,1551l 84-B4 Lccr 4..a

-' )

EE StAS-S 45.5 :

WATER SUPPLY UNITS 18 2 CONCRETE INTAKE PUMPING STATION OUTLINE WATTS BAR NUCLEAR PLANT TENNESSEE VALLEY AUTHORfTY

, 1

.......... 7"1

"'I " i-I j

A4-A4

-Ale-ASIA 5,5515...

55755507 5455455,05 ASAlSW.5£SS5~')

l*I t.ii UUIIU I

I'IUU I

e-' -,

r

-&=:-

1ý-

7 I 5-AYS W s

~55j~~I-S.

Ill-A AC flO!sJC.TPIIflT r-1.5

~5 f~ 1.5t.5 -I4 5 p7 5

~

li v v I v li I I % u v I

101

- !.1

( 4 W L O ~I S O

.,E 1

~j AEtno-..+

ac-a -

LVT

'~0 a-Ct 7410

..*~j.-aE O0*;-t;.NO00'

-4 nrolcw Al-ato iocraraas ncrsE not0.TOEOt CW 1,10 007,15 sF07 toors ct-car onrar a no.

a tttOI 011'000.

-- 'O'*-,.

ST*"Ae,

ali, o,1

'En-I"**

t*

~,~,

5-5..

E_

OS..t 01 cotsv,-o E

00 101..

,X**--**

0

1O. -'*

IE o, a.

9 7W

  • .-STOT--"

05 SECTION AS-AS DETAIL 05 05

'Li 4572005 1.-f

~I.

.5-05-I 7--.

1 -

F-I-i C.

S..TA-*

1.

I' OCICIS%*

11 5

.C TCOT.

  • iL' i' 0

i

, S, I

,ett -

"145

-OT4-..,

o O IEE O *OTO2

° i

,t ar r

-E T.Ot~ ~ ~ DEAI

115451, rWOW'l&OTEOS DEIL MT)'1 I,

rL

-~~~LIS I, & Z5.IL ts~

015,041 o n.

n E

5 Q -

.2

-78 000N*N

/

m c*

-II-.:,1 Aon'o.rtY_*,-onW

.:;-i *

-U-N

..,ii -il U

a no 0t-....

I,Th L,--

g* :

ECEJAlTO#

05T,I,

_--____i_____-,_I__________":*

w~S ES-.CE i-- i,

.i A-,a M xn-.-

I LT E-1.

4 41 I

i*,f i i

DETAIL 55 DETAIL F5 OF7XI1 6I5-DErAIL, C5 CONCRETE INTAKE PUMPING STATION OUTLINE.:

IL.

CjSt4rtTTstS5155ytlwAZ WATTS BAR NUCLEAR PLANT V,*-IP*,

Ig~l*.*t i

r TENNESSEE VALLEY AUTHRIT NO.1

,0,' S1

,J'a,*'

I

,OtOI*.

-. 5MA~Lo~.-..--~t t

1- -to5I "Y

'INOVIIEt 15T c

c 3Nl221-55 Rn It~'

1Q11C~t_1050__404-IOIN~

~'AACfI(TF 7

-ý911-Lar-j

-L T

  • .'1. -..

"L,0*",Sj LU F

, U*

L 1

L

_A ~

C w ~

I 9-ISEZN1 1 3 1Igel III III II II 1

I If I I I I

IIIIIIIIIIIIIII II l

l III Illtl Il l

I f

I I

III Il l

l l

1ll III 111111111111111111 1 T ll II I

I l I I I II II I

tl A-H-

74L 74A

~EL 7550 EL PAL EL 04EL7E0O-~

U,

  • .j.

~AStoCs L/SOR~~ SEE 40/5454-A CLEL /SL4,~

EL 054/-.

S 86-a8 ADNAE1 UNIT 1 ONLY I

m -

-3 1

C1 1

SCSLALEO

  • 'A C

ELCEPT AS ~S WATER SUPPLY UNITS I B 2 CONCRETE INTAKE PUMPING STATION OUTLINE 11*~*,o

  • v R -SU" WATTS BAR NUCLEAR PLANT t

TENNESSEE VA.LLY AUTHORITY

,A/.A/ SC S. ///

/f.LI.

..GA IT I Q I

[ic KNOXVILLE q6-33 I I"* I SIN221-6 no i

I I

'I T 7 I

1 '

I I

7

"....1 i

ii

!!!1!

411111

'I'-

IH11111111 IIII AS CONSTRUCTED

OIZNOT 111-1991 1AIS B

v p.AwPlNG 3TArlON DECK PLAN EL 741!0o AM fI....

rZ..

AIW L.A rYPICAL PLAN MK JANZlO'/ 4 RfRO K/dES tOt"p. A, e-N*

0*105~~~

W01..C Wc SrC E.l ASnI ASAS I

..,R ENSON.

537Sf A-5~K.

A~A-S.

Sr no flED SONS V.i'-V AcETANr£ PRESNVO SIAR KEr PLAN SEM. A 400

,WiS P NIA PIEPS LES *iNN.NI I

T.'

WIll R 1,

4 I.-M( - "J-t 51 t

c--

i SSSEl AI t

I.12*41)

'lR!

NA ECAION A -A At..CA/N.0/S.

2

' -*i Ce~t -l 9-i-1 by f-K1/NVI 10 REP((pJ m-ARA NK flON2*,

NP

/E~

AG/

K

,51

!GMRlrNS/S AE I-QUALITY ASSUJRANCE It.AFIT KErO R 0.10 SC*EIIISP A

  • N,,/.

Wl8565 I.

AE EI EMIoEI*pn R.PPARRIEESEN A. IITE mER~I-$

NOENG I*TONIECEWF S. PlA TOJEIRIPC PVAFIET IN FPIND K C*4R81 E N C-C Na I-.- O WATER SUPPLY UNITS I t 2 INTAKE PUMPING STATION B-9 TRAVELING SCREENS ARRANGEMENT TS.a,SEN Rope N ENS -

SO CPU/al 81.51V IRS laNAI RPdt 55,1... 815.

Il C57 4-SEATS I/K R81SJIR INNS. II RRW SR MACSEEd WATTS BAR NUCLEAR PL:ANT TENNESSEE VALLEY AUTHORITY Q

OMz,,S Ce tK.GWI,,,I 045M.

INSTNOTES MN ADONCET ENR REIN EONS" P.JOCT MAGARIR Ii

=

LIAl I -r-e.l~SL 5.NSOEIILLSIS13431551 E S I 34N2IO~o 3NXU*g13"3 51 1I-I 34N210..

00_N9-I

.* -,..1 5-0, SECT..

jr/ OL.

0-0-t CIT1~

F ~

Cl

'LAGILT cL 750'-0 SECT AA 8-8 8

a-

.ELO54S-0"

  • Cr-I "

A f 71 W

I~-~

r-F

.IGO/

me wOoL 4I CeG Jill0/1?

I im I

-1.

WLL 0'Ca TRASH RACA 1fL

.-i ELEVATION A-A, Al-Al. B-B & BI-Al SECTION E-E AL 1,ECIEAON

'01 A4 IA *OO-4' AL $NNCCN A CA-OCL,/.

-GAO A',O3OC..4.

C CA.11/0 WI-AC A-SLI, e AL O/L 05 /S C/RAN A

C O

P*ZO t

0/C LOASE A 1=L OGSLOS-O PEAN OF HORIZONT'AL MRASH RACK ARES/-tACO ELEVATIONl C-C & D-D c

~ ~

L-L

-CLE CALe.COO CL C¢i-RIA F-F& P/-Fl G-G

/*,*.J!F

" T SOAL

.I.0....

LOGELIS.L*

~a 4wr s

e,

S.-LI=

T UC UALC LSTL EL C lt L/-S A-RIC J~CCG

/

ALLGOLLT A/Cý A

ý$WýA/ SL/IAM II.

CL~tA lA ALLICE LSLAý *.GC,OIA A/TA/A/A7 L.

=

SCALI

-3.A-"

-M

-DLL

-OON

/OA/O CL/C 001 C0 (N /00 C

  • MSS RIM4S ICEAGOI 726100 SEc" SCLr.II 0'

C I. IA n.XEP G /

='LE,.S Q.Q, SUCTURAL STEEL N

SE 0/ /410 f/0/4/~

Cf K-A' (CwILOT DEtAIl.

ALL L

O rS 1C*4907 12.00C/

L

-RCW INTAKE PUMPING STATION TRASH RACKS & GUIDES 11 II WATT TEN?

II

=

-,RI-I J

S BAR NUCLEAR PLANT NFSSE.E VALLEY AUTHORITY H*ptot

'ml

-C/.CSICC/I. IOC;LN L-On c

I h

1 1 11 vv ý vvll%)

H-12 Figures

'a W ý0 Fc

-v r

SECTION 0-0 S1-1 t.r-0o

4 I

sEcTI6N A-A A--

F D

CAP ciry.

-O RZCOfO OF -.

1K -S -ONSTrg R.A-r to -k

-ll -o *tl

-V

-~~ N. rV-S50M

[oNO TO SCALE SECTION C-C SR*'A j**-r O" PART ENLARCED SECTION B-8 S'.1. il'.-o'-

T Ci, -I

.cT 4

A lp 7 ZE H,

T-0 D"

12 71[

L-7514 Li t,1j J.

0 qp_

I, ill I It 1, 78'~~~~

!n"-

rf4'

.~

4'8 77 7*

-MA.t2 PLAN A-A 71-I r'--*r A~T 11, pioo" 8

44-I 757707KEY PLAN 7-l' 4j.7-

_j.

ij

"'0' 2'0'

~

~

~

~SCDO D-D SECTION E-F 17-4 77s8480077SC/NLL

,074 SECTIONAL PLAN P to'7,,,.

547 77 07, 777 I

' 0 -tiI O,

r0774,7

,'~7774o48-o-

5,7,

/I 7-7 445774700 77-7,7,48 r,.-

I o470Iibo2 A047,7 f57874o*7q7

~

7 I~~-,

.7

'fl 74777 1

NW7 44, SECT/ON I/-Il74770004

-71 117 4'-

DETAIL D SECT/ON J44 SECTION C CK477.

7840'.4447 POWRHUS SERVICE BAY I-'-.-

I SECTIONAL ELEVATION B-8 DETAIL C

,4

-DETAIL A

DETAIL 8 DETAILP DETAIL E 4*

l * -1

,47 SCREEN HOUSE OUTLINE WATTS BAR PROJECT TENNESSEE VALLEY AUTHORITY I-I I-44NOOVSLL7, 0 48 44 f'TJtFtt'iINSISsT

'VT

- ~ ~ 1 ico' leI h

IV o --1%.t I

-'I V.

.4:.~

~-1,4; SECTIO Ac-S,

  • ELEVTO.~

JPS-SSt M~c~c ~

2TffCA lpk E

M~c8 REQ

)lS

/-

7ae~-ac

_J.~

.2Fc0. Ac SEC 77O/N -P.

~ii

--S-i

.2' 7'4 cftftlIcAIlccfl MISAc IAcAcCRlccg, cc',cM&RW S/cC 1,,.

511MCRC4 NAAc~a/-agOCAcR a/c 579577,57'S 4./sAc C.cftM.t*4 ftC/~AccCcCc.

C)'

CR-SR-C

/1.4' SRR-rSraAcAa*s)

S/VA CRcAcc~/t*

CI'S' (S C/SM MMIII AM/SAIlS ft an cR1 p.~.tI.

7 4*5242 RECCRAACS' OcftVflftflt 841sf c,,.559,c 45)4.

, Fr1A7ME_ 7 IRZQD-AIK

.C~iEP r

COV6cQ SCTý/ONWCM CcK A;

i m

POc/E~cCo6~*

SECTI ON

  • 74 TUCTURAL SAFE:ýL.

TPASH. RACIK*& GUID S.

WATTS-BAR PROJECT-TNESE'VLY AUTHC~TY'/c. ~.~1

H-/ 12 Calc MDN1027-980006

OA Record TVAN CALCULATION COVERSHEET Title Page 1

of THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW)

Plant WBN SYSTEM SUPPLY. DISCHARGE AND BYPASS LINES Unit 1

Preparing Organization Key Nouns (For RIMS)

BUTTERFLY, BYPASS, COOLING TOWER, DISCHARGE, EZFLOW, SIZING, SUPPLY BranchlProject Identifiers Each time these calculations are issued, preparer must ensure thai the original (RO)

MDN1027-980006 RIMS accession number is filled in.

.Rev (for RIMS use)

RIMS Accession Number Applicable Design Document(s)

RD

' 8 WB-DC-40L3 I

(q E2 9-8 (;0 U

04-R SAR affected:

UNID System(s)

R (lYes E-]No Section(sF 027 R

1.2.2.8. 10.4.5 Rev 0 R

R R

Ousity Rotaed?

Yes No 0

W Design Change Document sareti related?

Yes No No. (or indicate Not Applicable) M39816-A Prep rd These C alcuJaiIJ containl Yes No unverified as$urnpilon(s) that a_3-27-0 MUMl b venni"ltle-'

WW Checked These calculationl ontain Yes No special requirements; andifot

__________ilmif eonmlons7 1

in "Riew v r"

o,.These calculatios contain a Yes No

,design output arracherim Calculation Relhviion:

Entire Calculatm r1[

ate

/SNolected pages 0

Not Applicable11 Stalement of Problem:

Perform a calculation to size the supply, discharge, and bypass lines, along with the location of the bypass line, for the Supplemental Condenser Cooling Water Project (SCCW). Also. delermine the number of traveling water screens at the Intake Screen House Plant that are required for the SCCW.

u L:GR GINAL Abstract This calculation determined the sizes of the supply, discharge, and bypass lines of the Supplemental Condenser Cooling Water Project (SCCW), The number of traveling water screens, thus bays, needed at the Watts Bar Fossil Plant Intake Screen House were determined. The location of the bypass line, and all three valves (supply, discharge and bypass) were determined, and their (valves) ranges of throttle angles were calculated, also.

LEGIWLIT EVALUATWD w4 ACCEpMD for IgM.,

Mlcmfikn and return calculation to Calculation Library.

Address: EQBIM-WBN film and destroy, Mlctofilm and return calculation to; WUNP Calculation Library I vP% %.J&

uyo-vt Ij r'age I ov a NEOPU 1 1

',O-05-97 (q)3

,I TVAN CALCULATION RECORD OF REVISION Page 2

of g3 Title MDNI027.980006 RevisIon f DESCRIPTION OF REVISION Date N o I

I Aproved 0

INITIAL ISSUE 16141%

d A.-

WA 40532 (00-971 Page 2013 NEDP.2.1 (08.05.97)

TVA 40532 [08-971.

Page 2 of 3 NEDP-2-1 [08-05-971

TVAN CALCULATION TABLE OF CONTENTS Page 3

of 93 TABLE OF CONTENTS SECTION TITLE PAGE Calculation Cover Sheet 1

Revision Log 2

Table of Contents 3

Calculation Design Verification (Independent Review) Form 4

Calculation Classification Sheet 5

Computer Input File Storage 7

1.0 Purpose 8

2.0 Criteria 8

3.0 Applicable Codes and Standards 8

4.0 Assumptions 9

5.0 Sources of Design Input Information (References) 13 6.0 Design Input Data 14 7.0 Methodology and Computations 17 8.0 Summary of Results 31 9.0 Conclusions 36 10.0 RequirementsLm ting Condtlons 37 11.0 Supporting Graphics Figure 1 SK-100, Alignment and Profile of SCCW Conduit 38 Figure 2:

SCCW Supply Flow Diagram 39 Figure 3:

SCCW Discharge Flow Diagram 40 Figure 4:

Intake Screen House Profile 41 Figure 5:

Trash Rack 42 Figure 6:

Sluice Gate 43 Figure 7:

Transitional Segment 1 (TS1) 44 Figure 8:

Transitional Segment 2 (TS2) 45 Figure 9:

SK-106, Details of Bypass Conduit and Supply. Discharge 46 and Bypass Valves Appendices Appendix A:

Summer.net: 'Summer EZFLOW Program 47 Attachments :

Watts Bar Reservoir 1997 Current Elevations 87 :

Monthly Average and Extreme Ambient River 88 Temperatures (5F) jRef. 5,2, Table 41 :

FMC Traveling Screen Data 89 :

Typical Kv Values for Butterfly Valves of Different Disc 93 Designs [Standard 3.1, Figure 3.10)

TVA 40532 (08-971 Page 3 of 3 NEDP-2-1 (08-05-97]

S.::':<..,

MDNI027-980006 Rev. 0 PAGE 4 of 93 TVAN CALCULATION DESIGN VERIFICATION (INDEPENDENT REVIEW) FORM MDN1027-980006 C

Calculation No.

Revision Method of design verification (independent review) used:

1.

Design Review

2.

Alternate Calculation

3.

Qualification Test fl Comments:

The results and conclusions within this calculation are reasonable when compared with the inputs. The methodology is consistent with previous calculations of this type. The calculation also conforms to the requirements of NEDP-2. This calculation is technically adequate and acceptable.

Design erifer Date TVA40533 108471 PS9O1 ot I NEOP.2.2 10805.971 TVA40533, 108-971]

Page I of I NEOP-2-2 [0a,.05-971

MDNIO27-980006 Rev. 0 PAGE 5 of 93 TVAN CALCULATION CLASSIFICATION FORM CALCULATION INFORMATION:

Plant WBN Unit 1

Identifier MDN1027-980006 Rev.

Issue N/A Date Title THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES.

0 System(s). Component, Feature or Subject of Calculation SYSTEM/DESCRIPTION (AS NEEDED)

O Safety system System No.

[]

Safety-related feature E]

Nonsafety system System No.

[]

Nonsafety-related feature E]

Quality-related system O

Quality-related feature 0

Non Quality related system CCW System, No. 027 O

Non Quality related feature

[

Plant environment (EQ, etc.)

O Appendix R 5

Civil structures C]

Instrumentation (PAM, etc.)

E]

Licensing C]

Other Calculation Category A01 Final Classification:

]

Essential C]

File Only 1

C w

Desirable

[]

Superseded 5]

C Preparer '& pfI. ?W 1.6toV ancel

)bsolete El 0

Checker a

a Verifier 9 t,i Date Date Date Engineering Output

~

t' TVA 40537 108-971 Page t ot2 NEDP-2-8 [08-05.971 TVA 40537 [08-971 Page I 0(,2 NEDP-2-8 10"5.0971

MDNI027.980006 Rev. 0 PAGE 6 of 93 TVAN CALCULATION CLASSIFICATION FORM Identifier:,

MON1027-980006 Preliminary Classification 0

Essential 5

File Only 0

Cancel El Engineering Output IM Desirable 53 Superseded 5

Obsolete 0

CALCULATION CLASSIFICATION JUSTIFICATION:

Preparer This calculation is classified as desirable because it supports the operational and design considerations of equipment and structures in a non-quality related system.

Checker Agree with classification 5

Disagree - comments required Verifier Agree with classification 5

Disagree - comments required "TVA 40537 [08-971 Page 2 of 2 NEDP-2.8 (08-05-971

WVAN COMPUTER INPUT FILE STORAGE INFORMATION SHEET Document MDN1027-980006 Rev. 0 1 Plant: WVBN Page 7

of 93

-Subject THE SIZING OF THE SUPPLEMNETAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS UNES Q

Electronic storage of the input files for this calculation is not required Comments:

l]

Input files for this calculation have been stored electronically and sufficient identifying information is provided below for each input file. (Any retrieved file requires re-verification of its contents before use.)

File Name SCCW-KeeperFiles User Name i01wo Group Name Keyword/Problem Number mdn1027-980006 ro Creation Date Modification Date 1998-05-26 14:44:00 Owner Name ila waldon Owner Address lp 4t-c Hardcopy Number mdn1027-980006 ro Source Hardware sparccenter-2000 Source OS System sunos 5.5 Application ezflow Access Class public Plant Name wattsbar File Size 148480 File Type catalog Reference ID 301208 Backup ID

/farm/iOlwo/s21784dO42698t184947

==

Description:==

supplemental condenser cooling water (scow) sizing programs for calc mdnl027-980006 rO This reference ID contains the nine files listed below 16343 May 22 05:51 SBYP135K.net 16322 May 21 20:52 SUMMER.net 16320 May 21 21:11 WBYPT73B.nat 16318 May 21 21:02 WINDYPAS.net 16316 May 21 20:37 WZNFLOOD.nat 16326 May 21 20:51 WINT6738.net 16313 May 21 20:49 WINTXR.not 16337 May 22 06:25 WKV@735.net 16330 May 22 06x51 WXV6739.net WA 40535 108-971 Page tot 1 NEDP-2-4 (08.05.971 TVA 40535 [08-971 Page I of 1 NEDP-24 [0B-0%97

SHEET 8 of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN1027-980006 1.0 PURPOSE The purpose of this calculation is to determine the following:

1.1 The size of the Supplemental Condenser Cooling Water System (SCCW) supply, discharge, and bypass lines that will accommodate the flow capacity requirements as described in the "Watts Bar Nuclear Plant Supplemental Condenser Cooling Water Project," Ref. 1.

1.2 The location of the bypass line.

1.3 The location of the motor-operated butterfly valves in the SCCW supply, discharge, and bypass lines.

1.4 The valve throttle positions that would meet the seasonal flow requirements as described in Ref. I.

1.5 The number of Intake Screen House bays needed to supply the flow capacity requirements in Ref. I.

2.0

!CRITERIA 2.1 The SCCW supply piping will supply between 115,000 and 135,000 gallons per minute (gpm) from the Watts Bar Lake to the Watts Bar Nuclear Plant (See Ref.

5.1). 115,000 gpm corresponds to the Nominal Winter level of 738', and 135,000 gpm corresponds to the Summer level of 740.5'.

2.2 The bypass line has to divert approximately 40% of the supply flow during the winter months to meet the "Thermal Plume Modeling" requirements (Ref. 5.2).

2.3 The supply, discharge and bypass valves must be placed in close proximity to each other and the Cooling Towers to facilitate electrical connections. The valves are placed at least 8 pipe diameters away from other piping components on either side of the valves.

2.4 The valves should have open angles between 300 and 90' (Standard 3.1).

.3.0 APPLICABLE CODES AND STANDARDS 3.1 "Application Guide for Motor-Operated Butterfly Valves in Nuclear Power Plants,"

(Addendum to Nuclear Maintenance Applications Center (NMAC) Document NP-6660-D), NP-7501 Research Project 2814-41, Electric Power Research Institute.

SHEET 9 of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDNIO27-980006

.4.0 ASSUMPTIONS 4.1 PIPING 4.1.1 EZFLOW Version 5 is used because of its capability to model rectangular duct.

4.1.2 All piping is clean, smooth, concrete piping with a minimum Hazen-Williams factor (HW) of 130. EZFLOW uses HW= 100 as a default value for concrete. However, the Hazen-Williams factor for new concrete pipe could range from approximately 140 to 150 for the pipe sizes used in this calculation (Section 13 of Ref. 5.2). HW=130 and HW=150 were used to find a range of possible flow rates. HW=l30 is a conservative value for both the existing Watts Bar Fossil Plant piping, and the new SCCW piping.

4.1.3 The entire length of SCCW piping is modeled as straight pipe runs, except where fittings are included. There are negligible head losses across the joints, straight or mitered, since the joints are grouted to create smooth transitions from one piping section to another.

4.1.4 The following nomenclature is used for piping lengths: 1+10, where the "I" represents "hundreds", and the "1 0" represents "tens".

4.1.5 The centerline elevations of the piping is used as node elevations in EZFLOW.

4.1.6 The supply line goes from the Watts Bar Lake to the Unit 2 Cooling Tower (the layout of Figure 1 is in the opposite direction). The discharge line goes from the Unit I Cooling Tower to the Energy Dissipater. The initial lines sizes used in the EZFLOW analyses for the supply and discharge are:

Supply Line:

96" to 108" Discharge Line:

60" to 72" 4.1.7 The flow rate supplied to the Unit 2 Cooling Tower is equal to the flow rate discharged from the Unit I Cooling Tower.

SHEET 10 of 93 WAITS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDNI027-980006 4.0 ASSUMPTIONS (continued) 4.2 RESERVOI RS 4.2.1 Watts Bar Lake, Unit I and 2 weir collection basins (weirs), and the Energy Dissipater are considered reservoirs.

4.2.2 The flow paths between Watts Bar Lake and the Intake Screen House, and between the Unit I & 2 Cooling Towers and SCCW piping (the weirs) are modeled as an 144" (12') diameter, 1' long vertical pipes ("dummy" links).

This was done for the following reasons:

A.

To ensure that there are minimal head losses between the water surfaces and the pipes' entrances/exits, and B.

To ensure that the entrances/exits of the piping system have the correct static head associated with difference in elevation between the water surfaces and the pipes' entrances/exits.

4.2.3 Watts Bar Lake can reach flood level (745') in either the summer or winter months.

4.2.4 The Unit I & 2 weirs are transition structures between the SCCW piping and the Unit I & 2 Cooling Towers, respectively. The Unit l& 2 Cooling Towers both have a water elevation of 730'.

4.2.5 The Unitrl & 2 Cooling Towers are the same temperature as the inlets to the Main Condenser.

4.2.6 The Unit I weir water surface elevation is the same as the top invert of the discharge pipe entrance at the Unit I weir. The Unit I weir water elevation is 730' for flood mode; 730' is the Unit 1 Cooling Tower water elevation.

4.2.7 The Unit 2 weir's outlet elevation is always 73 '; this elevation is V above the Unit 2 Cooling Tower water elevation. The "dummy" link, that represents the Unit 2 weir, dumps into the Unit 2 Cooling Tower. This is done to eliminatethe possibility of siphoning water from the Unit 2 Cooling Tower in the event there is a break in the supply line between the supply valve and Unit 2 weir.

4.2.8 The Energy Dissipater is modeled as a reservoir whose elevation is the same as the discharge pipe's centerline at that location. The Energy Dissipater's elevation is 705'.

  • ~

~

SHEET It of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN 1027-980006 4.0 ASSUMPTIONS (continued) 4.3 INTAKE SCREEN HOUSE 4.3.1 The Intake Screen House has six bays. Each bay is composed of a trash rack, two sluice gates, a traveling water screens (between the two sluice gates), and rectangular concrete conduit (See Figure 4).

4.3.2 TRASH RACKS 4.3.2.1 The trash racks are modeled as grillage with square edges.

4.3.2.2 The trash racks are not at an incline.

4.3.3 SLUICE GATES 4.3.3.1 The sluice gates are rectangular, metal gates on the inlet and outlet sides of the traveling water screens. The sluice gates are modeled as fully opened gate valves.

4.3.4 TRAVELING WATER SCREENS 4.3,4.1 The traveling water screens are modeled as 6' foot wide sections of 14 Gauge (0.080 diameter) screen cloth with 3/8" square openings.

4.3.4.2 The height of the traveling water screens varies with the water level in the Watts Bar Lake (See Table 3).

4.3.4.3 The screen cloth is 50% clean.

4.3.4.4 At the Nominal Winter Level of 738', the traveling water screens have the same pressure drop as the Summer Level of 740.5' (See Table 3).

SHEET 12 of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUBJECT.

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN 1027-980006 I

4.0 ASSUMPTIONS (continued) 4.4 TRANSITION CONDUIT 4.4.1 The Transition Conduit is divided into two consecutive transitional segments. The first transitional segment (TSI) is from Station 1+80 to 1+94, and the second transitional segment (TS2) is from 1+94 to 2+00.

TSI and TS2 both consist of two, side by side conduits that are assumed to be identical (Ref. 5.9.5).

4.4.2 TS I decreases in height, while it increases in width. These simultaneous changes are uniform throughout this conduit segment, and the conduit remains rectangular in shape (See Figure 7).

4.4.3 TS2 gradually transitions from rectangular conduit to circular conduit. TS2 conduit is modeled as "duct," with height and width dimensions, until the cross-sectional area becomes more circular, then the conduit is modeled as regular circular pipe (See Figure 8).

4.5 VALVES 4.5.1 The motor-operated valves used in the SCCW piping are generalized symmetric butterfly valves (Standard 3.1).

4.5.2 These valves are used to throttle the flow in the supply and bypass lines, and for isolation in all three lines.

* *~~~~~~~~~~~,i.i*

i

i *
  • i : :i

SHEET J 3 of L WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY. DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN 1027-980006

5.0 REFERENCES

5.1 "Watts Bar Nuclear Plant Supplemental Condenser Cooling Water Project," Draft Environmental Assessment, December 5, 1997.

5.2 "Watts Bar Nuclear Plant Supplemental Condenser Cooling Water Project,"

Thermal Plume Modeling, December 5, 1997.

5.3 Price Brothers Concrete Pressure Pipe Engineering Manual, Ninth Edition, Price Brothers Company.

5.4 "The Watts Bar Steam Plant," Technical Report No. 8, United States -Tennessee Valley Authority, 1949.

5.5 "Applied Fluid Dynamics Handbook," Van Nostrand Reinhold Company, Copyright C 1984.

5.6 Crane Technical Paper No. 410, "Flow of Fluids Through Valves, Fittings and Pipe," Crane Co., 0 1988.

5.7 Calculation WCG-1-1862, "Supplemental Condenser Cooling Water (SCCW)

System - Piping Alignment and Profile."

5.8 WBN Emergency Response Facility Data System (ERFDS - System 264) 5.9 Calculation MDNO027-980003, "SCCW (Supplemental Condenser Cooling Water)

Cooling Tower Weir Sizing Calculation."

5.10 TVA Drawings 5.10.1 41K500, Rev. 4, Powerhouse Units A & B, Concrete Water Supply Line Plan & Profile - Sheet 1.

5.10.2 41K501, Rev. 4, Powerhouse Units A & B, Concrete Water Supply Line Plan & Profile - Sheet 2.

5.10.3 411K502, Rev. 5, Powerhouse, Concrete Water Supply Line Plan & Profile -

Sheet 3.

5.10.4 SK-103, Rev. A, Concrete Discharge Structure At U I Cooling Tower -

Outline.

5.10.5 41N504, Rev. 5, Powerhouse, Concrete Water Supply Line Transition @

Station 1+11.5.

SHEET 144 of 3

WATTS BAR NUCLEAR PLANT - UNIT I SUBJECT; THE SIZING OF THE SUPF

SUBJECT:

THE SIZING OF THE SUPF SUPPLY, DISCHARGE AN[

DOCUMENT ID:

MDN 1027-980006

'LEMENTAL CONDENSER COOLING WATER

) BYPASS LINES 6.0 DESIGN INPUT DATA 6.1 The Design Inputs for the SCCW are listed in Tables I through 5. Any computations necessary to determine these inputs are located in Section 7, "Methodology and Computations."

TABLE 1 Reservoir Elevations and Temperatures Watts Bar Lake Unit I Weir Unit 2 Weir Energy Dissipater Winter Level

  • 735' 73 '

705' Nom. Winter Level

  • 738' 731' 705' Summer Level

@740.5' 73 '

705, Flood Level 0745' 730' 73 1 705' Winter Temp.

A35OF

-54 0F

-54 0F Nom. Winter Temp.

A 35°F

-54 0 F

-540F Summer Temp.

A830F

-92 0 F

-92 0 F Flood Temp.

A83"F

-920F

-92OF

  • Attachment I

@ Ref. 5.1

  1. Dependent upon discharge pipe diameter (Section 8.1.3)

A Attachment 2 Ref. 5.8

-- Determined by EZFLOW Model 6.2 Tables 2 and 3 are the Design Inputs for the Intake Screen House. There are no default components in EZFLOW to model these details, therefore, head loss coefficients are determined for these components (Sections 7.1, 7.2, & 7.3). These inputs are entered for each bay modeled in the EZFLOW analyses.

TABLE 2 Intake Screen House Components Component Head Loss Coefficient, K Computation Trash Rack K = 0.72 Section 7.1 Sluice Gate K = 0.072 Section 7.2

SHEET 15 of 923 WATTS BAR NUCLEAR PLANT-UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN I027-980006 6.0 DESIGN INPUT DATA (continued)

TABLE 3 Travelinw Water Screens Input Data Computation / Reference Winter Level (735')

Height [inch]

300"

-'Section 7.3 Centerline [feet]

722.50' Section 7.3 Pressure Drop j0.010 psid @ 90,300 gpm Nominal Winter Level (738')

Height [inch]

336" Section 7.3 Centerline [feet]

724.00' Section 7.3 Pressure Drop 0.015 psid @ 135,100 gpm, &

Section 4.3.4.4 Summer Level (740.5')

Height [inch]

366" Section 7.3 Centerline [feet]

725.25' Section 7.3 Pressure Drop 0.015 psid @ 135,'100 gpm Flood Level (745')

Height (inch]

..,_4_20"

"_Section 7'.3 Centerline [feet]

727,50' Section 7.3 Pressure Drop 0.0 17 psid @ 166,600 gpm 6.3 Tables 4 and 5 are the Design Inputs for the Transitional Segment #1 and #2. The computations for these inputs are located in Sections 7.4 and 7.5, TABLE 4 Transitional Seitment #1 Nodes Data Nodes Height, h [in.]

Width, w [in.]

Centerline Elev. [ft.]

Area [in.2) 32A & B 138 39.00 715.56 5382 34A&B 123 47.40 716.18 5830 36A & B 108 55.80 716.80 6026 38A & B 1

93 1

64.20 717.42 5971 40A & B 78 72.60 718,01 5663 it

~

q

SHEET 16 of 93 WATTS BAR NUCLEAR PLANT - UNIT I 6.0 DESIGN INPUT DATA (continied)

TABLE 5 Transitional-Seament N2 Nodes Data Rectangular Area - "Duct "

Nodes Height, h (in.]

Width, w (in.]

Area [in.]

41A&B 78.00 69.04 5385 42A & B 78.00 70.05 5464 43A & B 78.00 70.18 5474 44A & B 78.00 69.27 5403 Circular Area - "Pipe ""

Nodes Diameter (in.]

Area [in.-]

45A & B 81.78 5252 46A & B 79.44 4956 50A & B 78.00 4778 U

SHEET 17 of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN1027-980006 7.0 METHODOLOGY AND COMPUTATIONS 7.1 TRASH RACKS MODELING (Refer to Figure 5)

Each of the Intake Screen House bays has a trash rack. The trash rack is approximately 21' high and 9.5' wide. It is composed of vertical bars that are 5" wide and 3/8" thick, and are spaced 3" on centers. Since EZFLOW does not have a default component to match the trash rack, a head loss coefficient, K, has to be determined. In order to model the trash rack, first, it is assumed that the trash rack is grillage with square edges. To compute the number of bars and spaces, the width of the trash rack was divided by 3":

(9.5') e (12) = 114"/ 3" = 38 bars and spaces The total surface area of a trash rack is:

Total Surface Area = (21') * (9.5') = 199.5 ft' = 200 fte The bars' collective surface area is:

Bar Surface Area=(38 bars) * (21') o (3/8")112 = 24.94 ft - 25 ftW Therefore, the flow area of a trash rack is:

Flow Area - Total Surface Area - Bar Surface Area 200 ft - 25 fe = 175 ft' The percentage of flow area to total surface area is:

Flow Area / Total Surface Area = 175 fl 2200 ftr = 87.5%

The Flow Area is reduced to 80% to account for any structural support and possible debris against the trash rack.

The second part of modeling a trash rack uses the % Flow Area; % Flow Area is represented by a = 80%. The cross-sectional area between the bars is used to find a head loss coefficient, K. The cross-sectional area between the area is 2-5/8" wide, and 5" deep (5" is the width of the bars). Using Table 6.2 in Ref. 5.5, the dimensions of the cross-sectional area are:

a 5" and b 2-5/8" The above dimensions are used to calculate the hydraulic diameter, D, of the cross-sectional area.:

I':.i%

i* ',.:**i.-.

i*,*,*

., * : i.:.,..-:::*:.

. :. i.'.,;*.

SHEET 18 of 93 WATTS BAR NUCLEAR PLANT - UNIT I THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCC~ SYSTEM

SUBJECT:

DOCUMENT THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES ID:

MDN 1027-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued)

D (2. a. b)/(a + b)

D (2

  • 5"
  • 2-5/8")/(5" + 2-5/8") = 3.44" In Table 10-17 of Ref. 5.5, the depth of the cross-sectional are is described as t, such thatt= 5". The following is the equation for K, for the given conditions:

K = 1%(1 - a) +(I - a')]/a, forD <.I<SOD D<L<50D 3.44"< 5"< 172" K = [WA (1 - 0.80) + (1 -0.80 1)1/ 0.801 K = [Ys0.20 + 0.361/0.64 K = 0.72 K = 0.72 is used for the head loss coefficient for the trash racks in the EZFLOW analyses.

SHEET 19 of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDNI027-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued) 7.2 SLUICE GATES MODELING (Refer to Figure 6)

The sluice gates in the Intake Screen House are metal, rectangular openings on the inlet and outlet sides of the traveling water screens. Since EZFLOW does not model rectangular valves, the sluice gates are modeled as fully open gate valves. In order to determine a head loss coefficient, K, for the sluice gate, the cross-sectional is found. The sluice gate is 6' (72") wide and 8' (96") high. Therefore, the cross-sectional area is:

A=w*h A - 72"

  • 96" = 6912 in2 The cross-sectional area of the rectangular shape is used to find the diameter of a circle that would have the same area. For a circle:

A= nr2 r =(A / ir) r r

(6912 in' /,a)

=46.91 The diameter of the gate valve would be approximately 94". From Ref. 5.6 page A-23, the fully turbulent friction factor, ft, for 94" commercial steel pipe is fT = 0.009.

Also, from Ref. 5.6 page A-27, the head loss coefficient is:

K-8 f-K = 8

  • 0.009 K = 0.072 K = 0.072 is used for the head loss coefficient for the sluice gates in the EZFLOW analyses.

.f..

SHEET 20 of 93 WATTS BAR NUCLEAR PLANT - UNIT I 7.0 METHODOLOGY AND COMPUTATIONS (continued) 7.3 TRAVELING WATER SCREENS MODELING The width of the traveling screens is 6', however, the height of the water on the screens varies with the water level in the Watts Bar Lake. The height of the water on the traveling water screens is determined by:

Height = Water Bar Lake Lvi. - 710' (Intake Screen House floor elev.)

The height is the converted to inches to be input into EZFLOW. The centerline elevation of the Traveling Water Screens is determined by:

Elevation = Height /2 + 710' The traveling water screen heights and elevations are calculated below:

Winter Level 735' Height = 735'- 710' = 25' e 12 = 300" Elevation = 25'/2 + 710' = 722.5' Nominal Winter Level 738' Height - 738' - 710' = 28' o 12 = 336" Elevation - 28'/2 + 710'= 724' Summer Level 740.5' Height = 740.5' - 710' = 30.5' a 12 = 366" Elevation - 30.5'72 + 710' = 725.25' Winter Level 745' Height - 745' - 710' = 35' a 12 - 420" Elevation 35V/2 + 710' = 727.5' qw..

SHEET 2]

of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN1027-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued)

The head losses are given in inches of water (in. H20) in Attachment 3. These values are converted to lb/in.?. The conversion is:

in. HO

  • 0.036092 = lb/in.]

Winter Level (735')

0.278 in. H2 0 a 0.036092 = 0.010 lb/in. @ 90,300 gpm Summer Level (740.5')

0.416 in. H10 e 0.036092 = 0.015 lb/in.1 @ 135,100 gpm Winter Level (745')

0.478 in. H10

  • 0.036092 = 0.017 lb/in.1 @ 166,600 gpm 0*.

'.i.M

SHEET 22 of 93 WATrS BAR NUCLEAR PLANT - UNIT I 7.0 METHODOLOGY AND COMPUTATIONS (continued) 7.4 TRANSITIONAL SEGMENT #I MODELING (Refer to Figure 7)

The first transitional area (TSI) begins at Station 1+80, where splits into two separate conduits. There are five nodes in each conduit of TS I; the nodes begin with 32A and 32B, and end with 40A and 40B, respectively.

Conduit A 32A 34A 36A 38A 40A Conduit B 32B 34B 36B 38A 40B TSI uniformly decreases in height, while increasing in width. The complete transition happens within a horizontal span of approximately 14'. This span is divided into 4 - 3.5' horizontal sections. Furthermore, the height decreases from I 1.5' to 6.5', and increases in width from 3.25' to 5.6'. The overall differences of the height and the width are divided into four equal parts to find the heights and widths for the intermediate nodes.

Nodes 32A/B 34A/B 36AMB 38A/B 40A/B Heieht 11.50' 10.25' 9.00' 7.75' 6.50' Width 3.25' 3.95' 4.65' 5.35' 6.05' In order to model TS 1, the height, width, floor elevation, centerline elevation (c),

and cross-sectional area are needed for each 3.5' section. The cross-sectional area is needed to model reducers, since the cross-sectional areas are changing from node to node. The known dimensions are used to calculate the other required dimensions for TS 1.

Ki

SHEET 23 of 91 WATTS BAR NUCLEAR PLANT - UNIT I SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN1027-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued)

Node 32A & B h = 11.5' (138"), w 3.25' (39"), floor elev. =709.81' c = h

  • 0.5 + floor clov.

c = 11.5' b 0.5 + 709.81' = 715.56' Area = h e w Area = 138" e 39" - 5382 in' Node 34A & B h = 10.25' (123"), w = 3.95' (47.40"), floor elev.

711.05' c = h e 0.5 + floor elev.

c = 10.25' o 0.5 + 711.05' = 716.18' Area = h

  • w Area = 123" a 47.40" = 5830 inz Node 36A & B h

9.0' (108"), w = 4.65' (55.80"), floor Elmv. = 712.29' c = h s 0.5 + floor elev.

c = 9.0' e 0.5 + 712.29' = 716.8' Area = h ow Area = 108"

  • 55.80" - 6026 in2 Node 38A & B h = 7.75' (93"), w = 5.35' (64.20"), floor Elev. = 713.53' c - h
  • 0.5 + floor elev.

c - 7.75'

  • 0.5 + 717.42' = 717.42' Area = h 9 w Area = 93" a 64.20" = 5971 in' Node 40A & B h b 6.5' (78"), w = 6.05' (72.6"), floor Elev.

714.76' c = h

  • 0.5 + floor clev.

c-6.5'

  • 0.5 + 714.76' = 718.01' Area - h o w Area - 78" m 72.6" = 5663 In' i*~ i

SHEET 24 of 93 WATTS BAR NUCLEAR PLANT-UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY. DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDNIO27-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued) 7.5 TRANSITIONAL SEGMENT #2 MODELING (Refer to Figure 8)

The second transitional segment (TS2) continues from TSI. There are two separate conduits in TS2, also. There are seven nodes in each conduit of TS2; the nodes begin with 41A & 41B, and end with 50A and 50B, respectively.

Conduit A 41A 42A 43A 44A 45A 46A 50A Conduit B 41B 42B 43B 44A 45B 46B 50A Unlike TS 1 TS2 remains at a constant floor and centerline elevation:

Floor Elev. = 714.76', c = 718.01' The inside shape of the conduit changes from a rectangular shape to a circular shape. TS2 transitions over a span that is approximately 6.5'. The segment is divided into seven lengths: six V' lengths, and one 6" length.

In order to model TS2, the height, width, diameter (for circular sections), floor elevation, centerline elevation (c), and cross-sectional area are needed for each segmented length. The cross-sectional area is needed to model reducers, since the cross-sectional areas are changing from node to node.

The areas of the TS2 sections are irregular. They are in the shape of rectangles with rounded comers. The corners increase in radial length in order to change from a rectangular shape to a circular shape. Figure 8 gives the radius of curvature for the comers of each section (See comer and trapezoid nomenclature). The cross-sectional area is found for each section by using the area formulas for trapezoids, and circles in combination. After the area is found, it used to model a rectangular conduit whose height is 6.5' and whose width is determined by dividing the area by the height. For the sections that are more circular in shape, the area is found in the same manner, however, the area is then divided by pi (n) and the diameter determined.

Y'

.w

SHEET 25 or 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES I DOCUMENT ID:

MDNI027-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued)

The inlet to TS2 starts with the area for Node 40A for continuity. The following is the generic formula for the cross-sectional area:

Area

-Corner I +Corner 2 + Corner 3 + Corner 4 +

Trapezoid 1 + Trapezoid 2 + Trapezoid 3 + Trapezoid 4

+ Center Trapezoid Using the following nomenclature, R, being the radius for Corner 1, h

overall height of the section w

overall width of the section the area equation is:

Area

=Y4rR, 2+%,tR2 1+1/4tnR 3 2 +1/4n4hnR.

+ K (RI + R:)(w-Rj-RI) + VI (RI + R3)(h - R1-R3)

+ 1/ (R, + Rj)(W-R3-R4) + V. (RR 4 + Rt)(h-RP-RI)

+ Vi [(h - R, - R,) + (h - R, - R,)I(w - R1-R1)

Table 6 computes the areas of each sections using the formula above, and the modeled widths and diameters.

  • ) '*i',*i*,'
"...:.. '* i *,' *':

,.* - :.o".

. ", -o...*

.. *r.:," /",

',./, ' '. * ',

A*

SHEET 26 of 93 WATTS BAR NUCLEAR PLANT - UNIT I SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN 1027-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued)

TABLE 6 Cros-Sectional Areas in[ransitional Seeent#2 RECTANGULAR AREA - "DUCT" NOEIHeight Width Radius 1 Radius 2 IRadius 3Radius 41 Area Mod. Conduit h [in.] I w (in.]

[in

[in.]

(in.]

(in.]

[sq. in.] Width, w2 [In.i 40AIB 78 72.60 n/a n/a n/a n/a 5663 72.60 41A/B 78 69.50 6.500 6.375 6.375 6.500 5385 69.04 42AiB 78 71.88 12.750 12.500 12.500 12.500 5464 70.05 43A/B 78 74.13 19.250 18.625 18.625 19,250 5474 70.18 44A/B 78 76,25 25.500 24.875 24.875 25.500 5403 69.27 CIRCULAR AREA - "PIPE" NODE Height Width Radius 1 Radius 2 Radius 3 Radius 4 Area Mod. Pipe Jh [in.

w [in.]

(in.]

[in.]

[in.)

[in.]

(sq. in.]

Dia., d (in.]

45A/B.

78 78.00 31.250 31.000 31.000 31.250 5252 81.78 46AIB 78 78.00 36.500 36.000 36.000 WH0O 4956 79,44 50A/B 78 78.00 39.00 39.00 39.00 39.00 4778 78.00

.9 S..

C

~hb4~

.~

S

~

SHEET 27 of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN1027-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued) 7.6 EZFLOW METHODOLOGY 7.6.1 GENERAL 7.6.1.1 The total length of piping between two nodes, including the fittings lengths, is used to model a link in EZFLOW. Piping details are modeled using components listed in the EZFLOW program.

Components that are not listed in EZFLOW are modeled using a head loss coefficient, K, or a flow rate and its corresponding pressure drop.

7.6.1.2 The nodes for the piping layout are placed where there are changes in the slope of the pipe, Ref. 5.7 provides these points in the piping layout.

7,6.1.3 K, head loss coefficient, is used to model the three butterfly valves in the SCCW.

7.6.1.4 The flow rates for the SCCW are gravity driven.

7.6.1.5 HW=130 and HW= 150 are used for the concrete duct/piping.

These Hazen-Williams factors provide flow rates that range from conservative to the possible highest flow rate that may be passed through the SCCW at particular Watts Bar Lake elevations.

7.6.2 PIPE SIZING & BYPASS LINE LOCATION 7.6.2.1 The SCCW consists of three lines: supply, discharge and bypass lines. The supply line runs from the Intake Screen House to the Unit 2 Cooling Tower. The discharge line runs from the Unit I Cooling Tower to the Energy Dissipater. The bypass line connects the supply and discharge lines at a location near the Cooling Towers.

SHEET 28 of 93 WATTS BAR NUCLEAR PLANT - UNIT I 7.0 METHODOLOGY AND COMPUTATIONS (continued) 7.6.2.2-The supply and discharge line are modeled separately. The supply line is modeled incorporating all six bays of the Intake Screen House. The supply line has to pass at least 135,000 gpm when the Watts Bar Lake was at 740.5'. 108" is initially used as the diameter of the supply l ine. Since a pipe diameter of 108" passes more than the required amount of flow, the diameter of the supply line is reduced by 6", and the flow rate is calculated again. This reduction in pipe diameter continues until a flow rate of at least 135,000 gpm, with a marginal excess of flow (about 10,000 gpm), is achieved.

7.6.2.3 The discharge line is sized in a similar manner as the supply line.

72" is initially used as the diameter of the discharge line. The discharge line has to pass the flow calculated for the supply line when Watts Bar Lake elevation is 740.5'. An additional consideration is the capability of the discharge line to pass the supply flow if Watts Bar Lake reaches flood level of 745'. The 72" discharge line sufficiently passes the supply flow rate at 740.5', but does not pass the flood flow rate at 745'. The diameter of the discharge line is increased by 6" until it passes the flood flow rate at 74 5'.

7.6.2.4 The supply and discharge lines are connected by the bypass line to make a complete system. The bypass line is located between the supply and discharge lines near the Unit 2 Cooling Tower. The bypass line is optimized to a length that would be sufficient to locate a butterfly valve within the line, and minimize the head losses due to the piping length. The bypass line is sized to divert approximately 40% of the supply flow during the winter months.

7.6.3 VALVE LOCATIONS 7.6.3.1 The motor-operated butterfly valves are located in close proximity to the bypass line to facilitate electrical connections for all three valves. The valves are first placed in estimated locations, and the definite locations are to be determined later. All three valves are installed with the fully open head loss coefficient of K =0.55.

SHEET 29 of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY. DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDNI027-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued) 7.6.3.2 After the last profiles for the supply and discharge piping were established (Figure 1), the valves are placed at least 8 pipe diameters, and in most cases 10 pipe diameters, from the next piping components to minimize the turbulence affects on the valves.

7.6.4 VALVE THROTTLE POSITIONS 7.6.4.1 The valves are incorporated into the three lines, and the K values are set to 0.55, the fully open position. In order to achieve a particular flow rate, the K for any of the valves can be changed, thus simulating the valve being throttled at various open angles.

(See Attachment 4 for the K-to-open angle chart) 7.6.4.2 Before computing the summer supply flow, the flow in the bypass line is fixed to zero. The bypass line is not modeled to be in operation during summer months. The summer supply flow is then computed to ensure that at least the 135,000 gpm continues to be supplied by the SCCW.

7.6.4.3 The discharge valve remains fully open throughout the year. It is not necessary to throttle the discharge valve because the discharge piping is not supposed to control the fnow to the Energy Dissipater.

Furthermore, the discharge line is sized to accommodate more than any amount of flow that can be supplied by the supply line.

7.6.4.4 With the bypass line's flow fixed at zero, the supply valve is throttled, by changing the K value, until it passes the 135,000 gpm to the Unit 2 Cooling Tower. The K value for the supply valve will be denoted by Ks.

7.6.4,5 After Ks is found, the supply valve will remain in this position throughout the year. With Ks held constant, the fixed flow of zero is removed from the bypass line. K9, the K value for the bypass valve, has been previously set to Ka=0.55.

SHEET 30 of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDNI027-980006 7.0 METHODOLOGY AND COMPUTATIONS (continued) 7.6.4.6 The governing factor for the bypass valve is to throttle the bypass flow to pass approximately 40% of the supply flow during the winter months. K0 is changed, throttling the bypass valve, until 40% of supply flow is passed through the bypass line. As K, is changed, the flow in the discharge line has to be fixed, simultaneously. The flow is fixed immediately downstream of where the bypass line ties into the discharge line. The discharge flow is fixed to equal the supply flow upstream of the bypass line.

Fixing the flow here simulates the two Cooling Towers being connected, therefore, the amount going into the Unit 2 Cooling Tower is equal to the amount discharged from the Unit 1 Cooling Tower. K9 and the discharge fixed flow are change until:

Bypass Flow = 40% of Supply Flow, and Supply from Watts Bar Lake = Discharge to Energy Dissipater 7.6.5 INTAKE SCREEN HOUSE BAYS 7.6.5.1 The SCCW is initially assumed to have all six Intake Screen House bays in operation, and is modeled as such. After inspection, it was determine that it would not be economically feasible to restore all of the traveling water screens. The number of traveling water screens, thus the number of bays, necessary to provide the 135,000 gpm to the SCCW has to be determined.

7.6.5.2 The SCCW begins with 6 bays modeled. The number of bays is reduced by one until a flow rate above 135,000 gpm is maintained, with a margin of excess flow.

7.6.5.3 After the required number of bays is found, Section 7.6.4 is repeated to obtain the new valve throttle positions.

A

SHEET 31 of" 9 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT iD:

MDNI027-980006 8.0

SUMMARY

OF RESULTS 8.1 PIPE SIZING & BYPASS LINE LOCATION 8.1.1 The results of the pipe sizing analyses yield the following diameters for the three lines:

Supply Line Os = 90" (7.5')

Discharge Line

=o 78" (6.5')

Bypass Line

= 42" (3.5')

8.1.2 The bypass line entrance is at Supply Line Station 36+58, and its exit is at Discharge Line Station 10+35 (See Figure 1). The total length of the bypass line is approximately 145'. The bypass line ties into both lines with tees; 900 tee at the supply line, and a 450 tee at the discharge line. In order to create the contour between the supply an discharge lines, a 450 elbow is placed in the bypass line 10' downstream of the 900 tee. The remaining 135' is contoured, and sweeps into the discharge line at the 450 tee. The bypass valve is located approximately 75' downstream of the 450 c-lbow, 8.1.3 The Unit I weir elevation is omitted from Table I for three of the flow conditions. As stated in Section 4.2.6, the Unit I weir elevation is equal to the top invert elevation of the discharge line at its entrance at the Unit I weir. The bottom invert elevation of the discharge line at this station is 719.5' at the Unit 1 weir. The bottom invert elevation, 719.5', plus the discharge line diameter, 6.5', is equal to the top invert elevation, 726'.

8,2 INTAKE SCREEN HOUSE BAYS 8.2.1 Three (3) Intake Screen House bays are required to supply the necessary flow to the SCCW. The flow rates associated with the above supply and discharge pipe diameters, and 3 Intake Screen House bays are listed in Table 7.

8.2.2 The discharge flow rates for the Winter, Nominal Winter and Summer levels are all 176,579 gpm. They are the same because the Unit I weir collection basin is considered to be at a water elevation of 726' for all three conditions. The Unit I weir water elevation remains constant, except for flood conditions; the Unit 1 weir collection basin flood level is 730'.

ý i

SHEET 32 of 93 WATTS BAR NUCLEAR PLANT-UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN I027-980006 8.0

SUMMARY

OF RESULTS (continued)

TABLE 7 Sizing the SCCW Supply and Discharge Lines HW = 130 HW =150 WINTER LEVEL -735' Supply Diameter [inches]

90" 90" Flow rate [gpm]

91,977 103,028 Discharee (El. 726' a) Unit I Weir)

Diameter [inches]

781 78' Flow rate [gpm]

176,579 196,369

-NOMINAL WlINTER LEVrEL -*738' Suape. EU Diameter [inches]

90" 90" Flow rate [gpm) 124,029 138,794 Discharge (El. 726' @, Unit I Weir)

Diameter [inches]

78" 78" Flow rate [gpm]

176,579 196,369 SUMMER LEVEL-740.5'...

Uit......

Supply Diameter [inches]

90" 908" Flow rate [gpm]

145,953 163,225 Discharze (El. 726'(a, Unit I Weir}

Diameter [inches]

78" 78" Flow rate [gpm]

176,579 196,369 FLOOD LEVEL - 745' Supply Diameter [inches]

90" 90" Flow rate [gpm]

179,496 200,586 Discharce (El. 730' (_Unit I Weirl Diameter [inches]

78" 78" Flow rate [gpm]

194,018 215,708

SHEET 33 of 93 WATTS BAR NUCLEAR PLANT - UNIT I SUPPLY, DISCHARGE AND BYPASS LINES 8.0

SUMMARY

OF RESULTS (continued) 8.2.3 The bypass line has a diameter of 42". The bypass line was modeled to pass approximately 40% of the supply flow. Table 8 shows the supply, discharge and bypass flow rates for the SCCW at Watts Bar Lake elevations of 735' and 738'. All of the valves are fully open; KB = 0.55, The bold value is the percent of supply flow flowing through the bypass line.

TABLE 8 Sizing the SCCW Bypass Line HW 130 HW = 150 WINTER LEVEL - 735' Supply from Lake

[gpm]

97,607 110,379 Supply to Unit 2 Cooling Tower

[gpm]

50,680 61,723 Bypassed Flow

[gpm]

46,927 [48.1%]

48,656 [44.1%1 Discharge from UI Cooling Tower

[gpm]

50,680 61,723 Discharge to Energy Dissipater

[gpm]

97,607 110,379 NOMINAL WINTER LEVEL -738' Supply from Lake

[gpm]

130,667 147,417 Supply to Unit 2 Cooling Tower

[gpm]

80,095 94,754 Bypassed Flow

[gpm]

50,572 [38.7%1 52,663 135.7%]

Discharge from U 1 Cooling Tower

[gpm]

80,095 94,754 Discharge to Energy Dissipatcr

[gpm]

130,667 147,417

SHEET 34 of 93 WATTS BAR NUCLEAR PLANT - UNIT I THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM

SUBJECT:

DOCUMENT THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES ID:

MDN 1027-980006 8.0

SUMMARY

OF RESULTS (continued) 8.2.4 Table 9 lists the head loss coefficients and their corresponding open angles for the supply and discharge lines. Keep in mind that for the summer condition, the required flow is 135,000 gpm, and the bypass line is closed.

TABLE 9 Supply and Discharge Valve Positions (Bvnass Line Closed)

HW = 130 HW = 150 SUMMER LEVEL - 740.5' Desire Flow Rate jgpm]

135,000 135,000 Flow Rate fgpm]

135,059 135,056 Supply Valve K

/ 0 Open K = 2.27 / 63' K = 4.36 / 580 Discharge Valve K / ° Open K = 0.55 / 90*

K = 0.55 / 900 FLOOD LEVEL - 745' Flow Rate

[gpml 165,795 182,051 Supply Valve K

/ 0 Open K = 2.27 / 650 K = 4.36 / 58° Discharge Valve K /

  • Open K = 0.55 / 900 K = 0.55 / 900 S.

S

SHEET 35 of 93 WATTS BAR NUCLEAR PLANT-UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN1027-980006 8.0

SUMMARY

OF RESULTS (continued) 8.2.5 Table 10 presents the head loss coefficients and their corresponding open angles for the bypass valve given the K values for the supply and discharge valves in Table 9. Keep in mind that the bypass line is to be used in the winter months only. Therefore, the two elevations that are of concern are Winter and Nominal Winter Levels of 735' and 738', respectively. The bypass line has to bypass approximately 40% of the supply flow. The bold values are the percent of the supply flow that is bypassed.

TABLE 10 Sunnly, Discharge and Bypass Valve Positions HW = 130 HW = 150 WINTER LEVEL - 735' Supply from Lake

[gpm]

93,943 101,391 Supply to Unit 2 Cooling Tower

[gpm]

56,165 59,937 Bypassed Flow [approx. 40%]

[gpm]

"37,778 140,2%]

41,454 140.9I1 Supply Valve

/ 0 Open K=2.27

/ 63' K=4.36 / 580 Discharge Valve/ *Open K = 0.55

/ 900 K = 0.55 1 900 Bypass Valve

/ 0 Open K = 2.50

/ 63' K = 2.00

/ 660 NOMINAL WI[NTER LEVEL - 738' Supply from Lake rgpm]

126,854 141,630 Supply to Unit 2 Cooling Tower

[gpm]

75,365 87,761 Bypassed Flow [approx. 40%)

[gpm]

51,489 140.6%]

53,869 138.0%]

Supply Valve

/ 'Open K = 2.27

/ 630 K= 4.36

/ 580 Discharge Valve/ *Open K - 0.55

/ 900 K = 0.55

/ 90' Bypass Valve

/ °Open K = 0.55

/ 900 K = 0.55

/ 90*

a

SHEET 36 of 93 WATTS BAR NUCLEAR PLANT - UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY. DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN 1027-980006

9.0 CONCLUSION

S 9.1 The SCCW system is sized properly with:

Supply Line:

90" (7.5')

Discharge Line:

78" (6.5')

Bypass Line:

42" (3.5')

Table 7 shows that for elevations 738' and 740.5', the supply line flows approximately 124,000 to 146,000 gpm, respectively. The SCCW will pass the required flow of 115,000 to 135,000 gpm from the Watts Bar Lake to the Watts Bar Nuclear Plant. The 115,000 gpm and 135,000 gpm correspond to the Watts Bar Lake Nominal Winter and Summer levels of 738' and 740.5'.

Table 10 shows that the bypass line flows approximately 40% of the supply flow during the winter months. Therefore, the bypass line is adequately sized for the SCCW system.

9.2 Three bays are necessary to flow 146,000 gpm through the SCCW system. This flow rate is conservatively greater than the i 35,000 gpm that is required.

9.3 The location of the bypass line allows the required 8 pipe diameters from other piping components on either side of the bypass valve. The bypass line accomplishes this requirement with minimal head losses due to the piping length.

9.4 All of the valves are located in close proximity to each other, and in the vicinity of the Unit 2 Cooling Tower. Their exact locations arc on Figure 9.

9.5 Using Hazen-Williams factors of HW=I30 and HW=l50, below are listed the open angle ranges for the supply, and bypass valves. The discharge valve remains fuIlly open.

Supply Valve:

580 -630 Discharge Valve:

900 Bypass Valve:

630 - 900 These supply valve values throttle the flow to 135,000 gpm, while the discharge valve value allows the flow to discharge without restriction. The bypass valve values allows approximately 40% of the supply flow to be divert to the discharge line. These values are well within the range of 30* to 900 for the best operating range for a butterfly valve in nuclear power plant service.

&J.

SHEET 37 of 93 WATTS BAR NUCLEAR PLANT - UNIT I SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN1027-980006 10.0 REQUIREMENTS/LIMITING CONDITIONS There are no requirements or limiting conditions generated by this calculation as described in NEDP-2, Section 3.1.21.

71I I

I

SHEET 39 of 91 WATTS BAR NUCLEAR PLANT-'UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN 1027-980006 11.0 SUPPORTING GRAPHICS (continued)

"I Figure 2: SCCW Supply Flow Diagram

SHEET 40 or 93 WATTS BAR NUCLEAR PLANT'-UNIT I 11.0 SUPPORTING GRAPHICS (continued)

UI4IT I

6.0oU N~ TrOWEK 200 20 220 1ý 233 135 240 Z70 2go 2400 310 OPEN CH-ANNe.L 330 3zo LFMeN Rcly Dtsst1pATe1g Figure 3: SCCW Discharge Flow Diagram

~.,..,-..

~.-

-~, I - ý, I r L-,qjU--1 IMM2 1F,&RtrA2xj NO M " KwTA

ý Fý-

, ý -

7

SHEET 41i of 22 WATTS BAR NUCLEAR PLANT'--UNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID.

MDN 1027-980006 S11.0 SUPPORTING GRAPHICS (continued) 3CR (EN NOU~iS Mgwmman. &W4, oif wcIhIrd rAipd a

w No 4iItA& CO-A~it Figure 4: Intake Screen House Profile

.:....,A~

..n~..,..

Sr S.

1/4.

SHEET 42 of 93 WATTS BAR NUCLEAR PLANT---NIT I SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDNI027-980006 11.0 SUPPORTING GRAPHICS (continued) 9TAIL A II I!

U II I

I FLOW AREA bH-b-2/" --

/

SECTION A-A 5/'

V Figure 5: Trash Rack

mwmý SHEET 43 oF--93 WAT'TS BAR NUCLEAR PLANT - UNIT I SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDN 1027-980006 11.0 SUPPORTING GRAPHICS (continued)

I I(/

5LUICE GIATh.

OPEN IN(ý MO DELE P GATE VA LVE Figure 6: Sluice Gate

SHEET 44 of 93 WATTS BAR NUCLEAR PLANT-UNIT I SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDNI027-980006 11.0 SUPPORTING GRAPHICS (continued) 20-2 034w 03CK 038v1 0

T-

-414 IA-7 PRO FI L-E, LlKOT To 5CALG)

  • E-A +-B Figure 7: Transitional Segment 1 (TS1)

Aýl

SHEET 45 of 93 WATTS BAR NUCLEAR PLANT fJNIT I

SUBJECT:

THE SIZING OF THE SUPPLEMENTAL CONDENSER COOLING WATER (SCCW) SYSTEM SUPPLY, DISCHARGE AND BYPASS LINES DOCUMENT ID:

MDNI027-980006 11.0 SUPPORTING GRAPHICS (continued) ii L

I Alto R;A -

zfc~v CSeCr'OA' 7

I-'VLýy&

£~Cfl~N a sev?0gAJ 3,01,;W S4r Figure 8: Transitional Segment 2 (TS2) 4,r'N t 1 19

.1

APPENDIX A MDNI027-98006 Rev. 0 PACE 47 of 93 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer~net:

SUMMER Timer 1450 I

Page __ of _

Prepared J

/

Date 512 Checked+

Date 15/1774


TVA AUTHORIZED USE ONLY ----------------------------

system contains 180 parts: 90 links, 84 nodes, 0 pumps, 6 tees Default values of parameters:

default_temperature-83 barometric_pressure-14.7 default reaches-1 solution-control optian=l Parameters for initial estimation of density:

temperature-83 pressure=0 standard=Raw water (liquid; standard density=62.3735 Ibm/ft3)

FG CS CI CL CO Cu PV PO SS pipe material fiberglass........

carbon steel......

cast iron.........

cement-lined......

concrete..........

copper............

PVC...............

polyethylene......

stainless steel...

Hazen-W C dia.red.

130.00 55.00

.100.00 140.00 130.00 130.00 130.00 130.00 120.00 0.000 0.400 0.000 0.000 0.000 0.000 0.000 0.000 0.000 c-- non-standard

                        • .*t**.t

~SOLUTION

SUMMARY

i************~*

Solution Status = Converged.

Number of Iterations = 26 Largest Corrections in Last Iteration:

Flow -

-8.25e-005 agpm Pressure -

5.57e-010 psig Tee Loss Coefficient -

0.O0e+000 i

J-

'icApQ.

't."*. "

APPENDIX A NIDNIC27-98006 Rev. 0 PAGE 48 of 93 Dates 05/26/98 (Tue)

EZFLOWt Version 5.00 site: unspecified Summer.net: SUMMER Time: 1450 2

Page __ of Prepared Checked Date Date _

TVA AUTHORIZED USE ONLY NETWORK DETAIL link 000A..005A-> "O00A>005A" inlet=000A, exit-005A, sch=NS, mal "slightly rounded entrance"

-straight pipe".

len=l link 000B--005B-> "000B>00SB" inlet=000B, exitx005B, sch-NS, ma "slightly rounded entrance" "straight pipe",

ler=1 link 000C--005C0>

"OOC>0O0SC" inlet-000C, exit00SC, sch=NS, ma "slightly rounded entrance" "straight pipe", len-I link 005A-007A"> "O05A;007A" inlet=005A, exit-007A, sch=DUCT, "other: TRASH RACK",

K=0.72 "decreaser", dia=0 link 005B--007B "005B>007B" inlet-005B, exit-007B, sch-DUCT, "other: TRASH RACK",

K-0.72 "decreaser", diamo link 005C--007C-> "0O5C>007C" inlet-OOSC, exit-007C, sch=DUCT, "others TRASH RACK",

K-0.72 "decreaser",

dia-0 link 007A.-009A=> "007APO09A" inlet.007A, exit-009A, sch=DUCT,

  • straight pipe", len-8 "decreaser", diaO0 link 0078-w009Bu> "007B'009B" inlet.007B, exit=0098, sch-DUCT, "straight pipe", len-8 odecreaser", dia-0 link 007C-.009C-> "007C>009C" inlet.007C, exit=009C, sch.DUCT, "straight pipe",

len-S

-decreaser",

dia-0 link 009Am-01lA->

"009A"011A" t."carbon steel", dia=144 t="carbon steel", dia-144 t-"carbon steel", dian*144 mat-"carbon steel", high-252, wide-li4 mat="carbon steel", high-252, widaa**4 matm"carbon steel", high-252, wide,114 mat-"concrete", high-366, widea72 mat="concrete",

high=366, wide-72 mat-"concrete",

high-366, wide-72 inletnO009A, exit-011A, sch-NS, mat-"carbon steel", dia*94 mothers SLUICE GATE",

K%0.072 "increaser", dia.O q,

"u,_

APPENDIX A MDNIO27-98006 Rev. 0 PAGE 49 or 93 Date: 05/26/98 (Tue)

Time: 1450 EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER


TVA AU 3

Page of Prepared Checked Date _/_/_

Date 1/

THORIZED USE ONLY ----------------------------

NETWORK DETAIL I

14 link 009B-=011B=> "009B>011B" inlet-0098, exit-011B, sch-NS, mat-"carbon steel", d:

"other: SLUICE GATE",

K-'0.072 "increaser", dia=0 link 009C--0llCs> "009C>011C" inlet-009C, exit-011C, sch-NS, mato'carbon steel", d.

"other% SLUICE GATE",

K=O.072 "increaser", dia-0 link 011A==013A->

"011A>013A" inlet011A, exit=013A, sch=DUCT, matu"carbon steel",

"other: TRAVELING SCREEN",

flow'135100, dp.0.015 "decreaser", dia-0 link 011B==013BD> "011B>013B" inlet-011B, exit=013B, sch=DUCT, mat."carbon steel",

"other: TRAVELING SCREEN",

flow-135100, dp.o.01S "decreaser", dia=0 link 011C--013Cf> "011C>013C" inlet=011C, exit-013C, sch-DUCT, mat=1'carbon stee.",

"other: TRAVELING SCREEN",

flow-135100, dp-0.015 "decreaser", dia-0 link 013A-=015A-> "013A>015A" inlet-013A, exit-01SA, sch-NS, mat."carbon steel", d Uother: SLUICE GATE",

K-0.072

  • decreaser",

dia=0 link 013B=-015B-S "013B>015B" inleto013B, exit-01SB, sch-NS, mat="carbon steel", d "other: SLUICE GATE",

Ku0.072 "decreaser", diaa0 link 013C--015Cfi-

"013C>015C" inlet4013C, exit-015C, sch'=NS, mat-"carbon steel",

d "other: SLUICE GATE",

K=0.072 "decreaser", dia-O higha366, wides'72 high=366, wide-72 hi1jh-366, widas7Z ia=94 ia-94 ia"94 ia-94 ia=94 link 01SA--020A-> "015A>020A" inlet-01SA, exit=020A, sch-DUCT, mat-"concrete", high*96, wide.72 "atraight pipe",

len-a "mitered bend",

angle=90 "increaser", area-10764 A

APPENDIX A L!DNI027-98006 Rev. 0 PAGE 50 or 93 Date: 05126/98 (Tue)

Time: 14S0 4

Page of _

EZFLOW: Version 5.00 Prepared Date __

siter unspecified Checked Date _/_/

Summer.net:

SUMMER


TVA AUTHORIZED USE ONLY ----------------------------

NETWORK DETAIL link 01SB=.O20B-> "01SB>O20B" inlet--LSB, exit=020B, sch-DUCT, m

"other: SLUICE GATE",

K=0.072 "straight pipe",

len-B link O0SC--020C->

"015C>020C" inlet-01SC, exitO020C, sch=DUCT, m

"other: SLUICE GATE", K-0.072 "straight pipe", len=8 link 020A=-TEE.B> "020A>TEE.B" inlet-020A, exit-TEE.B, sch=DUCT, "straight pipe",

len=12 link 020BssTEE.B> "020B>TEE.B" inlet=020B, exit=TEE.B, sch-DUCT,

-straight pipe",

len-1 link 020C--TEE.C>.020C>TEE.C" inlet-020C, exit-TEE.C, sch-DUCT,

'straight pipe", len-i link 025-w.028-.5 002S>028" inlet-=025, exit028, sch=DUCT, ma "straight pipe", len-1ll.5 link 02B-ao030q.> "028>030" inlet=028, exit-030, sch-DUCT, ma "straight pipe",

len.56.56 "mitered bend",

angle=7 "straight pipe",

Ien=15.95 at""corncrete". high'.96, wide-72

at-"cor'crete", high=96, widew72 mat ="concrete", high-2.38, wide-78 mac-"concrete", high-96, wide-72 mat-"concrete". high-96, wideu72 t.,"concretem, high-I138, wide*78 t="concrete". high-138, wide-78 link 030...TRANS;- "030>TRANS.TEE" inlet-030, exitnTR.ANS.TEE, sch=DUCT, mat."concrete", high.138, widew78
  • straight pipe", lenal link 032A.-034A->

"032A>034A" inlet-032A, exit=034A, sch=DUCT.

"straight pipe", len-3.5 "increaser", area.5830 link 032B.=034a=> "032B>034B" inlet=O32B, exit034B,

schaDUCT, "straight pipe",

lenw3,5 "increaser", areamS830 mat,,"concrete", high-138, wide-39 iaat."concrete". highs236, widen39 5;5

-*<rtt..

APPENDIX A MDNI027-98006 Rev. 0 PAGE 51 of 93 Date: 05/26/98 (Tue)

EZFLCW: Version 5.00 site: unspecified Summer.net:

SUMMER Time: 1450 5

Page of Prepared Checked Date _/_/

Date


TVA AUTHORIZED USE ONLY ----------------------------

NETWORK DETAIL link 034An=036A=> "034A>036A" inlet-034A, exit=036A, sch-DUCT, "straight pipe", ien-3.5 "increaser", area-6026 link 034B==O36B=-

"034B>036B" inlet-0349, exit-O36B, sch.DUCT, "straight pipe", len=3.5 "increaser", area=6026 link 036A--038A-> "036A>038A" inlet-036A, exit-038A, sch=1UCT, "straight pipe",

len-3.5 "increaser", area=5971 link 036B."038B6=

"036B>038B" inlet=036B, exit=03BB, sch-DUCT, "straight pipe", lent3.5 "increaser", area-5971 link 035A--040A'> "038A>040A" inlet=038A, exitt040A, sch=DUCT, "straight pipe",

len-3.5 "increaser", area-S663 link 038B--040B-> "038Bf040B" inlet=0386, exita040B, sch.DUCT, "straight pipe", len-3.5 "increaser", area-5663 link 040A--041A-> "040A>041A" inlet-040A, exit-041A, sch-DUCT, "straight pipe", len-i "increaser", area=5385 link 040DB=041B-> "040B*041B" inlet-040B, exit-041B, sch=DUCT, "straight pipe", len-i "increaser", area-5385 link 041A--042A-> "041A>042A" inlet-041A, exit-042A, sch-DUCT, "straight pipe",

len-i "increaser", area-5464 link 041Bu-042B-> "041B>042B" inlet-041B, exit-042B, sch-DUCT, "straight pipe", len-i "increaser", area-5464 mat-"concrete", high-123, wide-47.4 mat."concrete", high-123, wide=47.4 matu"concrete", hight108, wide-55.8 matn"concrete", high=108, wide-55.8 mat="concrete", higbh93, wide"60.24 mat-"concreta',

high-93, wide.60.24 mac-"concrete", high-78, wide-72.6 mat-"concrete", high-7e, wide-72.6 mat- "concrete", higha78, wide-69.04 mat-"concrete", high-78, wideu69.04 j

APPENDIX A MDNI027-98006 Rev. 0 PAGE 52 of 93 Date: 05/26/98 (Tue)

EZFLOW: Version S.00 sitei unspecified Summer.net: SUMMER Time: 1450 6

Page _- of _

Prepared Date

/_/_

Checked Date _/_/_


TVA AUTHORIZED USE ONLY ----------------------------

NETWORK DETAIL link 042A=.043A>,, "042A>043A"

,inlet-042A. exit-043A, sch=DUCT, "straight pipe",

len-i "increaser", dia-5474 link 042B=-0438-> "042B>043B" inlet=042B, exit=0438, sch=DUCT, "straight pipe", len-1 "increaser", dia-5474 link 043As.044A.> "043A>044A" inlet-043A, exit-044A, sch-DUCT, "straight pipe",

len-I "increaser",

area-5403 link 043B.n04413> "0438>0448" inlet-0439, exit-0440, sch-DUCT, "straight pipe",

len.i

  • increaser", area=5403 link 044An-045A-> "044A>045A" inlet-044A, exit-04SA, sch-DUCT, "straight pipe",

len-i "increaser",

dia-0 link 044B==045Ba.

"044B>045B" inlet-044B, exit'045B, sch"DUCT, "straight pipe", len-l "increaser", dia=0 link 045A-.046A-> "045A>046A" inlet-045A, exit-046A, sch-NS, m "straight pipe", lenal "decreaser", diac0 link 0458..0468-> "045B5045B" inlet-0453, exit-046B, sch-NS, m "straight pipe", len-i "decreaser", diae0 link 046AS-050A> "046A>050A" inlet-046A, exit-OSOA, schuNS, "straight pipe-, len=o.S "decreaser", dia-0 link 046B--OS08-> "0459>050B" inlet-C468, exitmOSOB, schaNS, "straight pipe",

lenio.5 "decreaser", diae0 mat-"concrete",

high-78, wide-70.05 mat-"concrete", high-78, widea70.05 mats"concrete", high-78, wide-70.18 maeu"concrete", high-78, wide-70.18 mat-"concrete", h4gh-70, widce69,27 matn"concrete", high=78, wide=69.27 at-"concrete", dia-81.78 at-"concrete", dia-81.78 Iat-"concrete", diau79.44 tat."concrete", dia.79.44 t

S A.

i9*?44

APPENDIX A MDNI027-98006 Rev. 0 PAGE 53 of 93 Date: 05/26/98 (TUe)

Time: 1450 7

Page __ of _-

EZFLOW; Version 5.00 Prepared Date _/_/

site: unspecified Checked Date _/_/_

Summer~net: SUMMER


.------------- TVA AUTHORIZED USE ONLY NETWORK DETAIL link 050A=-060A=> "0SA>060A" inlet=050A, exit.060A, sch=NS "straight pipe",

len-B00 "mitered bend",

angle"2 "straight pipe", len-500 "mitered bend", angle-I "straight pipe",

len=1400 "mitered bend", angle=2 "straight pipe",

1enw292 link 050B-=060B=> "S08>6O080" inlet-050B, exit=060B, schmNS "straight pipe", len800 "mitered bend",

angle-2 "straight pipe",

len=Soo "mitered bend", angle-I "straight pipe",

len=1400 "mitered bend", angle=2 "straight pipe", Ien.315 link 060A"-SCCW.> "060A>SCCWT inlet-060A, exit-SCCW.TEE, sc "straight pipe", len-1 link 060B=sSCCW.> "0609>SCCW..

inletO060B, exit-SCCW.TEE, ac "mitered bend", angle-90 "straight pipe", len-40 link 070-=.0.0=-8.>

070>o80" inlet-070, exit-080, sch=NS, "straight pipe", len.150 link 080---090-w>

"080>090" inlet=080, exit=090, sch.NS, "straight pipe", len=100 link 090=--100..> "090>100' inlet-090, exit.100, sch"NS, "straight pipe-, ien-650 link 100---LID=.:

"I00>1i0" inlet-=00, exit-it0, sch-NS, "straight pipe", len-440 link 110ww-120an> "110>120" inlet-hO0, exitm120, schaNS, "straight pipe", Ien-139 mat-"concrete", dia=78 mat-,concrete", dia-75 h-NS, mat."Concrete", diau78

'EEO

!h=NS, mat."concrete", dia-7a mat."eoncretel, dia=90 mat',"concrete", dia=90 cnat."concrete", dia-90 mnat."concrete", dia.'90 mat-"Concrete", dia"'90 N

J,-,

APPENDIX A MDNIO27-98006 Rev. 0 PAGE 54 of 93 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER Time: 1450 8

Page _-

of Prepared Checked Date _/_/

Date _/_/


TVA AUTHORIZED USE ONLY ----------------------------

NETWORK DETAIL link 120=..130-->

"120>130" inlet=120, exitnl30, sch-NS, "straight pipe", len-814 link 130...140.:, "130>140" inlet.130, exit=140,

schuNS, "straight pipe",

len-248 link 140-=150==O-

"140>150" inlet-140, exit-150, sch=NS, "straight pipe",

len=250 link 150===160--> "150>160" inlet=l50, exit-16D, sch-NS, "straight pipe",

len=4S0 mat-"concrete",

dia-90 mat-"concrete",

dia-90 mat="concrete",

dia-90 mat-"concrete",,

dia-90 link 160==-BYPAS> "160ý.BYPASSUP.TEE" inlet-E60, exit=BYPASSUP.TEE, sch-NS, mat-"concrete", dia"90 "straight pipe",

1enn287 link 163-=-w165->

"SUPPLY VALVE" inlet-163, exit-16S, sch-NS, mat-"carbon steel", dia=90 "butterfly valve,",

K=O.SS link l65-.-170--. "165>FACE OF WEIR" inlet-I6S, exit-l70, sch-NS, mat="concrete", dia-90 "straight pipe", len-17 link 170.--180--> "FACE OF WEIR>FACE OF TOWER" inlet-170, exit=180, sch-NS, mat-"concrete", dia-144 "straight pipe".

len=1 link 200-..205--> "UNIT 1 WEIR" inlet=200, exit=205, sch-NS, matu"concrete",

dia-144 "square edged entrance" "straight pipe", len-1 link 205-.z210.-> "205>210" inlet-205, exit-210,

schnNS, mat-"concrete", dia-78 "straight pipe", len.45 link 210-na220-=> "210>220" inlet-210, exit-220, sch"NS, mat-"concrete",

dia-78 "mitered bend", angle-45 "straight pipe", len-S5 i

t

    • .**WOW:.*.

APPENDIX A MDNI027-98006 Rev. 0 PACE 55 of 93 Date: 05/26/98 (Tue)

Time: 14S0 9

Page __ of __

EZFLOWi Version 5.00 Prepared Date

//

site:

unspecified Checked Date _/_/

Summer.net; SUMNER T V A A U T H O R I Z E D U S E O N L Y ----------------------------

NETWORK DETAIL link 220f..'e230=->

"220>230" inlet.220, exit=230, sch=NS, "straight pipe", len-700 link 230=-=233w-> "230>233" inlet=230, exit=233, sch-NS, "straight pipe", len=80 mat="concrete", dia.78 mat-"concrete", dia.78 link 233.==235=-> "DISCHARGE VALVE" inlet'233, exit-232, sch=NS, mat."carbon steel", dia-78 "butterfly valve", K=0.55 link 235n=nBYPAS> "235>BYPASDIS.TEE" inlet=235, exitnBYPASDIS.TEE, sch=NS, mat-"concrete", dia-78 "straight pipe", len=155 link 240...250o-> "240>250" inletu240, exit=250, sch=NS, "straight pipe", lens450 link 250-..260==w "290>260" inlet-250, exit=260, sch=NS,

'straight pipe", len=250 link 260=uc270-=> "260>270" inlet-260, exit=270, sch-NS, "straight pipe", len-250 link 270n=s280=.> "270>280" inlet-270, exitu280, schaNS, "straight pipe",

lenw820 link 280---290--> "280>290" inlets280, exit-290, sch-NS, "straight pipe", len.140 link 290-5u300-=-

"290>300" inlet-290, exit.300, schaNS, "straight pipe",

len=440 link 300su-310--.> "300>310" mat="concrete",

dia=78 mat="concretQ",

4+/-as78 mat-"concrete", dia.78 mat="concrete",

dia=78 mat-"concrete", dia=78 mat-"concrete", dia-78 inletw300, exit-310, sch-NS, mat-"concrete", dia-78 "straight pipe", len.400 link 310---320-->

"310>320" inlet-310, exit-320n sch-NS, mat-"concrete", diau*9 "straight pipe", lenmS5

'. V4.

.V'"'

APPENDIX A DMDNI027-98006 Rev. 0 PAGE 56 of 93 Date: 05/26/98 (Tue)

EZFLOW: Version S.00 site: unspecified Summer.net: SUMMER Time: 1450 10 Page of __

Prepared Checked Date

/_/_

Date _/_/_


TVA AUTHORIZED USE ONLY ----------------------------

NETWORK DETAIL link 320=-330=n-

"INLET TO ENERGY DISSIPATER" inlet=320, exit=330, sch=NS, mat="concrete",

dia-78 "mitered bend", angle-75 "straight pipe", len=1 "exit" link SYPAS"163=-" "BYPASSUP.TEEz163" inlet=BYPASSUP.TEE, exit=163, sch=NS, "straight pipe", leno80 link BYPAS-240.s> "BYPASDIS.TEE>240" inlet-BYPASDIS.TEE, exit-240, sch.NS, "straight pipe", len=165 mat-"concrete", dia-90 mat="concrete", diaa78 link BYPAS-BYPAS> "BYPASS LINE FROM SUPPLY TO DISCHARGE" inletuBYPASSUP.TEE, exitnBYPASDIS.TEE, schaNS, mat="concrete",

dia-42 fixed flow=0 "straight pipe", len-10 "mitered bend", angle.45 "straight pipe", len-7S "butterfly valve",

K-O.S5 "straight pipe", len-60 link SCCW.n070.=> "SCCW.TEE>070" inletnSCCW.TEE, exit-070, sch=NS, mat-"concrete", dia-90 "straight pipe", len-90 link TEE.B-TEE.C> "TEE.B>TEE.C" inlet-TEE.B, exit-TEE.C, schmDUCT, mats"concrete", high.138, wide-78 "straight pipe", len=12 link TEE.C-025.-; "TEE.C>02S" inlet-TEE.C, exit-025, ach-DUCT, mat-"concrete",

high-138, wide-78 "straight pipe", len-l link TRANS-032A-'

inlet-TRANS.TEE, "straight pipe",

link TRANS=O32B->

inletuTRANS.TEE, "straight pipe",

"TRANS.TEE.032A" exit-032A, schwDUCT, len-1 "TRANS.TEE.032B" exit-032B, sch-DUCT, len-l mata-"concrete",

highli38, wide-39 mat-"concrete",

high-138, wide-39 node OOOA "WATTS BAR RESERVOIR" elev-740.5, pres-O, temp-83 node OoaB "WATTS BAR RESERVOIR" eleva740.S, pres-0, temp-83 Ci.,

A..**,

.'I*

.si-sJ*

'-t',

APPENDIX A MDNI027-98006 Rev. 0 PAGE 57 of 93 Date: 05/26/98 (Tue)

Time:

1450 11 Page of EZFLOW: Version 5.00 Prepared Date _/_/_

site: unspecified Checked Date _/_/_

Summer.net:

SUMMER TVA AUTHORIZED USE ONLY NETWORK DETAIL node 000C "WATTS BAR RESERVOIR" elev-740.5, pres-0, temp-83 node 005A '*TRASH RACK - A INLET" elev=720.5 node 005B "TRASH RACK - B INLET" elev=720.5 node 005C "TRASH RACK -

C INLET" elev=720.5 node 007A "TRASH RACK A OUTLET" elev=725.25 node 007B "TRASH RACK -

B OUTLET" elev-725.25 node 007C "TRASH RACK -

C OUTLET" elev=725.25 node 009A "4i SLUICE GATE -

A INLET" elev=714 node 0098 "41 SLUICE GATE -

B INLET" elev.714 node 009C "f1 SLUICE GATE -

C INLET" elev-714 node 011A "INLET TO TRAVELING SCREEN A" elev=725.25 node 011B "INLET TO TRAVELING SCREEN B" elev=725.25 node 011C "INLET TO TRAVELING SCREEN C" elev=725.25 node 013A "#2 SLUICE GATE A INLET" elevu714 node 013B "f2 SLUICE GATE B INLET" elev"714 node 013C "#2 SLUICE GATE INLET" e~ev-714 z..

APPENDIX A MDN1027-98006 Rev. 0 PAGE L8 of 93 Date: 05/26/98 (Tue)

Time: 1450 12 Page -

of EZFLOW: Version 5.00 Prepared __

Date jj/_

site: unspecified Checked Date

/_/_

Summer.net: SUMMER


TVA AUTHORIZED USE ONLY ----------------------------

NETWORK DETAIL node 015A "no description" elev-714 node 0150 "no description" elev-s14 node 015C "no description" elevn714 node 020A "no description" elevs714 node 0209 "no description" elevm714 node 020C "no description" elev-714 node 025 "INTAKE SCREEN HOUSE OUTLET -

CONDUIT THRU DAM INLET" elev-715.75 node 028 "CONDUIT THRU DAM OUTLET" elev=715.7 node 030 "CONDUIT TRANSITIONS & SPLITS INTO A & B PIPING RUNS" elev-716.56 node 032A "no description" elev-715.56 node 032B "no description" elev=715.56 node 034A "no description" elev-716.18 node 034B "no description" elev-716.18 node 036A "no description" elevu716..

node 0368 "no description" elevn71.9 node 038A "no description" elev-717.42

APPENDIX A MDNI027-98006 Rev. 0 PAGE 59 of 93 Date: 0S/26/98 (TMe)

Time: 1450 13 Page __ of __

EZFLOW; Version 5.00 Prepared Date _/_/

site:

unspecified Checked Date _/_/

Summer.net: SUMMER TVA AUTHORIZED USE ONLY ----------------------------

NETWORK DETAIL node 038B "no description" elev-717.42 node 040A "A PIPE TRANSITION AREA" elev-718.01 node 040B "B PIPE TRANSITION AREA" elev-718.01 node 041A "no description" elev=718.01 node 041B "no description" elev-718.01 node 042A "no description" elev-71B.01 node 042B "no description" elev.718.01 node 043A "no description" elev-718.01 node 043B "no description" elev-718.01 node 044A "no description" elev-718.01 node 044B "no description" elev.718.01 node 045A "no description" elev,718.01 node 045B "no description" elev-719.01 node 046A "no description" alev=718.01 node 046B "no description" elev-718.01 node 050A "78 INCH A PIPE" elev-718.01

. *.i.

* -.i *,i,:,;*,.:, *,

i

a APPENDIX A MDNI027-98006 Rev. 0 PAGE 60 of 93 Date: 05/26/98 (Tue)

Time: 1450 14 Page

_ of EZFLOW: Version 5.00 Prepared Date _/_/_

site: unspecified Checked Date

//

Summer.net: SUMMER


TVA AUTHORIZED USE ONLY ----------------------------

NETWORK DETAIL node 050B "78 INCH B PIPE" elev=718.01 node 060A "060A TIE INTO EXISTING 78" elevE684.75 node 0603 "060B TIE INTO EXISTING 78" elev-684.25 node 070 "no description" elev-6u6.15 node 080 "no description" elev-694.85 node 090 "no description" elevu696.25 node 100 "no description" elev-721.25 node 110 "no description" elev-721.25 node 120 "no description" elev-716.25 node 130 "no description" elev=715.35 node 140 "no description" elev-708.95 node 150 "no description" elevu718.95 node 160 "no description" elevu721.45 node 163 "SUPPLY VALVE OUTLET" elev-721.45.

node 165 "SUPPLY VALVE OUTLET" elev,721.45

'..+

ii;*'.

+node 110,.*,

"UNIT 2 EI INLET"

++
  • /

i I!`::+I elev-721'+55

APPENDIX A MDNI027-98006 Rev. 0 PAGE 61 or 93 Date: 05/26/98 (Tue)

Time: 1450 15 Page __

of EZFLOW: Version 5.00 Prepared Date _/_/

site: unspecified Checked Date

/_/

Summer.net: SUMMER


TVA AUTHORIZED USE ONLY ----------------------------

NETWORK DETAIL node 180 "UNIT 2 WEIR OUTLET" elev-731, pres=0, temp-92 node 200 "UNIT 1 WEIR INLET" elev-726, pres.0, temp-92 node 205 "UNIT 1 WEIR OUTLET" elev.722.75 node 210 "OUTLET OF 45 ELBOW" elev-723.55 node 220 "no description" elev.724.35 node 230 "no description" elev*721.05 node 233 "DISCHARGE VALVE INLET-elev-721.05 node 235 "DISCHARGE VALVE OUTLET" elev.7Z1.05 node 240 "no description" elev-720.95 node 250 "no description" elev.718.45 node 260 "no description" elev-708.45 node 270 "no description" elev-714.85 node 280 "no description" elev-715.75 node 290 "no description" elev.720.75 node 300 "no description" elev-720.75 node 310 "no description" elevn705.65

APPENDIX A MDNIO27-98006 Rev. 0 PAGE 62 of 93 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER Time: 1450 16 Page __ of __

Prepared __

Checked Date _/_/_

Date _/_/_

-TVA AUTHORIZED USE ONLY NETWORK DETAIL node 320 "INLET TO 75 ELBOW" elev=705.25 node 330 "ENERGY DISSIPATER" elev=705.25, pres=0 tee BYPASDIS.TEE "235>BYPASSUP.TEE>240" nodel=235, node2-BYPASSUP.TEE, node3=240, "non-standard converging", angles=45,0 tee BYPASSUP.TEE "160>BYPASDIS.TEE>163" nodel=160, node2=BYPASDIS.TEE, node3=163, "standard diverging (run tolateral)"

elev=721.05 elev-721.55 tee SCCW.TEE "060B>060A>070".

nodel-060B, node2-060A, node3-070, elev-684.25 "standard converging" tee TEE.B "020A>020B>TEE.C" nodel=020A, node2-020B, node3-TEE.C, elev-714 "standard converging" tee TEE.C (TEE.!>020C>025" nodelTEE.B, node2O02OC, node3-025, elev-714 "standard converging" tee TRANS.TEE "030>032A>032B" nodel-030, node2-032A, node3a032B, elev-715.56 "non-standard diverging",

anglesi22,22 5L.

uv t.Ž~n 1/4.~4Y 4vy,..t@

APPENDIX A NtDN1027-98006 Rev. 0 PAGE _Q of 93 Date: 05/26/98 (Tue)

Time: 1450 17 Page __ of __

EZFLOW: Version 5.00 Prepared Date _/_

site: unspecified Checked Date _/_/_

Summer.net: SUMMER


. TVA AUTHORIZED USE ONLY ----------------------------

SUMMARY

OF LINKS Inlet node exit node mat dia sch red Hzn-Will sgpm c-head head-> dPdrop O00A 005A CS 144 NS def default 35895 740.5 740.49 -8.659 00OB 0058 CS 144 NS def default 43957 140.5 740.49 -8,657 00CC 00SC CS 144 NS def default 66102 740.5 740.47 -8.648 005A 007A CS 0 DUC def default 35895 740.49 740.47 2.0655 0059 0079.

CS 0 DUC def default 43957 740.49 740.46 2.0695 005C 007C CS 0 DUC def default 66102 740.47 740.4 2.0848 007A 009A Co 0 DUC def default 35895 740.47 740.43 -4.856 007B 009B CO 0 DUC def default 43957 740.46 740.4 -4.847 007C 009C CO 0 DUC def default 66102 740.4 740.27 -4.814 009A 011A CS 94 NS def default 35895 740.43 740.45 4.8652 0098 011o CS 94 NS def default 43957 740.4 740.42 4.8613 009C 011C CS 94 NS def default 66102 740.27 740.33 4.8467 011A 013A CS 0 DUC def default 35895 740.45 740.4

-4.85 0118 013B CS 0 DUC def default 43957 740.42 740.35 -4.839 011C 013C CS 0 DUC def default 66102 740.33 740.15 -4.796 013A 015A CS 94 NS def default 35895 740.4 740.35.01835 0138 015B CS 94 NS def default 43957 740.35 740.28.02752 013C 015C CS 94 NS def default 66102 740.15 740.01.06225 01SA 020A CO 0 DUC def default 35895 740.35 740.31.01747 0159 0205 CO 0 DUC def default 43957 740.28 740.27.00423 015C 020C CO 0 DUC def default 66102 740.01 739.98.00945 020A TEE.B CO 0 DUC def default 35895 740.3i 740.27.01835 0209 TEE.9 CO 0 DUC def default 43957 740.27 740.08.08362 020C TEE.C CO 0 DUC def default 66102 739.98 739.37.26696 025 028 CO 0 DUC def default 145953 739.37 739.27.04144 028 030 CO 0 DUC def default 145953 739.27 739.2 -. 0507 030 TRANS.TEE CO 0 DUC def default 145953 739.2 738.37.35909 032A 034A CO 0 DUC def default 78111 738.37 738.93.02255 0329 0349 CO 0 DUC def default 67842 738.72 739.15.08305 034A 036A CO 0 DUC def default 78111 738.93 739.27.12243 0349 036B CO 0 DUC def default 67842 739.15 739.41.15836 036A 038A CO 0 DUC def default 78111 739.27 739.49

.1745 036B 038B CO 0 DUC def default 67842 739.41 739.57.19764 038A 040A CO 0 DUC def default 78111 739.49 739.7.1654B 0389 0408 CO 0 DUC def default 67842 739.57 739.73.18764 040A 041A CO 0 DUC def default 78111 739.7 739.84 -. 0615 0409 0419 CO 0 DUC def default 67842 739.73 739.83 -. 0463 041A 042A CO 0 DUC def default 78111 739.84 740.03 -. 0835 041B 0428 CO 0 DUC def default 67842 739.83 739.98

-. 063 042A 043A CO 0 DUC def default 78111 740.03 740.03.00042 0428 0439 CO 0 DUC def default 67842 739.98 739.98.00033 043A 044A CO 0 DUC def default 78111 740.03 740.2 -. 0749 0439 0448 CO 0 DUC def default 67842 739.98 740.11 -. 0565 044A 045A CO 0 DUC def default 78111 740.2 740.37 -. 0737 0449 0458 CO 0 DUC def default 67842 740.11 740.24 -. 0556 045A 046A CO 81.78 NS def default 78111 740.37 740.32.02543 0459 046B CO 81.78 NS def default 67842 140.24 740.19.01919 046A 050A CO 79.44 NS def default 78111 740.32 740.27.01751 0469 050B CO 79.44 NS def default 67942 740.19 740.16.01321 050A 060A CO 78 NS def default 78111 740.27 737.61 -13.25 0509 0609 CO 78 NS def default 67842 740.16 738.09 -13,73

4.

APPENDIX A MDNI027-98006 Rev. 0 PAGE 64 or 93 Date: 05/26/98 (Tue)

Time: 1450 2

EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER TVA AUTHORIZED

.8 Page _ of _

Prepared Checked Date Date _/_

USE ONLY -----------------------------

SUMMARY

OFLINKS inletnode 060A 060B 070 080 090 100 110 120 130 140.

150 160 163 165 170 200 205 210 220 233 235 240 250 260 270 280 290 300 310 320 BYPASSUP.TEE BYPASDIS.TEE BYPASSUP.TEE SCCW.TEE TEE.9 TEE.C TRANS.TEE TRANSTEE exitnode mat SCCW.TEE Co SCCW.TEE CO 080 CO 090 Co 100 CO 110 CO 120 CO 130 CO 140 CO 150 CO 160 CO BYPASSUP.TEE CO 165 CS 170 CO 180 CO 205 CO 210 CO 220 CO 230 CO 233 CO 235 CS BYPASDIS.TES CO 250 CO 260 CO 270 CO 280 CO 290 CO 300 CO 310 CO 320 CO 330 CO 163 CO 240 CO BYPASDIS.TEE CO 070 Co TEE.C CO 025 CO 032A CO 032B CO dia sch red 78 NS def 78 NS def 90 NS def 90 NS def 90 NS def 90 NS def 90 NS def 90 NS def 90 NS def 90 NS def 90 NS def 90 NS def 90 NS def 90 NS def 144 NS def 144 NS def 78 NS def 78 MS def 78 NS deo 78 NS deo 78 NS deo 78 MS def 78 NS def 78 MS def 78 NS det 78 MS deo 78 NS def 78 NS def 78 NS def 78 NS def 78 NS def 90 NS det 78 MS def 42 MS def 90 NS def 0 DUC def 0 DUC def 0 DUC deo 0 DUC dof Hzn-Will default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default default sgpm 78111 67842 145953 145953 145953 145953 145953 145953 145953 145953 145953 145953 145953 145953 145953 176579 176579 176579 176579 176579 176579 176579 176579 176579 176579 176579 176579 176579 176579 176579 176579 145953 176579 0

145953 79851 145953 78111 67842

<-head 737.61 738.09 736.58 736.37 736.23 735.31 734.69 734.5 733.35 733 732.65 732.01 731.5 731,02 731 726 725.72 725.54 724.88 722.06 72i.74 720.49 717.76 715.95 714.94 713.94 710.64 710.07 708.3 706.69 706.47 721.55 721.05 731.62 684.25 714.

714 738.73 715.56 head->

736.71 737.61 736.37 736.23 735.31 734.69 734.5 733.35 733 732.65 732.01 731.62 731.02 731 731 725.72 725.54 724.88 722.06 721.74 720.49 719.92 715.95 714.94 713.94 710.64 710.07 708.3 706.69 706.47 705.25 731.5 717.76 718.43 736.58 739.98 739.37 738.37 738.72 dPdrop

.17118

.2104 3.86

.66748 11.226

.26873

-2.081

.10731

-2.621 4.4842 1.3577

.2127

.20791

.0537 4.0933

-1.285

.42496

.63201

-. 2091

.13946

.54241

.24341

-. 2984

-3.896 3.208 1.8193 2.4098

.76702

-5.843

-. 0774

.52964

-4.355 1.3811 5.4972

-21.85

-11.26

-10.23

,15575

-10.03 4,"

,2t..~dhrt;

~.--

4 4

APPENDIX A MDN1027-98006 Rev. 0 PAGE 65 of 93 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer.net:

SUMMER Time: 1450 19 Page _ of __

Prepared Checked Date _/_/_

Date _/_/_


TVA AUTHORIZED USE ONLY ----------------------------

SUMMARY

OF NODES node-name COCA 0008 000C 005A 005B 00SC O07A 007B 007C 009A 0099 0a9C 011A 011B 011C 013A 013B 013C 015A O158 015c 020A 0208 020C 025 028 030 032A 032B 034A 0348 036A 0368 030A 0388 040A 040B 041A 041B 042A 0428 043A 0439 044A 0449 045A 045B 046A 0469 OSOA elev f

740.5 740.5 740.5 720.5 720.5 720.5 725.25 725.25 7254.2 714 714 714 725.25 725.25 725.25 714 714 714 714 714 714 714 714 715.75 715.75 715.56 715.56 715.56 716.18 716.18 716.8 716.8 717.42 717.42 718.01 718.01 718.01 718.01 718.01 718.01 718.01 718.01 718.01 718.01 718.01 718.01 718.01 718.01 718.01 head f

740.5 740.5 740.5 740.49 740.485 740.466 740.471 740.457 740.403 740.431 740.397 740.267 740.449 740.424 740.327 740.397 740.345 740.15 740.355 740.282 740.007 740.314 740.272 739.985 739.368 739.272 739.199 738.367 738.724 738.935 739.152 739.272 739.407 739.489 739.571 739.697 739.727 739.839 739.834 740.032 739.98 740.031 739.979 740.204 740.109 740.374 740.238 740.315 740.193 740.275 pres psig 0

0 0

8.65866 8.6565 8.64833 6.59315 6.58697 6.56356 11.4487 11.4338 11.3775 6.58349 6.57248 6.53082 11.4338 11.4115 11.327 11.4154 11.3839 11.2647 11.398 11.3797 11.2553 10.2299 10.1885 10.2392 9.87876 10.0335 9.85621 9.95046 9.73378 9.79209 9.55928 9.59446 9.3938 9.40682 9.45525 9.45317 9.53875 9.51615 9.53833 9.51583 9.6132 9.5723 9.68689 9.62788 9.66147 9.60869 9.64396 temp F

83 83 83 83.026 83.026 83.026 83.02 83.02 83.02 83.034 83.034 83.034 83.02 83.02 83.02 83.034 83.034 83.034 83.034 83.034 B3.034 83.034 83.034 83.034 83.031 83.031 83.031 83.031 83.031 83.031

83. 031
93. 031 83.03 83.03 83.03 83.03 83.029 83.03 83.03 83.03 83.03 83.031 83.03 83.031 83.03 83.032 83.031 83.032 83.031 83.032 dens lb/f3 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 supply sgpm 35895 43957 66102 status OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK ox OK OK OK OK OK OK
  • ~

APPENDIX A MDNI027-98006 Rev. 0 PAGE 66 of 93 718.01 740.163 9.59548 83.031 62.37 OK 0SOB

v~

APPENDIX A Date: 05/26/98 (Tue)

Time: 1450 20 EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER


. -----. -- ----- TVA AUTHORIZED USE NIDNI027-98006 Rev. 0 PAGE 67 of 93 Page

_ of Prepared Checked Date

/_

Date _/

ONLY ----------------------------

SUMMARY

OF NODES node-name 060A 0608 070 080 090 100 110 120 130 140 150 160 163 165 170 180 200 205 210 220 230 233 235 240 250 260 270 280 290 300 310 320 330 elev 684.75 684.25 686.15 694.85 696.25 721.25 721.2s 716.25 715.35 708.95 716.95 721.45 721.45 721.45 721.SS 731 726 722.75 723.55 724.35 721.05 721.05 721.05 720.95 718.45 700.45 714.85 715.75 720.75 720.75 705.65 705.25 705.25 head 737.606 738.091 736.584 736.372 736.231 735.315 734.694 734.499 733.351 733.001 732.648 732.014 731.504 731.024 731 731 726 725.718 725.537 724,878 722.06 721.738 720.486 717.762 715.951 714.944 713.938 710.638 710.075 708.304 706.694 706.473 705.25 pres psig 22.8945 23.3211 21.8454 17.9854 17.3179 6.09218 5.82345 7.90431 7.79699 10.4177 5.93351 4.5758 4.35493 4.14702 4.09332 0

0 1.28548

.860514

.228506

.437643

.298185

-. 24422

-1.3811

-1.0826 2.81304

-. 39492

-2.2142

-4.624

-5.391

.452254

.529636 0

temp F

83.074 83.074 83.071 83.06 83.056 83.026 83.026 83.033 83.034 83.042 83.029 83.026 83.026 83.026 83.026 83.014 92 92.004 92.003 92.002 92.006 92.006 92.006 92.006 92.009 92.022 92.014 92.013 92.007 92.007 92.026 92.026 92.029 dens supply lb/t3 sgpm 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 -1.E+5 62.37 176579 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 -2.E+5 status Ox OK Ox OK OK OK OK OK OK Ox OK OK OK Ox OK OK OK OK OK OR Ox OK OK OK OK OR OK Ox alt OK OK Ox Ox

ý4c

APPENDIX A A DNID 027-98006 Rev. 0 PAGE 68 of 93 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Time; 1450 21 Page __ of --

Prepared __

Checked Date _/_/_

Date _/_/_

,Summer.nst: SUMMER


.--.------------- TVA AUTHORIZED USE ONLY

SUMMARY

OF TEES tee-name type leg elev head pres f

f psig BYPASDIS.TEE NCON 1 721.05 719,862 -. 51442 2

719.924 -. 48763 3

7i8.426 -1.1368 BYPASSUP.TEE SDRL I 721.55 731,609 4.3572 2

731.623 4,36309 3

731,617 4.36048 SCCW.TEE SCON 1 684.25 737.762 23.1787 2

737.605 23.1107 3

736.711 22.7233 TEE.B SCON 1 714 740.313 11.3976 2

740.272 11.3796 3

740.079 11.2961 TEE.C SCON 1 714 740.076 11.2946 2

739.984 11.255 3

739.368 10.9883 TRANS.TEE NDIV 1 715.56 739.198 10.2388 2

738.37 9.80006 3

738.726 10.0345 temp F.

92.006 92.006 92.006 83,026 83.026 83.026 83.074 83.075 83.074 83.034 83.034 83.034 83.034 83.034 83.033 83.031 83.031 83.031 dens lb/f 3 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 62.37 flow sgpm 176579 0

176579 145953 0

145953 67842 78111 145953 35895 43957 79851 79851 66102 145953 145953 78111 67842 status OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK

  • ~.

\\

~

~'t. ~

~ '

"r'

  • -~

APPENDIX A ANIDNIO27-98006 Rev. 0- PAGE 69 of 93 Date: 05/26/98 (Tue)

Time: 1450 22 Page of _

EZFLOW: Version 5.00 Prepared Date __

site: unspecified Checked Date

//

Summer.net: SUMMER


TVA AUTHORIZED USE ONLY ----------------------------

SUMMARY

OF FIXED FLOWS inlet-node exitnode BYPASSUP.TEE BYPASDIS.TEE throt pump tdh sgpm Cv feet action 0

0 LOSS

{~,.

-.~

..~.

. -~

APPENDIX A MDN1Ol7-98006 Rev. 0 PAGE 70 or 93 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER Time: 1450 23 Page __ of __

Prepared Checked Date _/_/

Date _/_/


TVA AUTHORIZED USE ONLY LINK DETAIL LINK 000A-00SAAw sgpmw35894.8 000A>005A sch=NS, mat-"carbon steel*, Di=143.2 componentname --------------------. 4--K-> c-L->

inletnodew000A..................

slightly rounded entrance.........

.25 straight pipe, len-i.............

I change in elevation..............

exit node-O0 SA...................

LINK 000B.-005B->

sgpm-43956.6 000B>005B schwNS, mat-"carbon steel", Di-143.2 component name -------------------. <--K-> <-L->

inlet node-000B..................

slightly rounded entrance.........

.25 straight pipe, len-1.............

1 change in elevation..............

exit node-005B...................

LINK 000C=-005C->

sgpm-66101.9 000C.005C schwNS, mat-"carbon steel,, Di-143.2 component-name --------------------. <--K-> <-L->

inlet node-000C..................

slightly rounded entrance.........

.25 straight pipe, len

.l change in elevation..............

exit node-005C...................

LINK 00SA.007A=.

sgpmo35894.8 00SAA007A c--H-) c-dH->

0 740.5 740.49 740.49 740.49 740.49 c--H->

740.5 740.49 740.49 740.49 740.49

"<--H-)

740.5 740.47 740.47 740.47 740.47

<-dP-> <T-:

83

-.0043 83

-2.9-S I

-. 0099 -. 0043

-5.E-5 I

8.6587 8.6587 8.663 83 83 c-dH-> 4--P-> <-dP->

0

-. 0149 -. 0065 E-5 S

8.6565 6.6565

-. 0065

-3.E-5 8.663

<T- >

83 83 93 83 83 83 83 8383 c-dHl-> <--P-> c-dP->

0

-. 0337 -. 0146

-. 0002 I

8,6483 8.6483

-.0146

-7.E-5 8.663 sch-DUCT, mat-"carbon steel", high=252, wide=114 component name ------------------- > c--K-P c-L-> c--H->

inlet node-OOSA.....................

740.49 other: TRASH RACK. K.0.72.........

.72 740.49 change in elevation..............

740.49 decreaser, dia.0..................

.26534 740.47 exit node-007A.......................

740.47 LINK 005Bw-007.,- sgpm-43956.6 OOSB>007B sch-DUCT, mat-"carbon steel", high-252, wide114 component name -------------------- b <--K-: <-L-: <--H->

inlet-_nodemOOSB.....................

740.49 other: TRASH RACK, K-0.72.........

.72 740.48 change in elevation..............

740.48 decreaser, dia-0...................

.26534 740.46 exit.node=007D.......................

740.46 C-dH-,

<--P-> 4-dP-> cT-:

8.6587 83

-. 0027 I

-. 0012 8.6569 0

83

-. 0145 6.5931 -2.064 83 6.5931 83

<-dH-> c--P-> c-dP-> <T->

8.6565 83

-. 0041 I

-. 00o 8 1

8.6539 0

83

-. 0218 6.587 -2.067 83 6.587 83

APPENDIX A MDNI027-98006 Rev. 0 PAGE 31 of 23 Date: 05/26/98 (Tue)

Time: 1450 24 Page

_ of __

EZFLCW: Version S.00 Prepared Date _/_/_

site: unspecified Checked Date jj Summer.net: SUMMER


TVA AUTHORIZED USE ONLY LINK DETAIL LINK 005C--007C=>

sgpm-66101.9 OOSC>007C ech-DUCT, mat-"carbon steel", high-252, wide=114 component name -------------------

-K-

-L-c--H-inlet node=O05C..................

740.47 other: TRASH RACK, K-0.72.........

.72 740.46 change in elevation..............

740.45 decreaser, dia-0..................

.26534 740.4 exit nodem=l7C..........................

740.4 LINK 007A-=009A-.

sgpm=35894.8 007A>009A sch=DUCT, mat="concrete", highu366, wide-72 componentname ------- ------------

c--K-> <L-c--H-:.

inlet node-007A.......................

740.47 straight pipe, len-8.............

8 740.47 change in elevation..............

740.47 decreaser, dia-0..................

.26193 740.43 exit node-009A..........................

740.43 c-dH-> <--P-> <-dP-> cT-.

8.6483 83

-. 0093 I

-.004 I

8.6424 0

83

-. 0493 6.5636 -2.079 83 6.5636 83

<-dH-> c--P-> c-dP-, <T->

6.5931 83

-9.E-5

-4.E-5 6.5931 0

83

-. 0399 11.449 4.8556 83 11.449 83 LINK 007B8.009B->

sgpM=43956.6 007B>009B sch-DUCT, mat."concrete", high.366, wide=72 component name --------------------, c--K-,

c-L-.-

inlet node-007B..................

straight pipe, len-8.............

8 change in elevation..............

decreaser, dia.0

.26193 exit node-009B...................

LINK 007C--009C->

sgpm.66101.9 007C>009C schuDUCT, mat-"concrete", high-366, wide.72 componentname --------------------. c--K-. c-I-.

inlet node-007C..................

straight pipe, len-8.............

8 change in elevation..............

decreaser, dia-0..................

.26193 exit-node OOP9C...................

LINK 009Aa-011A=>

sgpma35894.S 009A>011A sch.NS, mats"carbon steel", Di=93.2 component name --------------------.

<--K-.

c-L->

inlet node=009A..................

other: SLUICE GATE, K.0.072......

.072 change in elevation..............

increaser, diano.................

.1508 exit node-011A...................

c--H-> <-dH-.

740.46 740.46 -. 0001 740.46 740.4 -. 0599 740.4 c--P-> c-dP->

6.5871 6.5868 11.434 11.434

-6.E-5 0

4.847

<cT-83 83 83 83 c--H-;

740.4 740.4 740.4 740.27 740.27

<--H->

740.43 740.43 740.43 740.45 740.45 c-dlH-> c--P->

6.5636

-. 0003 1

6.5633

-. 1355 11.378 11.379

<-dP-> cT->

63

-.0001 1

0 4.8143 83

.3 83 c-dx-.

<- -P-a

<-dP-cT->

11.449 83

-. 0032 I

-. 0014 11.447 0

83

.02103 6,5835 -4.864 83 6.5983 83

.1

2. Y C -.

3/4,.-... LV

-4.. -4S~aJ-'~ -

I b-t.tA.r7S'-

.,.,*~.

APPENDIX A MDNIO27-98006 Rev. 0 PAGE 72 of 23 Date: 05/26/98 (Tue)

Time: 1450 25 Page of __

EZFLOW: Version 5;00 Prepared __

Date _/_/

site: unspecified Checked Date

//

Summer.net: SUMMER


TVA AUTHORIZED USE ONLY LINK DETAIL LINK 009B-011Bffi>

sgpm-43956.6 009B>011B sch-NS, matw"carbon steel", Di.93.2 componentname ------------------- > <--K-> <-L->

inlet node=009B..................

other: SLUICE GATE, K-0.072......

.072 change in elevation..............

increaser, dia0...................

.1508 exit-node-011B...................

<--H-> <-dE,-> <-oP-> e-dP-> <T->

740.4 11.434 83 740.39 -. 0048 1

-. 0021 i

740.39 11.432 0

83 740.42.03154 6.5725 -4.859 83 740.42 6.5725 83 LINK 009C=-011C=>

sgpm.66101.9 009C>011C sch-NS, mat="carbon steel", Dis93.2 component_name -------------------

> <--K-> c-L-,

inlet-node-009C..................

other: SLUICE GATE, K-0.072........

072 change in elevation..............

increaser, dia-0...................

.1508 exit node-011C...................

LINK 011Af-013A=>

sgpm-35894.8 011A,013A sch-DUCT, mat-"carbon steel", high=366, wide-72 cornponent name --------------------. -- K-inlet node-011A..................

other: TRAVELING SCREEN, flow=13S1.80187 change in elevation..............

decreaser, dia=0.................

. 25458 exit node-013A...................

LINK 0113--013B->

sgpm=43956.6 0118>0138 sch=DUCT, mat,"carbon steel", high=366, wide=72 component_name -------------------- > -- K-> <-L->

inletnode-011B..................

other: TRAVELING SCREEN, flow-1351.80187 change in elevation..............

decreaser, dia-0..................

25459 exitnode=013B...................

LINK 011C--013C->

sgpm-66101.9 011C>013C s1ch.DUCT, mat."carbon steel", highs366, wide-72 component name -------------------.-. <-K-> <-L->

inlet node-011C..................

other: TRAVELING SCREEN.

Elow-1351.80187 change in elevation..............

decreaser, dia-0..................

25458 exit node-0l3C...................

<--7->

740.27 740.26 740.26 740.33 740.33 740.44 740.44 740.44 740.4 740.4 740.42 740.42 740.4 740.35 740.35

,--H->

740.33 740.31 740.28 740.15 740.15 c-dH-:- <--P-> <-dP-> 4T-:>

11.378 83

-. 0108 1

-. 0047 11.373 0

93

.07134 6,5308 -4.942 83 6.5308 83

<-dH-> c--P-ý, <-dP-> <T->

9.5939 83

-. 0057 1

-. 0025 6.5777 0

83

-. 039 11.434 4.856 83 11.434 83 c-dH-.> <--P-> <-dP-> cT->

6.5725 83

-. 0085 I

-. 0037 6.5639 0

83

-. 0585 11.411 4.8476 83 11.411 83 c-dH{-> <--P <-dP-> cT->

6.5308 83

-. 0193 I

-. 0084 6.5113 0

83

-. 1322 11.327 4.8157 83 11,327 83

APPENDIX A DMDNIO27-98006 Rev. 0 PAGE 73 of 93 Date: 05/26/98 (Tue)

Time: 1450 26 Page of __

EZFLOW: Version 5.00 Prepared Date

/_/

site: unspecified Checked Date _/_/

Summer.net: SUMMER


TVA AUTHORIZED USE ONLY ----------------------------

LINK DETAIL LINK 013A-=015A->

sgpm=35894.8 013A>015A sch=NS, mat="carbon steel", Di-93.2 componentname------- ------------ > <--K-> <-L-> <--H->

inlet node-013A..................

740.4 other: SLUICE GATE, K-0.072........

072 740.39 change in elevation................

740.39 decreaser, dia=O.................

.14524 740.35 exit.node-015A..............

740.35 LINK 013B=a015B=>

sgpm=43956.6 013B>015B sch-NS, mat,'carbon steel", Di=93.2 componentname -------------------- > <--K->

>-L->

<--H->

inlet nodes013B......................

740.35 other: SLUICE GATE, K=0.072

.072 740.34 change in elevation................

740.34 decreaser, dia-0..................

. 14524 740.28 exit_-node-015B.......................

740.28 LINIK 013C==015C->

agpm-66101.9 013C>015C sch.NS, mat-"carbon steel", Di=93.2 component name ------------------- > <--K-> <-L-> <--H->

inlet node-013C..................

740.15 other: SLUICE GATE, K=0.072........

072 740.14 change in elevation................

740.14 decreaser, dia

.D..................

14524 740.01 exit node=01SC.......................

740.01 LINK 015A-=020A=-

agpm.35894.8 01SA>020A sch-DUCT, mat."concrete", high=96, wide=72 component-name ------------------- > <--K-> <-L-> 4--H->

inlet node-015A...................

740.35 straight pipe, len-8.............

8 740.35 mitered bend, angle=90...........

399.7 740.3 change in elevation..............

740.28 increaser, area-10764 25599 740.31 exit-node-020A......................

740.31

,c-dH-> 4--P-> <-dP-> <T->

11.434 83

-. 0032 1

-. 0014 11.432 0

83

-. 0392 11.415

-. 017 83 11.415 83

<-dH-> <--P-> <-dP-> <T->

11.411 83

-. 0048 I

-. 0021 11.409 0

83

-. 0588 11.384 -. 0254 83 11.384 83

-c-dH-;,

P=

e=dPz=o -T-5 11.327 83

-. 0108 1

-. 0047 11.322 0

83

-. 1329 11.265 -. 0576 83 11.265 83

<-dH-> <--P-> <-dP-> <T->

11.415 83

-. 001

-. 0004 I

-. 0581

-. 0251 11.382 0

83

.03643 11.398.01578 83 11.398 83 LINK 015.B-0208->

sgpm-439S6.6 015B>0208 ach.DUCT, mat."concrete", high.96, widew72 component name -------------------- > x--K-> <-L->

inlet node-01SB..................

other: SLUICE GATE, K-0.072........

072 straight pipe, len-8.............

8 change in elevation..............

exit node-0208...................

c- -H-> <-dli-> c--P-,

740.28 11.384 740.28 -. 0061 740.27 -. 0015 740.27 11.38 740.27 11.38 c-dP-> 'cT->

83

-. 0026

-. 0006 1

0 83 83 4

r

APPENDIX A MDNIO27-98006 Rev. 0 PAGE 74 or 93 Date, 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER Time: 1450 27 Page

_ of __

Prepared Checked Date _/_

Date j/


TVA AUTHORIZED USE ONLY LINK DETAIL LINK 01SC--020C.>

ogpm.66101.9 015C>020C sch=DUCT, mat-"concrete",

high-96, wide-72 component_name ------------------- > <--K-> <-L->

inlet node-015C..................

other: SLUICE GATE, K-0.072......

.072 straight pipe, len-8.............

change in elevation..............

exit_nodem020C...................

<--H->

740.01 739.99 739.99 739.98 739.98

<-dH-> <--P-:- <-dP-> cT-;>

11.265 83

-. 0137

-. 0o59 I

-. 0031 I

-.0013 I

11.255 0

83 11.255 83 LINK 020A='TEE.B>

sgpm=35894.0 020A>TEE.9 sch"DUCT, mat-"concrete", high-138, wide-78 componentname ------------------- > <--K-5 <-L-> <--H-> <-dH->

inlet _node-020A....................

740.31 straight pipe, len-12............

12 740.31 -. 0006 change in elevation..............

740.27 exit node-TEE.B..................

740.27

<-P- -dP-> <T->

11.398 83 I

-.0002 I 11.38 0

83 11.38 83 LINK 020S.PTEE.B>

sgpm-43956.6 0208>TEE.B sch-DUCT, mat-"concrete", higha96, wide-72 component name --------------------.

><--K-> <-L>

inletnode-o20B ieraiiht pipe, lenci change in elevation..............

exit node-TEE.8..................

<--H-:. <-dH-> <--P-> <'dP-> cT->

740.27 11.38 83 740.27 -. 0002 1

-8.E-5 I

740.08 11.296 0

83 740.08 11.296 83 LINK 020C==TEE.C>

sgpm-66101.9 020C>TEE.C chbDUCT, mat-"concrete",

high-96, wide-72 component name -------------------

-K-> <-L->

Inlet-node-020C..................

straight pipe, len-1.............

I change in elevation..............

exitnodenTEE.C..................

LINK 025-..028-->

sgpm-145953 025>028 echaDUCT, mat."concrete",

highw138, wide-78 componentname ----------------------.

K-(-L-inlet node-02S...................

straight pipe, len-l1l.5.........

111.5 change in elevation..............

exit node-028....................

<--7->

739.98 739.98 739.37 739.37 c--H->

739.37 739.3 739,27 739.27

<-H><--P-n-c-dP-> <T->

11.255 83

-. 0004 I

-. 0002 10.988 0

83 10.988 93

<-dH-> <--P->- <-dP->i <T-:-

10.23 83

-. 0694 1

-. 03 10.188 0

83 10.188 93

<-dH-> <--P-> <-dP-> <cT->

10.198 83

-. 03S2 I

-. 0152 I

-.0078

-. 0034

-. 0099 I

-. 0043 10.239

.0823 83 10.239 83 LINK 028s==030%.->

sgpmwL45953 028>030 sch-DUCT, mat-"concrete", high-138, wide-78 component-name ------------------- b <--K-> c-L-> <--H->

inlet-node-028.......................

739.27 straight pipe, len-56.56.........

56.56 739.24 mitered bend, angle-7............

... 10.81 739.23 straight pipe, Len-15.95.........

15.95 739.22 change in elevation..............

739.2 exit-node.030.....................

739.2 u-

APPENDIX A MDNI027-98006 Rev. 0 PAGE 75 of 93 Date: 05/26/98 (Tue)

Time: 1450 28 Page

_ of __

EZFLOW: Version 5.00 Prepared Date _/_/_

site: unspecified Checked Date _/_/_

Summer.net: SUMMER TVA AUTHORIZED USE ONLY -- --------------------------

LINK DETAIL LINK 030===TRANS>

sgpm=145953 030>TRANS.TEE sch-DUCT, mat."concrete", high.138, wide=78 component name ------------------- > <--K-> <-L->

inlet node=030 straight pipe, len-i.............

I change in elevation..............

exit node=TRANS.TEE LINK 032A==034A->

agpm-78110.9 032A>034A sch-DUCT, mat="concrete".

high=138, wide-39 component_name ------------------- > <--K-> <-L->

inlet node-032A..................

straight pipe, len-3.S...........

3.5 change in elevation..............

increaser, area=5830..............

25178 exitnode,034A...................

LINK 032B--034B->

sgpm=67842.3 0328>034B sch=DUCT, mat="concrete", high=138, wide-39 componentname ------------------- > <--K-> <-L-,

inletnode-032B..................

aeraight pipe, len-3.5...........

3.5 change in elevation..............

increaser, area-S830...............

25178 exit node-0342...................

LINK 034A=-036A->

sgpm-78110.9 034A>036A schaDUCT, mat-"concrete".

highs123, wide-47.4 component name ------------------- > <--K-> <-L->

inlet node-034A..................

straight pipe, len-3.5...........

3.5 change in elevation..............

increaser, area=6026..............

15186 exit node-036A...................

LINK 034B--036B->

sgpm-67842.3 034B>036B sch.DUCT, mat-"concrete",

high=123, wide=47.4 componentname --------------------> <--K-> c-L->

inlet node-034 straight pipe, len3.5 3.5 change in elevation..............

increaser, area=6026..............

15186 exit-node-036B...................

LINK 036A--038A->

sgpm.78110.9 036A>038A chaDUCT, mat-"concrete",

high.108, wide-55.8 component name --------------------> <--K-> <-L->

inlet node-036A..................

straight pipe, len-3.5...........

3.5 change in elevation..............

<--H->

739.2 739.2 738.37 738.37 c--H->

738.37 738.36 738.36 732.93 738.93 c--H->

738.72 738.72 738.72 739.15 739.215 c--H->

738.93 738. 93 738.93 739.27 739.27

<--H->

739.1S 739.15 739.15 739.41 739.41

<-dH-> <--P-> <-dP-> cT->

10.239 83

-.0006

-.0003 I 9.8801 0

83 9.8801 83

<-dH-> <--P-> c-dP-> <T->

9.8788 83

-. 0056 I

-.0024 I

9.8742 0

83

.5784 9.8562

-. 018 83 9.8562 83

<-dH-> e--P-> <-dP-> <T-;

10.034 83

-. 0043 I

-. 0019 10.03 0

83

.43632 9.9505 -. 0796 83 9.9505 83

<-dH-> 4--P-> c-dP-> <T->

9.8562 83

-. 0037

-.0016 I

9.8537 0

83

.34324 9.7338 -. 1199 83 9.7338 83

<-dH-> <--P-> <-dP-> <T->

9.9505 83

-. 0029 1

-.0012 I

9.9485 0

83

.25893 9.7921 -. 1564 83 9.7921 83 4--H-> <-dc--> <--P-> c-dP-> <T->

739.27 9.7330 83 739.27 -. 0029 1

-. 0013 739.27 9.732 0

83

APPENDIX A NIDNI27-98006 Rev. 0 PAGE 76 or 93 Date: 05/26/98 (Tue)

Time: 1450 29 Page __ oc EZFLOW: Version 5.00 Prepared site: unspeciEied Checked Summer.net: SUMMER

---....... TVA AUTHORIZED USE ONLY -----------

Date Date _/_/_

LINK DETAIL LINK 036A=-038A=> continued componentname ---------------------.

4--K-.

-L->

increaser, area-5971..............

08284 exit node*038A....................

LINK 036B--0385->

sgpm-67842.3 0365>038B schuDUCT, mat-mconcrete",

high-108, wide-S5.8 component name --------------------. <--K-> <-L-,

inlet node-036B..................

straight pipe, lenn3.5...........

3.5 change in elevation..............

increaser, area=5971..............

.08284 exit nodea 038A LINK 038A=-040A=>

sgpm=78110.9 038A>040A sch-DUCT, mat-"concrete",

high-93, wide=60.24 component name -------------------

c-K-. --

inlet node-O38A..................

straight pipe, len.3.5...........

3.5 change in elevation..............

increaser, area=5663..............

.06684 exit_node-040A...................

c--H-.

739.49 739.49

<--H->

739.41 739.4 739.4 739.57 739.57 c-dH-> <--P-> <-dP-> cT->

.22126 9.5593 -. 1727 83 9.5593 83 c-d<-. c-P--, <-dP-! <T->

9.7921 83

-. 0022 1

-. oo0 I

9.7907 0

83

.16691 9.5945 -. 1963 93 9.5945 83

<--H-.- <-dH-> c--P-> c-dP-> cT->

739.49 9.593 83 739.49 -. 0032

-. 0014 1

739.48 9.5574 0

83 739.7.21222 9.3938 -. 1636 83 739.7 9.3938 93 LINK 039B--0408s>

sgpmn67S42.3 038B>040B sch-DUCT, mat="concrete",

high=93, wide=60.24 component name --------------------. c--K-.

--L->

inlet node=038B.................

straight pipe, 1en-3.5...........

3.5 change in elevation..............

increaser, area.5663..............

.06684 exit nodem040B...................

LINK 040A--041A.>

sgpm-78110.9 040A;041A sch-DUCT, mat-"concrete",

high-78, wide-72.6 component_name ------------------- > <--K-> <-L->

inlet node-040A..................

straight pipe, len-l.............

1 change in elevation.............

increaser, area-S385.............

.03068 exitnode-O41A...................

LINK 0409--041B->

agpm-67842.3 0408>0415 schwDUCT, mats"concrete",

high-78, wide-72.6 component name -------------------

c-K-. c--

inlet node=O40B..................

straight pipe, len-1.............

1 change in elevation..............

increaser. area=5385...............

03068 exit nodeu041B...................

.c--H-739.57 739.57 739.57 739.73 739.73 c--H->

739.7 739.7 739.7 739.84 739.84 739.73 739.73 739.73 739.83 739.83

<-dH-> <--P-> <-dP-.

<T-.

9.5945 83

-.0025

-. 0011 I

9.593 a

83

.16009 9.4068 -. 1862 83 9.4068 83 c-dH-.

c--P-. <-dP-.

<T->

9.3938 83

-.0008 1

-. 0004 I

9.3933 0

83

.14293 9.4552.06191 83 9.4552 83 c-dl-> <--P-> c-dP-> CT->

9.4068 83

-.0006 I

-. 0003 I

9.4065 0

83

.10782 9.4532

.0467 83 9.4532 83

~".

.x.~t

APPENDIX A MDNIO27-98006 Rev. 0 PAGE 77 of 93 Date: 05/26/98 (Tue)

Time: 1450 30 Page __ of __

EZFLOW: Version 5.00 Prepared Date

/

site: unspecified Checked Date _/_/_

Summer.net: SUMNER


TVA AUTHORIZED USE ONLY LINK DETAIL LINK 041A-w042A->

agpm-78110.9 041A>042A sch-DUCT, mat="concrete",

high=78, wide=69.04 component-name ---------------------. 4--K-> <-L->

inlet node-041A..................

straight pipe, len-I.............

1 change in elevation..............

increaser, area=5464 05236 exit node-042A....................

LINK 0418=042B->

sgpmz67842.3 041B>042B sch-DUCT, mat-"concrete",

high-7a, wide-69.04 component name ---------------------> c--K->

-L->

inlet node=041B..................

straight pipe, len=l.............

change in elevation..............

increaser, area=5464..............

05236 exit node-0429 7--H-.

739.84 739.84 739.84 740.03 740.03 c-dH-> c--P-> <-dP-> <T->

9.4552 83

-.0009 1

-. 0004 9.4547 0

83

.19399 9.5388.08403 83 9.5388 83

<--H-> <-dH-> <--P-> c-dP-> cT->

739.83 9.4532 83 739.83 -. 0007 1

-. 0003 739.83 9.4528 0

83 739.98.14634 9.5162.06339 83 739.98 9.5162 83 LINK 042A=a043A=>

sgpm=78110.9 042A>043A sch-DUCT, mat-"concrete", high-78, wide-70.05 componentname ------------------- > c--K-> <-L->

inlet node-042A..................

straight pipe, len=l.............

1 change in elevation..............

increaser, dia-5474...............

.99964 exit node-043A...................

LINK 0428..043B->

sgpmn67842.3 0428>0438 sBh-DUCT, mat-"concrete", high-78, wide-70.05 component name ------- -----------

> c--K->

>-L->

inlet node-042B..................

straight pipe, len-i.............

change in elevation..............

increaser, dia-5474...............

99964 exitnode-043B...................

LINK 043A--044A-,

agpm-78110,9 043A>044A sch-DUCT, mat-"concrete",

high-78, wide-70.18 component-name -------------------

-K->

>-L->

inlet node-043A..................

straight pipe, len-1.............

change in elevation..............

increaser, area-5403..............

04264 exit node-044A...................

<--H->

740.03 740.03 740.03 740.03 740.03

<--H->

739.98 739.98 739.98 739.98 739.98

-- H-->

740.03 740.03 740.03 740.2 740.2

<-dH-> <--P-> <-dP-,

<T->

9.5388 83

-. 0009 1

-. 0004 9.5382 0

83

.00019 9.5383 8.3E-5 83 9.S383 83 c-dH-> <--P-> <-dP-> <T->

9.5162 83

-o.0007 1

-. 0003 9.5158 0

83

.00015 9.5158 6.3E-5 83 9.5158 83 c-dJH-> c--P-> <-dP-,

4T-2 9.5383 83

-. 0009 I

-. 0004 9.5378 0

83

.174 9.6132.07537 83 9.6132 83

..ý"

  • (

-:.i N

-s<

i..

S

,, t

APPENDIX A MDNIO27-98006 Rev. 0 PAGE 78 of 93 Date: 05/26/99 (Tue)

Times 1450 31 Page __ of _

EZFLOW: Version 5.00 Prepared Date

/_/

site:

unspecified Checked Date

//

Summer.net:

SUMMER


TVA AUTHORIZED USE ONLY LINK DETAIL LINK 043B=O044B-> sgpm=67842.3 043B>0441 sch.DUCT, mat-"concrete",

high=78, wide=70.18 componentname -------------------

-K-> <-c->

inletnode=043B..................

straight pipe, len=1 change in elevation..............

increaser, area=5403..............

04264 exit node-0448...................

<--H-> <-dH-> <--P-> c-dP-> <T->

739.98 9.5158 83 739.98 -.0007 J

-. 0003 I

739.98 9.5154 0

83 740.11.13126 9.5723.05686 83 740.11 9.5723 83 LINK 044A=-045A=>

sgpm=78110.9 044A>045A schaDUCT, mat-"concrete", high-78, wide-69,27 componentname -------------------. > <--K-3 <-L-> c--H->

inlet node=044A..................

740.2 straight pipe, len=1.............

1 740.2 change in elevation..............

740.2 increaser, dia=0..................

. 03801 740.37 exit node=045A.......................

740.37 LINK 044B==045B=>

sgpm-67842.3 044B>045B sch=DUCT, mat-"concrete",

high-78, wide-69.27 component name --------------------> c--K-> c-L-> c--H-,

inlet nodwas0440..................

740.11 straight pipe, len-1.............

1 740.11 change in elevation..............

740.11 increaser, dia.0.................

.03801 740.24 exitnode-045B.......................

740.24 LINK 045As-046A->

sgpm.78110.9 045A>046A sch.NS, mat-"concrete", Di-81.78 componentname -------------------...

--K-ý, c-L-> <--H->

inlet node=045A.....................

740.37 straight pipe, len=1.............

1 740.37 change in elevation..............

740.37 decreaser, dia-0.................

.03634 740.32 exit node-046A.......................

740.32

<-dH-> <--P-> c-dP-> <T->

9.6132 83

-.0009 1

-o.0004 9.6127 0

83

.17133 9.6869.07421 83 9.6869 83 9.S723 83

-.0007 1

-. 0003 9.5719 0

83

.12925 9.6279.05598 83 9.6279 83

<c-dH-> 4c--P->- <-dP-> <T->

9.6869 83

-.0007

-o.0003 9.6866 0

83

-. 058 9.6615 -. 0251 83 9.6615 83

-<--P-i <-dP-> cT->

9.6279 83

-. oo005

-. 0002 9.6276 0

83

-. 0437 9.6087

-. 019 83 9.6087 83 LINK 0459.-046B=>

egpm-67842.3 045B>046B sch-NS, mat=-concrete",

Di.81.78 component name ------------------- > c--K-. <

inlet node-045B..................

straight pipe, len-1.............

change in elevation..............

decreaser, dia=0..................

03634 exit node-046B...................

-L--> c--H->

740.24 1 740.24 740.24 740.19 740.19

.~u.!;r;~'~' 4

APPENDIX A MDN1027-98006 Rev. 0 PAGE 79 or 23 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER Time: 1450 32 Page -

of __

Prepared Checked Date _/_/_

Date TVA AUTHORIZED USE ONLY LINK DETAIL LINK 046A==OSOA=>

sgpm=78110.9 046A>050A sch-NS, mat-"concrete",

Dim79.44 component name------------------->

-K-

-L->

inlet-node-046A..................

straight pipe, len-0.5 S

change in elevation decreaser, dia-0..................

.02304 exit node-OSOA...................

LINK 046B8-0509->

sgpm-67842.3 046B>0509 sch-NS, matn"concrete",

Di-79.44 component-name -------.--------- > <--K-> <-L-,

inletnodea046B..................

straight pipe, Ien-O.5............

5 change in elevation..............

decreaser, dia-0...................

02304 exitnode-050B...................

LINK 0S0Aw060Au>

agpm-78110.9 OSOA>060A sch-NS, mat-"concrete", Di-78 component name ------------------- > 4--K-> <-L->

inletnode-OSOA.................

straight pipe, len.Boo......

9 00 mitered bend, angle-2............

2.282 straight pipe, len-BO0...........

500 mitered bend, angle-1............

1.128 straight pipe, len=1400..........

1400 mitered bend, angle-2.............

2.282 straight pipe, len-292...........

292 change in elevation..............

exit node-060A...................

LINK 050B9u060B->

sgpm-67842.3 050B>060B c--H->

740.32 740.31 740.31 740.27 740.27 c--H->

740.19 740.19 740.19 740.16 740. 16

<--H->

740.27 739.56 739.56 739.12 739.11 737.87 737.87 737.61 737.61 737.61

<--H-,

740.16 739.61 739.61 739.27 739.27 738.31 738.31 738.09 738.09 738.09 c-dH-> <--P-> c-dP-> <T->

9.6615 93

-.0004 1

-.0002 I 9.6613 0

93

-. 04 9.644 -. 0173 83 9.644 83 c-dH-> c--P-> <-dP-> cT->

9.6087 83

-.0003 I

-.0001 9.6086 0

83

-.0302 9.5955 -. 0131 83 9.5955 83 c-dH-> c--P-> <-dP-> cT->

9.644 83

-. 712

-. 3084

-. 0024

-. 001

-. 445

-. 1928

-. 0012

-. 0005

-1.246

-. 5397

-. 0024

-. 001

-. 2599

-. 1126 1

22.895 14.407 83.1 22.895 83.1 c-dH-,

c*-.P-> <-dP-> c?->

9.5955 93

-. 5486

-. 2376

-. 0018

-. 0008

-. 3429

-. 1485

-. 0009

-. 0004

-. 96

-. 4158

-. 0018

-. 0008

-. 216

-. 0936 23.321 14.623 83.1 23.321 83.1 schuNS, mat-"concrete",

Dim78 componentname ------------------- >

inlet node-050B..................

straight pipe, len-BO0...........

mitered bend, angle.2............

straight pipe, len-500...........

mitered bend, angle.1............

straight pipe, lena1400..........

mitered bend, angle-2............

straight pipe, len-315...........

change in elevation..............

exit node-060B...................

<--K->. c-L-=.

800 2.282 500 1.128 1400 2.282 315

t.

A

APPENDIX A MDNl027-98006 Rev. 0 PACE SO of 91 Date: 05/26/98 (Tue)

Time: 1450 33 Page of _

EZFLOW: Version 5.00 Prepared Date _/

site: unspecified Checked Date _/_/_

Summer.net:

SUMMER


TVA AUTHORIZED USE ONLY LINK DETAIL LINK 06OA--SCCW.>

sgpm=78110.9 060A>SCCW.TEE schaNS, mat."concrete",

Di=78 component name ---------------------.

-K-.

'-L->

inlet node-060A..................

straight pipe, len...............

1 change in elevation..............

exit node-SCCW.TEE...............

LINK 060-SCCW.> sgpm-67842.3 060B>SCCW.TEE sch=NS, mat-"concrete",

Di-78

<--H--

737.61 737.61 736.71 736.71 c-dH-> 4--P->

22.895

-. 0009 1

22.723 22.723

<-dH-> <--P->

23.321

-. 3013 I

-. 0274 I

23.111 23.111

<-dP-> <T-:

83.1

-. 0004 1

.21657 93.1 83.1 c-dP-z. <T->

83.1

-. 1305

-. D119 0 83.1 83.1 component name -------------------. >

-- K->

inlet node-0608..................

mitered bend, angle=90...........

straight pipe, len-40............

change in elevation..............

exitnode.SCCW.TEE...............

LINK 070=.=080-:-

sgpm-145953 070.080 sch-NS, mat-"concrete", Di-90 component name ---------------------. >--K-inletnode-070...................

straight pipe, lenulSO...........

change in elevation..............

exit node-080.....................

LINK 080=-=090=->

sgpmm145953 080-090 sch-NS, mat-"concreie",

Di-90 component name --------------------. <--K->

inletnode=080...................

straight pipe, len,100...........

change in elevation..............

exit-node-90.....................

LINK 090.. 100--.

agpm.14S953 090>100 sch=NS, matn"concrete", Di-90 component name ---.-----------------. >--K-inlet node-090...................

straight pipe, len-650...........

change in elevation...............

exit node-100....................

c-L-> <--H->

738.09 378.9 737.79 40 737.76 737.61 737.61 c--

-- H-.

736.58 150 736.37 736.37 736.37

,-L-> <--H->

736.37 100 736.23 736.23 736.23 c-L-> <'--H-.,

736.23 650 735.31 735.31 735.31 4-dH-> 4--P-> <-dP-> -cT-.

21.845 83.1

-. 2115 I

-.0916 1

17.985 -3.768 83.1 17.985 93.1

<-H><--P-> 4-dP->. <T-2, 17.995 93.1

-. 141 I

-. 0611 I

17.318 -. 6064 93.1 17.318 83.1

<-dH-.

c--PF-> A-dP->

cT->

17.318 83.1

-. 9165 I

-. 397 I

6.0922 -10.83 83 6.0922 83

<-H*<--P-> <-dP-> cT-:o 6.0922 83

-. 6204 I

-. 2687 I

5.8235 0

83 5.823S 83 LINK 100w=-110-.>

sgpm=145953 100>110 schwNS, mata"concrete", Di-90 component-name -------------------. > <--K-inlet node=00....................

straight pipe, 1enw440...........

change in elevation..............

exit-node-.10....................

C- -L-. <c--H-.

735.31 440 734.69 734.69 734.69

APPENDIX A MONI027-98006 Rev. 0 PAGE..

of 93 Date: 05/26/98 (Tuel EZFWOW: Version 5.00 site: unspecified Summar.net: SUMMER Time: 1450 34 Page _ of __

Prepared __

Checked Date _/_/_

Date _/_/_

TVA AUTHORIZED USE ONLY ----------------------------

LINK DETAIL LINK 110-=120-=>

sgpmn145953 110>120 sch=NS, mats"concrete", Di-90 component_name ------------------- >

inletnode-ll0...................

straight pipe, len-139...........

change in elevation..............

exit node-120....................

LINK 120umu130..>

sgpmn145953 120>130 sch.NS, mat="concrete",

Di.90 component-name ------------------. > <--K->

inlet node-120...................

straight pipe, Ien.814...........

change in elevation..............

exitnode=130....................

LINK 130-..140-.>

sgpm-145953 130>140 sch-NS, mat-"concrete",

Di=90 componentname -------------------- > c-K->

inlet node-130...................

straight pipe, len-248...........

change in elevation..............

exit-node=140....................

LINK 140=--150--:.

gpm-145953 140>.150 sch-NS, matr"concrete", Di-90 component_name -------------------. >

-- K-inlet node-l40...................

straight pipe, len-2S0...........

change in elevation..............

exit node l50.....................

LINK 150---160=u>

sgpm-1459S3 lS0160 schwNS, mat-"concrete",

Di=90 component name -------------------->

inlet node-lSO...................

straight pipe, len.450...........

change in elevation..............

exit-node-160....................

c-L-> < --

734.69 139 734.5 734.5 734.5

<-dH-> c--P-> <-dP-> <T->

5.8235 83

-. 196 1

-. 0049 7.9043 2.1657 83 7.9043 83 c-L->, <--H-> <-dHl-> <--P-> c-dP-;. cT->.

734.5 7.9043 83 814 733.35 -1.148 1

-. 4971 733.35 7.797.38983 83 733.35 7.797 83

  • 'L:.*-H-*

-dH-> <--P-., <-dP-:p cT->

733.35 7.797 83 248 733 -. 3497 1

-. 1515 733 10,418 2.7722 83 733 10.418 83 c-L-> <-H*<-dH->

<--P-> c-dP-:>

733 250 732.65 732.65 732.65 732.65 450 732.01 732.01 732.01 10.418

-. 3525 1

-. 1527 5.9335 -4.331 5.9335 9T-3 83 83 63 LINK 160.-.BYPAS>

sgpm-145953 160>BYPASSUP.TEE sch-NS, mata"concrete",

Di.90 componentname -------------------. >

c-L-> c--H->

inlet nodeal60......................

732.01 straight pipe, len=2B7............

287 731.61 change in elevation..............

731.62 exit node-BYPASSUP.TEE 731.62

-c-dH-> <--P-:- <-dP-> cT-Do 5.9335 83

-. 634S 1

-. 2749 4.5758 -1.083 83 4.5758 93

-d-c -- P-> <-dP-;- <T-ý,

  • 4.5758 83

-. 4047 1

-. 1753 4.3631 -. 0433 83 4.3631 83

APPENDIX A MDNI027-98006 Rev. 0 PAGE 82 of 93 Date: 05/26/98 (Tue)

EZFLOWs Version 5.00 site:

unspecified Sunner.net: SUMMER Time: 1450 35 Page of _

Prepared Checked Date _t Date


T V A A U T H O R I Z E D U S E O N L Y ------------------ ----------

LINK DETAIL LINK 163---165-->

sgpm-145953 SUPPLY VALVE sch-NS, mat-"carbon steel", Di=89.2 component_name ------------------- > <--K-> c-L->

inlet node-163 butterfly valve, K-0.55...........

.55 change in elevation..............

exit-node-165.....................

<--H-> <-dH-> c--P-> <-dP-> cT->

731.5 4.3549 83 731.02 -. 4799 1

-. 2079 I

731.02 4.147 0

83 731.02 4.147 83 LINK 165-..170-->

sgpm-145953 165>FACE OF WEIR schNS, mat-"concrete",

Di=90 component name ------------------- > c--K-> c-L-> c--H->

inlet node-165 731.02 straight pipe, len-i7 17 731 change in elevation..............

731 exit-node-170....................

731 c-dH-> c--P-> c-dP-,

<T->

4.147 83

-. 024 1

-. 0104 1

4.0933 -. 0433 83 4.0933 83 LINK 170---180O->

sgpm14SSS3 FACE OF WEIR>FACE OF TOWER schwNS, mat."concrete", Di=144 component name ------------------- > <--K-> <-L->

inletu node-170...................

straight pipe, len-i.............

1 change in elevation..............

exit_node-180....................

c--H->

731 731 731 731

<-dH-> <--P-a <-dP-> <T->

4.0933 83

-.0001

-6.E-5 I 0 -4.093 83 0

LINK 200-a-205--,

sgpms76579 UNIT I WEIR sch-NS, mat-"concrete",

Di-144 component_name ------------------- > <--K-> c-L-> <--H->

inlet node-200...................

726 square edged entrance................

.5 725.72 straight pipe. len-i.............

1 725.72 change in elevation..............

725.72 exitnode-205........................

725.72 LINK 205---210u->

agpm-176579 205>210 sch-NS, mat-"concrete",

Di-78 component name ------------------- > c--K-> 4-L-> c--H->

inlet node-205......................

725.72 straight pipe, lenu45............

45 725.54 change in elevation................

725.54 exit-node-210........................

725.54

<-dH-> <--P <-dP-:,x 83 92 92 92 92 0

-. 282 -. 1222

-. 0002 1.2855 1.2855

-.1222

-9.E-5 1.4077 c-dH-> <--P-> c-dP-> <T->

1.2855 92

-. 1911 1

-.0784 I

.86051 -. 3465 92

.86051 92 LINK 210=--220.->

sgpm-1 7 6 5 79 210>220 sch-US, mat-"concrete",

Diw78 component-name ------------------- > c--K inlet node-210...................

mitered bend, angle-45...........

straight pipe, len-aS change in elevation..............

exit-noden220....................

->)

C

<-L->

c--K->

725.54 93.8 725.1 55 724.88 724.88 724.88

<-dH-> <--P->

.86051

-. 4378 I

-. 2213

.22851

.22851 c-dP-> 4T->

92

-. 1896 I

-. 0959

-. 3465 92 92 70,

APPENDIX A MDNI027-98006 Rev. 0 PAGE 83 of 93 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER Time: 1450 36 Page _of Prepared Checked Date _/_/_

Date _

N--

TVA AUTHORIZED USE ONLY ----------------------------

LINK DETAIL LINK 220...230..>

sgpm-176579 220>230 sch-NS, mat-"concrete",

Diu78 component name -------------------- >

K->

inletnodea22o...................

straight pipe, len700...........

change in elevation..............

exit nodea230....................

LINK 230=a=233=.>

sgpm-176579 230>233 sch=NS, mat-"concrete", Di-78 component-name ---------------------- c--K->

inlet noden230...................

straight pipe, len-80............

change in elevation..............

exit node=233....................

<-L-> c--H->

724.89 700 722.06 722.06 722.06 c-L-> <--H-;

722.06 80 721.74 721.74 721.74 LINK 233n=-23Sa.>

sgpm=176579 DISCHARGE VALVE sch-NS, mat-"carbon steel", Di=77.2 componentname ---------------------. c--K-c-L->

inlet node-233...................

butterfly valve, K=0.55...........

.55 change in elevation..............

exit_nodes235 c--H->

721.74 720.49 720.49 720.49 LINK 235---BYPAS>

sgpm-176579 235>BYPASDIS.TEE

<-dH-> c--P-> c-dP-> <T->

.22851 92

-2.817 1

-1.22

.43764 1.4294 92

.43764 92

<-dH->- c--P->x <-dP-:> <T->

.43764 92

-. 322

-. 1.395

.29819 0

92

.29819 92 c-dH-> <--P-. c-dP-> <T->

.29819 92

-1.252

-. 5423

-. 2442 0

92

-. 2442 92

-c-dH-> <--P-:. c-dP-> <T-;,

-. 2442 92

-. 6238

-. 2702

-. 4876 0

92

-. 4876 92

<-dW-> c--P-> c-dP-,

<T->

-1.381 92

-1.811 1

-. 7844 1

-1.083 1.0829 92

-1.093 92

<-d.H-.

<--P-> c-dP-> 4T->

-1.083 92

-1.006

-. 4359 2.813 4.3315 92 2.813 92 sch.NS, maC-"concrete",

Dil78 component name ---------------------. c--K-inlet,..node-235...................

straight pipe, lenr 155...........

change in elevation..............

exit node-BYPASDIS.TEE...........

LINK 240---250..>

sgpm-176579 240>250 sch.NS, mata"concrete",

Di078 componentname ------------------- > c--K->

inlet node-240...................

straight pipe, len.450...........

change in elevation.............

exit node.250....................

c-L-> <--H->

720.49 155 719.86 719.92 719.92 c-L-. c--H->

717.76 450 715.95 715.95 715.95 LINK 250n=.260..>

sgpm-176579 250>260 schuNS, mat."concrete",

Di=78 componentname --------------------.

<--K inlet node-25o...................

straight pipe, len-25O change in elevation..............

exit node.260...................

-. c-*L-> c--H->

715.95 250 714.94 714.94 714.94

APPENDIX A MDNIO27-98006 Rev. 0 PAGE 84 of 93 Date: 05/26/98 (Tue)

Time: 1450 37 Page __ of __

EZFLOW: Version 5.00 Prepared l

Date

//

site: unspecified Checked Date _/_/_

Summer.net: SUMMER


TVA AUTHORIZED USE ONLY LINK DETAIL LINK 260..-270=->

agpm.176579 260>270 sch-NS, mat="concrete", Di=78 component name ---------------------. <--K-> <-L-inlet node=260...................

straight pipe, len-250...........

250 change in elevation..............

exit node=270....................

LINK 270---280-=>

sgpm-176579 270>280 sch=NS, mati"concrete",

Di=78 componentname ------------------- > <--K->

  • -L-*

inlet node-270....................

straight pipe, len=820.............

't 820 change in elevation..............

exit node-280....................

<--H->

714.94 713.94 713.94 713.94 713.94, 710.64 710.64 710.64 LINK 280.-.290-n-sgpm-176579 280:290 sCh-NS, mata"concrete",

Di-78 component name ------------------- > c--K->

inlet node=280 straight pipe, len-140...........

change in elevation..............

exit node-290.....................

LINK 290=...300-=:

agpm176579 290>300 achwNS, mats"concrete",

Di.79 componentname ----- 7 --------------

K inlet node=290 straight pipe, len-440...........

change in elevation..............

exit_node 300.....................

LINK 300=-=310-=>

sgpm-176S79 3003310 schwNS, mat-"concrete*, Dix78 component_name -------------------- z. 4--K-inlet.node-300...................

straight pipe, len.400...........

change in elevation..............

exit node-310....................

<-c-dH-> c--P-> <-dP-> <T-ý.

2.813 92

-1.006 1

-. 4358

-. 3949 -2.772 92

-. 3949 92

-. 3949 92

-3.3 I

-1.429

-2.214 -. 3898 92

-2.214 92

<-dH-> <--P-> <-dP-> <T->-

-2.214 92

-. 5634 1

-. 2441

-4.624 -2.166 92

-4.624 92

<c-dH-> <--P-> <-dP-;- <T->

-4.624 92

-1.771 1

-. 767

-5.391 0

92

-5.391 92 710.64 140 710.07 710,07 710.07 710.07 440 708.3 708.3 708.3

<-L*. -- H> <-dH-> c--P-> <-dP->. <T->

708.3

-5.391 92 400 706.69

-1.61 I

-. 6973 706.69

.45225 6.5406 92 706.69

.45225 92 LINK 310==-320-->

agpm.176579 310>320 schmNS, mat="concrete",

Di.78 componentname ------------------- > <--K-inlet node.310...................

straight pipe, len=S5............

change in elevation..............

exit node-320....................

-> <-L L-b <--H->

706.69 55 706.47 706.47 706.47

<-diH-> <--P-2> <-dP-z. <T-3.

.45225 92

-. 2213 1

-. 0959

.52964.17326 92

.52964 92

APPENDIX A X MDNIO27-98006 Rev. 0 PAGE 85 of 93 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer.net:

SUMMER Time: 1450 38 Page -

of __

Prepared Checked Date _/_/_

Date TVA AUTHORIZED USE ONLY ----------------------------

LINK DETAIL LINK 320Dw-330=.>

agpm-176579 INLET TO ENERGY DISSIPATER ach-NS, mat-"concrete", Di=78 component-name ------------------- >c<--K-> <-k-> c--H-> <-dH-> c--P-> <-dP-> cT->

inlet node=320...................

706.47

.52964 92 mitered bend, angle-75...........

261.1 705.25 -1.219 I

-. 5279 I

straight pipe, len=1.............

1 705.25

-. 004 J

-. 0017 change in elevation..............

705.25

-2.E-6 0

92 exit.....

1 705.25 4.4E-6 0 1.9E-6 92 exit-node-330....................

..... 705.25 0

92 LINK BYPASlI63n->

sgpm-145953 BYPASSUP.TEE>163 sch=NS, mata"concrete", Di=90 component name --------------------> c--K-> c-L-, c--H-c <-dl-> c--P-> <-dP-> CT->

inlet-node-BYPASSUP.TEE 721.55 0

83 straight pipe, len=80............

80 721.44 -. 1128

-. 0489 change in elevation..............

731.5 4.3549.04331 83 exit node

.163 731.5 4.3549 83 LINK BYPAS-240.->

agpm=176579 BYPASDIS.TEE>240 sch.NS, mat."concrete",

Di-78 component name ------------------- > <--K-> <-L-> c--H-?

<--P-3. c=dP'% 4T->

inlet nede-BYPASDIS.TEE..........

721.05 0

92 straight pipe, len=165 165 720.39

-. 664 I

-. 2876 change in elevation..............

717.76

-1.381

.04331 92 exit node.240....................

..... 717.76

-X.381 92 LINK BYPAS-BYPAS>

sgpm-0 BYPASS LINE FROM SUPPLY TO DISCHARGE sch-NS, mat."concrete", Di=42 componentname ------------------- >

inlet node=BYPASSUP.TEE..........

fixed..low.0.....................

straight pipe, len=LO............

mitered bend, angle-45...........

straight pipe, len=75............

butterfly valve, K=0.55..........

straight pipe, len=60............

change in elevation..............

exit_node-BYPASDIS.TEE...........

C- -

3.

-K-> c-k-> c--H->

731.62 E+7 719.92 10 719.92 50.51 719.92 75 719.92

.55 719.92 60 719.92 718.43 718.43 c-dli-> c--P'-,

4.3605

-11.69 -. 7042 0

0 o0

-1.137

-1.137 c-dP-> cT->

70

-5.065 70 01 ojI 01 01

.21657 70 70 LINK SCCV.-070-->

sgpm-145953 SCCW.TEE>070 sch-NS, mat-1concrete", Di-90 component-name -------------------

> c--K->

<-L-inlet node-SCCW.TEE..............

straight pipe, len-90............

90 change in elevation..............

exit_node-070....................

c--H->,

684.2S 684.12 736.58 736.58

<-di-> c--I-> <-dP->

0

-. 1269

-. 055 21.845

-. 823 21.845

<T->

83.1 83.1 93.1

'it U

APPENDIX A MDNIO27-98006 Rav. 0 PAGE 86 or 93 Date: 05/26/98 (Tue)

EZFLOW: Version 5.00 site: unspecified Summer.net: SUMMER Timet 1450 39 Page _-

of __

Prepared Checked Date

/

Date _/_/_

TVA AUTHORIZED USE ONLY ----------------------------

LINK DETAIL LINK TEE.B-TEE.C>

sgpm-79851.4 TEE.B>TEE.C sch-DUCT, mat="concrete",

high-138, wide-78 component name -------------------

-K->

>-L->

inlet node=TEE.B.................

straight pipe, len=12............

12 change in elevation..............

exitnode-TEE.C..................

LINK TEE.Ca025=.>

sgpm145953 TEE.C>025 bch-DUCT, mat="concrete",

high=138, wide-78 componentname -------------------. >

-- K-> 4-L->

inlet nodea TEE.C.................

straight pipe, len=l.............

1 change in elevation..............

exit_node-025

<--H-> <-dH->

714 114 -. 0024 739.98 739.98

<--P-, <-dP->

0 I

-.0011 11.255 0

11.2S5

<T-z-83 83 83 4--H-> <-dH-> <--P-> <-dP-> cT->

714 0

83 714 -. 0006

-. 0003 1

739.37 10.23

-. 758 83 739.37 10.23 83 LINK TRANS-032A=>

sgpm=78110.9 TRANS.TEE>032A sch-DUCT, mat-"concrete",

high=138, wide=39 component name -------------------. >

-- K-> c-L-,

inlet node-TRANS.TEE straight pipae len-l........

I change in elevation..............

exitnode-032A...................

LINK TRANS-032B=>

sgpm-67842.3 TRANS.TEE>032B sch-DUCT, mat-"concrete", high-138, wide-39 component name --------------------. c--K-> c-L->

inlet-node-TRANS.TEE straight pipe, len-i.............

change in elevation...............

exit node-032B....................->

738.73 738.12 738.37 738.37

<--H->

715.56 715.56 738.72 138.72

<-dH-> 4--P-> <-dP-> cT->

10.035 83

-. 00o19

-. 0007 9.8786 0

83 9.8788 83

<-dH-> c--P-, <-dP-,

<T->

0 83

-. 0012

-. 0005 10.034 0

83 10.034 63

i GIF image 700x560 pixels Atta-c+A YAr-F http:Ilterraserver1.knx.tva,gQvlhthinitweb?dpy1damHeadwater-WBH Ua6tts 9-w Resr.-otr I"? c'rT-,m Elfe11.t~cs Si I"

75.

749 744 74?

747 741 744 741 748 I"

MT6 M2 Ma r34

~

229 2:7 221 225 V24 tJRR 1097.

1t.24 MPNI2-v7-dtqIoj*

0 g"0

-Po o 7aP q; I

Dw of Year

-~~-g 11 i4~'7 i

-c

A t,+ozvtirm n-rb -2 MDN 1O2-7-,IocjyG -Ro

?Pa3e I

Table 4 MonthIy Average and Extreme Ambient River Temperatures ('17)

)

I Oct No e

LMin Avg Jn Feb 42.01741.9 Mar Apr May Jun Jul Aug 37.6 48.6 57.7 62.5 66.1 70.7 67.4 Sep I

I I

5817 47.6F39.6 47,7 56.7 64.5 70.7 74.9 76.5 75.0 56.1 65.1 71.9 78.8 82.5 81.7 81.1 I

)

I

]

-.9

'2-v

I MAR,.-23.F3 1 2:DO~PM nMC H C/

IGHPOINT I Date r, 0.g 30 P. I MDNt OZ7-q&*oo0&,

-PP-j e-89 March 23, 1998 I Number of pages including cover sheet 7

TO; Charlie Allen 7VA - Watts Bar Dam Phone Fax Phone (423) 365-1750 FROM:

Phone Fax Phone Glenn P. Zetterberg FMC Corporation P.O. Box 904 Chalfont, PA 18914 (215) 822-4423 (215) 822-4342 ICC:

REMARKS:

Urgent F

Foryourreview

[I RepfyASAP C3 Please Comment RE: Expected Headloss Calculations. Different Water Level, # of Screens. Flow Volume

Charlie, Following are our Expected Headloss calculations based on the different variables (Water Level, # of Screens, and Flow Volume).

The calculations were based on the following:

- 6 ft. wide steel tray

-14 Gauge (.080 diameter) screen cloth with 3/8" square openings

- Velocity and headloss were calculated at the low water depths I will mail the originals to your attention.

Please feel free to give me a call if you have any questions.

Best regards, A

~

CLEAN SCREEN 100 go 80 70 60 SO ao 30 20 to (3) SCREENS 1 1111,400 OPM TOTAL CAPACITV LOW WATER OEPTH 25 FT WATER VEL FTJSEC 1.43 1.59 1.79 2.05 2.83 3.58 4,75 7.17 14.33 i10o.

L P,.7 MD K)

ItC? 271-130 (a

'1ý f ?t6e, 10-!E-9 HEAD LOSS INCHES

.375

.424

.486

.716 Ssa 1.374 2.294 4.928 19.134

% CLEMA SCREEN 100 90 70 60 50 40 30 20 10 LOW WATER DEPTH 30.5 FT WATER VEL FTISEC 1.17 1.30 1.46 1.67 2.34 2.93 3,90 585 11.70 LOW WATER OEPTH 35 FT HEAD LOSS INCHES

.252

.212

.324

.384

.478

.632

.916 1.53 3.286 12.762

  • A CLEAN SCREEN 100 90

,.,80 70

/

so 20 10 WATER VEL FTISEC 1,02 1.13 1.27 1.45 2.04 2.54 03,,1 5.09 10.19 HRAO LOSS INCHES

.192

.214

,244

.29

.30

.478

.692 I.: 5a 2,444 9164

Irqp..Z73.1998s j.-olpf FrP': H1GaHPQ~r1T~t t& k (3) SCREENS 138100~PMTOTAL. CAPCrrY-LOW WATER DEPTH 25 FT

3

)A1>Moz1- 'qooOfa HEAD LOSS INCHES i

% CLEAN SCREEN WATER VEL FTISEC 90 go 70 80 so 40 30 20 10 I

% CLEAN SCREEN 100 go 60 70 60 40 30 20 10

% CLEAN SCREEN 1.16 1.29 1.45 1.60 1.91 2.32 2.91 3.87 5.81 11.62 LOW WATER DEPTH 30.5 PT WATER VEL FTISEC O.95 1.09 1.19 1.36 1.58 1.90 2.37 3.16 4.75 9.49 LOW WATeR OEPTH 35 FT WATER VEL FTISEC

.25

.. 278 32

.318

.47

.822

,904 1.508 3,24 12.582 HEAD LOSS INCHES

.1J8

.188

.212

.252

.314

.416

.602 1.006 2.18 8.392 HEAO LOSS INCHES 100 soo so I0 70 60 40 40 30 20 to 0.83 0.92 1.03 1.16 1.38 1,05 2.06 2.75 4.13 A128

.14

.18

.192

.23a 314 ASS

.76 1.634 944M

CLEIA SCREEU 100 90 80 70 60 o5 s1o 30 20 I0 r~

~

t~

k'* ro iepr,.,il, (3) SCREENS

  • .0,300 dPM TOTAL CAPACITY LOW WA"EA Q0TN 25 FT WATER VEL FTfSEC 0.78 0.88 0.97 1.11 1.29 1.55 1,94 2.sq 3.88 7.77 MPM 10271 -91 8000C1 fRO HEAD LOSS INCHt~5

.112

.124

.142

.17

.21

.074 I.A7S

% CLEAN SCREEN 100 80 70 60 50 40 30 20 10 Low WATER DEPTM 30.5 FT WATER VEL FTISEC 0.63 0.70 0.79 0.91 1.06 1.27 1.59 2.11 3.17 8.34 LOW WATER DEPTH 35 FT WATER VEL PTISEic HEAD LOSS INCHES

.074

.082

.098

.112

.14

.186

.27

.45

.g88 3.75 HEAD LOSS INCHES i

% CLEAN SCREEN 100 0.so

.0n8 90

'"0,61

,062 70 0..9

.072 70 03~g

.066:..

80 0.92

.106 50 1.10

.14 4Q 1,38

.204 30 1.84

.34 20 2.78

.711 s*5~

2834

+.

6'.

.~

~'6

A+-Utctc~k rvv~eev+ +

M'DI10-277-9Sc0oG 1RQ I

-P, EPRI Licensed Material Nuclear Maintenance Applications Center 10000 1000 w

A!100 QI' 10 ILa i

0.1 0

10 20 30 40 so 60 70 s0 90 DISC Opening Angle, z (degrees)

Figure 3.10 Typical Kv Values for Butterfly Valves of Different Disc Designs I.

I..

3.30 w.-

H-14 Figure

A SCCW intake structure (old fossil intake)

(idle)

SCCW intake conduit Bypass conduit with bypass valve -

Intake valve ---

Unit 2 cooling tower -- v

- Disc

" *.-- SCCW discharge conduit charge valve Blowdown Blowdown conduit to i',j diffusers (Outfall 101) and yard holding pond Unit 2 condenser cooling water loop (active)

Turbine building Unit 1 cooling tower Unit 1 condenser cooling water loop (active)

Unit 2 condenser Unit 1 condenser Figure 1. Schematic for Operation of Supplemental Condenser Cooling Water System for the Combined Operation of Unit 1 and Unit 2 1

List of Commitments

1.

TVA will provide additional information on or before March 12, 2010.