Other: CNL-15-039, Severe Accident Management Alternatives for Reactor Coolant Pump Seals, ML090360589, ML093630039, ML100120107, ML100210350, ML100630115, ML100630139, ML100630140, ML100630146, ML100630155, ML100630167, ML100630169, ML100630170, ML100630171, ML100630173, ML100630174, ML100630175, ML100630176, ML100630177, ML100630178, ML100630192, ML100630193, ML100630194, ML100630234, ML100630235, ML100630263, ML100630264, ML101130395, ML101130397, ML101130398, ML101130399, ML101130401, ML101130403, ML101130404, ML101130405, ML101130407, ML101130408, ML101130409, ML101170096, ML101390048, ML103080030, ML110871475, ML110890472, ML11264A052, ML11294A461, ML11329A001, ML12166A068, ML12296A227, ML13130A031, ML13150A376... further results
|
MONTHYEARML1011303992004-05-15015 May 2004 Drawing, Hydrogeologic Cross-Section A-A, Attachment D Project stage: Other ML1011304082004-05-15015 May 2004 Drawing, Distribution of Tritium Concentrations in Groundwater, March 2004, Attachment J Project stage: Other ML1011304072004-05-15015 May 2004 Drawing, Water Table at Power Block, March 2004, Attachment I Project stage: Other ML1011304052004-05-15015 May 2004 Drawing, Water Table, Attachment H Project stage: Other ML1011304042004-05-15015 May 2004 Drawing, Hydrogeologic Cross-Section D-D, Attachment G Project stage: Other ML1011304032004-05-15015 May 2004 Drawing, Hydrogeologic Cross-Section C-C, Attachment F Project stage: Other ML1011304012004-05-15015 May 2004 Drawing, Hydrogeologic Cross-Section B-B, Attachment E Project stage: Other ML1011304092004-05-15015 May 2004 Drawing, Distribution of Tritium Concentration in Groundwater at Power Block, March 2004, Attachment K Project stage: Other ML1011303982004-08-10010 August 2004 Map, Bedrock Contours, Attachment C Project stage: Other ML1011303952004-08-12012 August 2004 Site Map. Attachment a Project stage: Other ML1011303972004-08-12012 August 2004 Block Site Map, Plate B Project stage: Other ML1011700962004-08-12012 August 2004 Groundwater Investigation Report Project stage: Other ML0733300822008-02-15015 February 2008 IMC 2517, Watts Bar Unit 2 Construction Inspection Program Project stage: Request ML0814300282008-05-14014 May 2008 Transmittal of Annual Radiological Environmental Operating Report of 2007 Project stage: Request ML0812102702008-06-0303 June 2008 Request for Supplemental Information to Support Acceptance Review of Final Supplemental Environmental Impact Statement Project stage: Acceptance Review ML0818504602008-07-0202 July 2008 Final Supplemental Environmental Impact Statement - Request for Additional Information Project stage: Supplement ML1006301392008-12-12012 December 2008 WB-DC-20-20, Revision 0009, Traveling Water Screens and Trashracks, Project stage: Other ML0903605892009-01-21021 January 2009 Enclosure 1 - Watts Bar, Unit 2 Severe Accident Management Alternatives Analysis Project stage: Other ML0903605882009-01-27027 January 2009 Final Supplemental Environmental Impact Statement - Severe Accident Management Alternatives Project stage: Supplement ML1006302632009-11-0707 November 2009 Map - Final Map of the Watts Bar Nuclear Plant Project stage: Other ML1006302642009-11-0707 November 2009 Map of the Wetlands Streams Project stage: Other ML0922300242009-11-30030 November 2009 Watts, Unit 2, RAI, Regarding Severe Accident Management Alternatives Project stage: RAI ML0930301482009-12-0303 December 2009 RAI, Regarding Environmental Review Project stage: RAI ML0932900732009-12-0303 December 2009 Environmental RAI Enclosure Project stage: RAI ML1001201072009-12-14014 December 2009 December 14, 2009, TVA Letter Additional Information Regarding Environmental Review - Cultural Resources Project stage: Other ML0936300392009-12-22022 December 2009 Severe Accident Management Alternatives Additional Information Project stage: Other ML0935613292009-12-23023 December 2009 Notice of Meeting with Tennessee Valley Authority to Discuss Tennessee Valley Authoritys (TVA) Use of Digital Instrumentation Platforms on Watts Bar Unit 2 Project stage: Request ML1002103502009-12-23023 December 2009 Submittal of Additional Information Regarding Environmental Review Project stage: Other ML1006301672010-01-15015 January 2010 Intact Containment Loss of Coolant Accident (LOCA) Analysis Project stage: Other ML1006302332010-01-26026 January 2010 Response to Tennessee Valley Authority Request for Plant Water Flow Information Project stage: Request ML1006302342010-02-25025 February 2010 Annual Estimates 2008 - Average Net Megawatts = 1180 Mwe, Non-Outage O&M Project stage: Other ML1006302352010-02-25025 February 2010 Yard Holding Pond Wsel Graph Overflow for 2001 Project stage: Other ML1006301692010-02-25025 February 2010 Drawing, Plot: 6059KX Bull Run Project stage: Other ML1006301942010-02-25025 February 2010 Drawing, Plot: 5167GF Winchester-Watts Bar FP Project stage: Other ML1006301932010-02-25025 February 2010 Drawing, Plot: 6092KX Watts Bar-Volunteer Project stage: Other ML1006301702010-02-25025 February 2010 Drawing, Plot: 5047CL Sequoyah-Watts Bar HP Project stage: Other ML1006301712010-02-25025 February 2010 Drawing, Plot: 5173KX Watts Bar HP-Great Falls Project stage: Other ML1006301732010-02-25025 February 2010 Drawing, Plot: 5127CL Watts Bar HP-Watts Bar 1 Project stage: Other ML1006301742010-02-25025 February 2010 Drawing, Plot: 5791KX Watts Bar HP-Rockwood Project stage: Other ML1006301922010-02-25025 February 2010 Drawing, Plot: 6084KX Watts Bar NP-Roane Project stage: Other ML1006301752010-02-25025 February 2010 Drawing, Plot: 5733KX Watts Bar HP-Spring City Project stage: Other ML1006301762010-02-25025 February 2010 Plot: 6080CL Watts Bar HP-Sequoyah 1 Project stage: Other ML1006301772010-02-25025 February 2010 Plot: 608 1CL Watts Bar NP-Sequoyah Np 2 Project stage: Other ML1006301782010-02-25025 February 2010 Drawing, Plot: 5645 Cl Watts Bar-Athens Project stage: Other ML1006301152010-02-25025 February 2010 Additional Information Regarding Environmental Review Project stage: Other ML1006301552010-02-25025 February 2010 Operating Conditions for Intake Pumping Station, Table 1 Project stage: Other ML1006301402010-02-25025 February 2010 Plant Withdrawal Impacts, Water Supplied by Intake Pumping Station (Ips)/Average Velocity for All Openings Project stage: Other ML1006301462010-02-25025 February 2010 Plant Withdrawals Impacts, Water Supplied by Sccw Intake/Average Velocity for Expect No. of Bays in Service Project stage: Other ML1009902062010-04-0909 April 2010 Memorandum to the Participants Re Commissioner William C. Ostendorffs Upcoming Tour of the Watts Bar Nuclear Power Plant, Unit 2 Project stage: Request ML1011303932010-04-0909 April 2010 Response to U.S. Nuclear Regulatory Commission (NRC) Request for Additional Information Regarding Environmental Review Project stage: Request 2009-01-27
[Table View] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 June 11, 2012 10 CFR 50.54(f)
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Bellefonte Nuclear Plant, Units 1 and 2 Construction Permit Nos. CPPR-122 and CPPR-123 NRC Docket Nos. 50-438 and 50-439 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391
Subject:
Reference:
Tennessee Valley Authority (TVA) Day Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)
Regarding Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident; dated March 12, 2012 Printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 June 11, 2012 On March 12, 2012, the NRC issued Reference 1 to all power reactor licensees and holders of construction permits in active or deferred status. Enclosure 1 of Reference 1 contains specific Requested Actions, Requested Information, and Required Responses associated with Recommendation 2.1, Seismic Evaluations. Reference 1 requires that, if an addressee cannot meet the requested response date, it must provide a response to NRC within 90 days of the date of the information request describing the licensee's proposed alternative course of action, the basis for the acceptability of the proposed alternative course of action, and the estimated completion dates.
TVA will meet the requested response dates in Reference 1 for submitting the Seismic Hazard Evaluation provided that the NRC and industry reach a mutual understanding of critical implementation details associated with calculating the seismic hazard by the end of July 2012.
For example, the critical details that need to be mutually understood prior to commencement of the new seismic hazard evaluations including the elevation(s) at which the hazard/ground motion response spectra (GMRS) will be calculated.
Within 60 days of the NRC endorsement of the Screening, Prioritization and Implementation guidance, TVA will submit: (1) its intention to follow the endorsed guidance, or (2) provide an alternative approach. At that time, TVA will assess whether it can meet the submittal deadlines for the Seismic Risk Evaluation and take the appropriate regulatory action.
Because the response provided in this letter and the future responses discussed in this letter are required by Reference 1, they are considered to be regulatory requirements. Therefore, this letter contains no regulatory commitments.
If you have questions regarding our comments, please telephone Fredrick Mashburn at (423)751-8817.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on the 1 1th day of June 2012.
Respe ly, J.
Shea arger, Corporate Nuclear Licensing cc: See Page 3
U.S. Nuclear Regulatory Commission Page 3 June 11, 2012 cc:
NRC Regional Administrator - Region II NRR Director - NRC Headquarters NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant NRR Project Manager - Browns Ferry Nuclear Plant NRR Project Manager - Sequoyah Nuclear Plant NRR Project Manager - Watts Bar Nuclear Plant