Other: ML062080142, ML062480361, ML062480362, ML062480381, ML062480383, ML062480388, ML062480391, ML062510295, ML062510296, ML062510299, ML062510302, ML062510306, ML062510307, ML062510324, ML062510346, ML062510350, ML062510355, ML062510359, ML062510361, ML063050380, ML063050385, ML063050388, ML063050392, ML063050396, ML063050501, ML063050504, ML063050506, ML063050512, ML063050514, ML063050518, ML063050603, ML063050610, ML063050613, ML063060239, ML063060249, ML063060259, ML063060267, ML063060296, ML063060299, ML063060302, ML063060309, ML063060322, ML063070187, ML063070190, ML063070217, ML063070219, ML063070220, ML063070222, ML063070225, ML063070232... further results
|
|
|
---|
Category:E-Mail
MONTHYEARML22335A2802022-11-0404 November 2022 11-4-2022 Email Transmitting Draft Questions Pertaining to Pilgrim ISFSI Exemption Request ML22270A0422022-09-26026 September 2022 Acknowledgement Email for Holtec'S Request for Reporting Exemption with Regards to the Pilgrim ISFSI Annual Radioactive Effluent Release Report (Docket No. 05000293) ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22007A2602021-12-0606 December 2021 E-mail from P. O'Brien, Holtec, to A. Snyder, NRC, on Pilgrim Effluent Discharge ML21287A6192021-10-14014 October 2021 E-mail from S. Phillips, MEMA, to A. Snyder, NRC, Pilgrim Nuclear Power Station, Commonwealth of Massachusetts Consultation Response to Amendment Review for Emergency Preparedness ML21266A2512021-09-23023 September 2021 Consultation with Commonwealth of Massachusetts Regarding Proposed Amendment Application for Emergency Plan and Emergency Action Levels ML21266A2772021-09-23023 September 2021 HDI Clarification of Exemption Requested from 10 CFR 20, Appendix G, Section Iii.E ML21267A0012021-09-23023 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E Acceptance Review ML21257A3832021-09-15015 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Follow-on Request Re Request for Additional Information 2 Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Pl ML21211A5912021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21211A5162021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Physical Security Plan ML21200A2352021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21200A1522021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim Isfi Only Physical Security Plan ML21176A1842021-06-25025 June 2021 Email from HDI Regarding Pilgrim Nuclear Power Station Training ML21180A0582021-06-17017 June 2021 Email from Region I Regarding Pilgrim Nuclear Power Station Inspection - EA-13-132 ML21097A0402021-04-0606 April 2021 E-Mail Consult with Commonwealth of Mass Re - Amendment Application - Physical Security Plan for the Pilgrim Nuclear Power Station L-20-092, Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B,2020-12-10010 December 2020 Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B, L-20-096, Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 20102020-12-10010 December 2020 Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 2010 ML20328A2982020-11-16016 November 2020 Response from Commonwealth of Massachusetts on No Significant Hazard for Pilgrim ISFSI Amendment to Address ISFSI II Dated November 16, 2020 ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20266G4032020-09-22022 September 2020 Acceptance Review Email - Request for Approval of HDI Fleet Decommissioning Quality Assurance Program, Revision 0 ML20163A6802020-06-11011 June 2020 Confirmation of the Scope of the Requested Regulatory Relief for Pilgrim Security Qualifications ML20280A1912020-04-17017 April 2020 Request for Additional Information- Clarifying Information for Pilgrim ISFSI Physical Security Amendment Application ML20269A3542020-03-0505 March 2020 CFR 26.717 Reports 2019 Transmittal Email ML19336A0302019-11-27027 November 2019 OEDO-15-00479 - Re 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding ML19336A0332019-11-26026 November 2019 OEDO-15-00479 - E-mail to Petitioner - 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding (CAC No. MF6460; EPID L-2015-CRS-0002)- Issuance of Final Director'S Decision ML19331A1952019-11-21021 November 2019 NRR E-mail Capture - (External_Sender) Pilgrim Nuclear Power Station - Commonwealth Consultation Response - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1732019-11-12012 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Cyber Security Plan ML19331A1642019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1792019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Emergency Planning Exemption CY-19-007, LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station2019-11-0404 November 2019 LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station ML19275H1962019-09-24024 September 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Consult with Commonwealth - Amendment Regarding Permanently Defueled Technical Specifications (PDTS) ML19239A0372019-08-26026 August 2019 E-mail from Entergy Dated August 26, 2019, Notification of Pilgrim License Transfer ML19239A0262019-08-23023 August 2019 LTR-19-0330 Janet Azarovitz, E-mail a Plea for More Time and Reasonable Discussion Including the Citizens of the Commonwealth in the Sale of the Pilgrim Nuclear Power Station ML19234A2072019-08-20020 August 2019 LTR-19-0328 Lawrence Delafield, President, Six Ponds Improv Assoc., Plymouth, Ma, Ltr Requests NRC to Postpone Consideration of Transferring the Licenses for the Pilgrim Nuclear Power Until the NRC Has Answered Concerns by Pilgrim Watch, Se ML19232A4032019-08-20020 August 2019 LTR-19-0322 Diane Turco, Director, Cape Downwinders, Massachusetts, Letter/E-mail Requests Suspension of the Pilgrim License Transfer from Entergy to Holtec Until the Adjudicatory Hearing Is Held and Raised Contentions Are Resolved ML19308A9942019-08-19019 August 2019 Entergy Nuclear Operations, Inc. Confirmatory Order Rescission Supplemental Information ML19226A3912019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Decommissioning Trust Fund Exemption (Holtec) ML19226A3962019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Conforming Amendment in Support of Pilgrim License Transfer Application ML19226A1212019-08-13013 August 2019 OEDO-15-00479-2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Status (CAC No. MF6460; EPID L-2015-CRS-0002) ML19227A1032019-08-0707 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Draft Wording for Potential Condition of License Transfer Order ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc ML19176A3452019-06-25025 June 2019 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Information (OEDO-15-00479) (CAC No. MF6460; EPID L-2015-CRS-0002) ML19154A0652019-06-0303 June 2019 NRR E-mail Capture - Pilgrim - Permanent Cessation of Power Operations ML19154A5242019-06-0303 June 2019 NRR E-mail Capture - RAI - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML19161A2122019-05-20020 May 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of License Amendment Request to Remove Cyber Security Plan Requirements ML19123A0332019-05-0101 May 2019 NRR E-mail Capture - Logbook Entry: 05/01/2019 Endangered Species Report Regarding a Confirmed Sighting of North Atlantic Right Whale(S) (Balaena Glacialis) ML19122A4912019-04-29029 April 2019 NRR E-mail Capture - Logbook Entry: 04/29/2019 Regarding the Confirmed Sighting of Ten North Atlantic Right Whales (Balaena Glacialis) ML19108A2372019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 50.54(w)(1) - On-Site Property Damage Insurance ML19108A2362019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 140.11(a)(4) - Primary and Secondary Liability Insurance 2022-09-26
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML21223A2422021-08-16016 August 2021 Enclosure - Pilgrim Nuclear Power Station - Request for Additional Information Regarding Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan ML21161A1072021-07-0909 July 2021 Request for Additional Information Regarding Pilgrim License Amendment Request ISFSI Only Emergency Plan ML21013A5232021-01-15015 January 2021 Request for Additional Information Regarding the Request to Change the Physical Security Plan - Alternative Measures ML20297A2382020-10-22022 October 2020 Fleet DQAP RAIs - Enclosure ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20142A2422020-05-26026 May 2020 Acceptance of Requested Licensing Action Physical Security Plan Revision and License Amendment Request to Incorporate Additional Independent Spent Fuel Storage Installation with Requests for Additional Information ML20280A1912020-04-17017 April 2020 Request for Additional Information- Clarifying Information for Pilgrim ISFSI Physical Security Amendment Application ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc ML19154A5242019-06-0303 June 2019 NRR E-mail Capture - RAI - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML19086A3492019-03-21021 March 2019 NRR E-mail Capture - Pilgrim Power Station - Request for Additional Information Application for Order Consenting to Direct and Indirect Transfers of Control of Licenses and Approving Conforming License Amendment (EPID: L-2018-LL0-0003) ML19036A6512019-02-0404 February 2019 NRR E-mail Capture - RAI - Pilgrim EP Exemption ML18320A1292018-11-16016 November 2018 NRR E-mail Capture - Request for Additional Information (RAI) - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML18323A1192018-11-15015 November 2018 CAL 5 Document Request #2 ML18317A2202018-11-11011 November 2018 NRR E-mail Capture - (External_Sender) Questions and Comments Regarding Pilgrim EP Exemption RAI, October 16, 2018 ML18317A2192018-11-0808 November 2018 NRR E-mail Capture - (External_Sender) RAI EP 11.06.18-Question ML18310A0212018-11-0606 November 2018 NRR E-mail Capture - RAI - Pilgrim EP Exemption ML18289A4072018-10-16016 October 2018 NRR E-mail Capture - RAIs - Pilgrim EP Exemption ML18285A8182018-10-12012 October 2018 NRR E-mail Capture - for Your Action: RAIs - Pilgrim - LAR - EP and EAL Scheme to Address Permanently Defueled Condition ML18124A1392018-05-0404 May 2018 NRR E-mail Capture - RAI - Pilgrim ERO Staffing License Amendment Request ML18094B0922018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to B. S. Ford RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for ISFSI Docket Nos.: 72-43, 72-51, 72-1044, 72-07, 72-12, and 72-59) ML18005A5422018-01-0505 January 2018 NRR E-mail Capture - Second Round of RAI for DAEC Fifth Inservice Inspection Interval Program Plan, Relief Request RR-03 - EPID: L-2017-LLR-0110 ML16347A0042016-12-0909 December 2016 NRR E-mail Capture - Pilgrim: Request for Additional Information for Relief Requests on Volumetric Exam Requirements, PNPS-ISI-001, 002 and 003 ML16013A0642016-01-13013 January 2016 NRR E-mail Capture - Request for Additional Information Entergy CNRO-2015-00023 - Revision to Entergy Quality Assurance Program Manual (Fleet Submittal CAC Nos. MF7086-MF7097) ML15341A1662015-12-0707 December 2015 NRR E-mail Capture - Entergy Fleet RR-EN-15-1, Request for Additional Information (CACs MF6341-MF6349) ML15211A6612015-07-30030 July 2015 Licensed Operator Positive Fitness-For-Duty-Test ML15051A0322015-02-25025 February 2015 Request for Additional Information Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request ML14342A0942014-12-17017 December 2014 Request for Additional Information Regarding Relief Request PRR-24, Nozzle-to-Vessel Welds and Nozzle Inner Radii Examinations ML14042A0432014-02-18018 February 2014 Request for Additional Information Regarding Safety Limits to Resolve Pressure Regulator Fail-Open Transient License Amendment Request ML13333A9102013-12-0505 December 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool ins ML13323B4702013-11-25025 November 2013 Request for Additional Information Regarding Relief Request PRR-22 ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13179A4622013-07-0505 July 2013 Entergy Nuclear Operations, Inc., Decommissioning Funding Status Report Request for Additional Information Regarding the Decommissioning Funding Status Report ML13182A4252013-07-0101 July 2013 Request for Additional Information E-mail from R.Guzman to W.Lobo PR-03 and PR-05 Fifth Ten-Year Inservice Testing (IST) Program ML13165A2762013-06-20020 June 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (NRC Order EA-12-051) ML12278A3862012-10-0404 October 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2, and 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford, Request for Additional Information, Round 2, Amendment Request to Revise QA Program Manual and Staff Qualification TSs ML1209604492012-04-0505 April 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Request for Additional Information, Revise Quality Assurance Program Manual and Staff Qualification Technical Specificat ML1208601472012-03-26026 March 2012 Request for Additional Information - Pilgrim Nuclear Power Station Revision to Condensate Storage Tank Low Level Trip Setpoint ML12056A0512012-03-12012 March 2012 Enclosure 5 - Recommendation 9.3: Emergency Preparedness ML12056A0502012-03-12012 March 2012 Enclosure 4 - Recommendation 2.3: Flooding ML12056A0482012-03-12012 March 2012 Enclosure 2 - Recommendation 2.1: Flooding ML12056A0492012-03-12012 March 2012 Enclosure 3 - Recommendation 2.3: Seismic ML12056A0472012-03-12012 March 2012 Enclosure 1 - Recommendation 2.1: Seismic ML1132502282011-11-22022 November 2011 Request for Additional Information, Relief Request No. PRR-21 ML1132202342011-11-21021 November 2011 Request for Additional Information 60-Day Response to Bulletin 2011-01, Mitigating Strategies, ML1114402342011-05-25025 May 2011 Request for Additional Information to Support the Review of 2011 Decommissioning Funding Status Report ML1108202082011-04-11011 April 2011 Summary of Telephone Conference Call Held on March 23, 2011, Between the USNRC and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application ML1106101872011-03-0303 March 2011 Request for Additional Information to Support the Review of Pilgrim Nuclear Power Station Cyber Security Plan (Id: 2.10.034) ML1105403302011-02-15015 February 2011 Response to Request for Additional Information (Rai), Dated January 5, 2011 on the Cyber Security Plan ML1100900272011-01-10010 January 2011 Request for Additional Information Revision to TS for Setpoint and Setpoint Tolerance Increase for Safety Relief Valves and Spring Safety Valves, and Related Changes (ME3543) ML1034105062011-01-0707 January 2011 December 1, 2010, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application 2021-08-16
[Table view] |
Text
l[Kenýt pward_-RAI on Chapter 4.0 TLAAs ................ . .. .. . . .... _ _Page 1 From: Ram Subt *aratnam To: ChristophEer Sydnor; Ganesh Cheruvenki Date: 8/16/2006 10:36:35 AM
Subject:
RAI on Ch apter 4.0 TLAAs Ganesh/Chris:
These are the only RAIs so far on chapter 4.0 (from Simon). As I am wrapping up my RAIs for Pilgrim (I thank you all for the very prompt and pro-active coperation in providing me insight related to your assignment), I will very much appreciate it if you can let me know if you have any furhter Qs on Chapter 4.0.
Thanking you.
Ram Subbaratnam PM Pilgrim LRA (301) 415 1478 CC: Kimberly Gruss; Matthew Mitchell
Hc:\temD.\GWJ00001.TMP Paqe 1 1I c:\temi:AGWIOOOO1 .TMP Pacie 1 Mail Envelope Properties (44E32D73.74D:19:10294)
Subject:
RAI on Chapter 4.0 TLAAs Creation Date 8/16/2006 10:36:35 AM From: Ram Subbaratnam Created By: RXS2@ nrc. gov Recipients Action Date & Time nrc.gov OWGWPOO2.HQGWDO01 KAG1 CC (Kimberly Gruss) nrc.gov OWGWPOO3.HQGWDO01 GSC (Ganesh Cheruvenki) nrc.gov TWGWPOO1.HQGWDO01 MAM4 CC (Matthew Mitchell) nrc.gov TWGWPO02.HQGWDO01 CRS (Christopher Sydnor)
Post Office Delivered Route OWGWPO02.HQGWDO01 Pending nrc.gov OWGWPOO3.HQGWDOO1 Pending nrc.gov TWGWPOO1.HQGWDO01 Pending nrc.gov TWGWPO02.HQGWDOO1 Pending nrc.gov Files Size Date & Time MESSAGE 846 8/16/2006 10:36:35 AM CVlBSection4.2.1 RAIsFinal.wpd 37286 7/31/2006 6:12:40 PM Options Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard ReplyRequested: No Return Notification: None
Ic:\temp\GW}OOOO1 .IMP v'age z il I
Subject:
No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened
Kent Howard - CVIBSection4.2.1 RAIsFinal.wpd Page 1 11 Kent Howard CVIBSection4.2.1 RAIsFinaI.wpd Page 1 II July 31, 2006 Mr. Michael Kansler President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601-1839
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION (TAC MC9669)
Dear Mr. Kansler:
By letter dated January 25, 2006, Entergy Nuclear Operations, Inc. submitted an application pursuant to 10 CFR Part 54, to renew the operating license for Pilgrim Nuclear Power Station for review by the U.S. Nuclear Regulatory Commission (NRC). The NRC staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. These requests for additional information address Sections B.1.3 Control Rod Drive Return Nozzle, B.1.26 Reactor Vessel Surveillance Program and time-limited aging analysis aspects for Reactor Vessel Fluence (Section 4.2.1).
These questions were discussed with a member of your staff, Bryan Ford, and a mutually agreeable date for this response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-1478 or e-mail RXS2@nrc.qov.
Sincerely, IRN Ram Subbaratnam, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-293
Enclosure:
Requests for Additional Information cc w/encl: See next page
ML062120752 CVIBSection4.2.1 RAIsFinal.wpd OFFICE PM:RLRA:DLR LA:DLR BC:REBB:DLR NAME RSubbaratnam IKing LLund DATE 7/26 /06 7/21 /06 7/26 /06 Kent Howard - CVIBSection4.2.1 RAIsFinal.wpd Page 3 11 J~
Kent Howard - CVIBSection4.2.1 RAIsFinal.wpd Page 311 3
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION (TAC MC9669)
HARD COPY DLR R/F E-MAIL:
JFair RWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)
SDuraiswamy YL (Renee) Li RidsNrrDIr RidsNrrDIrRIra RidsNrrDIrRIrb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrI RidsOgcMailCenter RidsNrrAdes DLR Staff RSubbaratnam SHoffman SUttal JShea AWilliamson MMitchell Llambrose GCheruvenki GWilson CAnderson, Region 1 WRaymond, Region 1 NSheehan, Region 1 Pilgrim Nuclear Power Station cc:
i Kent HQward - CVlBSection4.2.1 RAIsFinal.wpjd ... ... ........ . .. . . . . . .... . .. .. Pag e 4 1 4
Regional Administrator, Region I Director, Massachusetts Emergency U. S. Nuclear Regulatory Commission Management Agency 475 Allendale Road Attn: James Muckerheide King of Prussia, PA 19406-1415 400 Worcester Road Framingham, MA 01702-5399 Senior Resident Inspector U. S. Nuclear Regulatory Commission Mr. William D. Meinert Pilgrim Nuclear-Power Station Nuclear Engineer Post Office Box 867' Massachusetts Municipal Wholesale Plymouth, MA 02360 Electric Company P.O. Box 426 Chairman, Board of Selectmen Ludlow, MA 01056-0426 11 Lincoln Street Plymouth, MA 02360 Mr. Michael A. Balduzzi Site Vice President Chairman Entergy Nuclear Operations, Inc.
Nuclear Matters Committee Pilgrim Nuclear Power Station Town Hall 600 Rocky Hill Road 11 Lincoln Street Plymouth, MA 02360-5508 Plymouth, MA 02360 Mr. Stephen J. Bethay
'Chairman, Duxbury Board of Selectmen Director, Nuclear Safety Assurance Town Hall Entergy Nuclear Operations, Inc.
878 Tremont Street Pilgrim Nuclear Power Station Duxbury, MA 02332 600 Rocky Hill Road Plymouth, MA 02360-5508 Office of the Commissioner Massachusetts Department of Mr. Bryan S. Ford Environmental Protection Manager, Licensing One Winter Street Entergy Nuclear Operations, Inc.
Boston, MA 02108 Pilgrim Nuclear Power Station 600 Rocky Hill Road Office of the Attorney General Plymouth, MA 02360-5508 One Ashburton Place 20th Floor Mr. Gary J. Taylor Boston, MA 02108 Chief Executive Officer Entergy Operations Director, Radiation Control Program 1340 Echelon Parkway Commonwealth of Massachusetts Jackson, MS 39213 Executive Offices of Health and Human Services 174 Portland Street Boston, MA 02114 Secretary of Public Safety Executive Office of Public Safety One Ashburton Place Boston, MA 02108
It-Kent Howard - CVIBSection4.2.1 RAIsFinal.wpd . . . ._ .. .. . . . . . . . .......... . . ... Pa g e 511 5
Pilgrim Nuclear Power Station cc:
Mr. John T. Herron Ms. Stacey Lousteau Sr. VP and Chief Operating Officer Treasury Department Entergy Nuclear Operations, Inc. Entergy Services, Inc.
440 Hamilton Avenue 639 Loyola Avenue White Plains, NY 10601 New Orleans, LA 70113 Mr. Oscar Limpias Mr. James Sniezek Vice President, Engineering 5486 Nithsdale Drive Entergy Nuclear Operations, Inc. Salisbury, MD 21801 440 Hamilton Avenue White Plains, NY 10601 Mr. Travis C. McCullough Assistant General Counsel Mr. Christopher Schwarz Entergy Nuclear Operations, Inc.
Vice President, Operations Support 440 Hamilton Avenue Entergy Nuclear Operations, Inc. White Plains, NY 10601 440 Hamilton Avenue White Plains, NY 10601 Mr. James Ross Nuclear Energy Institute Mr. John F. McCann 1776 I Street, NW, Suite 400 Director, Nuclear Safety Assurance Washington, DC 20006-3708 Entergy Nuclear Operations, Inc.
440 Hamilton Avenue Plymouth Public Library White Plains, NY 10601 Attn: Dinah O'Brien 132 South Street Ms. Charlene D. Faison Plymouth, MA 02360 Manager, Licensing Entergy Nuclear Operations, Inc. Duxbury Free Library 440 Hamilton Avenue ATTN: Ms. Elaine Winquist White Plains, NY 10601 77 Alden Street Duxbury, MA 02332 Mr. Michael D. Lyster 5931 Barclay Lane Naples, FL 34110-7306 Kingston Public Library ATTN: Reference Librarian Mr. Michael J. Colomb 6 Green Street Director of Oversight Kingston, MA 02364 Entergy Nuclear Operations, Inc.
440 Hamilton Avenue Ms. Mary Lampert White Plains, NY 10601 Duxbury Nuclear Advisory, Chair Pilgrim watch, Director 148 Washington Street Duxbury 02332
Kent Howard - CVIBSection4.2.1 RAIsFinaI.wpd Page 6 6
11Kent Howard - CVIBSection4.2.1 RAIsFinal.wDd Paqe 7 11 BKent Howard CVlBSection4.2.1 RAlsFinal.wDd Pacie 711 7
REQUESTS FOR ADDITIONAL INFORMATION (RAIs)
PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION SECTIONS B.1.3, B.1.26 and 4.2.1 B.1.26 Reactor Vessel Surveillance Program RAI-B.11.26-1 The applicant in the updated final safety analysis report (UFSAR) supplement A.2.1.28, "Reactor Vessel Surveillance Program," and in the aging management program (AMP) B.1.26, "Reactor Vessel Surveillance," states that it will implement the Boiling Water Reactor Vessel and Internals Project (BWRVIP) integrated surveillance program (ISP) at the Pilgrim Nuclear Power Station (PNPS) as specified in BWRVIP-1 16, "BWR Vessel Internals Project Integrated Surveillance Program Implementation for License Renewal." - By letter dated March 1, 2006, the staff has issued the final safety evaluation (SE) for the BWRVIP-1 16 report and therefore, the staff requests that the applicant include the following statement in UFSAR supplement Section A.2.1.28 and in AMP B.1.26 of the license renewal application (LRA).
"The BWRVIP-1 16 report which was approved by the staff will be implemented at PNPS with the conditions documented in Sections 3 and 4 of the staff's final SE dated March 1,2006, for the BWRVIP-116 report."
RAI-B.1.26-2 Title 10 of the Code Federal Regulations Part 50 (10 CFR Part 50), Appendix H requires that an ISP used as a basis for a licensee implemented reactor vessel surveillance program be reviewed and approved by the NRC staff. The ISP to be used by the applicant is a program that was developed by the BWRVIP. The applicant will apply the BWRVIP ISP as the method by which the PNPS unit will comply with the requirements of 10 CFR Part 50, Appendix H. The BWRVIP ISP identifies capsules that must be tested to monitor neutron radiation embrittlement for all licensees participating in the ISP and identifies capsules that need not to be tested (standby capsules). Table 3-3 of the BWRVIP-1 16 report indicates that the standby capsule from PNPS unit is not to be tested. This untested capsule was originally part of the applicant's plant-specific surveillance program and has received significant amounts of neutron radiation.
The staff requests that the applicant include the following statement in the UFSAR supplement Section A.2.1.28 of the LRA.
"If the PNPS standby capsule is removed from the reactor vessel without the intent to test it, the capsule will be stored in a manner which maintains it in a condition which would permit its future use, including during the period of extended operation, if necessary."
Enclosure
11Kent Howard - CVIBSection4.2.1 RAIsFinal.wi)d Page 8 11 Kent Howard - CVlBSection4.2.1 RAlsFinal.wpd Page 8D B.1.3-1 Control Rod Drive (CRD) Return Nozzle RAI-B.11.3-1 Provide information regarding the type of inspection and the inspection frequency of the capped CRD return line nozzle weld overlay during the extended period of operation.
RAI-B.11.3-2 The applicant states that it will take the following exception to the inspection requirements for the CRD return line nozzle weld as mandated by the American Society of Mechanical Engineers (ASME) Code, Section Xl.
PNPS proposes to examine 12" of the volume on either side of the widest part of the N10 nozzle-to-vessel weld in lieu of 1/2 the vessel wall thickness as required by the ASME Code, Section Xl, 1998 Edition, 2000 Addenda, Figure IAB-2500-7(b).
The staff requests that the applicant provide information regarding the state of stress that is present in the volume of the subject weld that will not be included in the future examinations.
Clarify whether the highly stressed volume of the weld, where cracks can initiate, will be examined effectively with the proposed alternative. The staff believes that the applicant should obtain prior approval from the staff for implementing the proposed alternative examination under the provisions of 10 CFR 50.55a before entering into the extended period of operation.
Provide information whether the proposed alternative examination of the CRD return line nozzle weld has previously been submitted to the staff for review and approval for the current ISI interval.
4.2.1 Reactor Vessel Fluence RAI 4.2.1-1 Section 4.2.1 of the submittal indicates that PNPS used the radiation analysis modeling application code for the calculation of the 54 effective full-power year (EFPY) vessel fluence values. Section 4.2.2 states that recent calculations done per Regulatory Guide 1.190 confirm that the fluence for 54 EFPY is less than the fluence used to calculate the pressure and temperature limits in Reference 4.2-5, "Pilgrim Nuclear Power Station - Issuance of Amendment Re: Pressure-Temperature Limit Curves (TAC NO.MB0561)," letter dated April 13, 2001, Wang, A., to M. Bellamy.
Please provide information to substantiate this statement, preferably in the form of a contractor's report that documented these fluence calculations.
8