ML062620505
ML062620505 | |
Person / Time | |
---|---|
Site: | Callaway |
Issue date: | 09/19/2006 |
From: | Laura Smith Division of Reactor Safety IV |
To: | Naslund C Union Electric Co |
References | |
IR-06-008 | |
Download: ML062620505 (8) | |
See also: IR 05000483/2006008
Text
September 19, 2006
Charles D. Naslund, Senior Vice
President and Chief Nuclear Officer
Union Electric Company
P.O. Box 620
Fulton, MO 65251
SUBJECT: CALLAWAY PLANT - NOTIFICATION OF AN NRC TRIENNIAL FIRE
PROTECTION BASELINE INSPECTION WHILE TRANSITION TO 10 CFR
PART 50.48 (c) IS IN PROGRESS. (05000483/2006008)
Dear Mr. Naslund:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC),
Region IV staff will conduct a triennial fire protection baseline inspection at your Callaway Plant
in October and November of 2006. The inspection team will be comprised of reactor inspectors
from the NRC Region IV office and a contractor. The inspection will be conducted in
accordance with Inspection Procedure 71111.05TTP, the NRCs baseline fire protection
inspection procedure for plants in the process of implementing 10 CFR 50.48(c), NFPA 805.
The inspection guidance is different from the regular triennial inspections in that the inspectors
will concentrate on the fire protection program infrastructure and the adequacy of compensatory
measures implemented for identified departures for code requirements. The inspectors will not
routinely inspect for or evaluate circuit related issues.
The schedule for the inspection is as follows:
- Information gathering visit: October 23 - 25, 2006
- Onsite inspection: November 13 - 17, 2006
November 27 - December 1, 2006
Members of the inspection team will visit the Callaway Plant on October 23 - 25, 2006, to gather
information and documents needed to support the inspection, obtain unescorted access, to
become familiar with your fire protection program, and to select the fire areas of interest for the
inspection. The enclosure to this letter provides a list of documents the team will need to
review. You are requested to transmit copies of some of the documents to the NRC Region IV
office for team use in preparation for the inspection by the dates listed.
We request that during the onsite inspection weeks, you ensure that copies of analyses,
evaluations, or documentation regarding the implementation and maintenance of the fire
protection program, including post-fire safe shutdown capability, be readily accessible to the
team for their review. Of specific interest are those documents that establish that your fire
Union Electric Company -2-
protection program satisfies NRC regulatory requirements and conforms to applicable NRC
and industry fire protection guidance. Also, appropriate personnel knowledgeable of: (1) those
plant systems required to achieve and maintain safe shutdown conditions from inside and
outside the control room, (2) the electrical aspects of the post-fire safe shutdown analyses,
(3) reactor plant fire protection systems, and (4) the fire protection program and its
implementation should be available to support the team at the site during the inspection.
Your cooperation and support during this inspection will be appreciated. If you have questions
concerning this inspection or the inspection team's information or logistical needs, please
contact John M. Mateychick at 817-276-6560.
Sincerely,
John M. Mateychick for
Linda J. Smith, Chief
Engineering Branch 2
Division of Reactor Safety
Docket: 50-483
License: NPF-30
cc w/enclosure:
Professional Nuclear Consulting, Inc.
19041 Raines Drive
Derwood, MD 20855
John ONeill, Esq.
Pillsbury Winthrop Shaw Pittman LLP
2300 N. Street, N.W.
Washington, DC 20037
Keith A. Mills, Supervising Engineer,
Regional Regulatory Affairs/
Safety Analysis
AmerenUE
P.O. Box 620
Fulton, MO 65251
Missouri Public Service Commission
Governors Office Building
200 Madison Street
P.O. Box 360
Jefferson City, MO 65102
Union Electric Company -3-
H. Floyd Gilzow
Deputy Director for Policy
Missouri Department of Natural Resources
P. O. Box 176
Jefferson City, MO 65102-0176
Rick A. Muench, President and
Chief Executive Officer
Wolf Creek Nuclear Operating Corporation
P.O. Box 411
Burlington, KS 66839
Dan I. Bolef, President
Kay Drey, Representative
Board of Directors Coalition
for the Environment
6267 Delmar Boulevard
University City, MO 63130
Les H. Kanuckel, Manager
Quality Assurance
AmerenUE
P.O. Box 620
Fulton, MO 65251
Director, Missouri State Emergency
Management Agency
P.O. Box 116
Jefferson City, MO 65102-0116
Keith D. Young, Manager
Regulatory Affairs
AmerenUE
P.O. Box 620
Fulton, MO 65251
David E. Shafer
Superintendent, Licensing
Regulatory Affairs
AmerenUE
P.O. Box 66149, MC 470
St. Louis, MO 63166-6149
Certrec Corporation
4200 South Hulen, Suite 630
Fort Worth, TX 76109
Union Electric Company -4-
Keith G. Henke, Planner
Division of Community and Public Health
Office of Emergency Coordination
930 Wildwood, P.O. Box 570
Jefferson City, MO 65102
Union Electric Company -5-
Electronic distribution by RIV:
Regional Administrator (BSM1)
DRP Director (ATH)
DRS Director (DDC)
DRS Deputy Director (RJC1)
Senior Resident Inspector (MSP)
Branch Chief, DRP/B (WBJ)
Senior Project Engineer, DRP/B (RAK1)
Team Leader, DRP/TSS (RLN1)
RITS Coordinator (KEG)
S. O'Connor, OEDO RIV Coordinator (SCO)
ROPreports
CWY Site Secretary (DVY)
SUNSI Review Completed: ADAMS: Yes G No Initials: LJS
Publicly Available G Non-Publicly Available G Sensitive Non-Sensitive
R:\_REACTORS\CW\2006\CW FPT Notification Letter.wpd
RIV: DRS/EB2/SRI C: EB2
JMMateychick LJSmith
/RA/ /RA/
09/18/2006 09/18/2006
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
ENCLOSURE
Triennial Fire Protection Inspection Documentation Requested
Please provide the following documentation prior to the onsite information gathering trip,
preferably no later than October 10, 2006. Where practical, please provide copies electronically
on compact discs.
1. The current version of your fire protection program and fire hazards analysis.
2. Post-fire safe shutdown analysis and any supporting calculations which demonstrate
acceptable plant response.
3. Copies of the licensing basis documents for fire protection (Safety Evaluation Reports,
pertinent sections of the Final Safety Analysis Report, exemptions, deviations, letters
to/from the NRC regarding fire protection/fire safe shutdown, etc.).
4. The Fire PRA or portions of the plants IPEEE addressing fire events.
Please provide the following documentation during the onsite information gathering trip
October 23 - 25, 2006. Where practical, please provide copies electronically on compact discs.
However, drawings should be provided as paper copies of sufficient size that all details are
legible. Fire protection program implementing procedures (e.g., administrative controls,
surveillance testing).
5. Operating procedures used for achieving and maintaining hot and cold shutdown
conditions from the control room in the event of a fire outside the control room (III.G.2
areas).
6. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas)
capability with or without control room evacuation.
7. Pre-fire plans for the selected fire areas (areas to be selected by the team during the
information-gathering trip).
8. A list of equipment used to achieve and maintain hot standby and cold shutdowns in the
event of a fire (safe shutdown equipment lists), and two copies of the piping and
instrumentation (flow) diagrams for these systems of a size sufficient to read all details.
These should include the systems used for RCS makeup, RCS pressure control, decay
heat removal, and reactivity control, including the essential support systems.
9. Piping and instrumentation (flow) diagrams showing the components used to achieve
and maintain hot standby and cold shutdowns for fires outside the control room and
those components used for those areas requiring alternative shutdown capability.
10. Plant layout and equipment drawings for the selected fire areas that identify (a) the
physical plant locations of major hot standby and cold shutdown equipment; (b) plant fire
Enclosure
area and/or fire zone delineation; and (c) the locations of fire protection equipment, such
as detection, suppression, and post-fire emergency lighting units, and (d) fire area
boundaries.
11. Procedures/instructions that govern the implementation of plant modifications,
temporary modifications, maintenance, and special operations, and their impact on fire
protection.
12. A listing of design change packages, which were determined to impact fire protection
and post-fire safe shutdowns, performed in the last 3 years.
13. A listing of Generic Letter 86-10 evaluations performed in the last 3 years.
14. A listing of open and closed fire protection condition reports initiated in the last 3 years
which relate to the fire protection program or equipment.
15. A listing of the applicable codes and standards (e.g. NFPA) related to the design of
plant fire protection features and evaluations of any code deviations.
16. Drawings the portions of the emergency lighting system which support fire response.
17. Procedures used to remove smoke from safety-related areas and the engineering
studies or calculations which support the design basis.
18. Drawings of communication systems credited in the license basis for firefighting and
plant operations during fires where control room is occupied and/or evacuated.
19. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems.
20. Maintenance and surveillance testing procedures for alternative shutdown capability and
fire barriers, detectors, pumps and suppression systems.
21. Maintenance Rule performance criteria and 3 years worth of performance history for fire
protection program systems or functions monitored within the Maintenance Rule
program.
22. A copy of fire protection program requirements (e.g. limiting conditions for operation,
surveillance test requirements) covered by Technical Specifications, Technical
Requirements Manual, UFSAR, or similar documents.
23. Copies of internal and external self-assessments, audits, peer-assessments or similar
reviews related to post-fire safe shutdown capability or the fire protection program
completed within the last 3 years.
24. A list of manual actions taken outside the control room which are credited to mitigate the
consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should
group actions by the initiating fire area or zone and indicate where the action must take
place.
-2- Enclosure
25. Electronic copies of operator study guides (lesson plan text and graphics) or design
basis documents that describe the purpose/function/operating characteristics of the safe
shutdown systems (RCS makeup, RCS pressure control, decay heat removal, and
reactivity control, including the essential support systems).
26. Two copies of one-line diagrams of the electrical distribution system. These should
depict how power gets from the switchyard to ESF loads (480V and 4160V). Also,
include the vital DC distribution system one-line diagrams.
27. Please provide a list of automatic and manually initiated gaseous fire suppression
systems in the plant, giving location and the key equipment being protected.
28. Please provide a list of repairs (and the procedure that controls the actions) needed to:
a) reach and/or maintain hot shutdown; b) reach and/or maintain cold shutdowns.
28. A list of high to low pressure interface valves.
29. A copy of procedures governing the training and operation of the fire brigade.
30. The team would like to observe a fire brigade drill in the plant, if possible, during the
week of November 27, 2006. Please put us in contact with the appropriate personnel
for planning drills during the onsite information gathering trip October 23 - 25, 2006.
31. Organization charts of site personnel down to the level of fire protection staff personnel.
32. A contact list of key site personnel who will be supporting this inspection, giving location
of their office and phone number onsite.
-3- Enclosure