Information Request for NRC Biennial Permanent Plant Modifications and 10 CFR 50.59 Baseline Inspection
ML061990294
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 07/14/2006
From: Dave Hills
NRC/RGN-III/DRS/EB1
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
IR-06-012
Download: ML061990294 (8)


Text

July 14, 2006 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 INFORMATION REQUEST FOR NRC BIENNIAL PERMANENT PLANT MODIFICATIONS AND 10 CFR 50.59 BASELINE INSPECTION

Dear Mr. Crane:

On September 18, 2006, the NRC will begin a 10 CFR 50.59 and Permanent Plant Modifications Baseline Inspection at the Dresden Nuclear Power Station. This inspection will be performed in accordance with NRC Baseline Inspection Procedures IP 71111.02 and IP 71111.17B. The on-site portion of the inspection will take place on September 18 through September 21, 2006, and October 2 through October 6, 2006.

Experience has shown that these baseline inspections are extremely resource intensive, both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site, and to ensure a productive inspection for both parties, we have enclosed a request for documents needed for the inspection. These documents have been divided into three groups.

The first group is necessary to ensure that the inspection team is adequately prepared for the inspection. This information should be available to the Region III Office no later than August 18, 2006. The inspection team will review the information, and by September 1, 2006, will request specific items that should be available for review by September 8, 2006. The second group of requested documents contains additional items that the team will review, or need access to, during the inspection. Certain documents in Group II will be requested for review in the Regional Office the week prior to the inspection. The remaining documents should be available at the plant on September 18, 2006, the first day of the on-site inspection.

The third group lists information necessary to aid the inspection team in tracking issues identified as a result of the inspection. It is requested that this information be provided to the lead inspector as the information is generated during the inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection.

The lead inspector for this inspection is Al Walker. We understand that our regulatory contact for the inspection is Joe Griffin 815 416-2813 of your organization. If there are questions about the inspection or the material requested, please contact the lead inspector at (630) 829-9728 or via e-mail at HAW@nrc.gov.

C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

David E. Hills, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25

Enclosure:

Modification and 50.59 Inspection Document Request (Information for Preparation Week and Information Available On-site During Inspection) cc w/encl: Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager Regulatory Assurance Manager - Dresden Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely, David E. Hills, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25

Enclosure:

Modification and 50.59 Inspection Document Request (Information for Preparation Week and Information Available On-site During Inspection) cc w/encl: Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager Regulatory Assurance Manager - Dresden Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission DOCUMENT NAME:E:\Filenet\ML061990294.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME HWalker: ls MRing DHills DATE 07/14/06 07/14/06 07/14/06 OFFICIAL RECORD COPY

C. Crane ADAMS Distribution:

DXC1 MXB RidsNrrDirsIrib GEG KGO DRC1 CAA1 DRPIII DRSIII PLB1 TXN ROPreports@nrc.gov

MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST Inspection Report: 05000237/2006012; 05000249/2006012(DRS)

Inspection Dates: September 18 through October 6, 2006 Inspection Procedures: IP 71111.02, Evaluation of Changes, Tests, or Experiments IP 71111.17B, Permanent Plant Modifications Lead Inspector: H. Walker (630) 829-9728 Haw@nrc.gov A. Information Requested for In-Office Preparation Week The following information is requested by August 18, 2006, or sooner, to facilitate the selection of specific items that will be reviewed during the on-site inspection week. The team will select specific items from the information requested below and submit a list to your staff by September 1, 2006. We will request that certain items be made available to the Regional Office during the week prior to the inspection, no later than September 8, 2006. We request that the remaining items selected from the lists be available and ready for review on the first day of inspection. All requested information should cover the time frame from the last NRC inspections of Evaluations of Changes, Tests or Experiments and Permanent Plant Modifications inspection (exit February 11, 2005) to the present. If you have questions regarding this information, please call the team leader as soon as possible.

1. List of permanent plant modifications to risk significant systems, structures or components. (For the purpose of this inspection, permanent plant modifications include permanent: plant changes; design changes; set point changes; equivalency evaluations; suitability analyses; and commercial grade dedications.)

The list should contain the number of each document, the title, the revision (or date),

and the affected system. In addition to the list, please provide a description of each modification, and a list of associated calculations, and affected procedures.

2. List the10 CFR 50.59 completed evaluations involving:
a. calculations;
b. procedure revisions;
c. changes to the facility (modifications);
d. non-routine operating configurations; and
e. departures in methods of analyses.

The list should contain the number and title of each document, a brief description of the change, and the corresponding number and type of the affected document (i.e., the modification or procedure to which the evaluation applies). The list should NOT include 1 Enclosure

any evaluations in which prior NRC approval was sought and obtained.

3. List of all 10 CFR 50.59 changes that have been screened out as not requiring a full evaluation involving:
a. calculations;
b. procedure revisions;
c. changes to the facility (modifications);
d. non-routine operating configurations; and
e. departures in methods of analyses.

The list should contain the number and title of each document, a brief description of the change, and the corresponding number and type of the affected document (i.e., the modification or procedure to which the evaluation applies).

4. List of any modifications, procedure revisions, or UFSAR changes where it was determined that 10 CFR 50.59 did not apply.
5. List of corrective action documents (open and closed) that address plant permanent modification or 10 CFR 50.59 issues, concerns, or processes. These documents should also include corrective action documents associated with modification, and 10 CFR 50.59 change implementation.

The list should contain the number, title and revision (or date) of each document, the affected system and corresponding documentation (if applicable), and should be sorted in order of significance.

6. Copies of procedures addressing the following: modifications, design changes, set point changes, equivalency evaluations or suitability analyses, commercial grade dedications, post-modification testing, 10 CFR 50.59 evaluation and screenings, and UFSAR updates.
7. UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide copies of the complete submittal.
8. Name(s) and phone numbers for the regulatory and technical contacts.
9. Current management and engineering organizational charts.

B. Information Requested to be Available the Week Prior to Inspection (Request will be made by September 1, 2006) or on the First Day of Inspection (September 18, 2006)

1. Copies of all selected items from Section I. This includes copies of associated documents such as calculations, post-modification test packages, 10 CFR 50.59 evaluations or screenings, and any corrective action documents.
2. Copies of these documents do not need to be solely available to the team as long as the inspectors have easy and unrestrained access to them.

2 Enclosure

a. Updated Final Safety Analysis Report;
b. Original FSAR Volumes;
c. Original SER and Supplements (for Original FSAR);
d. FSAR Question and Answers;
e. Quality Assurance Plan;
f. Technical Specifications;
g. Latest IPE/PRA Report;
h. Vendor Manuals; and IV. The Latest 10 CFR 50.59 FSAR Update Submittal.
3. Please ensure that other supporting documents for the selected items have been located and are readily retrievable as the team will likely be requesting these documents during the inspections. Examples of supporting documents are:
a. Drawings supporting the modifications;
b. Procedures affected by the modifications; and
c. UFSAR change papers generated due to a 10 CFR 50.59 evaluation.

C. Information Requested to be provided throughout the inspection

1. Copies of any corrective action documents generated as a result of the teams questions or queries during this inspection.
2. Copies of any corrective action documents generated that are related to documents from the list that was provided on September 1, 2006. For the purposes of this request, only provide corrective action documents generated from September 11, 2006, until the first day of the inspection, September 18, 2006.
3. Copies of the list of questions submitted by the team members and the status/resolution of the information requested, (provide daily during the inspection to each team member).

If you have questions regarding the information requested, please contact the team leader.

3 Enclosure