January 2006 Monthly Operating Report for the Virgil C Summer Unit 1
ML060410217
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 02/08/2006
From: Archie J
South Carolina Electric & Gas Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML060410217 (5)


Text

Jeffrey B. Archie Vice President, Nuclear Operations 803.345.4214 A SCANA COMPANY February 8, 2006 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555 Attention: Director, Office of Resource Management

Dear Sir / Madam:

Subject:

VIRGIL C. SUMMER NUCLEAR STATION DOCKET NO. 50/395 OPERATING LICENSE NO. NPF-12 JANUARY MONTHLY OPERATING REPORT Enclosed is the January 2006 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit No. 1. This submittal is made in accordance with the requirements of Technical Specifications, Section 6.9.1.10.

If there are any questions, please call Mr. Robert G. Sweet, (803) 345-4080, at your convenience.

JBA/mbb Attachment c: S. A. Byrne (email) W. R. Higgins (email)

T. D. Gatlin (email) INPO Records Center J. H. Hamilton (email) J&H Marsh & McLennan R. J. White (email) William G. Wendland (ANI)

W. D. Travers Pat Haught (Westinghouse)

R. E. Martin C. W. Adams (email)

G. A. Lippard (email) NSRC (email)

NRC Resident Inspector (email) CER (L-99-0350-1)

K. M. Sutton File (818.03-1, RR 4100)

Paulette Ledbetter (email) DMS (RC-06-0034)

-5 0 -,-?,q SCE&G I Virgil C.Summer Nuclear Station

  • P.0. Box 88 Am Jenkinsville, South Corolina 29065
  • T(803) 345.5209 www.scono.com

Director, Office of Resource Management January Monthly Operating Report RC-06-0034 Page 1 of 4 ATTACHMENT I AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE February 2, 2006 COMPLETED BY T. V. Dao TELEPHONE (803) 345-4812 January 2006 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (Mwe-Net) (Mwe-Net) 2 989 17 987 2 988 18 987 3 988 19 987 4 987 20 987 5 989 21 987 6 987 22 987 7 987 23 986 8 987 24 987 9 988 25 988 10 987 26 986 11 988 27 986 12 988 28 988 13 987 29 987 14 987 30 988 15 988 31 987 16 987

Director, Office of Resource Management January Monthly Operating Report RC-06-0034 Page 2 of 4 ATTACHMENT II OPERATING DATA REPORT DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE February 2, 2006 COMPLETED BY T. V. Dao TELEPHONE (803) 345-4812 OPERATING STATUS 1 Reporting Period: January 2006 Gross Hours in Reporting Period: 744 2 Currently Authorized Power Level (MVIt): 2900 Max. Depend. Capacity (MWe-Net): 966 Design Electrical Rating (MWe-Net): 972.7 3 Power Level to Which Restricted (If Any) (MWe-Net): N/A 4 Reasons for Restrictions: N/A THIS MONTH YR TO DATE CUMULATIVE 5 Number of Hours Reactor Critical 744.0 744.0 163842.4 6 Reactor Reserve Shutdown Hours 0.0 0.0 0.0 7 Hours Generator On Line 744.0 744.0 161740.7 8 Unit Reserve Shutdown Hours 0.0 0.0 0.0 9 Gross Thermal Energy Generated (MWH) 21 55550 2155550 441122191 10 Gross Electrical Energy (MWH) 764070 764070 149991639 11 Net Electrical Energy Generated (MWH) 734552 734552 143450081 12 Reactor Service Factor 100.0 100.0 84.6 13 Reactor Availability Factor 100.0 100.0 84.6 14 Unit Service Factor 100.0 100.0 83.5 15 Unit Availability Factor 100.0 100.0 83.5 16 Unit Capacity Factor (Using MDC) 102.2 102.2 80.9 17 Unit Capacity Factor (Using Design) 101.5 101.5 79.9 18 Unit Forced Outage Rate 0.0 0.0 3.0 19 Shutdowns Scheduled Over Next 6 Months (Type, Date, & Duration of Each):

N/A 20 If Shutdown at End of Report Period, Estimated Date of Startup:

N/A 21 Units in Test Status (Prior to Commercial Operation): N/A

Director, Office of Resource Management January Monthly Operating Report RC-06-0034 Page 3 of 4 ATTACHMENT III UNIT SHUTDOWNS AND POWER REDUCTION DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE February 2, 2006 COMPLETED BY T. V. Dao TELEPHONE (803) 345-4812 January 2006 NO. DATE TYPE DURATION REASON METHOD CORRECTIVE ACTION/COMMENTS None I REASON A: Equipment Failure B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error H: Other (Explain) 2 METHOD 1: Manual 2: Manual Trip/Scram 3: Automatic Trip/Scram 4: Continuation (Use Initial Date) 5: Power Reduction (Duration 0.0) 9: Other (Explain)

SUMMARY

Director, Office of Resource Management January Monthly Operating Report RC-06-0034 Page 4 of 4 ATTACHMENT IV NARRATIVE

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE February 2, 2006 COMPLETED BY T. V. Dao TELEPHONE (803) 345-4812 January 2006 V. C. Summer Station operated at full power for the entire month of January.