MONTHYEARML0429203002004-10-0404 October 2004 No. 2 - License Amendment Request Nos. 302 and 173 Project stage: Request L-04-124, License Amendment Request Nos. 318 and 1912004-10-0404 October 2004 License Amendment Request Nos. 318 and 191 Project stage: Request ML0433703072004-12-0202 December 2004 Meeting with Firstenergy Nuclear Operating Company (Fenoc), ET Al., Regarding Beaver Valley Power Station, Units 1 and 2 (BVPS-1 and 2) Extended Power Uprate Project stage: Meeting ML0434401132005-01-0606 January 2005 Extended Power Uprate (EPU) Acceptance Review Project stage: Acceptance Review ML0511604292005-02-23023 February 2005 Supplemental Information Supporting License Amendment Request Nos. 302 and 173, Attachment B Project stage: Supplement ML0511604262005-02-23023 February 2005 Supplemental Information Supporting License Amendment Request Nos. 302 and 173 Project stage: Supplement L-05-026, Supplemental Information Supporting License Amendment Request Nos. 302 and 173, Appendix a of Attachment D2005-02-23023 February 2005 Supplemental Information Supporting License Amendment Request Nos. 302 and 173, Appendix a of Attachment D Project stage: Supplement ML0506701272005-03-10010 March 2005 Notice of Meeting with Firstenergy Nuclear Operating Company, Senior Management Beaver Valley Power Station, Unit Nos. 1 and 2 Steam Generation Replacement (Unit 1 Only) and Extended Power Uprate Project stage: Meeting ML0506300622005-03-11011 March 2005 RAI, - Extended Power Uprate Project stage: RAI ML0511902682005-03-23023 March 2005 Meeting Presentation Slides - Summary of Meeting with FENOC Re Category 1, Pre-Application Review Re BVPS-1 Steam Generator (SG) Replacement and Related Alternate Source Term (AST) Approval Project stage: Meeting L-05-053, February 2005 NPDES Discharge Monitoring Report2005-03-28028 March 2005 February 2005 NPDES Discharge Monitoring Report Project stage: Request ML0508100022005-03-28028 March 2005 Request for Additional Information, Containment Conversion from Subatmospheric Conditions Project stage: RAI ML0510401672005-04-28028 April 2005 Summary of Meeting with FENOC Re Category 1, Pre-Application Review Re BVPS-1 Steam Generator (SG) Replacement and Related Alternate Source Term (AST) Approval Project stage: Meeting ML0511600692005-05-0505 May 2005 RAI, Extended Power Uprate (EPU) Project stage: RAI L-05-079, Responses to a Request for Additional Information in Support of License Amendment Request Nos. 317 and 1902005-05-12012 May 2005 Responses to a Request for Additional Information in Support of License Amendment Request Nos. 317 and 190 Project stage: Request ML0513001472005-05-18018 May 2005 (BVPS-1 and 2) - Extended Power Uprate (EPU) Acceptance Review Project stage: Acceptance Review L-05-078, Responses to a Request for Additional Information in Support of License Amendment Request Nos. 302 and 1732005-05-26026 May 2005 Responses to a Request for Additional Information in Support of License Amendment Request Nos. 302 and 173 Project stage: Request ML0518004852005-07-19019 July 2005 (BVPS-1 and 2) - Extended Power Uprate (EPU) Acceptance Review Project stage: Acceptance Review L-05-130, Responses to a Request for Additional Information (RAI Dated June 30, 2005) in Support of License Amendment Request Nos. 302 and 1732005-07-28028 July 2005 Responses to a Request for Additional Information (RAI Dated June 30, 2005) in Support of License Amendment Request Nos. 302 and 173 Project stage: Request ML0520800052005-08-0202 August 2005 RAI, Extended Power Uprate Project stage: RAI 05000412/LER-2005-002, Regarding Automatic Actuation of Standby Service Water Pump Following Unexpected Service Water Pump Trip2005-09-30030 September 2005 Regarding Automatic Actuation of Standby Service Water Pump Following Unexpected Service Water Pump Trip Project stage: Request ML0526600022005-09-30030 September 2005 RAI, Extended Power Uprate Project stage: RAI L-05-168, Supplement to License Amendment Request2005-10-28028 October 2005 Supplement to License Amendment Request Project stage: Supplement L-05-163, Supplement to License Amendment Request Nos. 327/197, 317/190, and 320, Regarding Steam Generator Level Allowable Value Setpoints, Containment Conversion & Replacement Steam Generators, Respectively2005-10-31031 October 2005 Supplement to License Amendment Request Nos. 327/197, 317/190, and 320, Regarding Steam Generator Level Allowable Value Setpoints, Containment Conversion & Replacement Steam Generators, Respectively Project stage: Supplement ML0529700862005-11-0101 November 2005 Request for Additional Information (RAI) - Extended Power Uprate Project stage: RAI L-05-180, Supplement to License Amendment Request Nos. 318 and 1912005-11-14014 November 2005 Supplement to License Amendment Request Nos. 318 and 191 Project stage: Supplement L-05-179, Supplement to Responses to Request for Additional Information Dated March 28, 2005 in Support of License Amendment Request Nos. 317 and 1902005-11-14014 November 2005 Supplement to Responses to Request for Additional Information Dated March 28, 2005 in Support of License Amendment Request Nos. 317 and 190 Project stage: Supplement L-05-169, Response to a Request for Additional Information (RAI Dated September 30, 2005) in Support of License Amendment Request Nos. 302 and 1732005-11-21021 November 2005 Response to a Request for Additional Information (RAI Dated September 30, 2005) in Support of License Amendment Request Nos. 302 and 173 Project stage: Response to RAI L-05-198, Supplemental Information for License Amendment Request2005-12-16016 December 2005 Supplemental Information for License Amendment Request Project stage: Supplement ML0603302622006-01-25025 January 2006 Additional Information in Support of License Amendment Request Nos. 302 and 173 Project stage: Request ML0601003252006-02-0606 February 2006 Units, 1 and 2 - Issuance of License Amendment 271 and 153 Containment Conversion from Subatmospheric to Atmospheric Operating Conditions Project stage: Approval ML0604000352006-02-0606 February 2006 Units, 1 and 2 - Tech Spec Pages for Amendment 271 and 153 Containment Conversion from Subatmospheric to Atmospheric Operating Conditions Project stage: Other ML0603900852006-02-0606 February 2006 Tech Spec Pages for Amendments 272 and 154 Applicability of Westinghouse Topical Report WCAP-12945-O-A, Volume 1 (Revision 2) 1996 and Volume 2-5 (Revision 1), Code Qualification Document for Best Estimate Loca Project stage: Other ML0603100312006-02-0606 February 2006 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Unit Nos. 1 and 2 Project stage: Withholding Request Acceptance ML0601201452006-02-0606 February 2006 License Amendment 272 and 154 Applicability of Westinghouse Topical Report WCAP-12945-O-A, Volume 1 (Revision 2) 1996 and Volume 2-5 (Revision 1), Code Qualification Document for Best Estimate LOCA (Beloca) Project stage: Approval L-06-018, Units, 1 and 2,Supplemental Response in Support of License Amendment Request Nos. 302 & 1732006-02-14014 February 2006 Units, 1 and 2,Supplemental Response in Support of License Amendment Request Nos. 302 & 173 Project stage: Supplement ML0604503032006-02-16016 February 2006 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Unit Nos. 1 and 2 Project stage: Withholding Request Acceptance ML0604503422006-02-22022 February 2006 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure Ffor Beaver Valley Power Station, Unit Nos. 1 and 2 Project stage: Withholding Request Acceptance L-06-025, Supplemental Information Pertaining to License Amendment Request No. 3022006-02-22022 February 2006 Supplemental Information Pertaining to License Amendment Request No. 302 Project stage: Supplement L-06-035, Supplemental Information - EPU Implementation Plan & Power Ascension Testing: License Amendment Request Nos. 302 and 1732006-03-10010 March 2006 Supplemental Information - EPU Implementation Plan & Power Ascension Testing: License Amendment Request Nos. 302 and 173 Project stage: Supplement ML0610004692006-05-0303 May 2006 (BVPS-1 and 2) - Draft Environmental Assessment and Finding of No Significant Impact Related to Extended Power Uprate Project stage: Draft Other L-06-083, Supplemental Information in Support of License Amendment Request Nos. 302 and 1732006-05-12012 May 2006 Supplemental Information in Support of License Amendment Request Nos. 302 and 173 Project stage: Supplement L-06-114, Additional Information in Support of License Amendment Request Nos. 302 and 1732006-07-0606 July 2006 Additional Information in Support of License Amendment Request Nos. 302 and 173 Project stage: Request ML0617706052006-07-10010 July 2006 Final Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Other ML0617202482006-07-19019 July 2006 (BVPS-1 and 2) - Issuance of Amendment 8-Percent Extended Power Uprate Project stage: Approval ML0620200662006-07-19019 July 2006 Issuance of Amendment Regarding the 8-Percent Extended Power Uprate, Technical Specifications Project stage: Approval L-08-340, Transmittal of 10 CFR 50.46 Report of Changes or Errors in ECCS Evaluation Models2008-11-26026 November 2008 Transmittal of 10 CFR 50.46 Report of Changes or Errors in ECCS Evaluation Models Project stage: Request ML14210A2392014-07-31031 July 2014 Correction Letter Regarding Amendment Nos. 275 and 156 Issuance of Amendment Regarding the 8-Percent Extended Power Uprate Project stage: Approval 2005-05-26
[Table View] |
Text
I r
Beaver Valley Power Station Unit 1 Replacement Steam Generator Project Replacement Steam Generator License Amendment Request March 23, 2005 FENOC I
C Desired Outcome
- Provide NRC with overview of replacement steam generator license amendment request
- Provide NRC with overview of proposed project approach and schedule FENOC 2
ftcel I
Agenda
- Overview of approach, timing, and schedule
- Concluding remarks/questions FENOC 3
Background
FENOC 4
_Fly__ rw Co."
Cot___
2
=
Background===
- BVPS Full Potential Program
- Containment Conversion
-Submitted June 2004
- Best Estimate LOCA (BELOCA)
>Submitted October 2004
- Extended Power Uprate (EPU)
>Submitted October 2004 FENOC 5
C=_
Background
- BVPS Full Potential Program cont'd
- Improved Standard Technical Specifications (ITS)
>Submitted February 2005
- License Renewal
-#Submitted February 2005
- Steam Generator Replacement (RSG)
> February 2006 outage (1 R17)
FENOC 6=
=
3
Full Potential Program Roadmap (Pre-January 2005) rO~t~iCO"MFENELO
.7
.29M 2t@
RSO.Ab-tFR
.FLSWRSO' S~
F 5
Mt14 Cl i
n t
oW~ P Galc_
C"_1 tn w
Tto_
o n+Cent-Cc n e ELOCA C L PUM 4-
'BVPS Unit I FENOC 7
o Issue Description FENOC 4
i Issue Description
- RSG project dependent on NRC approval of Containment Conversion, BELOCA, and EPU LARs
P Issue Description
- additional information required in six areas
>five of six items responded to February 2005
,-sixth item (PSA) response June 2005 FENOC 10 5
Issue Description
- Various options explored for obtaining needed approvals of the technical specification and methodology changes necessary for RSG
- Options evaluated from schedule and resource perspective (FENOC and NRC)
FENOC 1 1 a
=
=_-wM-C.
Issue Description a Option selected is RSG LAR based on EPU analyses
- RSG focus
- Eight technical specification changes
-reduction of 15 from EPU LAR FENOC 12
=
6
Issue Description
- Most efficient use of NRC and FENOC resources
- No additional analyses required
- Analyses currently under NRC review
- All methodologies previously accepted by NRC
- Allows most time for NRC review prior to steam generator replacement outage FENOC 13 Overview of Approach, Timing, and Schedule FENOC 14 7
Overview
- LAR will submit only the technical specification and methodology changes needed:
- RSG specific
- Required to use EPU analyses as basis for RSG FENOC 15
=
Overview
- Licensing report will contain the portions of the EPU analyses needed to support the eight changes
- No additional analyses
- Additional information on RSG component included as separate enclosure FENOC 18 Ad ca 8
Overview
- Technical specification change numbering consistent with EPU LAR
- Ease of cross-referencing
- Licensing report format and numbering consistent with EPU licensing report (LR)
- Portions of EPU LR not included designated as "EPU section"
- Text of retained EPU LR sections maintained with minimal editing
- Provide NRC with opportunity to optimize synergy with EPU FENOC 17
=
Overview
- LAR will be submitted April 2005
- Approval requested January 2006 to support steam generator replacement outage schedule
=
9
Overview
- RSG design improvements require technical specification changes
- RSG narrow-range span larger than current generators
-212 versus 144 inches
- Other improvements t-tubing materials
-,tube support plate design
>tube-to-tubesheet joint FENOC 19 Overview
- Narrow-range span technical specification changes
- Reactor trip system (Table 3.3-1)
-steam generator water level low-low setpoint
- ESF actuation system (Table 3.3-3)
>steam generator water level high-high and low-low setpoints
- Reactor coolant system - shutdown (4.4.1.3)
> minimum secondary side narrow range level FENOC 20 10
Overview
- RSG improvement technical specification changes
- Steam generators (4.4.5)
>deletion of non-applicable methodologies
- e.g., voltage based repair criterion deletion of single cycle approvals
-clarification of inservice inspection schedule for RSGs
- Methodologies and computer codes consistent with CLB except for:
- BELOCA for large break LOCA
- VIPRE code for non-LOCA and fuel hydraulic DNBR
- WRB-2M correlation for DNBR (RFA fuel assemblies)
FENOC 22 11
Overview
- Methodologies and computer codes consistent with CLB except for (cont'd):
- 1979 ANS decay heat + two sigma decay heat model
, main steamline break mass and energy release outside containment
- Selective implementation of alternative source term FENOC 23 Overview
- Analyses technical specification changes
- Safety limits DNB correlation limits (2.1.1.1)
>WRB-2M DNB correlation limit applicable to Robust Fuel Assemblies
- Core Operating Limits Report approved methods (6.9.5)
> adds VIPRE code and WRB-2M correlation to list of approved methodologies FENOC 24 12
I e
Overview
- Analyses technical specification changes (cont'd)
- Overtemperature/Overpressure Delta T reactor trip setpoint equations (Table 3.3-1)
--functions added for Delta T and T.,g lag compensation FENOC 25 Overview
- Analyses technical specification changes (cont'd)
- Reactor coolant seal injection flow (3/4.5.5)
> Increased minimum seal line resistance
- Additional charging flow credited for small break LOCA analysis FENOC 26 13
i Overview
- Relies on Containment Conversion analyses and modifications submitted in Containment Conversion LAR
- Relies on large break LOCA methodology included in BELOCA LAR FENOC 27 Overview
- Amendment issuance sequence
- Containment Conversion (original)
> Request approval by June 2005
- BELOCA (original)
> Request approval by October 2005
- RSG (new)
> Request approval by January 2006 FENOC 28 14
I I
Full Potential With RSG Roadmap (Post-January 2005) inta~ment Conmcnonr RSELOC
_RG oLtem Fteneam
+
.w w%*
BELmA CLB WM* fqd l
- 2900 Mb Asyp e 2900 Wt XConaww~l Cordon RSGW
. BELOCC
- ConlnlC~ron FENOC 29 Concluding Remarks FENOC 30 15
i Concluding Remarks
- Submittal of independent RSG LAR based on EPU analyses considered best overall option
- Most time for NRC review
- Most efficient use of NRC and FENOC resources
- RSG LAR content and format intended to provide NRC with opportunity to optimize synergy with EPU FENOC 31 Concluding Remarks
- Submittal will be provided April 2005
- Approval requested January 2006
- Dependent on approval of Containment Conversion and BELOCA LARs FENOC 32 I
n 16
Comments/Questions FENOC 33 Cat 17