Letter Sequence Withholding Request Acceptance |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARML0429203002004-10-0404 October 2004 No. 2 - License Amendment Request Nos. 302 and 173 Project stage: Request L-04-124, License Amendment Request Nos. 318 and 1912004-10-0404 October 2004 License Amendment Request Nos. 318 and 191 Project stage: Request ML0433703072004-12-0202 December 2004 Meeting with Firstenergy Nuclear Operating Company (Fenoc), ET Al., Regarding Beaver Valley Power Station, Units 1 and 2 (BVPS-1 and 2) Extended Power Uprate Project stage: Meeting ML0434401132005-01-0606 January 2005 Extended Power Uprate (EPU) Acceptance Review Project stage: Acceptance Review ML0511604292005-02-23023 February 2005 Supplemental Information Supporting License Amendment Request Nos. 302 and 173, Attachment B Project stage: Supplement ML0511604262005-02-23023 February 2005 Supplemental Information Supporting License Amendment Request Nos. 302 and 173 Project stage: Supplement L-05-026, Supplemental Information Supporting License Amendment Request Nos. 302 and 173, Appendix a of Attachment D2005-02-23023 February 2005 Supplemental Information Supporting License Amendment Request Nos. 302 and 173, Appendix a of Attachment D Project stage: Supplement ML0506701272005-03-10010 March 2005 Notice of Meeting with Firstenergy Nuclear Operating Company, Senior Management Beaver Valley Power Station, Unit Nos. 1 and 2 Steam Generation Replacement (Unit 1 Only) and Extended Power Uprate Project stage: Meeting ML0506300622005-03-11011 March 2005 RAI, - Extended Power Uprate Project stage: RAI ML0511902682005-03-23023 March 2005 Meeting Presentation Slides - Summary of Meeting with FENOC Re Category 1, Pre-Application Review Re BVPS-1 Steam Generator (SG) Replacement and Related Alternate Source Term (AST) Approval Project stage: Meeting L-05-053, February 2005 NPDES Discharge Monitoring Report2005-03-28028 March 2005 February 2005 NPDES Discharge Monitoring Report Project stage: Request ML0508100022005-03-28028 March 2005 Request for Additional Information, Containment Conversion from Subatmospheric Conditions Project stage: RAI ML0510401672005-04-28028 April 2005 Summary of Meeting with FENOC Re Category 1, Pre-Application Review Re BVPS-1 Steam Generator (SG) Replacement and Related Alternate Source Term (AST) Approval Project stage: Meeting ML0511600692005-05-0505 May 2005 RAI, Extended Power Uprate (EPU) Project stage: RAI L-05-079, Responses to a Request for Additional Information in Support of License Amendment Request Nos. 317 and 1902005-05-12012 May 2005 Responses to a Request for Additional Information in Support of License Amendment Request Nos. 317 and 190 Project stage: Request ML0513001472005-05-18018 May 2005 (BVPS-1 and 2) - Extended Power Uprate (EPU) Acceptance Review Project stage: Acceptance Review L-05-078, Responses to a Request for Additional Information in Support of License Amendment Request Nos. 302 and 1732005-05-26026 May 2005 Responses to a Request for Additional Information in Support of License Amendment Request Nos. 302 and 173 Project stage: Request ML0518004852005-07-19019 July 2005 (BVPS-1 and 2) - Extended Power Uprate (EPU) Acceptance Review Project stage: Acceptance Review L-05-130, Responses to a Request for Additional Information (RAI Dated June 30, 2005) in Support of License Amendment Request Nos. 302 and 1732005-07-28028 July 2005 Responses to a Request for Additional Information (RAI Dated June 30, 2005) in Support of License Amendment Request Nos. 302 and 173 Project stage: Request ML0520800052005-08-0202 August 2005 RAI, Extended Power Uprate Project stage: RAI 05000412/LER-2005-002, Regarding Automatic Actuation of Standby Service Water Pump Following Unexpected Service Water Pump Trip2005-09-30030 September 2005 Regarding Automatic Actuation of Standby Service Water Pump Following Unexpected Service Water Pump Trip Project stage: Request ML0526600022005-09-30030 September 2005 RAI, Extended Power Uprate Project stage: RAI L-05-168, Supplement to License Amendment Request2005-10-28028 October 2005 Supplement to License Amendment Request Project stage: Supplement L-05-163, Supplement to License Amendment Request Nos. 327/197, 317/190, and 320, Regarding Steam Generator Level Allowable Value Setpoints, Containment Conversion & Replacement Steam Generators, Respectively2005-10-31031 October 2005 Supplement to License Amendment Request Nos. 327/197, 317/190, and 320, Regarding Steam Generator Level Allowable Value Setpoints, Containment Conversion & Replacement Steam Generators, Respectively Project stage: Supplement ML0529700862005-11-0101 November 2005 Request for Additional Information (RAI) - Extended Power Uprate Project stage: RAI L-05-180, Supplement to License Amendment Request Nos. 318 and 1912005-11-14014 November 2005 Supplement to License Amendment Request Nos. 318 and 191 Project stage: Supplement L-05-179, Supplement to Responses to Request for Additional Information Dated March 28, 2005 in Support of License Amendment Request Nos. 317 and 1902005-11-14014 November 2005 Supplement to Responses to Request for Additional Information Dated March 28, 2005 in Support of License Amendment Request Nos. 317 and 190 Project stage: Supplement L-05-169, Response to a Request for Additional Information (RAI Dated September 30, 2005) in Support of License Amendment Request Nos. 302 and 1732005-11-21021 November 2005 Response to a Request for Additional Information (RAI Dated September 30, 2005) in Support of License Amendment Request Nos. 302 and 173 Project stage: Response to RAI L-05-198, Supplemental Information for License Amendment Request2005-12-16016 December 2005 Supplemental Information for License Amendment Request Project stage: Supplement ML0603302622006-01-25025 January 2006 Additional Information in Support of License Amendment Request Nos. 302 and 173 Project stage: Request ML0601003252006-02-0606 February 2006 Units, 1 and 2 - Issuance of License Amendment 271 and 153 Containment Conversion from Subatmospheric to Atmospheric Operating Conditions Project stage: Approval ML0604000352006-02-0606 February 2006 Units, 1 and 2 - Tech Spec Pages for Amendment 271 and 153 Containment Conversion from Subatmospheric to Atmospheric Operating Conditions Project stage: Other ML0603900852006-02-0606 February 2006 Tech Spec Pages for Amendments 272 and 154 Applicability of Westinghouse Topical Report WCAP-12945-O-A, Volume 1 (Revision 2) 1996 and Volume 2-5 (Revision 1), Code Qualification Document for Best Estimate Loca Project stage: Other ML0603100312006-02-0606 February 2006 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Unit Nos. 1 and 2 Project stage: Withholding Request Acceptance ML0601201452006-02-0606 February 2006 License Amendment 272 and 154 Applicability of Westinghouse Topical Report WCAP-12945-O-A, Volume 1 (Revision 2) 1996 and Volume 2-5 (Revision 1), Code Qualification Document for Best Estimate LOCA (Beloca) Project stage: Approval L-06-018, Units, 1 and 2,Supplemental Response in Support of License Amendment Request Nos. 302 & 1732006-02-14014 February 2006 Units, 1 and 2,Supplemental Response in Support of License Amendment Request Nos. 302 & 173 Project stage: Supplement ML0604503032006-02-16016 February 2006 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Unit Nos. 1 and 2 Project stage: Withholding Request Acceptance ML0604503422006-02-22022 February 2006 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure Ffor Beaver Valley Power Station, Unit Nos. 1 and 2 Project stage: Withholding Request Acceptance L-06-025, Supplemental Information Pertaining to License Amendment Request No. 3022006-02-22022 February 2006 Supplemental Information Pertaining to License Amendment Request No. 302 Project stage: Supplement L-06-035, Supplemental Information - EPU Implementation Plan & Power Ascension Testing: License Amendment Request Nos. 302 and 1732006-03-10010 March 2006 Supplemental Information - EPU Implementation Plan & Power Ascension Testing: License Amendment Request Nos. 302 and 173 Project stage: Supplement ML0610004692006-05-0303 May 2006 (BVPS-1 and 2) - Draft Environmental Assessment and Finding of No Significant Impact Related to Extended Power Uprate Project stage: Draft Other L-06-083, Supplemental Information in Support of License Amendment Request Nos. 302 and 1732006-05-12012 May 2006 Supplemental Information in Support of License Amendment Request Nos. 302 and 173 Project stage: Supplement L-06-114, Additional Information in Support of License Amendment Request Nos. 302 and 1732006-07-0606 July 2006 Additional Information in Support of License Amendment Request Nos. 302 and 173 Project stage: Request ML0617706052006-07-10010 July 2006 Final Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Other ML0617202482006-07-19019 July 2006 (BVPS-1 and 2) - Issuance of Amendment 8-Percent Extended Power Uprate Project stage: Approval ML0620200662006-07-19019 July 2006 Issuance of Amendment Regarding the 8-Percent Extended Power Uprate, Technical Specifications Project stage: Approval L-08-340, Transmittal of 10 CFR 50.46 Report of Changes or Errors in ECCS Evaluation Models2008-11-26026 November 2008 Transmittal of 10 CFR 50.46 Report of Changes or Errors in ECCS Evaluation Models Project stage: Request ML14210A2392014-07-31031 July 2014 Correction Letter Regarding Amendment Nos. 275 and 156 Issuance of Amendment Regarding the 8-Percent Extended Power Uprate Project stage: Approval 2005-05-26
[Table View] |
Text
February 22, 2006 Mr. J. A. Gresham, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company P.O. Box 355 Pittsburgh, PA 15230-0355
SUBJECT:
WESTINGHOUSE ELECTRIC COMPANY, REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR BEAVER VALLEY POWER STATION (BVPS), UNIT NOS. 1 AND 2 (TAC NOS. MC4645 AND MC4646)
Dear Mr. Gresham:
By letter dated May 26, 2005, FirstEnergy Nuclear Operating Company (the licensee) submitted an affidavit dated May 26, 2005, executed by yourself. You requested that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:
Responses to NRCWCAP-1638 RAI N.2, BVPS Reactor Vessel Internals Calculated Stress Values for Flow Induced Vibration (Proprietary) and NRC RAI N.4, BVPS Reactor Coolant Pump Component Maximum Upset Stress Intensities (Proprietary)
A nonproprietary copy of this document has been placed in the Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(a)
The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouses competitors without license from Westinghouse constitutes a competitive economic advantage over other companies.
(c)
Its use by a competitor would reduce [the] expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
J. A. Gresham Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, please call me at 301-415-1402.
Sincerely,
/RA/
Timothy G. Colburn, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 cc: See next page
J. A. Gresham Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, please call me at 301-415-1402.
Sincerely,
/RA/
Timothy G. Colburn, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 cc: See next page DISTRIBUTION:
PUBLIC RidsNrrLASLittle RidsAcrsAcnwMailCenter LPLI-1 R/F RidsNrrPMTColburn RidsNrrDssSpwb RidsOGC Rp BSingalRidsDorl DPR RidsNrrDorlLpLa ACCESSION NO. ML060450342 OFFICE LPLI-1/PM LPLI-1/LA PWSB/BC LPLI-1/BC NAME TColburn SLittle JNakoski RLaufer DATE 2/21/06 2/21/06 2/21/06 2/22/06 OFFICIAL RECORD COPY
Beaver Valley Power Station, Unit Nos. 1 and 2 cc:
Gary R. Leidich President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 Joseph J. Hagan Senior Vice Presdient of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-18 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GHE-107 395 Ghent Road Akron, OH 44333 James H. Lash Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077 Lew W. Myers Executive Vice President, Special Projects FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SGRP P.O. Box 4, Route 168 Shippingport, PA 15077 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Dr.
Harrisburg, PA 17110-9364 Ohio EPA-DERR ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149
Beaver Valley Power Station, Unit Nos. 1 and 2 (continued) cc:
Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077