Summary of Meeting with FENOC Re Category 1, Pre-Application Review Re BVPS-1 Steam Generator (SG) Replacement and Related Alternate Source Term (AST) Approval
ML051040167
Person / Time
Site: Beaver Valley
Issue date: 04/28/2005
From: Colburn T
NRC/NRR/DLPM/LPD1
To:
FirstEnergy Nuclear Operating Co
Colburn T, NRR/DLPM, 415-1402
References
TAC MC4645
Download: ML051040167 (6)


Text

April 28, 2005 LICENSEE:

FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC)

FACILITY:

BEAVER VALLEY POWER STATION, UNIT NO. 1 (BVPS-1)

SUBJECT:

SUMMARY

OF MARCH 23, 2005, CATEGORY 1, PRE-APPLICATION REVIEW MEETING WITH FENOC, ET AL., REGARDING BVPS-1 STEAM GENERATOR (SG) REPLACEMENT AND RELATED ALTERNATE SOURCE TERM (AST)

APPROVAL (TAC NO. MC4645)

On March 23, 2005, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of FENOC at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to conduct a working-level pre-application review of FENOCs planned application for a license amendment for BVPS-1 SG replacement and the related request for selected AST approval. A list of attendees is provided as Enclosure 1. FENOCs slides are provided as Enclosure 2.

FENOCs presentation included an overview of the replacement SG project approach, the need for the license amendment and the related schedules for the project and amendment implementation. The licensee discussed how the replacement SG project depended upon prior approval of previously submitted amendment applications for (1) containment conversion to atmospheric operating conditions, and (2) best-estimate loss-of-coolant accident analyses. The licensee also explained how the delay in the review of the previously submitted extended power uprate amendment application (due to incomplete information), which had contained the SG replacement and AST approval request, now necessitated the submittal of a separate application which could be reviewed in time to support the February 2006 BVPS-1 outage. The licensee also discussed how the methodologies and computer codes used in support of the SG replacement application would be consistent with the current licensing basis with certain exceptions. The licensee lastly discussed the Technical Specification changes associated with the proposed submittal.

CONTACT:

Timothy G. Colburn 301-415-1402 NRR/DLPM

FENOC No members of the public were in attendance. The licensee chose not to fill out public meeting feedback forms which were available.

Please direct any inquiries to Timothy G. Colburn at 301-415-1402, or tgc@nrc.gov.

/RA/

Timothy G. Colburn, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-334

Enclosures:

1. List of Attendees
2. Licensees Handout cc w/encls: See next page

ML051040167 NRC-001 OFFICE PDI-1/PM PDI-2/LA PDI-1/SC NAME TColburn MOBrien RLaufer DATE 4/26/05 4/21/05 4/27/05 LIST OF ATTENDEES CATEGORY 1 PUBLIC MEETING BETWEEN THE NUCLEAR REGULATORY COMMISSION (NRC), AND FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC)

REGARDING STEAM GENERATOR REPLACEMENT AND SELECTED USE OF AN ALTERNATE SOURCE TERM AT BEAVER VALLEY POWER STATION, UNIT NO. 1 MARCH 23, 2005 NAME ORGANIZATION

1. Timothy G. Colburn NRC
2. Michelle Hart NRC
3. Cornelius Holden NRC
4. L. B. Marsh NRC
5. Richard Laufer NRC
6. Emmett Murphy NRC
7. Greg Halnon FENOC Director of Regulatory Affairs
8. Mark Ackerman FENOC
9. Henry Hegrat FENOC Regulatory Affairs
10. L. W. Pearce FENOC Beaver Valley Site Vice President
11. Ralph Surman Westinghouse

LICENSEES HANDOUT

Beaver Valley Power Station, Unit Nos. 1 and 2 cc:

Mary OReilly, Attorney FirstEnergy Nuclear Operating Company FirstEnergy Corporation 76 South Main Street Akron, OH 44308 FirstEnergy Nuclear Operating Company Regulatory Affairs/Performance Improvement Larry R. Freeland, Manager Beaver Valley Power Station Post Office Box 4, BV-A Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Dr.

Harrisburg, PA 17110-9364 Ohio EPA-DERR ATTN: Zack A. Clayton Post Office Box 1049 Columbus, OH 43266-0149 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 J. H. Lash, Plant Manager (BV-IPAB)

FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077 Rich Janati, Chief Division of Nuclear Safety Bureau of Radiation Protection Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P O Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission Post Office Box 298 Shippingport, PA 15077 FirstEnergy Nuclear Operating Company Beaver Valley Power Station ATTN: R. G. Mende, Director Work Management (BV-IPAB)

Post Office Box 4 Shippingport, PA 15077 FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mr. B. F. Sepelak Post Office Box 4, BV-A Shippingport, PA 15077 Mr. L. William Pearce Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077