ML050980181
ML050980181 | |
Person / Time | |
---|---|
Site: | Trojan File:Portland General Electric icon.png |
Issue date: | 03/31/2005 |
From: | Quennoz S Portland General Electric Co |
To: | Document Control Desk, NRC/FSME |
References | |
PGE-1078, VPN-012-2005 | |
Download: ML050980181 (21) | |
Text
PG/N Portland General Electric Company Trojan Nuclear Plant 71760 Columbia River HMhy Rainier, OR 97048 March 31, 2005
_ (503) 556-3713 VPN-012-2005 Trojan Nuclear Plant Docket 50-344 License NPF-I U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Annual Report of the Status of Decommissioning Funding for the Trojan Nuclear Plant in Accordance with 10 CFR 50.75(f)(1)
In accordance with 10 CFR 50.75(f)(1), this letter transmits the Trojan Nuclear Plant co-owners' annual report of the status of decommissioning funding for Calendar Year 2004. The report, which is provided in Enclosure I to this letter, is based on the most recent analysis of the Trojan Nuclear Plant decommissioning cost estimate and funding plan as incorporated into Revision 21 of PGE-I 061, "Trojan Nuclear Plant Defueled Safety Analysis Report and License Termination Plan (PGE-1078)."
For convenience, a copy of Section 5, "Update of Site-Specific Decommissioning Costs," of PGE-1061, Revision 21, is provided in Enclosure II to this letter. The decommissioning cost estimate and funding plan is updated to reflect actual expenditures and fimd balances through December 31, 2004. The cost estimate revision also incorporates the actual inflation rate for 2004, which had been estimated in the previous cost estimate revision, and reflects current projections associated with staffing, radiological waste burial volumes, and work schedules.
If you have any questions regarding this correspondence, please contact Mr. Jerry D. Reid of my staff at (503) 556-7013.
Sincerely, Stephen M. Quennoz Vice President, Generation Enclosures c: J. T. Buckley, NRC, NMSS Director, NRC Region IV, DNMS D. Stewart-Smith, ODOE A. Bless, ODOE Connecting People, Power and Possibilities
Enclosure I VPN-012-2005 March 31, 2005 Page 1 of5 Annual Report of the Status of Decommissioning Funding for the Trojan Nuclear Plant (TNP) in Accordance with 10 CFR 50.75(f)(1)
As required by 10 CFR 50.75(0(1), this report constitutes the TNP co-owners' annual report of the status of decommissioning funding for the TNP for Calendar Year 2004. The information provided herein is based on the most recent analysis of the TNP decommissioning cost estimate and funding plan as detailed in Section 5 of PGE-1061, "Trojan Nuclear Plant Defueled Safety Analysis Report and License Termination Plan (PGE-1078)," Revision 21. For convenience, a copy of Section 5, "Update of Site-Specific Decommissioning Costs," of PGE-1061, Revision 21, is provided in Enclosure II to this letter concurrently with this report.
10 CFR 50.75(f)(1) states, in part:
Each powver reactorlicensee shall report, on a calendar-yearbasis, to the NRC... on the status of its decommissioningfundingfor each reactororpart of a reactorthat it owns.
The information in this report must include, at a minimum:
the amount of decommissioningffunds estimatedto be requiredpursuant to 10 CFR 50. 75 (b) and (c);
the amount accumulated to the end of the calendaryearpreceding the date of the report; a schedule of the annual amounts remainingto be collected; the assumptions used regardingrates of escalationin decommissioningcosts, rates of earnings on decommissioningfiunds, and rates of otherfactorsused in fiindingprojections; any contracts upon which the licensee is relyingpursuant to paragraph(e) (1) (v) ofthis section; any modifications occurringto a licensee 's current method ofprovidingfinancial assurancesince the lastsubmitted report;and any materialchanges to trust agreements.
Any licensee for a plant that... has already closed (before the end of its licensed life), or for plants involved in mergers or acquisitionsshallsubmit this reportannually.
Enclosure I VPN-012-2005 March 31, 2005 Page 2 of 5 This report addresses the requirements of 10 CFR 50.75(f)(1) for the TNP for Calendar Year 2004 as follows:
- 1. The amount ofdecommissioningfunds estimatedto be requiredpursuantto 10 CFR 50.75(b) and (c).
The amount of funds estimated to be required to decommission the TNP has been determined based on a TNP-specific cost estimate prepared by Portland General Electric Company (PGE).
As indicated in PGE-1061, Section 5.1 and Table 5-1, the total costs in 1997 dollars are estimated to be approximately $211,670,000 for radiological decommissioning activities, approximately $40,228,000 for nonradiological decommissioning activities (site restoration), and approximately $169,951,000 for spent fuel management. Costs associated with securing and maintaining decommissioning financial assurance and bridging funds totaled approximately
$16,000. A detailed schedule of the decommissioning and spent fuel management costs, totaling approximately $421,865,000 of decommissioning trust fund-related expenditures, is provided in Section 5.1 and Table 5-2 of PGE-1061.
- 2. The amount accumulatedto the end of the calendaryearpreceding the date of the report.
The following table reflects the amount of decommissioning funds accumulated by the TNP co-owners through December 31, 2004. Each of the co-owners separately collect, through rates, the funds for decommissioning. Two of the three TNP co-owners (PGE and Pacific Power and Light [PP&L]) deposit these funds in external trust funds in accordance with 10 CFR 50.75(e)(1)(ii). As a federal government agency fulfilling the decommissioning funding obligations of the Eugene Water and Electric Board (EWEB), the third TNP co-owner and licensee, the Bonneville Power Administration (BPA), has provided a statement of intent as allowed by 10 CFR 50.75(e)(1)(iv). The BPA statement of intent states that decommissioning funding will be provided as such funds are needed. Thus, BPA is not required to accumulate funds in an external trust.' Additional details of the TNP decommissioning funding plans and schedules for each of the co-owners are provided in Section 5.2 ofPGE-1061.
'A copy of the BPA's Statement of Intent, dated March 21,2001, was forwarded to the NRC on March 29, 2001, as Enclosure III to PGE letter VPN-016-2001.
Enclosure I VPN-012-2005 March 31, 2005 Page 3 of 5 Status of Decommissioning Trust Funds As of December 31, 2004 TNP Co-Owner Fund Balance as of 12/31/2004 Portland General Electric Company $19,259,000O Eugene Water & Electric Board/ N/Ab Bonneville Power Administration Pacific Power & Light $1,223,000a Total $20,482,000 a The 2004 end-of-year trust fund balance includes an adjustment for trust expenditures incurred in November and December 2004 that were not paid out of the trust in 2004.
bBPA provides decommissioning funding from its operating budget as such funds are needed. Financial assurance is provided by a Statement of Intent dated March 21, 2001. Therefore, no external trust fund is required.
- 3. A schedule of the annualamounts remainingto be collected.
The decommissioning funding cash flow for each of the TNP co-owners is described in Section 5.2 and quantified in Tables 5-4 through 5-6 of PGE-1061. As detailed in Section 5.2.2 of PGE-1061, each of the co-owners maintains a collection schedule that ensures that each co-owner's portion of the total decommissioning activity expenditures will be fully funded.
These funding schedules are based on funding requirements for both radiological and nonradiological decommissioning costs, as well as financing costs and specific spent fuel management costs.
- 4. The assumptions used regardingrates of escalation in decommissioning costs, rates of earningson decommissioningfunds, and rates of otherfactorsused infunding projections.
The following table provides the TNP co-owners' assumptions regarding escalation rates, earnings rates, and rates of other factors used to project the decommissioning cost and funding schedules as reflected in Section 5 of PGE-1061.
Enclosure I VPN-012-2005 March 31, 2005 Page 4 of 5 Assumptions Regarding Escalation, Earnings, and Interest Rates Escalation Trust Fund Line of Credit INP Co-Ovner Factor' (%) Rateba(i) Fees' (%)
PGE 2.31 '5.6 0.55
'4.21 BPA/EWEB 2.31 'N/A N/A PP&L 2.31 1.21 N/A a The escalation rate assumption of 2.31 percent represents the average of WEFA projected inflation rates for 2005 through 2024.
b Each TNP co-owner assumed a trust fund earnings rate based on recent fund earning performance with consideration for projected near-term growth and conservatism.
c BPA will continue to use a Statement of Intent, rather than secure a line of credit, to provide financial assurance in accordance with 10 CFR 50.75(e)(1)(iv). PP&L avoids the expense associated with a letter of credit by ensuring that the PP&L external trust fund is fully funded to cover PP&L's portion of radiological decommissioning costs.
d This rate is applied to the qualified portion of PGE's trust fund.
' This rate is applied to the non-qualified portion of PGE's trust fund.
f BPA provides decommissioning funding from its operating budget as such funds are needed. Financial assurance is provided by a Statement of Intent dated March 21, 2001. Therefore, no external trust fund is required.
- 5. Any contractsuipon which the licensee is relyingpursuantto paragraph(e)(l)(v) ofthis section.
The TNP co-owners do not rely on contractual obligations from customers to satisfy the financial assurance stipulations of 10 CFR 50.75(e)(1).
- 6. Any modifications occurringto a licensee's currentmethod ofprovidingfinancial assurancesince the last submitted report.
Since the last submitted report, no modifications have been made to the TNP co-owners' current methods of providing financial assurance that adequate funds will be available to complete radiological decommissioning of the TNP site. Specifically, both PGE and PP&L continue to maintain financial assurance in the form of an external trust fund in accordance with
Enclosure I VPN-012-2005 March 31, 2005 Page 5 of 5 10 CFR 50.75(e)(1)(ii) 2 , and BPA continues to maintain financial assurance in the form of a Statement of Intent in accordance with 10 CFR 50.75(e)(1)(iv).
- 7. Any materialchanges to trust agreements.
PGE and PP&L have not made any material changes to the decommissioning trust agreements since the last funding plan submittal. As stated previously, BPA provides financial assurance in the form of a statement of intent, and thus is not required to maintain trust agreements to provide financial assurance for TNP decommissioning.
2 As required in Section 5.2 ofPGE-1061, during any period prior to Trojan Nuclear Plant license termination that PGE's or PP&L's external trust does not contain the funds necessary for completion of radiological decommissioning, PGE or PP&L, as appropriate, would be required to secure a letter of credit as an additional financial assurance mechanism allowed by 10 CFR 50.75(e).
Enclosure II to VPN-012-2005 Section 5, "Update of Site-Specific Decommissioning Costs," of PGE-1061, "Trojan Nuclear Plant Defueled Safety Analysis Report and License Termination Plan (PGE-1078)," Revision 21
TNP DECOMMISSIONING PLAN
- 5. UPDATE OF SITE-SPECIFIC DECOMMISSIONING COSTS In accordance with Paragraphs (a)(4) and (a)(9)(ii)(F) of 10 CFR 50.82 (Reference 5-1), and consistent with the guidance of Regulatory Guide 1.179 (Reference 5-2), the TNP-specific cost estimate and funding plan as incorporated into this section provides:
- 1. An updated estimate of total and remaining TNP decommissioning costs;
- 2. A comparison of the estimated costs with present funds set aside for decommissioning; and
- 3. The plan for assuring the availability of adequate funds for completion of decommissioning and release of the TNP site for unrestricted use.
5.1 DECOMMISSIONING COST ESTIMATE This section provides the results of and basis for a site-specific cost estimate for the decommissioning of TNP. Incorporated into this cost estimate are costs of activities involved in radiological decommissioning necessary for termination of TNP's Part 50 license, as well as expenditures necessary to complete nonradiological site restoration activities. The costs of removal and disposal of nonradioactive structures and materials beyond that necessary for license termination have been identified separately from radiological decommissioning costs.
Also separately identified are costs incurred for construction of the Trojan Independent Spent Fuel Storage Installation (ISFSI), and cost projections and funding requirements for ISFSI storage operations and maintenance (O&M) until possession and title of the irradiated fuel is transferred to DOE for ultimate disposal. ISFSI decommissioning costs and associated funding and financial assurance requirements are provided in PGE-1069, Trojan ISFSI Safety Analysis Report.
5.1.1 COST ESTIMATE RESULTS Summarizing the results of the TNP cost estimate, Table 5-1 provides estimates of total decommissioning costs as well as decommissioning costs that remain as of January 1, 2005. As indicated in Table 5-1, the costs (in 1997 dollars) for the selected decommissioning alternative are estimated to total approximately $211,670,000 for radiological decommissioning activities, approximately $40,228,000 for nonradiological decommissioning activities (site restoration), and approximately $169,951,000 for ISFSI construction and storage O&M (hereafter referred to as spent fuel management). Costs associated with securing and maintaining decommissioning financial assurance and bridging funds are projected to total approximately $16,000. A detailed schedule of TNP's decommissioning and spent fuel management costs, totaling approximately
$421,865,000 of decommissioning fund-related expenditures, is provided in Table 5-2 and described in Section 5.1.2.
5-1 Revision 21
TNP DECOMMISSIONING PLAN 5.1.2 COST ESTIMATE DESCRIPTION The initial Decommissioning Plan decommissioning cost estimate was based largely on the TNP-specific cost estimate performed for PGE by TLG Services, Inc. in May 1994. The methodology used to develop the cost estimate followed the approach presented in AIF/NESP-036, "Guidelines to Producing Decommissioning Cost Estimates" (Reference 5-3) and the DOE "Decommissioning Handbook" (Reference 54). These guidance documents utilize a unit cost factor method for estimating decommissioning activity costs. Unit cost factors incorporate site-specific considerations whenever practicable. Using plant drawings and inventory documents, quantities and volumes of the equipment and material to be removed during decommissioning were estimated. Unit cost factors were applied to the volumes and quantities to estimate the "activity dependent" costs. "Period dependent" costs were determined from a critical path schedule based on the removal activity duration.
At the end of each year, PGE updates the TNP decommissioning cost estimate based on actual decommissioning progress and with an estimate of remaining costs based on the best available information about the remaining scope of the decommissioning effort. The update generally results in changes to the timing of fund expenditures, and may reflect changes to the scope of major projects. The cost estimate reflects updated staffing requirements and work/activity schedules, remaining scheduled decommissioning equipment removal efforts, adjustments for current radioactive waste disposal volumes and costs, and an update of the estimate to disposition non-radiological hazards.
The results of PGE's decommissioning cost estimate have been incorporated into Table 5-2, which provides a comprehensive expenditure schedule for the decommissioning of TNP. This table incorporates an annual breakdown of projected costs associated with radiological and nonradiological decommissioning, spent fuel management, and decommissioning expenditure financing activities. The decommissioning cost estimate expenditure schedule contained in Table 5-2 is described in the remainder of this section.
5.1.2.1 Radiological Decommissioning Costs The cost schedule for radiological decommissioning activities is incorporated into Table 5-2, which reflects the results of the decommissioning cost estimate for TNP. Consistent with current NRC policy, the TNP decommissioning cost estimate considers radiological decommissioning costs to be only those costs associated with normal decommissioning activities necessary for termination of the Part 50 license and release of the site for unrestricted use. The decommissioning cost estimate does not include in radiological decommissioning costs those costs associated with spent fuel management or the disposal of nonradioactive structures and materials beyond that necessary to terminate TNP's Part 50 license.
Radiological decommissioning activity costs are separately identified in Table 5-2. Burial costs were derived from PGE modeling and analysis of low-level radioactive waste disposal costs as updated in early 1999, which more conservatively reflect projected burial rates. Contingencies were applied to each area of the cost estimate (i.e., decontamination and dismantlement, waste 5-2 Revision 21
77VP DECOMMISSIONING PLAN disposal, final survey, etc.) at appropriate rates. No credit was taken for equipment salvage value.
Standard ongoing financial controls have been established and executed to ensure funds are expended consistent With the provisions of 10 CFR 50.82(a)(8) and 10 CFR 50.75(h)(2)
(Reference 5-5). Throughout the budgetary process and budget year, costs associated with new projects or activities are evaluated to determine their correct cost classification, i.e., spent fuel management, radiological decommissioning, nonradiological decommissioning, capital, etc. As a result, only costs that meet the intent of this TNP Decommissioning Plan and the established decommissiioning trust fund are submitted for reimbursement from the decommissioning trust.
Periodically, variances between the estimate and actual costs are reviewed as they relate to the total cost estimate to provide assurance that the cost estimate continues to be reasonable. This complies with 10 CFR 50.82(a)(8)(i)(A). In addition, PGE corporate finance personnel review the TNP co-owners' trust fund activity and balance periodically, as applicable. Any significant activity which is inconsistent with this TNP Decommissioning Plan would be brought to the attention of TNP management.
The decommissioning cost estimate reflects costs in 1997 dollars, and has been updated to account for work performed through 2004 where TNP expended funds for decommissioning activities. The decommissioning cost estimate reflects updated staffing requirements and work/activity schedules, remaining scheduled decommissioning equipment removal efforts, and adjustments for radioactive waste disposal volumes and costs.
In accordance with 10 CFR 50.82(a)(8)(i)(C) and 10 CFR 50.75(e) (Reference 5-5), the TNP co-owners periodically assess the financial assurance amount required to complete radiological decommissioning. The established financial assurance mechanisms (e.g., external trust fund, statement of intent, and/or letter of credit, as applicable) are adjusted as necessary to ensure the completion of radiological decommissioning. Financial assurance is described in Section 5.2.
"Bridge" funds are also described in Section 5.2.
5.1.2.2 Nonradiological Decommissioning Costs Although not required by NRC regulations, the decommissioning cost estimate for TNP incorporates nonradiological decommissioning costs, as indicated in Table 5-2. The TNP decommissioning cost estimate considers nonradiological decommissioning costs to be those costs associated with site remediation and demolition and removal of uncontaminated structures.
The decommissioning cost estimate does not include in nonradiological decommissioning costs those costs associated with spent fuel management or radiological decommissioning activities.
5.1.2.3 Spent Fuel Management Costs Implementation costs associated with spent fuel management, including JSFSI construction and O&M, are reflected in the projected cost schedule detailed in Table 5-2. With ISFSI construction completed and the spent nuclear fuel now transferred from the TNP Spent Fuel Pool to the Trojan ISFSI, the remaining spent fuel management costs consist of expenditures associated with ongoing Trojan ISFSI storage O&M. Trojan ISFSI storage O&M will continue 5-3 Revision 21
TVP DECOMMISSIONING PLAN until possession and title of the irradiated fuel is transferred to the DOE for ultimate disposal (due to DOE delays, the revised estimate for completion is 2023). Costs and associated funding necessary for ISFSI decommissioning activities are detailed in PGE-1069, Trojan ISFSI Safety Analysis Report.
5.1.2.4 Financial Activity Costs Additional costs may be incurred by each TNP co-owner as necessary during decommissioning to secure and maintain assurance that adequate funds will be available to complete radiological decommissioning of the TNP site, and to secure loans or other "bridging" mechanisms to augment existing funds to cover near-term decommissioning costs. Financial assurance costs indicated in Table 5-2 were the costs associated with securing a letter of credit until PGE could pre-fund the external trust fund.
5-4 Revision 21
7NP DECOMMISSIONING PLAN
5.2 DECOMMISSIONING FUNDING
PLAN 5.2.1 CURRENT DECOMMISSIONING FUNDING CAPABILITIES Each of the TNP co-owners separately collect through rates the funds for the decommissioning of TNP. PGE and PP&L deposit these funds in external trust funds in accordance with 10 CFR 50.75(e), while the BPA provides EWEB's portion of TNP decommissioning funds as necessary as described in Section 5.2.2.2. Because the TNP was shut down prematurely, the external trust funds established by PGE and PP&L may contain during some periods only a portion of the total amount needed for site radiological decommissioning. Table 5-3 summarizes the status of PGE's and PP&L's decommissioning trust funds as of December 31, 2004.
As indicated above, there may be periods during which the trusts established by PGE and PP&L for decommissioning do not contain the funds necessary for completion of radiological decommissioning. During such periods, PGE and PP&L are required to secure an additional financial assurance mechanism allowed by 10 CFR 50.75(e). If required, PGE and PP&L have each elected to use a letter of credit as the additional financial assurance mechanism. During any period prior to TNP license termination that a co-owner's external decommissioning trust fund does not contain the funds necessary to complete radiological decommissioning, the affected co-owner must maintain this additional financial assurance.
Furthermore, a decommissioning trust fund balance may be reduced to a point where it will be necessary in certain instances to borrow or otherwise provide "bridging" funds to complete decontamination activities and allow scheduled collections to restore the decommissioning trust fund balance.
5.2.2 TNP CO-OWNERS' DECOMMISSIONING FUNDING PLANS Each TNP co-owner maintains a decommissioning fund collection schedule which ensures that each co-owner's portion of the decommissioning activity expenditures will be fully funded.
These funding schedules are based on funding requirements for both radiological and nonradiological decommissioning costs, as well as financing costs and specific spent fuel management costs as discussed in Section 5.1.2. The decommissioning funding cash flow for each of the TNP co-owners, based on the expenditure schedule in Table 5-2 and the co-owner contribution schedules, is described below.
5.2.2.1 PGE Funding Table 5-4 provides PGE's decommissioning funding cash flow in nominal dollars (2.31% escalation) during decommissioning. Funded from an external trust fund, the expenditures described in this table are PGE's share (67.5%) of the expenditures described in Table 5-2. The funding schedule described in Table 5-4 ensures that PGE's portion of the decommissioning activity expenditures will be fully funded. This decommissioning funding schedule reflects projected needs, if any, and associated costs and funding for bridging funds and/or a letter of credit, if required.
5-5 Revision 21
7NP DECOMMISSIONING PLAN As indicated in Section 5.2.1, during any period prior to TNP license termination that PGE's external trust fund does not contain the funds necessary for completion of radiological decommissioning, PGE must secure a letter of credit as an additional financial assurance mechanism for radiological decommissioning costs as allowed by 10 CFR 50.75. The methodology used to determine the size of the letter of credit ensures that if a given amount of the decommissioning trust fund is used for purposes other than radiological decommissioning activities during a current year, the portion of the financial assurance provided by the letter of credit must be increased by the same amount. This methodology can be summarized as follows:
Lfa= Ti- T2 + T3 where Lfa = Letter of Credit Portion of Financial Assurance Needed for Current Year T, = Total costs of remaining radiological decommissioning activities T2 = Current decommissioning trust fund balance T3 = Portion of trust balance planned for purposes other than radiological decommissioning costs during current year Financial assurance for remaining radiological decommissioning activities will be calculated at the beginning of each year and will be periodically reviewed during each year to ensure that an adequate level of financial assurance is maintained.
5.2.2.2 EWEB/BPA Funding BPA is obligated through Net Billing Agreements to pay costs associated with EWEB's share of TNP, including decommissioning and spent fuel management costs. BPA fulfills the decommissioning funding obligations of EWEB, including providing financial assurance for EWEB's portion of decommissioning costs in a manner stipulated in 10 CFR 50.75(e)(1)(iv) for Federal government licensees as detailed further below. Table 5-5 provides BPA/EWEB's decommissioning funding cash flow in nominal dollars (2.3 1% escalation) during decommissioning. The expenditures described in this table are BPA/EWEB's share (30%) of the expenditures described in Table 5-2. The funding schedule described in Table 5-5 ensures that BPA/EWEB's portion of the decommissioning activity expenditures will be fully funded.
As allowed by 10 CFR 50.75(e)(1)(iv), BPA, as a Federal government entity fulfilling the decommissioning funding obligations of EWEB, a licensee, provides financial assurance in the form of a statement of intent. The statement of intent contains a reference to the TNP decommissioning cost estimate described in Section 5. 1, indicating that funds for radiological decommissioning of the TNP will be obtained when necessary.
5-6 Revision 21
7NP DECOMMISSIONING PLAN 5.2.2.3 PP&L FundinQ Table 5-6 provides PP&L's decommissioning funding cash flow in nominal dollars (2.31% escalation) during decommissioning. Funded from an external trust fund, the expenditures described in this table are PP&L's share (2.5%) of the expenditures described in Table 5-2. The funding schedule described in Table 5-6 ensures that PP&L's portion of the decommissioning activity expenditures will be fully funded. This decommissioning funding schedule reflects projected needs, if any, and associated costs and funding for bridging funds and/or a letter of credit, if required.
As indicated in Section 5.2.1, during any period pror to TNP license termination that PP&L's external trust fund does not contain the funds necessary for completion of radiological decommissioning, PP&L must secure a letter of credit as an additional financial assurance mechanism for radiological decommissioning costs as allowed by 10 CFR 50.75. The methodology for determining the size of the letter of credit is as described in Section 5.2.2.1, "PGE Funding."
5-7 Revision 21
TNP DECOMMISSIONING PLAN
5.3 REFERENCES
FOR SECTION 5 5-1 Code of Federal Regulations, Title 10, Part 50.82, "Application for Termination of License," August 28, 1996.
5-2 Regulatory Guide 1. 179, "Standard Format and Content of License Termination Plans for Nuclear Power Reactors," January 1999.
5-3 AIF/NESP-036, "Guidelines to Producing Decommissioning Cost Estimates."
5-4 U. S. Department of Energy DOE/EV/10128-1, "Decommissioning Handbook,"
November 1980.
5-5 Code of Federal Regulations, Title 10, Part 50.75, "Reporting and Recordkeeping for Decommissioning Planning."
5-8 Revision 21
7NP DECOMMISSIONING PLAN Table 5-1 Estimate of Decommissioning Costs (1997 dollars)
Total Total Costs (Start-to-Finish) Remaining As of Costs January 1, 2005 I Radiological (NRC) Decommissioning Costs Reactor Vessel and Internals Removal and Disposal 21,495,000 0 Dismantlement, Decontamination, and Remediation 143,207,000 6,315,000 Waste Disposal 39,391,000 61,000 Final Survey 7,577,000 0 Total 211,670,000 6,376,000 Nonradiological Decommissioning Costs Site Restoration 40,228,000 36,474,000 Total 40,228,000 36,474,000 Dry Spent Fuel Management Costs ISFSI Construction 74,161,000 0 ISFSI Operation and Maintenance 95,790,000 88,768,000 Total 169,951,000 88,768,000 Financing Costs Financial Assurance 16,000 0 I Total 16,000 0 I Total Decommissioning Expenditures $ 421,865,000 $ 131,618,000 I Revision 21
TNP DECOMMISSIONING PLAN Table 5-2 Decommissioning Cost estimate for Trojan Nuclear Plant Itemized Decommissioning Expenditure Schedule (1997 $ x 1000)
Total Decommissioning Expenditures' Total Total Total Total Total Radiological Nonradiological Spent Fuel Financing Combined Decommissioning Decommissioning Management Activity Decommissioning Year Costs Costs Costs Costs Costs 1993 2.673 0 0 0a 2,673 1994 5,320 68 0 0C 5.388 1995 15,896 45 1.100 0C 17,041 1996 9.087 243 3.144 0 12,474 1997 19.238 350 7.974 0C 27.562 1998 34,321 62 9.703 0C 44,086 1999 37.970 1.313 17,980 0C 57.263 2000 33,172 777 3.354 . 0 37.303 2001 8,383 198 6.731 0 15,312 2002 8.329 (46) 15.608 0 23,891 2003 13.876 244 12.896 0 27.016 2004 17.030 500 2.692 16 20.238 2005 6,375 3,383 4.760 0 14.518 2006 0 186 3.970 0 4.156 2007 0 0 3.676 0 3.676 2008 0 0 3.849 0 3.849 2009 0 0 3.799 0 3.799 2010 0 0 3,750 0 3,750 2011 0 0 3.693 0 3.693 2012 0 0 3,704 0 3,704 2013 0 0 3,693 0 3,693 2014 0 0 3.693 0 3.693 2015 0 0 3.693 0 3.693 2016 0 0 3.669 0 3.669 2017 0 0 3.693 0 3,693 2018 0 0 3.693 0 3.693 2019 0 0 3,693 0 3.693 2020 0 0 3.693 0 3,693 2021 0 0 3.693 0 3.693 2022 0 0 3.693 0 3.693 2023 0 18.687 20.662 0 39,349 2024 0 14,218 0 0 14,218 Total 211,670 40,228 169.951 16 421.865 Revision 21
TNP DECOMMISSIONING PLAN Table 5-3 Status of Decommissioning Trust Funds As of December 31, 2004 I Trojan Co-Owner Fund Balance as of 12/31/04 I Portland General Electric (PGE) $19,259,000a I Eugene Water & Electric (EWEB)/ N/Ab Bonneville Power Administration (BPA)
Pacific Power & Light (PP&L) $1,223,000a I Total $20,482,000 I a The 2004 end-of-year trust fund balance includes an adjustment for trust expenditures incurred in November and December 2004 that were not paid out of the trust in 2004.
b BPA provides decommissioning funding from its operating budget as such funds are needed. Financial assurance is provided by a Statement of Intent, dated March 21, 2001. Therefore, no external trust fund is required.
Revision 21
TNP DECOMMISSIONING PLAN Table 5-4 Portland General Electric Decommissioning Funding Cash Flow (Nominal S x 1000)
PGE PGE PGE PGE Bridge Letter of Trust Fund Trust Fund Trust Fund Trust Fund Prefund Funds Letter of Credit Expenditures Contributions Net Earnings EOY Balance Refund Interest Credit Fee Year A B C D E F G H 1996 . .
1997 _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _
1998 1999 _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _
2000 2001 I I 2002 200 3 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
2004 19.259 2005 (11.810) 13,343 835 21_627 2006 (3 458) 13.343 1.266 32.778 I 2007 (3 130 13.343 1,726 44,717 2008 (3.352) 13.343 2.550 57.258 2009 (3J385 13.343 3.135 70.351 2010 (3420 6.934 3442 77.307 2011 (3J446. 3432 77 293 2012 (3J534 3420 77.179 2013 (3J607 3,411 76.983 2014 (3.690_ 2,945 76 238 2015 (3 775 2,912 75 375 2016 (3 837_ 2.875 74.413 2017 3.952 __ 2.832 73,293 2018 (4 043 _ 2.784 72.034 2019 (4 136' 2,730 70.628 2020 (4,232_ 2,669 69 065 .
2021 (4 330_ 2.603 67.338 2022 . 4 430_ 2.530 65.438 2023 (48.280) '692 17,850 2024 (17.850 0 00 Total (141.697) 73.649 48.7891 0 0 177_____ 0 NOTE 1: Positive numbers indicate cash flow Into trust fund; negative numbers Indicate cash flow out of trust fund.
NOTE 2: Current EOY balance = previous year EOY balance + current year A + B + C + E + H.
Revision 21
TNP DECOMMISSIONING PLAN Table 5-5 EWEB / BPA Decommissioning Funding Annual Cash Obligations (Nominal S x 1000)
Eugene Water and Electric Board /
Bonneville Power Administration Year Decommissioning Obligations 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 5.249 2006 1.537 2007 1.391 2008 1.490 2009 1,505 2010 1.520 2011 1.531 2012 1.571 2013 1.603 2014 1.640 2015 1.678 2016 1.705 2017 1.756 2018 1,797 2019 1.838 2020 1.881 2021 1.924 2022 1.969 2023 21.459 2024 7,933 Total 62.977 Note 1: BPA provides decommissioning funding from its operating budget as such funds are needed. Financial assurance is provided by a Statement of Intent, dated March 21, 2001. Therefore, no external trust fund is required.
Revision 21
TNP DECOMMISSIONING PLAN Table 5-6 Pacific Power & Light Decommissioning Funding Cash Flow (Nominal S x 1000)
Year PP& L PP & L PP& L PP&L Bridge Letter of Trust Fund Trust Fund Trust Fund Trust Fund Bridge Funds Letter of Credit Expenditures Contributions Net Earnings EOY Balance Funds Interest Credit Fee A B C D E F G H 1997 1998 1999__ _ _ _ ___ _ _ _ _ _ _ _
2001 __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
2000 02QQ27 _ ___
2004 _ 1.223 _
2005 (437) 349 25 1.160 2006 (128) 349 34 1_415 2007 I (116) 349 50 1 698 2008 (124)l 349 61 _ 1_984 4MS(125)1 349 721 2.280 2010 (127) 349 83 2.585 2011 (128)1 350 95 2.902 2012 (1 31) 107 2.878 2013 (134) 105 2.849 2014 (137) . 104 2816 2015 I (140) 103 2.779 2016 (142) 101 2.738 2017 (146) 100 2.692
-201 (150) 98 2.640 2019 (153) 96 2_583 2020 (157) 94 2 520 2021 (160) . 91 2.451 2022 (164) 88 2.375 .
2023 (1.788) 62 649 2024 (661) 12 0W Totl 1(5.248) 2.672 1.581_
NOTE 1: Positive numbers indicate cash flow into trust fund; negative numbers indicate cash flow out of trust fund.
NOTE 2: Current EOY balance = previous year EOY balance + current year A + B + C Revision 21