ML042470435

From kanterella
Jump to navigation Jump to search
Submittal of 10-Q Report for Quarterly Period Ending, June 30, 2004
ML042470435
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 08/25/2003
From: Groblewski T
Progress Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PE&RAS-04-097
Download: ML042470435 (72)


Text

  • As 10 CFR 50.75(e)(1)(iii)(B) g Progress Energy PO Box 1551 411 Fayetteville Street Mall Raleigh NC 27602 Serial: PE&RAS-04-097 August 25, 2003 United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555-0001 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324 / LICENSE NOS. DPR-71 AND DPR-62 SUBMITTAL OF 10-0 REPORT Ladies and Gentlemen:

Carolina Power & Light Company, now doing business as Progress Energy Carolinas, Inc., submits the enclosed quarterly 10-Q Report for Progress Energy, Inc. for the quarterly period ended June 30, 2004.

Submittal to the NRC of financial reports filed with the U.S. Securities and Exchange Commission is required by the parent company guarantees used to provide financial assurance of decommissioning funds for the Brunswick Steam Electric Plant, Unit Nos. 1 and 2, pursuant to 10 CFR 50.75(e)(1)(iii)(B). This requirement was written into the parent company guarantees pursuant to the guidance in Appendix B-6.5 of Regulatory Guide 1.159.

This document contains no new regulatory commitment.

Please contact me at (919) 546-4579 if you need additional information concerning this report.

Sincerely, Tony Groblewski Supervisor - Regulatory Affairs HAS

Enclosure:

  • ' 4W

United States Nuclear Regulatory Commission PE&RAS-04-097 Page 2 c:

without enclosure:

W. D. Travers, Regional Administrator - Region II USNRC Resident Inspector - BSEP, Unit Nos. I and 2 B. L. Mozafari, NRR Project Manager - BSEP, Unit Nos. 1 and 2 M. A. Dusaniwskyj, USNRC NRR/DRIP/RPRP-OWFN, 12 D3 J. A. Sanford - North Carolina Utilities Commission

  • ~. ~ -.~ ~~ ~ - ,', f >
-UNITED STATES SECURITIES AND EXCHANGE COMMISSION

'Washington, D.C. 20549 FORM 10-Q

' [ X ] QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d)

OF THE SECURITIES EXCHANGE ACT OF 1934 For the quarterly period ended June 32004

'OR

: TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 For the transition period from -' to '_._-_'_'

Exact name of registrants as specified in their charters, state of I.R.S. Employer Commission incorporation,' address of principal executive offices, and telephone *Identification File Number number - .. Number 1-15929 Progress Energy, Inc. 2155481 410 South Wilmington Street Raleigh, North Carolina 27601-1748 Telephone: (919) 546-6111'  :

State of Incorporation: North Carolina 1-3382 Carolina Power & Light Company 56-0165465 d/bla Progress Energv Carolinas. Inc.

- 410 South Wilmington Street -

Raleigh, North Carolina 27601-1748 Telephone: (919)546-6111 "'

'State of Incorporation: North Carolina NONE (Former name, former address and former fiscal year, if changed since last report)

Indicate by check mark whether the registrants (1) have filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the

-' . :registrants'were required to file such reports), and (2) have been subject to such filing requirements for the past 90 days. Yes X No

Indicate by check mark whether Progress Energy, Inc. (Progress Energy) is an accelerated filer (as defined in' Rule 12b-2 of the Exchange Act). Yes X No _ -

Indicate by check mark whether Carolina Power & Light Company is an accelerated filer (as defined in Rule

- 12b-2 of the Exchange Act). Yes _ No X This combined Form I0-Q is filed separately by two registrants: Progress Energy and Carolina Power & Light Company d/b/a Progress Energy Carolinas, Inc. (PEC). Information contained herein relating to either individual registrant is filed by such registrant solely on its own behalf. Each registrant makes no representation as to information relating exclusively to the other registrant.

Indicate the number of shares outstanding of each of the issuers' classes of common stock, as of the latest practicable date. As of July 31,'2004, each registrant had the following shares of common stock outstanding:

Registrant Description Shares Progress Energy - - Common Stock (Without Par Value) - 246,793,015 PEC - Common Stock (Without Par Value) ' -159,608,055 (all of which.

were held by Progress Energy, Inc.)

1 ..

PROGRESS ENERGY, INC. AND PROGRESS ENERGY CAROLINAS, INC.

FORMI0 i -0 For the Quarter Ended June 30,2004 Glossary of Terms Safe Harbor For Forward-Looking Statements PART I. FINANCIAL INFORMATION Item I. Financial Statements; Cons'olidated Interim Financial Statements:

Progress EnergyInc.-

  • Unaudited Consolidated Statements of Income Unaudited Consolidated Balance Sheets
  • Unaudited Consolidated Statements of Cash Flows Notes to Consolidated Interim Financial Stitements Carolina Power &Light Company -

d/b/a Progress Energy Carolinas, Inc.

  • Unaudited Consolidated Statements of Income
  • Unaudited Consolidated Balance Sheets Unaudited Consolidated Statements of Cash Flows Notes to Consolidated Interim Financial Statements~

Item 2.' Management's Discussion and Analysis of Financial Condition and Results of Operations Item 3. QatttvanQulaive Diclosures About Market Risk

'Item 4. Controls and Procedures PART IL.OTHER INFORMATION Itemn I. Legal Proceedings Item 2. Changes in Securities, Use of Proceeds and Issuer Purchases of Equity Securities Item 4. Submission of Matters to aVote of Security Holders Item 5. Other Information Item 6. Exhibits and Reports on Form 8-K Signatures 2

GLOSSARY OF TERMS The following abbreviations or acronyms used in the text of this combined Form I 0-Q are defined below:

. TFRM DEFINITION the Act - Medicare Prescription Drug, Improvement and Modernization Act of 2003 AFUDC Allowance for funds used during construction the Agreement, Stipulation and Settlement Agreement Bcf Billion cubic feet CCO - Competitive Commercial Operations business segment Colona Colona Synfuel Limited Partnership, LLLP the Company or Progress Progress Energy, Inc. and subsidiaries Energy CR3. Progress Energy Florida Inc.'s nuclear generating plant, Crystal River Unit No. 3 CVO Contingent value obligation DIG Derivatives Implementation Group DOE United States Department of Energy DWM North Carolina Department of Environment and Natural Resources, Division of Waste Management EITF Emerging Issues Task Force ENCNG. Eastern North Carolina Natural Gas Company, formerly referred to as Eastern NC EPA United States Environmental Protection Agency FDEP  : -  : Florida Department of Environment and Protection Federal Circuit United States Circuit Court of Appeals FERC Federal Energy Regulatory Commission FIN No. 46 FASB Interpretation No. 46, "Consolidation of Variable Interest Entities - An Interpretation of ARB No.51" Florida Progress or FPC Florida Progress Corporation FPSC- Florida Public Service Commission Fuels Fuels business segment Genco Progress Genco Ventures, LLC Jackson Jackson County EMC MACT - Maximum Available Control Technology Mesa Mesa Hydrocarbons, LLC MGP Manufactured gas plant NCNG - North Carolina Natural Gas Corporation NCUC- -North Carolina Utilities Commission NOx - -Nitrogen oxide NOx SIP Call EPA rule which requires 23 jurisdictions including North and South Carolina and

- Georgia to further reduce nitrogen oxide emissions NRC United States Nuclear Regulatory Commission NSP Northern States Power PCH Progress Capital Holdings, Inc. -

PEC Progress Energy Carolinas, Inc., formerly referred to as Carolina Power & Light Company PEF Progress Energy Florida, Inc., formerly referred to as Florida Power Corporation PFA - IRS Prefiling Agreement the Plan  : Revenue Sharing IncentivePlan PLRs Private Letter Rulings Progress Rail - Progress Rail Services Corporation PTC LLC  : *Progress Telecom LLC :

Progress Ventures Business unit of Progress Energy primarily made up of nonregulated energy

- generation, gas, coal and synthetic fuel operations and energy marketing PUHCA Public Utility Holding CompanyAct of 1935, as amended'  :

PVI :Legal entity of Progress Ventures, Inc.

PWR . Pressurized water reactor Rail Services or Rail Rail Services business segment .

RTO - Regional Transmission Organization

. .: - .-.3

SCPSC Public Service Commission of South Carolina-Section 29 - : .' e'ction 29 of the Internal Revenue Code Service Company Progress Energy Service Company, LLC SFAS No. 71 Statement of Financial Accounting Standards No. 71, "Accounting for the Effects of

-Certain Types of Regulation".

SFAS No. 131 Statement of Financial Accounting Standards No. 131, "Disclosures about Segments of an Enterprise and Related Information"

'SFAS No. 133 Statement of Financial Accounting Standards No. 133, "Accounting for Derivative and Hedging Activities" SFAS No. 142 Statement of Financial Accounting Standards No. 142, "Goodwill and Other

-Intangible Assets" SFAS No. 143 Statement of Financial Accounting Standards No. 143, "Accounting for Asset Retirement Obligations" SFAS No. 148 Statement of Financial Accounting Standards No. 148, "Accounting for Stock-Based Compensation - Transition and Disclosure - An Amendment of FASB Statement No. 123"-

SFAS No. 149 Statement of Financial Accounting Standards No. 149, "Amendment of Statement 133 on Derivative Instruments and Hedging Activities" SMD NOPR - Notice of Proposed Rulemaking in Docket No. RMOI-12-000, Remedying Undue Discrimination through Open Access Transmission and Standard Market Design S02 Sulfur dioxide SRS Strategic Resource Solutions Corp.

the Trust FPC0 Capital I trust Westchester Westchester Gas Company I . . I

..1. I.I

- - , p

-. . I 4

SAFE HARBOR FOR FORWARID-LOOKING STATEMENTS J:

This combined report contains forward-looking statements within the meaning of the safe harbor provisions of

  • the Private Securities Litigation Reform Act of 1995. The matters discussed throughout this combined Form 10-Q that 'are not historical facts are frard-lof~w oking'aand, accordingly, involve estimates, projections, goals,.

forecasts, assumptions, risks'and uncertainties that could cause actual results or outcomes to differ materially

  • from those expressed in the forward-looking statements.:

In addition, forward-looking statements are discussed in "Management's Discussion and Analysis of Financial

-Condition and Results of Operationis" including, but not limited to, statements under the sub-headings "Liquidity.

  • and Capital Resources" and '!Other Matters" about the effects of. new environmental, regulations, nuclear decommissioning costs and the effect of electric utility industry restructuring.

Any forward-looking statement speaks only'as of the date on which suc statement is made, and neither Progress Energy,- Inc. (Progress Energy or the Company) nor.Progress Energy Carolinas, Inc. (PEC) undertakes any obligation to update any forward-looking statement or statements to reflect events or circumstances after the date on'which such statement is made.

  • .Example's of factors that you should consider with respect to any forward-looking statements made throughout this document include, but are not limited to, the following: the impact of fluid and complex government laws and regulations, including those relating to the environmnent; the impact of recent events in the energy markets that have increased the level of public and regulajory scrutiny in the energy industry adintecpalmrts deregulation or restructuring in the electric industry that may result in increased, competition and unrecovered
  • (stranded) 'costs;' the uncertainty regarding the timing, creation and structure of regional transmission organizations; weather conditions that directly influence the' demand for electricity; recurring seasonal
  • fluctuations in demand for electricity; fluctuations in the price of energy. comnmodities and purchased power;

.economic fluctuations and the corresponding impact on Progress EnergyInc. and its subsidiaries' commercial and industrial customers; the ability of the Company's subsidiaries to pay upstream dividends or distributions to' it; the impact, on the facilities and the businesses of the Company fromi a terrorist attack; the inherent risks

  • associated with the operation of nuclear facilities, including environm ental, health, regulatory and financial rinsks; the ability to'successfully.'access capital markets on favorable terms; the impact that increases in leverage.

May have 'on the, Co'pany; the. ability of the Company to maintain its current credit'ratings; the impact of derivativecontracts used in the normal course of business by the Company; investment performance of pension

  • and benefit plans and the ability to control costs; the availability and use of Internal Revenue Code Section 29 (Section 29) tax credits by synthetic fuel producers and the Company's continued ability. to' use Section 29 tax credits related to its coal and'synthetic fuel businesses; the impact to our financial condition and performance 'in theevet i isdeermined the Company i not entitled to previously taken Section 29 tax credits; the Company's*
  • .ability to successfully integrte newly, acquired assets, properties or businesses into its operations as quickly or..

as profitably as expected; the Company's ability to manage the risks involved with the operation of its nonregulated plants, including dependence on third parties and related. counter-party risks, and a lack of

-.. operating history; the Company's ability to manage the risks associated with its energy'marketing' operations; the outcomre of any ongoing or future litigation or similar disputes and the impact of any such 6utcome or related settlements; and unanticipated changes in operating expenses.'and capital expenditures. Many of these risks i mial impact the Company's subsidiaries.

These and other risk factor's-are detailed from time to time in the Progress Energy and FEC United States

  • Securities and Exchange Comrmission (SEC) reports. Many, but niot all of the factors that may~impact actual results are discussed in the Risk Factors sections of Progress Energy's and FEC's annual report on Form 10-K

'for the year ended December 31, 2003, which were filed with the SEC on March 12, 2004. These rep6rts should be carefully read. All such factors are difficult to predict, contain uncertainties that may materially affect actual results and may be beyond the control of Progress Energy and FEC. New factors emerge from time to time, and

  • it is not possible for management to predict all such factors, nor can it 'assess the effect of each 'such factor on
  • Progress Energy and FEC.

.5

- I'

--. . ,:. PART I. FINANCIAL INFORMATION Item 1'. Financial Statements -- -..

PROGESSENERGY, TINC.

CONSOLIDATED INTERIM FINANCIAL STATEMENTS

~June 30, 2004 UNAUDITED CONSOLIDATED STATEMENTS of INCOME Three Months Ended Six Months Ended

-June30 -June 30

  • (in millions except per share data) 2004 2003 2004 2003 Operating Revenues Utility S ,71S 1.583 'S 3,406 *53,237.

Diversified business 7467 . 1,270 . 1.000 Total Operating Revenues -2,425 2,050. 4,676 4,237 Operating Expenses Utility' Fuel used in electric generation 4834.961 805 Purchased power . 219 . 210 402 413 Operation and maintenance .372' 364 .'.735 '699 Depreciation and amortization 207 224' 409 ' 444' Taxes other thanon income* 109 .94' 214 .197

    • Diversified business Cost of sales -656 416' 1,177 891 Depreciation and amortization 46 .36 .91 69
  • Other ' .- 45 38 88 ' 88
  • Total Operating Expenses 2,122 1,776 4,077 3,606
  • . perating Income .303 . 274 599 631
  • Other Income (Expense)

Interest income ' .4 3 7 6

  • Other, net -(9) '2) ' (5 Total Other Income (Expense) 4 .(6) (18) (9)

Interest Charges Net interest charges 160 -159 326 315

  • Allowance for borrowed funds used during construction -(2) (2) (3) (5)
  • Total Interest Charges, Net '158 157 323 . 310

-Incom~e from Continuing Operations before Income Tax and Cumulative Effect of Change In Accounting Principle 149 III 258 312 Income Tax Benefit .. (4) .(43) (3) (49)

Income from Continuing Operations before Cumulative Effect of Change In Accounting Principl .' 153 ,.*' 154 26136

'Discontinued Operations, Net of Tax I* 3 1I 14

  • Inecone before Cumulative Effect of Change In Accounting Principle ., 154 157 .262 375
  • CumulativeEffect of Change In Accounting Principle, Net of Tax.

"Net Income . 15 17' '262 . S 376 Average Common Shares Outstanding . 22236 22235 Basic Earnings per Common Share Change in Accounting Principle' ' 0.63 S 0.65 S 1.08 ' S 1.54 Discontinued Operations, Net of Tax00 06 Net Income S 0.63 'S 1.08 ' S 1.60

  • DilutedEarnings per Common Share Income from Continuing Operations before Cumulative Effect of'.'

Change in Accounting Principle . .- S 0.63 -' S 0.65 S 1.08 'S 1.53 Discontinued Operations, Net of Tax *. ' -. 0.01 -0.06 Net Income' - .S 0.63- 'S 0.66

  • S 1.08.
  • 1.59 Dividends Declared per Common Share S 0.575 SO5.560 * " S 1.150 SI.120 See Notes to Progress Energy, Inc. Consolidated Interim Financial Statemnents.'

-PROGRESS ENERGY, INC.

UNAUDITED CONSOLIDATED BAL'ANCE SHEETSJue0 Dcmr3 (in millions) Jn3 eebr3

  • ASSETS 2004. 2003
Utility Plant
  • Utility plant in service . .S 21,991 S21,67S

'Accumulated depreciation .(8,240) (8,077)

  • Utility plant in service, net 13,751 13,598 Held for future use . - 13 13
  • Construction 'work in progress  :.63634
  • .Nuclear fuel, net of amortization .. .218 228 Total Utility Plant, Net 14,625 14,473 Current Assets

'Cash and cash equivalents - . . .78 273 Accounts rec'eivable .854 798 Unbilled accounts receivable 245:. 217 Iventory 77S.795 Deferred fuel cost .304 . 317 Prepaymnents and other current assets 352 375' Total Current Assets 2,608 2,775 Deferred Debits and Other Assets Regtlatory assets 645 . 612 Nuclear decommissioning trust funds 978 938

  • Diversified business property, net 2,197 .2,158 Miscellaneous other property and investments . 458 464 Goodwill .3,730 . 3,726 Prepaid pension costs . .S 449 . .462 Intangibles, net . 306 327 Other assets and deferred debits .. 239 253.
  • Total Deferred Debits and Other Assets 9,002 8,940 Total Assets . . . S 26,235 S 26.188 CAPITALIZATION AND LIABILITIES Common.Stock Equity Commnon stock without par value, 500 million shares authorized, 247 and 246 million shares issued and outstanding, respectively S 5,339 .S 5,270 Unearned restricted shares . (17) (17)

Unearned ESOP shares .(76) (9

  • .Accumulated other comprehensive loss (5)(50)

Retained earnings .2,313 2,330 Total Common Stock Equity 7,503 . 7,444

  • Preferred Stock of Subsidiaries-Not Subject to Mandatory Redemption 93 -. 93 LongTr DbAffiliate .309 309 Long-TermDebi.Net .. .9,282 9.625
  • Total Capitalization 17,187 17,471 Current Liabilities

' Current portion of long-term debt .343 .868 Accounts payable .684 . 643 Interest accrued ..- 189 209

  • .Dividends declared 141 140 Short-term obligations - 628 .4
  • Customerdeposits . 172 *.167 Other current liabilities 836 580 Total Current Liabilities .2,993 2,611 Deferred Credits and Other Liabilities Accumulated deferred income taxes . 525S 737 Accumulated deferred investn ent tax cedit' * *~-* 184 190 Regulatory liabilities . ~3,053 2,977
  • Asset retirement obligations
  • 1,306 * . 1,271 Other liabilities and deferred credits *.-*987 931
  • Total Deferred Credits and Other Liabilities 6,055 6,106 Commitments and Contingencies (Note 12)

Total Capitalization and LIabilities S 26,235 S 26,188 See Notes to Progress Energy, Inc. Consolidated Interim Financial Statements.

m, . - - .

7.-

PROGRESS ENERGY, INC.

UNAUJDITED CONSOLIDATED STATEMENTS of CASH FLOWS

..Six Months Ended June30 (in millions) .2004 2003 Operating Activities Net income S 262 S 376' Adjustments to reconcile net income to net cash provided by operating activities:

Income from discontinued operations I .(14)

  • Cumulative effect of change in accounting principle -(I)

Depreciation and amortization 557 .572 Deferred income taxes . (210) (118)

-Investment tax credit. (6) (8)

  • Deferred fuiel cost (credit) . .13 . .(94)

Cash provided (uised) by changes in operating asset's and liabilities:

Accounts receivable (80)

  • Inventories 13 *. 31 Prepayments and other current assets (53) .. 15 -

.Accounts payable 72 (5)

Income taxes, net . 207. .105 Other current liabilities* 47 35

  • Other . 1593
  • Net Cash Provided by Operating Activities 915 907 Investing Activities.

Gross utility property additions (483) '(541)

Diversified business property additions (2) . (367)

  • Nuclear fuel additions'.. (47) . (84)

Contributions to nuclear deconmmissioning trust (18) . (8)

  • Investments in non-utility activities (7) (8)

Acquisition of intangibles' (191)

Proceeds from sales of investments and assets ...-- .92 ..

'Net decrease in restricted cash .5 17

'Other 4 1).(4)

Net Cash Used in nvesting Activities. (591) (1,195)

Financing Activities Issuance of common stock .58 .172

  • Purchase of restricted shares (7)* (7)
  • .Issuance of long-tr detI 6S5
  • Netincrease in short-term indebtedness 624 163 Net decrease in cash provided by checks drawn in excess of bank balance. . (58) (44)
    • Retirement of long-'term debt' - .(865) .(392)

Dividends 'paid on common stock *.(8) .. (268)

Other .*8 . (5)

  • Net Cash (Used In) Provided by Financing Activities (519) 274 Cash Used In Discontinued Operations - . (1
  • Net Decrease In Cash and Cash Equivalents . .(195) . (15)
  • .Cash and Cash Equivalents at Beginning of Period 273- 61 Cash and Cash Equivalents at End of Period . *S 78 S 46 Supplemental Disclosures of Cash FowlInrormation Cash paid during the year-7 interest (net of amount capitalized) .S 341 .S:305 income taxes (net of refunds) *.S 43S*2
  • See Notes to ProgressEnergy, Inc. Consolidated Interim Financial Statements.

PROGRESS ENERGY, INC.

NOTES TO CONSOLIDATED INTERIM FINANCIAL STATEMENTS

1. ORGANIZATION AND BASIS OF PRESENTATION A. Organization Progress Energy, Inc. (Progress Energy or the Company) is a holdirig'company headquartered in Raleigh, North Carolina. The Company is registered under the Public Utility Holding Company Act of 1935 (PUHCA), as amended and as such, the. Company and its subsidiaries are subject to the regulatory

' provisions of PUHCA..

Through its wholly-owned subsidiaries, Carolina Power & Light Company d/b/a Progress Energy

. Carolinas, Inc. (PEC) and Florida Power Corporation d/b/a Progress Energy Florida, Inc. (PEF), the Company's PEC Electric and PEF segments are primarily engaged in the generation, transmission, distribution and sale of electricity in portions of North Carolina, South Carolina and Florida. The Progress Ventures business unit consists of.the Fuels (Fuels) and the Competitive Commercial Operations (CCO)

  • business. segments. The Fuels segment is involved in natural gas drilling and production, coal terminal
  • services,'coal mining, synthetic fuel production, fuel transportation and delivery. The CCO segment includes nonregulated electric generation and energy marketing activities. Through the Rail Services (Rail) segment, the Company is involved in nonregulated railcar repair, rail parts reconditioning and sales, and scrap metal recycling. Through its other business units, the Company engages in other nonregulated business areas, including telecommunications and energy management and related services. Progress Energy's legal structure is not currently aligned with the functional management and financial reporting of
the Progress Ventures business unit. Whether, and when, the legal and functional structures will converge depends upon regulatory action, which cannot currently be anticipated. '.

.'B. Basis ofPresentation These financial statements have been prepared in accordance with accounting principles generally accepted, in the United States of America (GAAP) for interim financial information and with the instructions to Form IO-Q and Regulation S-X. Accordingly, they do not include all of the information and footnotes required by GAAP for annual statements. Because the accompanying consolidated interim financial statements do not include all of.the information and footnotes required by GAAP, they should be read in

-conjunction with the audited financial statements for the period ended December 31, 2003, and notes thereto included in Progress Energy's Form 10-K for the year ended December 31, 2003.

. In accordance with the provisions of Accounting. Principles Board Opinion (APB) No. 28, "Interim Financial Reporting," GAAP requires companies to apply a levelized effective tax rate to interim periods

that is consistent with the estimated annual effective tax rate. Income tax expense was increased by $5 million for both the three months ended June 30, 2004 and 2003, in order to maintain an effective tax rate consistent with the estimated annual rate. Income tax expense was increased by S43 million and decreased by $5 million for the six months ended June 30, 2004 and 2003, respectively. The income tax provisions for the Company differ from amounts computed by applying the Federal statutory tax rate to income before

.income taxes, primarily due to the recognition of synthetic fuel tax credits.

PEC and PEF collect from customers certain excise taxes, which include gross receipts tax, franchise taxes, and other excise taxes, levied by the state or local government upon the customers. PEC and PEF account for excise taxes on a gross basis. For the three months ended June 30, 2004 and 2003, excise taxes of approximately $61 million and $51 million, respectively, are included in taxes other than on income in the accompanying Consolidated Statements of Income." For the six months ended June 30, 2004 and 2003, excise taxes of approximately $114 million and $102 million, respectively, are included in taxes other than on income in the accompanying Consolidated Statements of Income. These approximate amounts are also included in utility revenues. . .

The amounts included in the consolidated interim financial statements are unaudited but, in the opinion of

' . management, reflect all normal recurring adjustments necessary to fairly present the Company's financial

position and results of operations for the interim periods. Due t6 seasonal weather variations and the timing of outages of electric generating units, especially nuclear-fueled units, the results of operations for interim periods are not necessarily indicative of amounts expected for the entire year or future periods.
  • : . :- .... , . e _ - ....... ,. ,9

I..--

assumptions that affect the reported amounts of assets and liabilities, disclosure of contingent assets and, liabilities at the date of the financial statements and amounts of revenues and expenses reflected during the "reporting period.. Actual results could differ from those estimates. Certain amounts for 2003 have been

-reclassified to conform to the 2004 presentation.

The results 'of operations of the Rail Services segment are reported one month in arrears.

C. Subsidiary Reporting Period Change '.

In the fourth quarter of 2003, the Company,'ceased recording portions of Fuels' segment operations,

-'primarily synthetic fuel operations, one month in arrears. As a result, earnings, for the year ended'.

December 31, 2003 as reported in the Company's Form 10-K, included 13 months of results for these

- operations. The 2003 quarterly results for periods ended March 31, June 30 and September 30 have been restated for'the'above-mentioned reporting period change. This resulted in four months of earnings in the first quarter of 2003. The impact of the reclassification of earnings between quarters is outlined for the first two quarters of 2003 in the table below:

'Three Months Ended June 30, 2003 'As Previously Quarter As (in millions, except per share data) Reclassification -Reported

'Restated Income from Continuing Operations before Cumulative Effect of Change in Accounting Principle S 150' ' $ 154

- : 'Net Income '$ 153 $ 4 - . .$ 157 Basic earnings per common share Income from Continuing Operations before Cumulative' Effect of Change in Accounting Principle S 0.64 $ 0.01 'S 0.65 Net Income S '0.65 $ 0.01 I S 0.66 Diluted earnings per common share

-Income from Continuing Operations before Cumulative ..

Effect of Change in Accounting Principle $ 0.63 $ 0.02 $ 0.65

'Net Income 5 0.64 $ 0.02 S 0.66 Six Months EndedJune30,2003 As Previously Quarter I As '

(in millions, except per share data) 0 Reported Reclassification Restated Income from Continuing Operations before Cumulative Effect of Change in Accounting Principle ' S 346 S 361

- .. V 1IMS

.,axuIL1 .. ' $ 361' - $ 15 ' S'376'

.'- 'Basic earnings per common share I. , 1 Income from Continuing Operations before Cumulative Effect of Change in Accounting Principle .'- $ 1.48' 'S 0.06 $ 1.54 Net Income '$ 1.54 S 0.06 $ 1.60

- Diluted earnings per common share Income from Continuing Operations before Cumulative Effect of Change in Accounting Principle $ 1.475 S 0.06 $ 1.53' Net Income $ 1.53 S 0.06 $ 1.59 D. Stock-Based Compensation The Company'measures compensation expense for stock options as the difference between the market price of its common stock and the exercise price of the option at the grant date. The exercise price at which options are granted by the Company equals the'market price at the grant date, and accordingly, no compensation expense has been recognized for stock option grants. 'For purposes of the pro forma disclosures required by. SFAS No. 148, "Accounting for Stock-Based Compensation - Transition and Disclosure - an Amendment of FASB Statement No. 123" the estimated fair' value of the Company's stock options is amortized to expense over the options' vesting period. The following table illustrates the effect on net income and earnings per share if the fair value method had been applied to all outstanding and "unvested awards in each period: ' ' ' '

'10

Three Months Ended Six Months Ended

  • june'30 June 30 (in millions except per share data) 2004 2003' 2004 2003
  • Net Income, as reported . $.154 $ 5S 6 376 Deduct: Total stock option expense determined under fair value method for all awards, net of related tax effects *...3 *2 6 4 Pro forma net income $ 151 $155 $ 256 $ 372 Basic earnings per share.

Aseore 0.63 $06 $1.08 $ 1.60.

Pro forrna $062 $.6 1.06 $ 1.58 Fully diluted earnings per share As reported . $0.63 . $0.66 .S 1.08 $ 1.59 Pro forma $ .2 $ 0.65 S 1.05 $ 1.57 E. Consolidation of Variable Interest Entities The Company consolidates all voting interest entities in which it owns a majority voting interest and all variable interest entities for which it is the primary beneficiary in accordance with FASB Interpretation No.

46R, "Consolidation of Variable Interest Entities -an Interpretation of ARB No. 51" (FIN No.-46R).

During the first six months of 2004 and 2003, the Company.did not participate in the creation of, or obtain

  • asignificarnt new variable interest in, any variable interest entity. .

The Company is the primary beneficiiary of a limited partne'rship which invests in 17 low-income housing

-partnerships that qualify for federal and state tax credits. The Company has requested but has not received all the necessary information to' determine the primary beneficiary of the limited partnership's underlying

'17 partniership investments, and has applied the information scope exception in FIN No. 46R, paragraph.

4(g) to the 17 partnerships., The Company has no direct exposure to loss from the 17 partnerships; the

-Company's only exposure to loss is from its investment of approximately Si million in the consolidated limited partnership. The Company will continue its efforts to obtain the 'necessary information to fully apply.FIN No. 46R to the 17 partnerships. . The Company believes that if the limited partnership is deterindto' be the primary beneficiary -of the 17 partnerships, the effect of consolidating the 17

~partnerships would not be significant to the Company's Consolidated Balance Sheets.

The Company has variable interests in two power plants resulting from' long-term power purchase

  • contracts. -The Company has'requested the necessary informnation'to determine if the counterparties are

.variable interest entities or to identify the primary beneficiaries. Both entities declined to provide the

'Company with the necessary financial'informiation, and the Company has applied the information scope exception in FIN No. 46R, par-agraph 4(g). The Company's only significant exposure to variability from

  • these contracts results from fluctuations in the market price of fuel used by the two entities' plants to
  • produce the power purchased by the Company. The Company is able to recover these fuel costs under

-PEC's fuel clause. Total purchases from these counterparties were approximately'$21,million and $19 midllion in the first six months of 2004 and 2003, respectively.. The Company will continue its efforts to obtain the 'necessary information to fully apply FIN No. 46R to these contracts. The combined generation

  • capacity of the two entities' power plants is approximately 880 MW. The Company believes that if it is' determined to be the primary beneficiar of these two entities, the effect of consolidating the entities would
  • ~ result in increases to total assets, long-term debt and other liabilities, but would have an insignificant or no
  • impact on the Compan' comosokequity, net earnings, or cash flows. However, as the Company' has not received any financial information from these two counterparties, the impact cannot be determined at this time.
  • The Company also ha's interests in several other variable interest entities for 'which the Company is not the primary beneficiary. These arrangements include investments in approximately 28 limited partnerships, "limited liability corporations and venture capital'-funds and two building leases with special-purpose
  • entities. The aggregate maximum loss exposure at June 30, 2004, that the Company could be required to

.record in its income statement as a result of these arrangements totals approximately $38 million. The:

  • creditors of these' variable interest entities do not have recourse to the general* credit of the Company ini excess 'ofthe aggregate maxi'mum loss exposure..
  • 4t..,,..-.
2. -'NEW ACCOUNTING STANDARDS -

In December 2003, the Medicare Prescription Drug, Improvemet and Modeization Act of 2003 (the Act) was signed into law. In accordance with guidance issued by the FASB in FASB Staff Position FAS 106-1, the Company has elected to defer accounting for the effects of the Act due to uncertainties regarding the effects of the implementation of the Act and the accounting for certain provisions of the Act.

Therefore, OPEB information presented in the financial statements does not reflect the effects of the Act.

The FASB recently issued definitive accounting guidance for the Act in FASB Staff Position 106-2, which is effective for the Company in the third quarter of 2004.' FASB Staff Position 106-2 will result in the

' recognition of lower OPEB costs to reflect prescription drug-related federal subsidies to be received under

the Act. The Company is in the process of quantifying the impact of the Act on OPEB costs.
3. DIVESTITURES -

A. Divestiture of Synthetic Fuel Partnership Interests '

In June 2004, the Company through its subsidiary, Progress Fuels sold, in two transactions, a combined 49.8 percent partnership interest in Colona Synfuel Limited Partnership, LLLP, one of its synthetic fuel facilities.' Substantially all proceeds from the sales will be received over time, which is typical of such sales in -the industry. Gain from the sales will be recognized on a cost recovery basis. The Company's book value of the interests sold totaled approximately $5 million. Based on projected production levels,'

the Company anticipates receiving total gross proceeds of approximately 530 million per year, on an*

annualized basis. Under the agreements, the buyers have a right to unwind the transactions if an IRS reconfirmation private letter ruling (PLR) is not received by October 15, 2004. Therefore, no gain would be recognized prior to the expiration of that right.

B.' Railcar Ltd.Divestiture In December 2002, the Progress Energy Board of Directors adopted a resolution approving the sale of Railcar Ltd., a subsidiary included in the Rail Services segment. In March 2003, the Company signed a letter of intent to sell'the majority of Railcar Ltd. assets to The Andersons, Inc., and the 'transaction closed in February 2004. Proceeds from the'sale were approximately $82 million before transaction costs and taxes of approximately S13 million. The assets of Railcar Ltd. were grouped as assets held for sale and are included in other current assets on the Consolidated Balance Sheets'at June 30, 2004 and December 31,

-2003. The assets were recorded at approximately $6 million and $75 million at June 30, 2004 and

' December 31, 2003, respectively, which reflects the Company's estimates of the fair value expected to be realized from the sale of these assets less costs to sell. 'In July 2004, the Company sold the remaining assets classified as held for sale to a third-party for net proceeds ofS6 million.

C.' NCNG Divestiture - -

In October 2002, the Company announced the Board of Directors' approval to sell North Carolina Natural Gas Corporation (NCNG) and the Company's equity investment in Eastern North Carolina Natural Gas Company (ENCNG) to Piedmont Natural Gas Company, Inc. On September'30, 2003, the Company completed the sale. The 2003 net income of these operations is reported as discontinued operations in the Consolidated Statements of Income. Interest expense of $3 million and $7 million for the three and six' months ended June 30, 2003, respectively, has been allocated to discontinued operations'based on the net assets of NCNG, assuming a uniform debt-to-equity ratio across the Company's operations. Results of discontinued operations were as follows:: - ' ' '

(in millions)

'-- - -- : Three Months Ended Six Monts Ended June 30, 2003 - June 30,2003 Revenues  ; S 71 -- S225

.Earnings before income taxes .4 S23

-. Income tax expense'

- . Net earnings from discontinued operations S -3 S14

12 -

During the three months ended June 30, 2004, the Company recorded an additional gain after taxes of approximately $1 million related to deferred taxes on the loss from the NCNG sale.

4. REGULATORY MATTERS A. Retail Rate Matters PEC has exclusively utilized external funding for its decommissioning liability since 1994. Prior to 1994,
PEC' retained funds internally to meet its decommissioning liability. A North Carolina Utilities Commission (NCUC) order issued in February 2004 found that by January 1, 2008, PEC must begin transitioning these amounts to external funds. The transition of $131 million must be completed by.

December 31, 2017, and at least 10% must be transitioned each year.

PEC filed with the Public Service Commission of South Carolina (SCPSC) seeking permission to defer expenses incurred from the first quarter.2004 winter storm. The SCPSC approved PEC's request to defer

  • the costs and amortize them ratably over five years beginning in January 2005. Approximately $10 million related to storm costs incurred during the first quarter of 2004 was deferred in that quarter.

During the first quarter of 2004, PEC met the requirements-of both the NCUC and the SCPSC for the implementation of.'a depreciation study which allowed the utility to'reduce the rates.used to calculate depreciation'expense. As a'result, depreciation expense decreased $10 million for the three months ended June 30, 2004 compared to the prior year quarter and decreased $18 million for the six months ended June 30, 2004 compared to the prior year six month period;.'

On June 29, 2004, the FPSC approved a Stipulation and Settlement Agreement, executed on April 29,

.2004, by PEF, the Office of Public Counsel and the Florida Industrial Power Users Group. The stipulation

..and settlement resolved the issue pending before the FPSC regarding the costs PEF will be allowed to recover through its Fuel and Purchased Power Cost Recovery clause in 2004 and beyond for waterborne

' coal deliveries by the Company's affiliated coal supplier, Progress Fuels Corporation. The settlement sets

-fixed per ton prices based.on point of origin for all waterborne coal deliveries in 2004, and establishes a market-based pricing methodology for determining recoverable waterborne coal transportation costs through a competitive solicitation process or market price proxies beginning in 2005 and thereafter. The settlement reduces the amount that PEF.will charge to the Fuel and Purchased Power Cost Recovery clause

'for waterborne transportation by approximately $13 million beginning in 2004. This concludes the FPSC's investigation of PEF's recoverable waterborne coal transportation costs.

B. Regional Transmission Organizations.

In 2000,. the Federal.Energy Regulatory Commission (FERC) issued Order 2000 regarding regional

- transmission organizations (RTOs). This Order set minimum characteristics and functions that RTOs must meet, including independent transmission service. In July 2002, the FERC issued its Notice of Proposed Rulemaking in Docket No. RMOI-12-000, Remedying Undue Discrimination through Open Access Transmission Service and Standard Electricity Market Design (SMD NOPR). If adopted as proposed, the

. . - rules set forth in the SMD NOPR would materially alter the manner in which transmission and generation services are provided and paid for. In April 2003, the FERC released a White Paper on the Wholesale Market Platform. The White Paper provides an overview of what the FERC currently intends to include in a final rule in the SMD NOPR docket. The White Paper retains the fundamental and most protested aspects of SMD NOPR, including mandatory RTOs and the FERC's assertion of jurisdiction over certain

. aspects of retail service. The FERC has not yet issued a final rule on SMD NOPR. The Company cannot

. .predict the outcome of these matters or the effect that they may have on the GridSouth and GridFlorida proceedings currently ongoing before the FERC. It is unknown what impact the future proceedings will

'have on the Company's earnings, revenues or prices.

. The Company has $33 million and $4 million invested in GridSouth and GridFlorida, respectively, related to startup costs at June 30, 2004. The Company expects to recover these startup costs in conjunction with

- - the GridSouth and . GridFlorida original structures or in conjunction with any alternate combined transmission stnictures that emerge.

13

C. Implementation'of SFAS No. 143 I-n connection with the ipleinentation of SFAS No. 143 in 2003, PEC filed a request with the NCUC requesting deferral of the difference between expense pursuant to SFAS No. 143 and expense as previously determined by the NCUC. The NCUC granted the deferral of the January 1; 2003 cumulative adjustment.

Because the clean air legislation discussed in Note 10 under "Air Quality" contained a prohibition against cost deferrals unless certain criteria are met, the NCUC denied the deferral of the ongoing effects. Since

- '-the NCUC order denied deferral of the ongoing effects, PEC ceased deferral of the ongoing effects during the second quarter for the six months ended June 30, 2003 related to its North Carolina retail jurisdiction.

Pre-tax income for the three and six months ended June 30, 2003 increased by approximately S14 million, which represents a decrease in non-ARO cost of removal expense, partially offset by an increase in decommissioning expense. : The Company provided additional information to the NCUC that

'demonstrated that deferral of the ongoing effects should also be allowed. In August of 2003, the NCUC revised its decision and approved the deferral of the ongoing effects of SFAS No. 143 at which time the

$14 million was reversed.

D. FERC Market Power Mitigation

- A FERC order issued in November 2001 on certain unaffiliated utilities' triennial market based wholesale' power rate authorization'updates required certain mitigation actions that those utilities would need to take

' - ' for sales/pur'chases within their control areas and required those utilities to post information on their websites regarding their power systems' status. As a result of a request for rehearing filed by certain market participants, FERC issued an order delaying the effective date of the mitigation plan until after a planned technical conference on market power' determination. In December 2003, the FERC issued a staff paper discussing alternatives and held a technical conference in January 2004. In April 2004; the FERC issued two orders concerning utilities' ability to sell wholesale electricity at market based rates. In the first order, the FERC adopted two new, interim screens for assessing potential generation market power of applicants

' -for wholesale market based rates,' and described additional analyses and mitigation measures that could be

- presented if an applicant does not pass one of these interim screens. In July 2004, the FERC issued an order on rehearing affirming its conclusions in the April order. In the second order, the FERC initiated a rulemaking to consider whether the FERC's current methodology for determining whether a public utility should be allowed to sell wholesale electricity at market-based rates should be modified in any way.

Management is unable to predict the outcome of these actions by the FERC or their effect on future results of operations and cash flows. However, the Company does not anticipate that the current operations of PEC or PEF would be impacted materially if they were unable to sell power at market-based rates in their

'respective control areas. '

. 5 GOODWILL'AND OTHER INTANGIBLE ASSETS

-The Company performed the annual goodwill impairment test in accordance with FASB Statement No.

142, Goodwill and Other Intangible Assets, for the CCO segment in the first quarter of 2004, and the annual goodwill impairment test for the PEC Electric and PEF segments in the second quarter of 2004, each of which indicated no impairment. The first annual impairment test' for the Other segment will be performed in the fourth quarter 2004, since the goodwill was acquired in 2003.

The changes in the carrying amount'of goodwill for the periods ended June 30, 2004 and December 31, 2003, by reportable segment, are as follows:'--

'(in millions) PEC Electric PEF CCO Other Total Balance as of January 1, 2003 $1,922 .$1,733 $ 64 $ - $3,719

-Acquisitions ----'-7 7 rBalanceas of December31,2003 S 1,922 S1,733 $64 S 7 $3,726 aseaccounting adjustment' - ' - '

BalanceasofJune30,2004 1,922 $1,733 S $64 S 11 ' $3,730

.14.

  • ls@.s -* :;,; I ;d The gross carrying amount and accumulated amortization of the Company's intangible assets at June 30, 2004 and December 31, 2003, are as follows:

June 30, 2004  : December 31, 2003 (in millions) ' Gross Gross

.~,- Carrying Accumulated Carrying Accumulated 4 Amount Amortization Amount Amortization Synthetic fuel intangibles ' $ 134 'S. (71) $140 $(64)

Power agreements acquired '221 (29) 221 (20)

'Other ' ' ' 64 (13) 62 (12)

Total - ' $ 419 S (113) $423 $ (96)

In June 2004, the Company sold, in two transactions, a combined 49.8 percent partnership interest in Colona Synfuel Limited Partnership, LLLP, one of its synthetic fuel operations. Approximately $6 million in synthetic fuel intangibles and $4 million in related accumulated amortization were included in the sale of the partnership interest.

All .of the Company's intangibles are subject to amortization. Synthetic fuel intangibles represent intangibles for synthetic fuel technology. These intangibles are being amortized on a straight-line basis until the expiration of tax credits under Section 29 of the Internal Revenue Code (Section 29) in December 2007. The intangibles related to power agreements acquired are being amortized based on the economic benefits of the contracts. Other intangibles are primarily acquired customer contracts and permits that are amortized over their respective lives.'

Amortization expense recorded on intangible assets for the three months ended June 30, 2004 and 2003 was $12 million and $9 million, respectively. Amortization expense recorded on intangible assets for the six months ended June 30, 2004 and 2003 was $21 million and $16 million, respectively. The estimated annual amortization expense for intangible assets for 2004 through 2008, in millions, is approximately S41,

$34, $35, $35 and $17, respectively. . '

6.- EQUITY

A. are... . . .:

A. ' Earnings Per Common Share .

A reconciliation of the weighted-average number of common shares outstanding for basic and 'dilutive

'earnings per share purposes is as follows:

(in millions) Three Months Ended Six Months Ended

- June 30 June 30 2004 2003 2004 2003 Weighted-average common shares -basic 242 - . 236 . 242 . 235 Restricted stock awards - I I I Weighted-average shares - fully dilutive 243 237 243 236 B. Comprehensive Income -

Comprehensive income for the three months ended June 30, 2004 and 2003 was $159 million and $154 million, respectively. Comprehensive income for the six months ended June 30, 2004 and 2003 was $256 million and $373 million, respectively. Changes in other comprehensive income for the periods consisted primarily of changes in the fair value of derivatives used to hedge cash flows related to interest on long-term debt and gas sales. . . .

7. FINANCING'ACTIVITIES Progress Energy took'advantage of favorable market conditions and entered into a new $1.1 billion five year line of credit, effective August 5, 2004, and expiring August 4, 2009.. This facility replaces Progress Energy's S250 million 364 day line of credit and its three year $450 million line of credit, which were set to expire in November 2004.

15

On July 28, 2004, PEC extended its $165 million 364-day line of:credit, which was to expire on July 29, 2004; The line of credit will expire on July 27, 2005.

~ ~

4.~ of crdi Th lin -.

On April 30, 2004, PEC redeemed $34.7 million of Darlington County 6.6% Series Pollution Control Bonds at 102.5% of par, $1.795 million of New Hanover County 6.3% Series Pollution Control Bonds at 101.5% of par, and $2.58 million of Chatham County 6.3% Series Pollution Control Bonds at 101.5% of par with cash from operations. ' ' ' 5 On March 1, 2004, Progress Energy used available cash and proceeds from the issuance of commercial paper to pay at maturity $500 million 6.55% senior unsecured notes. Cash and commercial paper capacity for this retirement was created primarily from proceeds of the sale of assets and early long-term debt financings in 2003.

On February 9, 2004, Progress Capital Holdings, Inc. paid at maturity $25 million 6.48% medium term notes with excess cash.

On January 15, 2004, PEC paid at maturity $150 million 5.875% First Mortgage Bonds with commercial paper proceeds. On April 15, 2004, PEC also paid at maturity $150 million 7.875% First Mortgage Bonds with commercial paper proceeds and cash from operations.

For the three months ended June 30, 2004, the Company issued approximately 0.6 million shares of its common stock for approximately $29 million in proceeds from its Investor Plus Stock Purchase Plan and its employee benefit plans. For the six months ended June 30, 2004, the Company issued approximately 1.3 million shares of its common stock for approximately $58 million in proceeds from its Investor Plus Stock Purchase Plan and its employee benefit plans. For the six months ended June 30,2004 and 2003, the dividends paid on common stock were approximately $280 million and $268 million, respectively.

18. BENEFIT PLANS The Company and some of its subsidiaries have a non-contributory defined benefit retirement (pension)'

-plan for substantially all full-time employees. The Company also has supplementary defined benefit pension plans that provide -benefits to higher-level employees. In addition to pension benefits, the Company and some of its subsidiaries provide' contributory other postretirement benefits (OPEB),

including certain health care and life insurance benefits, for retired employees who meet specified criteria.

The components of the net periodic benefit cost for the three and six months ended June 30 are:

Other Postretirement Three Months Ended June 30 ' I Pension Benefits ' - Benefits (in millions) -2004 2003 2004: 2003 Service cost - S 13 $ 13 S 4 $ 3 Interest cost 28 ' 27 - 8.. ' 8

- Expected return on plan assets (37) - (36) (1) . (1)

Amortization of actuarial (gain) loss '5 5  :- 1I I Other amortization, net .1 1

. Netperiodiccost . .9.$ ' 9 S ' 13 S 12 Additional cost / (benefit) recognition (a) (4) (4) *1 ' 1

' Net periodic cost recognized - $ 5 $ 5 S ' 14 S 13

. .- I I i- ., . . . I -

  • 16

f .*I-1 "!.

Other Postretirement

-Six Months Ended June 30 a: Pension Benefits; Benefits (in millions) ' 2004 2003- 2004 2003 Service cost S 27$ ' 26 S 8 S. 7 Interest cost '  ; 55- 54 17 15 Expected return on plan assets  : ' (75) (72) (2) (2)

Amortization of actuarial (gain) loss 11 9 . 2 '2 Other amortization, net - - '1 2

'Netperiodiccost ' '- 18 $S 17 S 26 $ 24 Additional cost / (benefit) recognition (a) (8) (7) ' 1 I Net periodic cost recognized S 10 $ 10' S 27 S 25 (a) Due to the acquisition of FPC. See Note 16B of Progress Energy's Form 10-K -for year ended December 31, 2003.

9. RISK MANAGEMENT ACTIVITIES AND DERIVATIVE TRANSACTIONS Progress Energy and its subsidiaries are exposed to various risks related to changes in market conditions.

The Company has a'risk management committee that includes senior executives from various business groups. The risk management committee is responsible for administering risk management policies and monitoring compliance with those policies by all subsidiaries.

Under its risk management policy, the Company may use a variety of instruments, including swaps, options and forward contracts, to manage exposure to fluctuations in commodity prices and interest rates. Such

-instruments contain credit risk if the counterparty fails to perform under the contract. The Company minimizes such risk by performing credit reviews using, among other things, publicly available credit ratings. of such counterparties. Potential nonperformance by counterparties is not expected to have a material effect on the consolidated financial position or consolidated results of operations of the Company.

Progress Energy uses interest rate derivative instruments to adjust the fixed and variable rate debt

'- - - ' components of its debt portfolio and to hedge interest rates with regard to future fixed rate debt issuances.

As of June 30, 2004, Progress Energy had $1 billion of fixed rate debt swapped to floating rate debt by executing interest'rate derivative agreements. Under terms of these swap rate agreements, Progress Energy will receive a fixed rate and pay a floating rate based on 3-month LIBOR. These agreements expire between March 2006 and March 2011. During the year, Progress Energy has entered into $350 million notional of open interest rate fair value hedges. In March 2004, two interest rate swap agreements totaling

$200 million were terminated. These swaps were associated with Progress Energy 5.85% Notes due'in

'2008. The loss on the agreements was deferred and is being amortized over the life of the bonds as these agreements had been designated as fair'value hedges for accounting purposes.

As of June 30, 2004, PEC had $70 million notional of pay fixed forward starting swaps, entered into in March 2004, to hedge its exposure to interest rates with regard to a future issuance of debt and $26 million notional of pay fixed forward starting swaps, entered into in April 2004, to hedge its exposure to. interest rates with iegard to an upcoming railcar lease. In July 2004, PEC entered into an additional $30 million notional pay fixed forward swap related the future issuance of debt, increasing the total notional of pay fixed forward starting swaps to $126 million. These agreements have a computational period of ten years.

In May 2004, the Company terminated interest rate cash flow hedges, with a total notional amount of $400 million, related to projected outstanding balances of commercial paper. Amounts in accumulated other comprehensive income related to these terminated hedges will be reclassified to earnings as the hedged

' -interest payments occur.

The Company holds interest rate collars with a varying notional amount (currently at the maximum of $195 million) to hedge floating rate exposure associated with variable rate long-term debt at Progress'Ventures.

The Company is required to hedge 50% of the amount outstanding under its bank facility through March 2007.

17

- The notional amounts of interest rate derivatives are not exchanged and do not represent exposure to credit loss. In the event of default by a counterparty, the risk in the' trnsaction is the cost of replacing the agreements at current market rates. Progress Energy only enters into interest rate derivative agreements with banks with credit ratings of single A or better.

PEF has entered into derivative instruments to hedge 'its exposure to price fluctuations on fuel oil purchases. These instruments did not have a material impact on the Company's consolidated financial position or results of operations.

' ' Progress Fuels Corporation, through Progress Ventures, Inc. (PVJ),'periodically enters into derivative instruments to hedge its exposure to price fluctuations on natural gas sales. As of June 30, 2004, Progress Fuels Corporation is hedging exposures to the price variability of portions of its natural gas production through December 2005. These instruments did not have a material impact on the Company's consolidated

' financial position or results of operations.

  • 'Nonhedging derivatives, primarily electricity and natural gas contracts, are entered into for trading purposes and for economic hedging purposes. While management believes the economic hedges mitigate exposures to fluctuations in commodity prices, these instruments are not designated as hedges for accounting purposes and are monitored consistent with trading positions.

The Company 's July 2004 forward mark-to-market'losses were $7 million for the first quarter of 2004 and S3 million for'the second quarter of 2004'. These mark-to-market losses are reflected in diversified business revenues and were related to an agreement to provide energy needed to fulfill a contract

- obligation and economic hedges used to mitigate exposures to fluctuations in commodity prices.

- 10.FINANCIAL INFORMATION BY BUSINESS SEGMENT The' Company currently provides services through the following business segments: PEC Electric, PEF, Fuels, CCO, Rail Services and Other.

PEC Electric and PEF are primarily engaged'in the generation, trafismission, distribution and sale'of

' electric energy in'portions of North Carolina, South Carolina and Florida. These electric operations are

subject to the rules and regulations of the FERC, the NCUC, the SCPSC, the FPSC and the United States Nuclear Regulatory Commission (NRC). These electric operations also distribute and sell electricity to other utilities, primarily on the east coast of the United States.

' Fuels' operations, which are located throughout the United States, are involved in natural gas drilling and production, coal terminal services, coal mining, synthetic fuel production, fuel transportation and delivery.

CCO's operations, which are located in' the southeastern United States, include nonregulated electric generation operations and marketing activities.,

Rail Services' operations include railcar repair, rail parts reconditioning and sales, and scrap metal recycling. These activities include maintenance and reconditioning of salvageable scrap components of railcars, locomotive repair and right-of-way maintenance. Rail Services'. operations are located in the United States, Canada and Mexico.'

The Other segment, whose operations are in the United States, is composed of other nonregulated business areas including telecommunications and energy service operations arnd other nonregulated subsidiaries that do not separately meet the disclosure requirements of SFAS No. 131, "Disclosures about Segments of an Enterprise and Related Information." ' -

In addition to these reportable operating segments, the Company has other corporate activities that include holding company operations, service company operations and eliminations. ' The profit or loss of the identified segments plus the loss of Corporate represents the Company's total income from continuing operations before cumulative effect of change in accounting principle. '

 : 1 8 - --'

-Revenues.

Income from Continuing

.(in millions) unafriliated Intersegment Total Operations Assets FOR THE THREE

-MONTHS ENDED RINE 302004 PEC Electric S 861

  • 5861
  • S 97 5 10,711 PEF - .860 860 84 7,457 Fuels 32S . .68 393 56 1,156 CCO, 72 72 *5 1,784

.i Rail Services 285 285 4.- 532 Other 22 .1I -23 (30) - 312

  • Corporate (69) (69) . 4,283 S 2,42S S - S 2,425 S 153
  • S 26,235 FOR THE THREE

-MONTHS ENDED PEC Electric S 816 S 816 5. 89.

767 -767 I .61 Fuels 206 88 294 58

  • CCO 33
  • 33 2 Rail Services 214 214 2-Other 14 3 17 Corporate (9 1)
  • Consolidaied totals' *S2.050 S 2,050 S 154 Revenues,

- . . .. . .Income from (in millions) Unaffiliated Intersegment -Total '. Operations FOR THE SIX MONTHS ENDED JUNE 30.2004.

PEC Electric S 1,762 51,762 S S 213 PEF

  • 1,644 1,644 133 Fuels *598 . .151. .749. 104 CCO 105 105 *(3)

Rail Services *523 452 9 Other 44 1 - * (31)

Corporate (152) (152). (164)

Consolidated totals S 4,676 S.I- S4,676 S 261 FOR THE SIX MONTHS

  • ENDED JUNE 30.2003 PEC Electric $ 1,742 S 1,742 S 223 PEF, - 1.495
  • 1,495 - 132 Fuels - 510 . 169 679-
  • 97*

.CCO .71-- - 71

  • 11
  • Rail Services -392 392 (I)
  • -Other -27 . I8 -. 35 Corporate - (177)
  • 172L.

Consolidated totals - 4,237 S - . S 4,237 *S -361

11. .. OTHER INCOME AND OTHER EXPENSE

.Other income and expense includes interest income and other income and expense items as discussed below..-Te opnnso tenta'hw nteacmayn osldtdSaeet fIcm

. I are as Tholompnnsowtentashono:h copnigCnoldtdSaeet fIcm I - . 9 . .
  • ' 19
14. - ; t 1 i '! , . . . I---

. : _,, ,": ,i i .;. .I Three Months Ended Six Months Ended

- June 30 June 30

- (in millions) -- 2004 2003 2004 2003 Other income Net financial trading gain (loss) 54 $ 5I $ (1)

Nonregulated energy and delivery services income *. 5' 5 11 11 Investment gains 3 AFUDC equity .2. .4 4 6

'Other .3. .9 8 Total other income  : S 17 S 17 S 28 . 25 Other expense .5 .

Nonregulated energy and delivery services expenses S 5 $ 5 S. 9 S 10

'. Donations - 2 .3 10 7 Investment losses - 9 8

- 'Contingent value obligations unrealized loss - 5 2 13 Loss from equity investments .1 - 2 . *3 Write-off of non-trade receivable . . . .

.7

.Other  : 4 " 7 ' 12 12 Total other expense . S 17 - S '26 S 53 S 40 Other, net ' S - S (9) S (25) S (15):

-Net financial trading -gains and losses' represent non-asset-backed trades of electricity and gas.

Nonregulated energy and delivery services include power protection services and mass-market programs such as surge protection, 'appliance services and area light sales, and delivery, transmission and substation work for other utilities.

12.- COMMITMENTS AND CONTINGENCIES Contingencies and significant changes to the commitments discussed in Note 21 of the Company's 2003 Annual Report on Form 10-K are described below.

.- A. Guarantees '

As a part of normal business, Progress Energy and certain subsidiaries enter into various agreements providing financial or performance assurances .to third parties. Such agreements include guarantees, standby letters of credit and surety bonds. ' These 'agreements are .entered into primarily to support or enhance the creditworthiness otherwise attributed to Progress Energy and subsidiaries on a stand-alone basis, thereby facilitating the extension of sufficient credit to accomplish the subsidiaries' intended commercial purposes. At June 30, 2004, management does not believe conditions are likely for significant

performance under the guarantees of performance issued by'or on behalf of affiliates discussed herein.

Guarantees at June 30, 2004, are summarized in the table below and discussed more' fully in the subsequent paragraphs.

(in millions)j.

Guarantees issued 'on behalf of affiliates '-

Guarantees supporting nonregulated portfolio and energy marketing activities issued by Progress Energy *$ .405 Guarantees supporting nuclear decommissioning 181 Guarantee supporting power supply agreements 457 Standby letters of credit: 54 Surety bonds - -132 Guarantees supporting nonregulated portfolio and energy marketing

- activities issued by subsidiaries of Progress Energy 82 Guarantees issued on behalf of third parties Other guarantees 24 Total S 1,335 20.

Guarantees Supporting Nonregulated Portfolio and Energv Marketing Activities Issued by Progress Enery.

Progress Energy has issued appioximately $404 million of guarantees on behalf of Progress Ventures (the business unit) and its subsidiaries for obligations under tolling agreements, transmission agreements, gas agreements, construction agreements, fuel procurement agreements and trading operations. Approximately

$19 million and $57 million of these guarantees were issued during the second three and six months ended June 30,.2004, respectively, to support Fuels and energy-marketing activities. The majority of the marketing contracts supported by the guarantees contain provisions that trigger guarantee obligations based on downgrade events, ratings triggers, monthly netting of exposure and/or payments and offset provisions

. '. in the event of a default. Based upon current business levels at June 30, 2004, if the Company's ratings-were to decline below investment grade, the Company estimates that it may have to deposit cash or provide

.letters of credit or other cash collateral of approximately $115 million for the benefit of the Company's

- counterparties to support ongoing operations within a 90-day period. The remaining $1 million in guarantees issued by Progress Energy on behalf of affiliates is primarily related to performance and payments subject to other contingencies.

Guarantees Supporting Nuclear Decommissioning

  • In 2003, PEC determined that its external funding levels did not fully meet the nuclear decommissioning financial assurance levels required by the NRC. Therefore, PEC met the financial assurance requirements by obtaining guarantees from Progress Energy in the amount of $276 million. On May 12,2004, PEC sent notice to the NRC informing them that due to the Renewed Facility Operating License for Robinson 2, the

. parent 'guarantee related to Robinson, would be cancelled as of June 30, 2004. As a result, the total parent guarantees for decommissioning decreased from $276 million to $ 181 million during the second quarter.

Guarantees Supporting Power Supply Agreeinents In March 2003, PVI entered into a definitive agreement with Williams Energy Marketing and Trading, a subsidiary of The Williams Companies, Inc.,.to acquire a long-term full-requirements power supply agreement at fixed prices with Jackson County EMC (Jackson). The power supply agreement included a performance guarantee by Progress Energy. The transaction closed during the second quarter of 2003.

The Company'. issued a payment and performance guarantee to Jackson related to the power supply agrement of $280 million. In the event that Progress Energy's credit ratings fall below investment grade, Progress Energy may be required to provide additional security for this guarantee in form and amount (not to exceed $280 million) acceptable to Jackson.

During the third quarter of 2003, PVI entered into an agreement with Morgan Stanley Capital Group Inc.

(Morgan :Stanley) to. fulfill Morgan Stanley's obligations to schedule resources and supply energy to Oglethorpe Power Corporation of Georgia through March 31, 2005. The Company issued a payment and performance guarantee to Morgan Stanley related to the power supply, agreement.' In the event that

- Progress Energy's credit ratings fall below investment grade, Progress Energy estimates that it may have to deposit cash or provide letters of credit or other cash collateral of approximately $27 million for the benefit of Morgan Stanley as of June 30,2004. '

. In June 2004, PVI entered into a definitive agreement with five electric cooperatives in Georgia to provide long term full requirements, power. The transaction closed during the second quarter of 2004. The Company issued a payment and performance' guarantee to the cooperatives related to the power supply agreement totaling $150 million. In the event that Progress Energy's credit ratings fall below investment

-grade, Progress Energy would be required to provide additional security for this guarantee in form and amount acceptable to the cooperatives. .The Company would immediately be required to deposit cash or provide letters of credit or other cash collateral up to 50% of the coverage amount of the guarantees issued (for a maximum of $75 million) in the event of a downgrade. Beyond that requirement, additional security requirements would be'determined based upon a calculation of mark-to-market exposure, not to exceed

'$150 million.

21

I  :.

- Standby Letters of Credit:.. , '

As of June 30, 2004, financial institutions have issued $54 million of standby letters of credit to financial institutions for the Company for the benefit of third parties that have extended credit to the Company and

' certain subsidiaries. These letters of credit have been issued primarily for the purpose of supporting

- payments of trade payables, securing performance under contracts and lease obligations and self-insurance for workers' comnpensation. If a subsidiary does not pay amounts when due under a covered contract, the

'counterparty may present itsclaim for payment to'the financial institution, which will in turn request payment from the Company. Any amounts owed by the Company's subsidiaries are reflected in the accompanying Consolidated Balance Sheets.

Suretv Bonds At June 30, 2004, the Company had $132 million in surety bonds purchased primarily for purposes such as providing workers' compensation coverage, obtaining licenses, permits, rights-of-way and project performance. To the extent liabilities are incurred as a result of the activities covered by the surety bonds, such liabilities are included in the accompanying Consolidated Balance Sheets.

Guarantees SupportinE Nonregulated Portfolio and Energv Marketing Activities Issued by Subsidiaries of Progress Energy Subsidiaries of Progress Energy have issued approximately $82 million of guarantees for obligations under tolling agreements, transmission agreements, gas agreements,' construction agreements, fuel procurement agreements and trading operations. '

-Other Guarantees The Companyhas other guarantees outstanding of approximately S24 million. Included in the $24 million

' are $10 million of guarantees issued on behalf of third parties, which'is in support of synthetic fuel

' operations at a third-party plant. The remaining $14 million in affiliate guarantees is related primarily to prompt performance payments and other payments subject to contingencies.

'In connection with the sale of partnership'interests in Colona (see Note 3.A), Progress Fuels indemnified the buyers against any claims related to Colona resulting from violations of any environmental laws.

Although the terms of the agreement provide for no limitation to the maximum potential future payments under the indemnification, the Company hasestimated that the maximum total of such payments would be insignificant.

B. Insurance

'Both PEC and PE are insured against public liability for a nuclear incident up to $10.76 billion per' occurrence: Under the current provisions of thePrice Anderson Act, which limits liability for accidents at nuclear power plants, each company, as an owner of nuclear units, can be assessed a portion of any third-

- -party liability claims arising from an accident at any commercialnuclear power plant in the United States In the event that public liability claims from an insured nuclear incident exceed $300 million (currently available through commercial insurers), each company would be subject to assessments of up to $101 million for each reactor owned per occurrence. Payment of such assessments would be made over time as

' necessary to limit the payment in any one year to no more than$10million per reactor owned. Congress is

- . - considering revisions to the Price Anderson Act during 2004 that could include increased limits and assessments per reactor owned. The final outcome of this matter cannot be predicted at this time.

PEC and PEF self-insure their transmission and distribution lines against loss due to storm damage and

other natural disasters. PEF accrues $6m illion annually to a storm damage reserve pursuant to a' regulatory order and may defer losses in excess of the reserve.

22

.. r. . ...

C. Claims and Uncertainities The Company is subject to federal, state and local regulations addressing hazardous and solid waste management, air and water quality and other environmental matters.

Hazardous and Solid Waste Management Various organic materials associated with the production of manufactured gas, generally referred to as coal tar, are regulated under federal and state laws. The principal regulatory agency that is responsible for a specific former manufactured gas plant (MGP) site depends largely upon the state in which the site is located. Both electric utilities and other potentially responsible parties (PRPs) are participating in,

'investigating and, if necessary,-remediating former MGP sites with several regulatory agencies, including, but not limited to, the U.S. Environmental Protection Agency -(EPA), the Florida Department of Environmental Protection (FDEP) and the North Carolina Department of Environment and Natural

-Resources, Division of Waste Management (DWM). In addition, the Company and its subsidiaries are

  • periodically notified by regulators such as the EPA and various.state agencies of their involvement or

- potential involvement in sites, other than MGP sites, that may require investigation and/or remediation. - A discussion of these sites by legal entity follows.

PEC, PEF and Progress Fuels Corporation have filed claims with the Company's general liability insurance

. carriers to recover costs arising out of actual or potential environmental liabilities. Some claims have been settled and others are still pending. -While the Company cannot predict the outcome of these matters, the outcome is not expected to have a material effect on the consolidated financial position or results of

  • . operations. .  : .. - - -  : - - .

- The Company is also currently in the process of assessing potential costs and exposures at other environmentally impaired sites. As the assessments are developed and analyzed, the Company' will accrue

  • costs for the sites to the extent the costs are probable and can'be reasonably estimated.

.'. EC There are nine former MGP sites and other sites associated with PEC that have required or are.

anticipated to require investigation and/or remediation costs. PEC received insurance proceeds to address costs associated with environmental liabilities related to its involvement with some sites. All eligible

  • ' ' expenses related to these are charged against a specific fund containing these proceeds. At June 30, 2004,

'approximately S8 million remains in this centralized fund with a related accrual of $8 million recorded for the associated expenses of environmental issues. PEC is unable to provide an estimate of the reasonably

. *possible total remediation costs beyond what is currently accrued due to the fact that investigations have

  • not been completed at all sites. 'This accrual has been recorded on an undiscounted basis. PEC measures

- its liability for these sites based on available evidence including its experience in investigating and remediating environmentally impaired sites. The process often involves assessing and developing cost-

- sharing arrangements with other PRPs. PEC will accrue costs for the sites to the extent its liability is probable and the costs can be reasonably estimated. 'Presently, PEC cannot determine the total costs that may be incurred in connection with the remediation of all sites.-

In September 2003, the Company sold NCNG to Piedmont Natural Gas Company, Inc. As part of the sales

- agreement, the Company retained responsibility to remediate five former NCNG MGP sites, all of which also are associated with PEC, to state standards pursuant to an Administrative.Order on Consent. These sites are anticipated to have investigation or remediation costs associated -with them. NCNG had

- -previously accrued approximately $2 million for probable and reasonably estimable remediation costs at

  • - . ' -. these sites. These accruals have been recorded on an undirounted basis. At the timeiof the sale, the

. iability for these costs and the related accrual was transferred to PEC. PEC does not believe it can provide

- an estimate of the reasonably possible total remediation costs beyond the accrual because investigations have not been completed at all sites. Therefore, PEC cannot currently determine the total costs that may be incurred in connection with the investigation and/or remediatiori of all sites. .

- 23

- 3 j . -' [

-EF At June 30, 2004,'PEF has accrued $27 million for probabl and estimable costs related to various environmental sites. Of this accrual, $17 million is for costs associated with the remediation of distribution and substation transformers for which PEF has received approval from the FPSC for recovery through the Environmental Cost Recovery Clause (ECRC). For the six months ended June 30 2004, PEF accrued an additional $8 million related to the remediation of transformers and a regulatory asset for the probable recovery through the ECRC. The remaining $10 million is related to two former MGP sites and other sites associated with PEF that have required or are anticipated to require investigation and/or remediation costs.

PEF is' unable to provide an estimate of the reasonably possible total remediation costs beyond what is currently accrued..

These accruals have been recorded on an undiscounted basis. PEF measures its liability for these sites

-based on available evidence including its experience in investigating and remediating environmentally impaired sites. This process often includes assessing and developing cost-sharing arrangements with other PRPs. Presently; PEF cannot determine the total costs that may .be incurred in connection with the remediation of all sites. As more'activity occurs at these sites, PEF will assess the need to adjust' the accruals.

Florida Progress Corporation (FPC) In 2001, FPC sold its Inland Marine Transportation business operated

'by MEMCO Barge Line,' Inc. to AEP Resources, Inc. FPC established an accrual to address indemnities and retained an environmental liability associated with the transaction. FPC estimates that its contractual

.'liability to AEP Resources, Inc., associated with Inland Marine Transportation, is $4 million at June 30, 2004 and has accrued'such amount. 'The previous accrual of $10 million was reduced in 2003 based on a change in estimate. This accrual has been determined on an undiscounted basis. FPC measures its liability

for this site based on estimable and probable remediation scenarios.

Certain historical sites' exist that are being addressed voluntarily by FPC. 'An immaterial accrual has been established to address investigation expenses related to these sites.' The Company cannot determine the total costs that may be incurred in connection with these sites. -

Rail Rail Services is voluntarily addressing certain historical waste sites: The Company cannot determine the total costs that may be incurred in connection with these sites.

-Air Quality' There has been and may be further proposed legislation requiring reductions in air emissions for NOx,:

S02, carbon dioxide and mercury. Some of these proposals establish nationwide caps and emission rates over an extended period of time. This national multi-pollutant approach to air pollution control could.

involve significant capital costs which could be material to the Company's consolidated financial position or results of operations.- Control equipment that will be installed on North Carolina fossil generating facilities as part of the North Carolina legislation discussed below may' address some of the issues outlined above. However, the Company cannot predict the outcome of this matter.

The EPA is conducting an enforcement initiative related to a number of coal-fired utility power plants in an

-effort to determine whether modifications at those facilities were subject' to New Source Review requirements or New Source Performance Standards under the Clean Air Act. Both PEC and PEF were

- ' asked

' to provide information to the EPA as part of this initiative and cooperated in providing the requested

- information.

- The EPA initiated civil enforcement actions against other unaffiliated utilities as part of this

initiative.' Some of these actions resulted in settlement agreements calling for expenditures by these unaffiliated utilities, ranging from $1.0 billion to S1.4 billion. A utility that was not subject to a civil enforcement action settled its New Source Review issues with the EPA for $300 million. These settlement.

-agreements have generally called for expenditures to be made over extended time periods, and some of the companies may seek recovery of the related cost through rate adjustments or similar mechanisms. The Company cannot predict the outcome of this matter. ' '

-24

- In 2003, the EPA published a final rule addressing routine equipmentreplacement under the New Source

-Review program. The rule defines routine' equipment replacement and the types of activities that are not subject to New Source Review requirements or New Source.Performance Standards under the Clean Air Act. The rule was challenged in the Federal Appeals Court'and its implementation stayed. In July 2004, the EPA announced it will reconsider certain issues arising from the final routine equipment replacement rule. Reconsideration does not impact the court-approved stay. The agency plans to issue a final decision on these reconsidered issues by year end. The Company cannot predict the outcome of this matter.

In 1998, the EPA published a final rule at Section 110 of the Clean Air Act addressing the regional transport of ozone (NOx SIP Call).- The EPA's rule requires 23 jurisdictions, including North Carolina, South Carolina and Georgia, but not Florida, to further reduce NOx emissions in order to attain a preset

- emission level during each year's "ozone season," beginning May 31, 2004. The EPA rule allows credit to

- companies taking early action to meet the May 31, 2004 deadline. PEC is currently installing controls necessary to comply with the rule and, with the use of early action credits, expects to be in compliance as required by the final rule. Total capital expenditures to meet these measures in North and South Carolina could reach approximately $370 million, which has not been adjusted for inflation. The Company has spent approximately $265 million to date related to these expenditures. Increased operation and maintenance costs relating to the NOx SIP Call are not expected to be material to'the Company's results of operations. Further controls are anticipated as electricity demand increases.'

-In 1997, the EPA issued final regulations establishing a new 8-hour ozone standard. In 1999, the District

'of Columbia Circuit Court of Appeals ruled against the EPA with regard to the federal 8-hour ozone standard. The U.S. Supreme Court has upheld, in part, the District of Columbia Circuit Court of Appeals'

' decision. In April 2004, the EPA identified areas that do not meet the standard. The states with identified areas, including North and'South Carolina are proceeding with the implementation of the federal 8-hour ozone standard. Both states promulgated final regulations, which will require PEC to install.NOx controls under the states' 8-hour standard..' The costs of those controls are included in the $370 million cost estimate above.' However, further technical analysis and rulemaking may result in a requirement for

'- additional controls at some units. The Company cannot predict the outcome of this matter.

In June 2002, legislation was enacted in Noith Carolina requiring the state's electric utilities to reduce the emissions of NOx and S02 from coal-fired power plants. Progress Energy expects its capital costs to meet

-these emission targets will be approximately $813 million by 2013. PEC has expended approximately S45 million of these capital costs through June 30, 2004. PEC currently has approximately 5,100 MW of coal-fired generation capacity in North Carolina that is' affected by this legislation. The law requires the

'emissions reductions to be completed in phases by 2013, and applies to each utility's total system rather than setting requirements for individual power plants. The law also freezes the utilities' base rates for five years unless 'there are extraordinary events beyond the control of the utilities or unless- the' utilities persistently earn a return substantially in excess of the rate of return established and found reasonable by the NCUC in the utilities' last general rate case. Further, the law allows the utilities to recover from their retail customers the projected capital costs'during the first seven years of the ten-year compliance period beginning on January '1,'2003. The utilities must recover at least 70% of their projected capital costs during the five-year rate freeze period. PEC recognized amortization of $15 million and $34 million in the quarters ended June 30, 2004 and 2003, respectively. PEC recognized amortization of $31 million and $54 million in the six months ended June 30, 2004 and 2003, respectively.' Pursuant to the law, PEC entered into an agreement with the state of North Carolina to transfer to the state certain NOx and S02 emissions allowances that result from compliance with the collective NOx and S02 emissions limitations set out in the law. The law also requires the state to undertake a study of mercury and carbon dioxide emissions in II North Carolina.' Operation and maintenance costs will increase due to the additional personnel, materials and general maintenance associated with the equipment Operation and' maintenance expenses are recoverable through base rates, rather than as part of this program. Progress Energy cannot predict the future regulatory interpretation, implementation or impact of this law. ' '
' .25

In 1997, the EPA's Mercury Study Report and Utility Report to Congress conveyed that mercury is not a!

risk to the average Anieiidan and expressed uncertainty about w'hether reductions in mercury emissions from coal-fired power plants would reduce human exposure. Nevertheless, the EPA determined in 2000 that regulation of mercury emissions from coal-fired power plants was appropriate. In 2003, the EPA proposed alternative control plans that would limit mercury emissions from coal-fired power plants. The

-first, a Maximum Achievable Control Technology (MACT) standard applicable to every coal-fired plant,

-would require compliance in 2008. The second, which the EPA has stated it prefers, is a mercury cap and trade program that would require limits to be met in two phases, 2010 and 2018. The EPA expects to finalize the mercury rule in March 2005. Achieving compliance with the proposal could involve significant capital costs which could be material and adverse to the Company's consolidated financial position or results of operations. The Company cannot predict the outcome of this matter.

In conjunction with the proposed mercury rule, the EPA proposed a MACT standard to regulate nickel.

emissions from residual oil-fired units. The agency estimates the proposal will reduce national nickel emissions to approximately 103 tons. The EPA expects to finalize the nickel rule in March 2005. The Company cannot predict the outcome of this matter.

In December 2003, the EPA released its proposed Interstate Air Quality Rule, currently referred to as the Clean Air Interstate Rule (CAIR). The EPA's proposal requires 28 jurisdictions, including North Carolina,

'South Carolina, Georgia and Florida, to further reduce NOx and S02 emissions in order to attain preset state NOx and S02 emissions levels. The rule is expected to become final in 2004. The air quality controls already installed for compliance with the NOx SIP Call and currently planned by the Company for compliance with the North Carolina law will reduce the costs required to meet the CAIR requirements for the Company's North Carolina units. Additional compliance costs will be determined later this year once the rule is finalized.

In March 2004, the North Carolina Attorney General filed a petition with the EPA under Section 126 of the Clean Air Act, asking the federal government to force coal-fired power plants in thirteen other states,.

-including South Carolina to reduce their NOx and S02 emissions. The state of North Carolina contends these out-of-state polluters -are interfering with North Carolina's ability to meet national air quality standards for ozone and particulate matter. The EPA has not made a determination on the Section 126' petition, and the Company cannot predict the outcome of this matter.

Water Quality As a result of the operation of certain control equipment needed to address the air quality issues outlined above, new wastewater streams may be generated at the applicable facilities. Integration of these new.

wastewater streams into the existing wastewater treatment processes may result in permitting, construction and treatment requirements imposed on PEC and PEF in the immediate and extended future.

After many years of litigation and settlement negotiations the EPA adopted regulations in February 2004 for the implementation of Section 316(b) of the Clean Water Act. These regulations become effective September 7, 2004. The purpose of these regulations is to minimize adverse environmental impacts caused by cooling water intake structures and intake systems. Over the next several years these regulations will impact the larger base load generation facilities and may require the 'facilities to mitigate the effects to

  • aquatic organisms by constructing intake .'modifications or undertaking other restorative activities.

Substantial costs could be incurred by. the facilities in order to -comply with the new regulation. The Company cannot predict the outcome and impacts to the facilities at this time.

The EPA has published for comment a draft Environmental Impact Statement (EIS) for surface coal mining (sometimesreferred to as "mountaintop mining") and valley fills in the Appalachian coal region, where

Progress Fuels currently operates a surface mine and may operate others in the future. The final EIS, when

'published, may affect regulations for the permitting of mining operations and the cost of compliance with environmental regulations. Regulatory changes for mining may also affect the cost of fuel for the coal-fueled electric generating plants. The Company cannot predict the outcome of this matter.'

- - --:26

Other Environmental Matters The Kyoto Protocol vas' 'adopted in 1997 by the United Nations to address global climate change by reducing emissions of carbon dioxide and other greenhouse gases. The United States has not adopted the

- Kyoto Protocol; however, a number of carbon dioxide emissions control proposals have been advanced in Congress and by the Bush administration. The Bush administration has stated it favors voluntary programs. Reductions in carbon dioxide emissions to the levels specified by the Kyoto Protocol and some legislative proposals could be materially'adverse to the Company's consolidated financial position or results of operations if associated costs cannot be recovered from customers. The Company favors the' voluntary program approach recommended by the administration and is evaluating options for the

- reduction, avoidance and sequestration of greenhouse gases. However, the Company cannot predict the

- : outcome of this matter.

Other Contingencies

1. As required under the Nuclear Waste Policy Act of 1982, PEC and PEF each entered into a contract

-with the United States Department of Energy'(DOE) under which the DOE agreed to begin taking spent nuclear fuel by no later than January 31, 1998. All similarly situated utilities were required to sign the

-same standard contract. -

In 1995, the DOE issued a final interpretation that it did not have an unconditional obligation to take spent nuclear fuel by January 31, 1998. In Indiana Michigan Power v. DOE, the Court of Appeals vacated the DOE's final interpretation and ruled that the DOE had an unconditional obligation to begin taking spent nuclear fuel. The Court did not specify a remedy because the DOE was not yet in default.

After the DOE failed to comply with the decision in Indiana Michigan Power v. DOE, a group of utilities

. petitioned the Court of Appeals in Northern States Power (NSP) v. DOE, seeking an order requiring the DOE to'begin taking spent nuclear fuel by January 31, 1998. The DOE took the position that their delay was unavoidable, and the DOE was excused from performance under the terms and conditions of the contract. The Court of Appeals found that the delay was' not unavoidable, but did not order the DOE to begintaking spent nuclear fuel, stating that the utilities had a potentially adequate remedy by filing a claim for damages under the contract.

After the DOE failed to begin taking sp'ent nuclear fuel by January 31, 1998, a group of utilities filed a motion with the Court of Appeals to enforce the mandate in NSP v. DOE.- Specifically, this group of utilities asked the Court to permit the utilities to escrow their waste fee payments, to order the DOE not to use the waste fund to pay damages to the utilities, and to order the DOE to establish a schedule for disposal of spent nuclear fuel. The Court denied this motion based primarily on the grounds that a review of the matter was premature, and that some of the requested remedies fell outside of the mandate in NSP v. DOE.

- Subsequently, a number of utilities each filed an action for damages in the Federal Court of Claims. The U.S. Circuit Court of Appeals (Federal Circuit) ruled that utilities may sue the DOE for damages in the

-Federal Court of Claims instead of having to file an administrative claim with the DOE.

-In January 2004, PEC and PEF filed a complaint with the DOE claiming that the DOE breached the Standard Contract for Disposal of Spent Nuclear Fuel by failing to accept spent nuclear fuel from various Progress Energy facilities on or before January 31, 1998. Damages due to DOE's breach will likely exceed

$100 million. Similar suits have been initiated by over two dozen other utilities.:

In July 2002, Congress passed an override resolution to Nevada's veto of DOE's proposal to locate a permanent underground nuclear waste storage facility at Yucca Mountain, Nevada. DOE plans to submit a license application for the Yucca Mountain facility by the end of 2004. In November 2003, Congressional negotiators approved $580 million for fiscal year 2004 for the Yucca Mountain project, $123 million more than the previous year. In January 2003, the State of Nevada, Clark County, Nevada, and the City of Las Vegas petitioned the U.S. Court of Appeals for the District' of Columbia Circuit for review of the Congressional override resolution. On July 9, -2004, the Court rejected the challenge to the constitutionality, of the resolution approving Yucca Mountain, but ruled that the EPA was wrong to set a 10,000-year compliance period. The DOE continues to state it plans to begin operation of the repository at

- Yucca Mountain in 2010.' PEC and PEF cannot predict the outcome of this matter.

27.

With certain modifications and additional approval by the NRC including the installation of onsite dry storage facilities at Robinson'(2005) and Brunswick (2010), PEC's spent nuclear fuel storage facilities will be sufficient to provide storage space for spent fuel generated on PEC's system through the expiration of the operating licenses for all of PEC's nuclear generating units.

PEF is currently storing spent nuclear fuel onsite in spent fuel pools. PEF's nuclear unit, Crystal River Unit No. 3 (CR3), 'has sufficient storage capacity in place for fuel consumed through the end of the expiration of the current license in 2016. PEF will seek renewal of the CR3'operating license and if approved, additional dry storage may be necessary.

2. In November 2001, Strategic Resource Solutions Corp. (SRS) filed a claim against the San Francisco Unified School District (the District) and other defendants claiming that SRS is entitled to approximately

$10 million in unpaid contract payments and delay and impact damages related to the District's $30 million contract with SRS. In March 2002, the District filed a counterclaim, seeking compensatory damages and liquidated damages in excess of $120 million, for various claims, including breach of contract and demand on a performance bond. SRS asserted defenses to the District's claims. SRS amended its claims and asserted new claims against the District and other parties, including a former SRS employee and a former District employee. '

In March 2003, the City Attorney and the District filed new claims in the form of a cross-complaint against SRS, Progress Energy, Inc., Progress Energy Solutions, Inc., and certain individuals, alleging fraud, false claims, violations of California statutes, and seeking compensatory damages, punitive damages, liquidated damages, treble damages, penalties, attorneys' fees and injunctive relief. The filing stated that the City and

' *'theDistrict seek "more than $300 million in damages and penalties." PEC was later added as a cross-defendant. In November 2003, PEC filed a motion to dismiss the plaintiffs' first amended complaint.

InJune 2004 the Company reached a settlement agreement with the District in this matter. The settlement

' totaled 'approximately $43.1 million and is included in diversified business cost of sales in the

- accompanying Consolidated Statement of Income for the three-months 'and six-months ended June 30, 2004. The accrual of the settlement was recorded on an undiscounted basis. The terms of the settlement require SRS to pay the District $10.1 million upon approval, and an additional $16 million in 2005 and $17

- million 2006. In addition, during a transition period ending September 10, 2004, SRS will provide

maintenance and training on the equipment and software it installed and maintained for the District. The
  • agreement, upon approval,' settles all claims and cross-claims related to SRS, Progress Energy, Progress Energy Solutions and PEC. - '

3.- In 'August 2003, PEC was served as a co-defendant in a purported class action lawsuit styled as Collins

v. Duke Energy Corporation et al, in South Carolina's Circuit Court of Common Pleas for the Fifth Judicial Circuit. PEC is one of three electric utilities operating in South Carolina named in the suit. The plaintiffs are seeking damages for the alleged improper use of electric easements but have not asserted a dollar amount for their damage claims. The'complaint alleges that the licensing of attachments on electric utility

'poles, towers and other structures to nonutility third parties or telecommunication companies for other than the electric utilities', internal use along the electric right-of-way constitutes a trespass.

- In September 2003, PEC filed a motion to' dismiss all counts of the complaint 'on 'substantive and procedural grounds. In October 2003, the plaintiffs filed a motion to amend their complaint. PEC believes the amended complaint asserts the same factual allegations as are in the original complaint and also seeks money damages and injunctive relief. In March 2004,'the plaintiffs in this case filed a notice of dismissal without prejudice of their claims against PEC and Duke Energy Corporation.

4. In 2001, PEC entered into a contract to purchase coal from Dynegy Marketing and Trade (DMT). After
DMT experienced financial difficulties, including credit ratings downgrades by certain credit reporting agencies, 'PEC requested credit enhancements in accordance with the terms of the coal purchase agreement in July 2002.. When DMT did not offer credit enhancements, as required by a provision in the contract, PEC terminated the contract in July 2002.

'28

.- 'II PEC initiated a lawsuit* seeking a declaratory judgment that" the termination'was lawful. DMT counterclaimed, stating the termination was a breach of contract. On March 23, 2004, the United States District Court for the Eastern District of North Carolina ruled that PEC was liable for breach of contract, but ruled against DMT on its unfair and deceptive trade practices claim. On April 6, 2004, the Court entered a judgment against PEC in the amount of approximately $10 million. The Court did not rule on DMT's pending motion for attorneys' fees.

-On May 4, 2004, PEC authorized its outside counsel to file a notice of appeal of the April 6, 2004,

-judgment and on May 7, 2004, the notice of appeal was filed with the United States Court of Appeals for the Fourth Circuit. On June 8, 2004, DMT filed a motion to dismiss the appeal in the appeals court on the ground that PEC's notice of appeal should have been filed on or before May 6, 2004. On June 16, 2004, PEC filed a motion with the trial court requesting an extension of the deadline for the filing of the notice of appeal. On July 7, 2004, the parties agreed to postpone the appellate proceedings to allow the trial court to resolve PEC's motion for an extension of the notice of appeal deadline.

PEC recorded a liability for the judgment of approximately $10 million and a regulatory asset for the probable recovery through its fuel adjustment clause in the first quarter of 2004. The Company cannot predict the outcome of this matter.

5. The Company, through its subsidiaries, is a majority owner in five entities and a minority owner in one entity that owns facilities that produce synthetic fuel as defined under the Internal Revenue Code (Code).

The production and sale of the synthetic fuel from these facilities qualifies for tax credits under Section 29

- if certain requirements are satisfied, including a requirement that the synthetic fuel differs significantly in

chemical composition from the coal used to produce such synthetic fuel and that the fuel was produced from a facility that was placed in service before July 1, 1998. Synthetic fuel tax credit amounts not utilized

-are carried forward indefinitely as alternative minimum tax credits. All entities have received private letter rulings (PLRs) from the Internal Revenue Service (IRS) 'with respect to their synthetic fuel operations. The PLRs do not limit the production on which synthetic fuel credits may be claimed. Total Section 29 credits generated to date (including those generated by FPC prior to -its acquisition by the Company) are approximately $1.4 billion, of.which $584 million have been used and $807 million are being carried

- forward as deferred tax credits. The current Section 29 tax credit program expires at the end of 2007.

In September 2002, all of Progress Energy's majority-owned synthetic fuel entities were accepted into the

'IR's Pre-Filing Agreement (PFA) program. The PFA program allows taxpayers to voluntarily accelerate the IRS exam process in order to seek resolution of specific issues.' Either the Company or the IRS can withdraw from the program at any time, and issues not resolved through the program may proceed to the next level of the IRS exam process.

- In July 2004, Progress Energy was notified that the Internal Revenue Service (IRS) field auditors anticipate taking an' adverse position regarding the placed-in-service date of the Company's four Earthco synthetic fuel facilities. Due to the auditors' position, the IRS has decided to exercise its right to withdraw from the Pre-Filing Agreement (PFA) program with Progress Energy. With the IRS's withdrawal from the PFA program, the review of Progress Energy's Earthco facilities is back on the normal procedural audit path of the Company's tax returns. The IRS has indicated that the field audit team will provide its written

- recommendation later this year. After the field audit team's written recommendation is received, the

Company will begin the Appeals process within the IRS. -Through June 30, 2004 the Comnpany, on a consolidated C w basis, has claimed $1 billion of tax credits generated by Earthco facilities. If these credits were disallowed, the Company's one time exposure for cash tax payments would be $229 million

..(excluding interest), and earnings and equity, would be reduced by SI billion, excluding interest. The

' Company

- believes that the ap'peals process could take up to two years to complete, however, it cannot

control the actual timing of resolution and cannot predict the outcome of this matter.

- In February 2004, subsidiaries of the Company finalized execution of the Colona Closing Agreement with

the IRS concerning their Colona synthetic fuel facilities.: The Colona Closing Agreement provided that the Colona facilities were placed in service before July 1,' 1998, which is one of the qualification requirements for tax credits under Section 29. The Colona Closing Agreement further provides that the fuel produced by

'the Colona facilities in 2001 is a "qualified fuel" for purposes of the Section 29 tax credits. This action concluded the IRS PFA program with respect to Colona:

-29

In October 2003, the United States Senate Permanent Subcommittee on Investigations began a general investigation concerning synthetic fuel tax credits claimed under Section 29. The investigation is examining the utilization of the credits, the nature of the technologies and fuels created, the use of the synthetic fuel and other aspects of Section .29 and -is niot specific to the Company's synthetic fuel operations. Progress Energy is providing information in connection with this investigation. The Company cannot predict the outcome of this matter.

In man'agement's opinion, the Company is complying with all the necessary requirements to be allowed such credits under Section 29, and, although it cannot provide certainty, it believes that it will prevail in these matters. Accordingly, the Company has no current plans to alter its synthetic fuel production*

schedule as a result of these matters. However, should the Company fail to prevail in, these matters, there could be material liability for previously, taken Section 29 credits, with'a material adverse impact on earnings and cash flows.-

6. The Company and its subsidiaries are involved in various litigation matters in the ordinary course of~

'business, some of which involve'substantial amounts. Where appropriate, accruals and disclosures have'

-been made in a cordance with SEAS No. 5, "Accounting for Contingencies," to provide for such matters.

In the opinion of management, the final disposition of pending litigation would not have a material adverse ieffect on the Company's'consolidated results of operations or financial position.

30

CAROLINA POWER & LIGHT COMPANY dfbfa PROGRESS ENERGY CAROLINAS, INC.

CONSOLIDATED INTERIM FINANCIAL STATEMENTS June 30, 2004.

~UNAUDITED CONSOLIDATED STATEMENTS of INCOME

..Three Months Ended' June 30 Six Months Ended June 30 (in millions) 2004 2003 2004 2003.

Operating Revenues

-Electric ~ S 861 S 816 S 1,762 S 1,742 Diversified business 13 16 Total Operating Revenues 862 819 1,763 1,748 Operating Expenses Fuel used in electric generation I 193 177 *. 417 -403 Purchased power ~ 80 69 142

  • 142.
  • .Operation and maintenance. . 226 210
  • 435 ...400 Depreciation and amortization 127 142 254 281 Taxes other than on income .:45  :..-35.~ 88 I79 Diversified business . -3 Total Operating Expenses 671 635 1,336 1,308 Operating Income
  • 11184 427 . 440 Other Income (Expense)

Interest income * - I* 2. 2 3

' Other, net . (8) 8) (0)

Total Other Income (Expense) 5()6) .(7)

Interest Charges

  • Interest charges . . 47 .49 96 98' Allowance fo borrowed funds used during construction - .() . (1) *. (2)

Total Interest Charges, Net *.47 48 95 96 Income before Income Tax *. ... 149 . 130 326 337.

Income Tax Expense 53' .41

  • 115 **1113.
  • NetIncome~ . 96 89 .211 224

'Preferred Stock Dividend Requirement--.I Earnings for Common Stock -S 96 $ 89 *S 210 .$ 223 See N~otes to'Con'iolidated Interim Financial Statements.

31.

CAROLINA POWVER & LIGHT COMPANY dlbla PROGRESS ENERGY CARkOLINA'S, INC.

  • UNAUDITED CONSOLIDATED BALANCE SHEETS (in millions). June30 December 31
  • ASSETS 2004 2003
  • Utility Plant Utility plant in service S 13,516. S 13.331
  • Accumulated depreciation .(5,390) (5,258)

Utility plant in service, net ,,268,073 Held forfuur ue 5 5

  • Construtction work in progress 294 306
  • Nuclear fuel, net of amortization 161 159
  • Total Utility Plant, Net 8,586 8,543 Current Assets Cash and cash equivalents *44 . .238
  • . Accounts receivable 253 .265 Unbilled accounts receivable . -146 145
  • Receivables from affiliated companies . 127
  • Inventory . . -307 .348 Deferred fuel cost 126 113 Prepayments and other current assets *57 82
  • TotalCurrentAssefts- 944 1;218

.. Deferred Debits and Other-Assets

  • Regulatory assets .506. . 477

-Nuclear decommissioning trust funds 542 505

  • .Miscellaneous other property and investments 169 .169 Other assets and deferred debits 115 118 Total Deferred Debits and Other Assets 1,332 1.269 Total Assets S 10,862 $ 11.030 CAPITALIZATION AND LIABILITIES Common Stock Equity
  • Common stock without par value, authorized 200 million shares, 160 million shares issued and outstanding S .1,971 $ 1,953 Uneamned ESOP common stock . . - .(76) (89)

Retmuained other comprehensive loss . .()(7).

Reandearnings 1,361 1,380 Total Common Stock Equity 3,252 .*3,237 Preferred Stock - Not Subject to Mandatory Redemption 59 59 Long-Term Debt, Net .. 2,748 .3.086 Total Capitalization .6,059 6,382 Current Liabilities

    • Current portion of longoterm debt .. 300 Accounts payable *181 188 payablestoaflae opn 77 136 Ntspayables to affiliated companies . - 26 25
  • interest accrued
  • 7 64 Short-term obligations 68 4 Other current liabilities *229 .*166 Total Current Liabilities .938 . 883 Deferred Credits and Other Liabilities

'Accumulated deferred income taxes 1,132 1,125

  • -Accumulated deferred investment tax cets.145 .148 Regulatory liabilities J1,262
  • 1,197 Asset retirement obligations -. 959 :932
  • Other liabilities and deferred credits * ** 367 363 Total Deferred Credits and Other Liabilties *
  • 3,865 3,765 Commitments and Contingencies (Note 10) .

Total Capitalization and Liabilities . .S 10,862 S 11,030 See Notes to Consolidated Interim Financial Statements.

.I  : .  : ,

.. 32 .-

CAROLINA PONVER & LIGHT COMPANY

-dbfaPROGRESS ENERGY CAROLINAS, INC.

  • UNAUDITEDCONSOLIDATED STATEMENTS of CASH FLOWS

-Six Months Ended June 30

. (in millions) 2004 2003.

Operating Activities Net income

  • S 211 $ 224

'Adjustments to reconcile net income to net cash provided by operating activities:

Depreciation and amortization ,.' ., 297

  • 326 Deferred income taxes .' ' 4 * (38)

Investment tax credit '(4) (5)

. . 'Deferredfuel cost (13) 9

, .Cash provided (used) by changes in operating assets and liabilities:

Accounts receivable . '. 23 35

Inventories - . 32 (1)

Prepayments and other current assets . 8 14 Accounts payable: *. (50) 2 Other current liabilities - 61 ' 58 Other . - 53 42

, Net Cash Provided by Operating Activities Investing Activities Gross'property additions (248) (259)

Nuclear fuel additions (47) (46)

Contributions to nuclear decommissioning trust (18) (18)

Other investing activities . .- .(4)

Net Cash Used In Investing Activities (313) (327)

. Financing Activities

- Net increase (decrease) in short-term obligations' 64 (74)

Net change in intercompany notes .'- .99 Retirement of long-term debt (339) .(165)

Dividends paid to parent (228) (203)

Dividends paid on preferred stock: (1) (I)

  • Net Cash Used In Financing Activities 7 ,(503) - (344)

Net Decrease in Cash and Cash Equivalents (194) (5)

--Cash and Cash Equivalents at Beginning of Period 238 18 Cash and Cash Equivalents at End of Period S 44 S 13 Supplemental Disclosures of Cash Flow Information Cash paid during the year- interest (net of amount capitalized) S 100 S .95 income taxes (net of refunds) S 82 $ 120 See Notes to Consolidated Interim' Financial Statements.

.33

CAROLINA POWVER & LIGHT COMPANY d/b/a PROGRESS ENERGY CAROLINAS, INC.

NOTES TO CONSOLIDATED INTERIM FINANCIAL STATEMENTS,!.

-1. ORGANIZATION AND BASIS OF PRESENTATION A. Organization Carolina Power' & Light Company d/b/a Progress Energy Carolinas, Inc. (PEC) is a public service corporation 'primarily engaged in the generation, transmission, distribution and sale of electricity in

- portions of North Carolina and South Carolina.' Through its wholly-owned subsidiaries, PEC is also involved in nonregulated business activities. PEC is a wholly-owned subsidiary of Progress Energy, Inc.

(the Company or Progress Energy). The Company is a registered holding company under the Public Utility Holding Company Act of 1935 (PUHCA). Both the Company and its subsidiaries are subject to the

-regulatory provisions of PUHCA. PEC is regulated by the North Carolina Utilities Commission (NCUC),'

the Public Service Commission of South Carolina (SCPSC), the Federal Energy Regulatory Commission (FERC) and the United States Nuclear Regulatory Commission (NRC).

B." - Basis of Presentation These financial statements have been prepared in accordance with accounting principles generally accepted

'in the United States of America (GAAP) for interim financial information and with the instructions to Form 10-Q and Regulation S-X. Accordingly, they do notdinclude all of the information and footnotes required by GAAP for. annual statements. Because the accompanying consolidated interim financial statements do not include all of the information and footnotes required by GAAP, they should be read in conjunction with the audited financial statements for the period ended December 31, 2003 and notes thereto included in PEC's Form 10-K for the year ended December 31, 2003.

PEC collects from customers certain excise taxes, which include gross receipts tax, franchise taxes, and' othe'r excise taxes, levied by the state or local government upon the customers. PEC accounts for excise taxes on a gross basis. For the three months ended June 30, 2004 and 2003, excise taxes of approximately

$23 million and S18 million, respectively, are included in taxes other than income in the accompanying Consolidated Statements of Income. For the six months ended June 30, 2004 and 2003, excise taxes of approximately S45 million and'$40 million, respectively, are included in taxes other than income in the accompanying Consolidated Statements of Income' These approximate amounts are also included in utility revenues.

The amounts included in the consolidated interim financial statements are unaudited but, in the opinion of management, reflect all normal recurring adjustments necessary to fairly present PEC's financial position and results'of operations for the interim periods. Due to seasonal weather variations and the timing of outages of electric generating units, especially nuclear-fueled units, the results of operations for interim periods are not necessarily indicative of amounts expected for the entire year or future periods.

In preparing financial statements that conform. with GAAP, management must' make estimates and assumptions that affect the reported amounts of assets and liabilities, disclosure of contingent assets and liabilities at the date of the financial statements and amounts of revenues and expenses reflected during the reporting period. Actual results could differ from those estimates. Certain amounts for 2003 have been

- reclassified to conform to the 2004 presentation.

-  : C. ' Stock-Based Compensation The Company measures compensation expense for stock options as the difference between the market

'price of its common stock and the exercise price of the option at the grant date. The exercise price at which options are granted by the Company equals the market price at the grant date,'and accordingly, no compensation expense has been recognized for stock option grants. For purposes of the pro forma

-disclosures required by SFAS No. 148, "Accounting for Stock-Based Compensation - Transition and Disclosure - an Amendment of FASB Statement No. 123" (SFAS No.' 148), the estimated fair value of the Company's stock options is amortized to expense over the options' vesting period. The following table illustrates the effect on net income and earnings per share if the fair value method had been applied to all outstanding and unvested awards in each period:

34

y.s

-Three Months Ended Six Months Ended June 30 June 30

  • (in millions). 2004 2003 2004 2003 Net Income, as reported . 96 S 89 S 211 S 224
  • Deduct: Total stock option expense determined under fair value method for all awards, net of related tax effects 2 14 2 Pro forma net income S 94 S 88 5 207, 5222 D. Consolidation of Variable Interest Entities PEG consolidates all voting interest entities in which it owns a majority voting interest and all variable
  • interest entities for which it is the primary beneficiary in accordance with FASB Interpretation No. 46R, "Consolidation of Variable Interest Entities - an Interpretation of ARB No. 51" (FIN No. 46R). During the first six months of 2004 and 2003, PEG did not participate in the creation of, or obtain a significant new variable interest in, any variable interest entity.

PEG is te primary beneficiary of ahelimited partnership which invests in 17 low-income housing partnerships~ that qualify for federal 'and state tax credits. PEG has requested but has not received all the necessary information'to determine the primary beneficiary of the limited pitrtnership's underlying 17 partnership investments, and has applied the information scope exception in FIN No. 46R, paragraph 4(g) to the 17 partnerships. PEG has no direct exposure to loss from the 17 partnerships; PEG's only exposure to lo'Ss is from its investment of approximately Si million in the consolidated limited partnership.' PEG will continue its efforts to obtain the necessary information to fully apply FIN No. 46R to the 17 p artnerships.

PEG believ'es that if the lirmited partnership is determined to be the primary beneficiary of the 17 partnerships, the effect of consolidating the 17 p~artnerships would not be significant to PEG's Consolidated Balance Sheets.-

PEG has variable interests in'two power plants resulting from long-term power purchase'contracts. PEG has requested the necessary information to' determine if the counterparties'are variable interest entities or to identify the primary beneficiaries. Both entities'declined to provide PEG with the necessary financial information, and PEC has'applied the information scope exception in FIN No. 46R, paragraph 4(g). PEG's

  • only significant exposure to variability from these contracts results from fluctuations in the market price 6f fuel used by the two entities' plants to produce the power purchased by PEG. PEG is able to recover these fuel costs under its fuel clause. Total purchases from these couinterparties were approximately $21 million and $19 rrllio ithfissimohsf204and 2003, respectiVely. PEG will continue its efforts to obtain the necessary information to fully apply FIN No. 46R to these contracts. The combined generation
  • capacity of the two entities' power plants is approximately 880 MW. PEG believes that if it is determined tbethe primary beneficiary of these two entities, the effect of consolidating the entities would result in

-increases to total assets, long-term debt and other liabilities, but would have an insignificant or no impact on PEG's 'comnmon stock equity, net earnings, or cash flows. However, as PEG has not received any finanicial information from these two counterparties, the impact cannot be'determined at this time.

PElohsinterests in several other variable interest entities -for which PEG is not theprmy beneficiary. These arrangements include investments in approximately.,22. limited partnerships, limited

'liability corporations and venture capital funds and two building leases with special-purpose entities. The

  • aggregae maximum loss exposure at June 30, 2004, that PEG could be required to record in its income
  • statement as a result' of these arrangements totals. approximately $23 million. The creditors of these variable interest entities do not have recourse to-.the general credit of PEC in excess of .the aggregate maximum loss exposure.

-35.

2. NEW ACCOUNTING STANDARDS In December 2003, the Medicare Prescription Drug, Improvement and Modernization Act of 2003 (the Act) was signed into law. In accordance with guidance issued by the FASB in FASB Staff Position FAS 106-1, PEC elected to defer accounting for the effects of the Act due to uncertainties regarding the effects of the implementation of the Act and the accounting for certain provisions of the Act. Therefore, OPEB information presented in the financial statements does not reflect the effects of the Act. -The FASB recently issued definitive accounting guidance for the Act in FASB Staff Position'106-2, which is effective

. .I for PEC in the third quarter of 2004. FASB Staff Position 106-2 will result in the recognition of lower OPEB costs to reflect prescription drug-related federal subsidies to be received under the Act. PEC is in the process of quantifying the impact of the Act on OPEB costs.

3. REGULATORY MATTERS

- :A. Retail Rate Matters PEC has'exclusively utilized external funding for its decommissioning liability since 1994. Prior to 1994,

' PEC retained funds internally to meet its decommissioning liability. An NCUC order issued in February 2004 found that by January 1, 2008 PEC must begin transitioning these'amounts to external funds. The transition of $131 million must be completed by December 31, 2017, and at least 10% must be transitioned each year. '

PEC filed with the SCPSC seeking permission to defer expenses incurred from the first quarter 2004 winter storm. The SCPSC approved PEC's request to defer the costs and amortize them ratably over five years beginning in January 2005. Approximately $10 million related to storm costs incurred during the first quarter of 2004 was'deferred in that quarter.

During the first quarter of 2004, PEC met the 'requirements of both the NCUC and the SCPSC for the implementation of a depreciation study which allowed'the utility to reduce the rates used to calculate depreciation expense. As a result, depreciation expense decreased $10 million for the three months ended June 30, 2004 compared to the prior year quarter and decreased $18 million for the six months ended June 30, 2004 compared to the prior year six month period.

B. 'Regional Transmission Organizations In 2000, the FERC issued Order No. 2000 on RTOs, which set minimum characteristics and functions that RTOs must meet, including independent transmission service. In July 2002, the FERC issued its Notice of Proposed Rulemaking in Docket No. RMOI-12-000, Remedying Undue Discrimination through Open

'Access Transmission Service and Standard Electricity Market Design (SMD NOPR). If adopted as proposed, the rules set forth in the SMI) NOPR would materially alter the manner in which transmission and generation services are provided and paid for. In 'April 2003, the FERC released a White Paper on the Wholesale Market Platform. The White Paper provides an' overview of what the FERC currently intends to include in a final rule in the SMD NOPR docket. The White Paper retains the fundamental and most protested aspects of SMD NOPR, including mandatory RTOs and the FERC's assertion ofjurisdiction over

'certain aspects of retail service. The FERC has not yet issued a final rule on SMD NOPR. PEC cannot predict the outcome of these matters or the effect that they may have on. the GridSouth proceedings currently ongoing before the FERC. It is unknown what impact the future proceedings will have on PEC's earnings, revenues or prices.

PEC has $33 million invested in' GridSouth related to startup costs at June 30, 2004. PEC expects to recover these startup costs in conjunction with the GridSouth original structure 'or in conjunction with any alternate combined transmission structures that emerge. - '

' 'C.'-- Implementation of SFAS No. 143
C  : . . MP . .. No-:: 143 - . -

'In connection with the implementation of SFAS No. 143 in 2003, PEC filed a request with the NCUC requesting deferral of the difference between expense pursuant to SFAS No. 143 and expense as previously determined by the NCUC. The NCUC granted the deferral of the January 1, 2003 cumulative adjustment.

Because the clean air legislation discussed in Note 12 under "Air Quality" contained a prohibition against

'cost'deferrals unless certain criteria are met, the NCUC denied the deferral of the ongoing effects. Since 36  ;

the NCUC order denied deferral of the ongoing effects, PEC ceased deferral of the ongoing effects during the second quarter for'th6 six months ended June 30, 2003 related to its North Carolina retail jurisdiction.

Pre-tax income for the three and six months ended June 30, 2003 increased by approximately $14 million, which represents a decrease in'non-ARO cost of removal expense, partially offset by an increase in decommissioning expense. '. The Company provided' additional information to the NCUC that demonstrated that deferral of the ongoing effects should also be allowed; In August of 2003, the NCUC revised its decision and approved the deferral of the ongoing effects of SFAS No. 143 at which time the

$14 million was reversed.

D. FERC Market Power Mitigation A FERC order issued in November 2001 on certain unaffiliated utilities' triennial market based wholesale power rate authorization updates required certain mitigation actions that those utilities would need to take for sales/purchases within their control areas and required those utilities to post information on their websites regarding their power systems' status. As a result of a request for rehearing filed by certain market participants, FERC issued an order delaying the effective date of the mitigation'plan until after a planned technical conference on market power determination. In December 2003, the FERC issued a staff paper

' '-discussing alternatives and held a technical conference in January 2004. In April 2004, the FERC issued two orders concerning utilities' ability to sell wholesale electricity at market based rates. In the first order, the FERC adopted two new interim screens for assessing potential generation market power of applicants for wholesale market based rates, and described additional analyses and mitigation measures that could be presented if an applicant does not pass one of these interim screens. In July 2004, the FERC issued an order on rehearing affirming its conclusions in the April order. In the second order, the FERC initiated a rulemaking to consider whether the FERC's current methodology for determining whether a public utility should be allowed to sell wholesale electricity at market-based rates should be modified in any way.'

Management is unable to predict the outcome of these actions by the FERC or their effect on future results of operations and cash flows. However, PEC does not anticipate that its current operations would be impacted materially if they were unable to sell power at market-based rates in their respective control areas.

4. COMPREHENSIVE INCOME Comprehensive income for the three months ended June 30, 2004 and 2003 was $98 million and $88

' million, respectively.- Comprehensive income for the six months ended June 30, 2004 and 2003 was $214 million and S223 million, respectively. Changes in :other comprehensive income for the periods consisted primarily of changes in fair value of derivatives used to hedge cash flows related to interest on long-term debt.

5. FINANCING ACTIVITIES On July 28, 2004, PEC extended its $165 million 364-day line of credit, which was to expire on July 29, 2004. The line of credit will expire on July 27,2005.

On April 30, 2004, PEC redeemed $34.7 million of Darlington County 6.6% Series Pollution Control Bonds at 102.5% of par, $1.795 million of New Hanover County 6.3% Series Pollution Control Bonds at

.101.5% of par, and $2.58 million of Chatham County 6.3% Series Pollution Control Bonds at 101.5% of par with cash from operations.-

On January 15, 2004, PEC paid at maturity $150 million 5.875% First Mortgage Bonds with commercial paper proceeds. On April 15, 2004, PEC also paid at maturity S150 million 7.875% First Mortgage Bonds with commercial paper proceeds and cash from operations.

6. BENEFIT PLANS  : ' - '- '. ' '  ::

PEC has a non-contributory -defined benefit retirement (pension) plan for substantially all full-time

- employees. PEC also has supplementary defined benefit pension plans'that provide benefits to higher-level

- : employees.* In addition to pension benefits, PEC provides contributory other postretirement benefits (OPEB), including certain health care and life insurance benefits, for retired employees who meet 'specified criteria. The components of the net periodic benefit cost for the three and six months ended June 30 are:

.. 37.-

Other Postretirement Three Months Ended June 30 Perision Benefits Benefits

- (in millions) 2004 2003 2004 2003 Service cost $ 6' S 5 '.$ 2 $. 2 Interest cost 13 12 .4 3 Expected return on plan assets (17) (16) . (1) (1)

Amortization, net 1 1 Net periodic cost .:' $ 2. $ 1 S 6 S 5

  • Other Postretirement Six Months Ended June 30 Pension Benefits . Benefits (in millions) 2004 2003
  • 2004 2003 Service cost . '. 12 $ 11 $ 4 S 3 Interest cost '  : *26-' (342. .  : 8 7 Expected return on plan assets .(34) .. (33) (2) (1)

-Amortization, net

  • 1 2 . 2 .

Net periodic cost *$ 5 S .2 S 12 S 11 7.- RISK MANAGEMENT ACTIVITIES AND DERIVATIVE TRANSACTIONS PEC uses interest rate derivative instruments to adjust the fixed and variable rate debt components of its

'debt portfolio and to hedge interest rates with regard to future fixed rate debt issuances.

As of June 30, 2004, PEC had $70 million notional of pay fixed forward starting swaps, entered into in March 2004, to hedge its exposure to interest rates with regard to a future issuance of debt and S26 million notional of pay fixed forward starting swaps, entered into in April 2004, to hedge its exposure to interest rates with regard to an upcoming railcar lease. In July 2004, PEC entered into an additional $30 million notional pay fixed forward swap, increasing the total notional of pay fixed forward starting swaps to 5126 million. These agreements have a computational period of ten years.

.The notional amounts of the' above contracts are not exchanged and do not represent exposure to credit loss. In the event of default by a counterparty, the risk 'in the transaction is the cost of replacing the

-agreements at current market rates. PEC only enters into interest rate derivative agreements with banks with credit ratings of single A or better..

  • . FNANCTAT. TIORMATION RY BTUSINESS 5SEGTMFNT.-

PEC's 'operations consist primarily of the PEC Electric segment which 'is engaged in the' generation, transmission, distribution and sale of electric energy primarily in portions of-North Carolina and South Carolina. These electric operations are subject to the rules'and regulations of the FERC, the NCUC, the

'SCPSC and the NRC. PEC Electric also distributes and sells electricity to other utilities, primarily on the east coast of the United States.

'The Other segment, whose operations are primarily in the United States, is made up of other nonregulated business areas that do not separately meet the disclosure requirements of SFAS No. 131, "Disclosures about Segments of an Enterprise and Related Information" and consolidation entities and eliminations.

The financial information for PEC segments for the three and six months ended June 30, 2004 and 2003 is as follows: ' . . .

  • .ThreeMonths Ended June 30 ...' .2004 2003 PEC . PECG (in millions) Electric Other . Total Electric Other Total.

Total revenues ' . S 86 I ' S I S 862 : S 816.

S- ' 3 S 819 Earnings available for common . 97 . (1) 96 .. ' 89 89

  • 38 . ' .

. . .I .. . 4 Six Months Ended June 30 2004 2003

'EC

  • PEC (in millions) ectric Other ' Total Electric Other Total

'Total revenues : - S .1,762 S 1 S 1,763 S 1,742 S 6. S 1,748 Earnings available '

for common .2. .: - 21 .. . (3 (3) 210 223 223

9. ' OTHER INCOME AND OTHER EXPENSE Other income and expense'includes interest income and other income and expense items as discussed.

below. The components of other, net as shown on the accompanying'Consolidated Statements of Income for the three and six months ended June 30 are as follows:

.U . .t. . . . 1 June 30 June 30

.(in millions) '2004 2003 2004 - 2003

'Other income

- Net financial trading gain (loss) ' ' - S 4 . S 'S 5 . 5 (1)

Nonregulated energy and delivery services income 2 ' 2 . 4 4 Investment gains - ' . 2 - -

' : AFUDC equity . I 1 2 Other .. - 4 3 .4

':.-Total other income - . ': $9 S 7 .S 14 $ 9

- Other expense Nonregulated energy and delivery services expenses S 2 . S 2 5$4 $ 4

- Donations -. ': I ' I 5 - . 3 Investment losses - 9 8 Write-off of non-tradc receivable  : 7 Other 2 3 6 4 Totalotherexpense ' S 5 S 15 S 22 $ 19

. Other, net ' $ 4. S (8) - S (8) S (10)

Net financial trading gains' ard losses represent non-asset-backed trades 'of electricity and tgas.

Nonregulated energy and 'delivery services include power protection services and mass market programs such as surge protection, appliance services and area light sales, and delivery; transmission and substation

work for other utilities.' - -' ' --

1IID. COMhlTMENTS AND CONTINGENCIES Contingencies and significant changes to the commitments discussed in Note 16 of the Company's 2003 Annual Report on Form 10 K are described below. .  :

A.' Guarantees" As a part of normal business, PEC enters into various agreements providing financial or performance assurances to third parties. Such agreements include guarantees, standby letters of credit and surety bonds.

These agreements are entered into'prinarily to support or enhance the creditworthiness otherwise attributed to PEC and subsidiaries on a stand-alone basis, thereby facilitating the extension of sufficient credit to accomplish PEC and the subsidiaries' intended commercial purposes. Guarantees at June 30, 2004, are summarized in the table and discussed in the subsequent paragraphs. '

At June 30, 2004, outstanding guarantees consisted of the following (in millions)

- Standbv lpttprs'ofcrednit -: ' 3  :. -

Surety bonds ' -

18'

' Total I ' : -' - - $21

": '39

I I. -

Standby Letters of Credit '

Financial institutions have issued standby letters of credit to financial institutions for PEC and certain subsidiaries for the benefit of third parties that have extended credit to PEC and certain subsidiaries. As of June 30, 2004, PEC and certain subsidiaries have' outstanding letters of credit totaling S3 million. These letters of credit have been issued primarily for the purpose of 'securing performance under contracts and supporting'payments on interest payments on outstanding debt obligations and self insurance for workers compensation. If PEC or a subsidiary does not pay amounts when due under a covered contract, the counterparty may present its claim for payment to the financial institution, which will in turn request payment from PEC. Any amounts owed by its subsidiaries are reflected in the PEC Consolidated Balance*

Sheets.

Surety Bonds At June 30, 2004, PEC had $18 million in surety bonds purchased primarily for purposes such as providing workers'. compensation coverage and obtaining licenses, permits' and rights-of-way. To the extent liabilities are incurred as a result of the activities covered by the surety bonds, such liabilities are included in the Consolidated Balance Sheets.

Gurainntees, Issu'ed hv the Parent In 2003, PEC determined that its external funding levels did not fully meet the nuclear decommissioning financial assurance levels required by the NRC. Therefore, PEC obtained parent company guarantees of

$276 million to meet the required levels.' On May 12, 2004 PEC sent notice to the NRC that due to the Renewed Facility Operating License for Robinson 2, the parent guarantee related to'Robinson, would be cancelled as of June 30, 2004. As a result, the total parent guarantees for decommissioning decreased from

$276 million to S 81 million during the second quarter.

B.': Insurance PEC is insured against public liability for a nuclear incident up to $10.76 billion per occurrence. Under the current provisions of the Price Anderson Act, which limits liability for accidents at nuclear plants, PEC, as an owner of nuclear units, can be assessed a portion of any third-party liability claims arising from an

accident at any commercial nuclear power plant in the United States. In the event that public liability claims from an insured nuclear incident exceed $300 million (currently available through commercial insurers), PEC would be subject to assessments of up to $101 million for each reactor owned per occurrence.. Payment of such assessments would be made over time as necessary to limit the payment in any one year to no more than $10 million per reactor owned. Congress is considering revisions to the Price Anderson Act during 2004 that could include increased limits and assessments per reactor owned. The final outcome of this matter cannot be predicted at this time.

- PE sefinue its trnmiso an ditibto lie agans los du to str daag an. teaua

-PEC self-iinsures its transmission and distribution lines against loss due to storm damage and other natural disasters.

C. Claims and Uncertainties

. . m-PEC is subject to federal, state and local regulations addressing hazardous and solid waste management, air and water quality and other environmental matters.

. I a I

.:  :- '  : 40

__-.7.,

Hazardous and Solid Waste Management

-Various organic materials associated with the'production of manufactured gas, generally referred to as coal tar, are regulated under federal and state laws. 'The principal regulatory agency that is responsible for a specific former manufactured gas plant (MGP) site depends'largely upon the state in which the site is

'located. There are several MGP sites to which PEC has some connection. In this regard, PEC and other potentially responsible parties (PRPs) are participating in, investigating and, if necessary, remediating former MGP sites with several regulatory agencies, including, but not limited to, the U.S. Environmental

-Protection Agency. (EPA) and the North Carolina Department of Environment and Natural Resources, Division of Waste Management (DWM)." In addition, PEC is periodically notified by regulators such as the EPA and various state agencies of its involvement or potential involvement in sites, other than MGP sites, that may require investigation and/or remediation.

PEC has filed claims with its general liability insurance carriers to recover costs arising out of actual or potential environmental liabilities. All claims have been settled other. than with insolvent carriers. These settlements have not had a material effect on the consolidated financial position or results of operations.

PEG isalso currently in the process of assessing potential'costs and exposures at other environmentally impaired sites. As the assessments are' developed and analyzed, PEC will accrue costs for the sites to the extent the costs are probable and can be reasonably estimated.

There are nine former MGP sites and other sites associated with PEC that have required or are anticipated to require investigation and/or remediation -costs. PEC received insurance proceeds 'to address costs associated with PEC environmental liabilities related to its involvement with some sites. All eligible

' expenses related to these are charged against a specific fund containing these proceeds. At June 30, 2004,:

'approximately $8 million remains in this centralized fund with a related accrual of S8 million recorded for the associated expenses of environmental issues. PEC is unable to provide an estimate of the reasonably.

possible total remediation costs beyond what is currently accrued due to the fact that inivestigations have not been completed at all sites.' This accrual has been recorded on an undiscounted'basis. PEC measures its liability for these sites based on available evidence, including its experience in investigating' and remediating environmentally impaired sites." The process often involves assessing and developing cost-sharing arrangements with other. PRPs. PEC will accrue costs 'for the sites to the extent its liability is probable and the costs can be reasonably estimated. Presently, PEC cannot determine the total costs that may be incurred in connection with the remediation' of all sites.

In September 2003, the Cornpany sold NCNG to Piedmont Natural Gas Company, Inc. As part of the sales

'agreement, the Company retained responsibility to' remediate five former NCNG MGP sites, all of which

also are associated with PEC, to state standards pursuant to an Administrative Order on Consent. These sites are anticipated to have 'investigation orf rem'ediation costs associated with them. NCNG had previously accrued approximately $2 million for probable and reasonably estimable remediation costs at

-these sites.' These accruals have been recorded on'an undiscounted basis. At the time of the sale, the

liability for these costs and the related accrual was transferred to PEC. PEC does not believe it can provide an estimate of the reasonably possible total 'remediation costs beyond the accrual because investigations have not been completed at all sites. Therefore, PEC cannot currently determine the total costs that may be incurred in connection with the investigation and/or remediation of all sites.'

Air Quality There has been and may be further proposed legislation requiring reductions in air emissions for NOx,

'S02, carbon dioxide and mercury. Some of these proposals establish nationwide caps and emission rates

-over an extended period of time.' This national multi-pollutant approach to air pollution control could involve significant capital costs which'could be material to PEC's consolidated financial position or results of operations. Control equipment that will be installed on North Carolina fossil generating facilities as part of the North' Carolina 'legislation.'discussed below may address some of the issues outlined above.

However, PEC cannot predict the outcome of this matter. ' '

The EPA is conducting'an enforcement initiative related to a number of coal-fired utility power plants in an effort to determine whether modifications at those facilities were subject to New Source Review requirements or New Source Performance Standards under the Clean Air Act. -PEC was asked to provide information to the EPA as part of this initiative and cooperated in providing the requested information.

The EPA initiated civil enforcement actions against other unaffiliated utilities as part of this initiative.

41

iiltedin setlent agreem Some of these actions resulted in settlement agreements calling for expenditures by' these unaffiliated utilities, ranging frorm $1:0 'billion to $1.4 billion. A utility thatfwas not subject to a civil enforcement action settled its New Source Review issues with the EPA for S300 million. These settlement agreements have generally called for expenditures to be made over extended time periods, and some of the companies may seek recovery of the related cost through rate adjustments or similar mechanisms. PEC cannot predict the outcome of this matter .

In 2003, the EPA published a final rule addressing routine equipment replacement under the New Source Review program. The rule defines routine equipment'replacement and the types of activities that are not subject to New Source Review requirements or New Source Performance Standards under the Clean Air Act. The rule was challenged in the Federal Appeals Court and its implementation stayed. In July 2004, the EPA announced it will reconsider certain issues arising from the final routine equipment replacement rule. Reconsideration does not impact the court-approved stay. The agency plans to issue a final decision on these reconsidered issues by year's end. PEC cannot predict the outcome of this matter.

In 1998,' the EPA published a final'rule at Section 110 of the Clean Air Act addressing the regional

- transport of ozone (NOx SIP Call). The EPA's rule requires 23 jurisdictions, including North Carolina and

' South Carolina, to further reduce NOx emissions in order to attain a preset emission level during each year's "ozone season,".beginning May 31, 2004. PEC is currently installing controls necessary to comply with the rule'and, with the use of early action credits, expects to be in compliance as required by the final rule. Total capital expenditures to meet these measures' in North and South Carolina could reach approximately $370 million, which has not been adjusted for inflation. PEC has spent approximately $265

- million

to date related to these expenditures. Increased operation and maintenance costs relating to the

'NOx SIP Call are not expected to be material to PEC's results of operations. Further controls are anticipated as electricity demand increases. '

In 1997, the EPA issued final regulations establishing a new 8-hour ozone standard. In 1999, the District of Columbia Circuit Court of Appeals ruled against the EPA with regard to the federal 8-hour ozone

- standard. The U.S. Supreme Court has upheld, in part, the District of Columbia Circuit Court of Appeals decision. In April 2004, the EPA identified areas that do not meet the standard. The states with identified areas, including North and South Carolina are proceeding with the implementation of the federal 8-hour

'- ' ozone standard . Both states promulgated final regulations, which will require PEC to install NOx controls under the states' 8-hour standard. The costs of those controls are included in the $370'million cost estimate above. However, further technical analysis and rulemaking may result in a requirement for additional controls at some units.JPEC cannot predict the outcome of this matter.

In June 2002, legislation was enacted in North Carolina requiring the state's electric utilities to reduce the emissions of NOx and S02 from coal-fired power plants. PEC expects its capital costs to meet these emission targets will be approximately $813 million by 2013.- PEC has expended approximately $45 million of these capital costs through June 30, 2004. PEC currently has approximately 5,100 MW of coal-fired generation capacity in North Carolina that is affected by this legislation. The law requires the emissions reductions to be completed in phases by 2013, and applies to each utility's total system rather than setting requirements for individual power plants. The law also freezes the utilities' base rates for five years unless there' are extraordinary events beyond the control of the utilities or unless the utilities

-persistently earn a return substantially in excess of the rate of return established and found reasonable by*

the NCUC in the utilities' last general rate case. Further, the law allows the utilities to recover from their retail customers the projected capital costs during the first seven years of the ten-year compliance period beginning on January .1, 2003. The utilities must recover at least 70% of their projected capital costs

'during the five-year rate freeze period. PEC recognized amortization of$ 15 million and $34 millioii in the quarters ended June 30, 2004 and 2003, respectively. PEC recognized amortization of $31 million and $54 million in the six months ended June 30, 2004 and 2003,'respectively. Pursuant to the law, PEC entered into an agreement with the state of North Carolina to transfer to the state certain NOx and S02 emissions

' -- allowances that result from compliance with the collective NOx and S02 emissions limitations set out in the law. The law also requires the state to undertake a study of mercury and carbon dioxide emissions in North Carolina. Operation and maintenance costs will increase due to the additional personnel, materials and general maintenance associated 'with the equipment." Operation and maintenance expenses are recoverable through base rates, rather than as part of this program. PEC cannot predict the future regulatory interpretation, implementation or impact of this law.

- 42

In 1997, the EPA's Mercury Study'Report and Utility Report to Congress conveyed that mercury is not a risk to the average American and expressed uncertainty about whether reductions in mercury emissions from coal-fired power planits would reduce human exposure. Neveriheless, the EPA determined in 2000 that regulation of mercury emissions from coal-fired power'plants was appropriate. In 2003, the EPA proposed alternative control plans that would limit mercury emissions from coal-fired power plants. The first, a Maximum Achievable Control Technology (MACT) standard applicable to every. coal-fired plant,

would require compliance in 2008. The second, which the EPA has stated it prefers, is a mercury cap and

-trade program that would require limits to be met ir'two phases, 2010 and 2018. The EPA expects to

-finalize the mercury rule in March 2005. Achieving compliance' with the proposal could involve significant capital costs which could be material'to PEC's consolidated financial position or results of operations. PEC cannot predict the outcome of this matter.

In conjunction with the proposed mercury rule, the EPA proposed'a MACT standard to regulate nickel emissions from residual oil-fired units. The agency estimates the proposal will reduce national nickel

-emissions to approximately 103 tons. The EPA expects to finalize the nickel rule in March 2005. PEC cannot predict the outcome of this 'matter..

- In December 2003, the EPA released its proposed Interstate Air Quality Rule, currently referred to as the Clean Air Interstate Rule (CAIR). The EPA's proposal requires 28 jurisdictions, including North Carolina, South Carolina, Georgia and Florida, to further reduce NOx and S02 emissions in order to attain preset NOx and SO2'emissions levels. The rule is-expected to become final in 2004. The air quality'

'- state controls already installed for compliance with the NOx SIP Call and currently planned by PEC for compliance with the North Carolina law will reduce the costs required to meet the CAIR requirements for

- PEC's North Carolina units. Additional compliance costs will be determined later this year once the rule is finalized.

In March 2004, the North Carolina Attorney General filed a petition with the EPA under Section 126 of the i ' 'Clean Air Act, asking the federal government to force coal-fired power plants in thirteen other states, including South Carolina, to reduce their NOx and S02 emissions. The state of North Carolina contends these out-of-state polluters are interfering with North Carolina's ability to meet national air quality standards for ozone and particulate matter. The EPA has not made a determination on the Section 126 petition, and PEC cannot predict the outcome of this matter.

Water Quality " .

As a result of the operation of certain control equipment needed to address the air quality issues outlined above, new wastewater streams may be generated at the applicable facilities. Integration of these new wastewater streams into the existing wastewater treatment processes may result in permitting, construction and requirements imposed on PEC in the immediate and extended future.'

- 'After many years of litigation and settlement negotiations the EPA adopted regulations in February 2004 for the implementation of Section 316(b) of the Clean Water Act. These regulations will become effective

' ' September 7, 2004. The purpose of these regulations is to minimize adverse environmental impacts caused by cooling water intake structures and intake systems. Over the next several years these regulations will

- impact the larger base load generation facilities and may require the facilities to mitigate the effects to aquatic organisms by constructing intake modifications or undertaking other restorative activities.

Substantial costs could be incurred by the'facilities in order to comply with the new regulation. PEC cannot predict the outcome and impacts to the facilities at this time.

-~ ' -Other Environmental Matters ' -

' The Kyoto Protocol was adopted in 1997 by the United Nations to address global climate change'by

  • reducing emissions of carbon dioxide and other greenhouse gases. The United States has not adopted the Kyoto Protocol, however, a number of carbon dioxide emissions control proposals have been advanced in

-' Congress and by .the Bush administration. The Bush administration has stated it favors voluntary programs.. Reductions in carbon dioxide emissions to the levels specified by the Kyoto Protocol and some legislative proposals could be materially adverse to PEC's consolidated financial position or results of operations if associated costs cannot be recovered from customers. iPEC favors the voluntary program approach recommended by the administration and is evaluating options for the reduction, avoidance, and sequestration of greenhouse gases. However, PEC cannot predict the outc&ne of this matter.

43 :

  • ) j Other Contingencies
1. As required under the' Niuclea'r Waste Policy Act of 1982, PEC enitered into a contract with the DOE under which the DOE agreed to begin taking spent nuclear fuel by no later than January 31, 1998. All similarly situated utilities were required to sign the same standard contract.

In 1995, the DOE issued a final interpretation that it did not have an unconditional obligation to take spent nuclear fuel by January 31, 1998. In Indiana Michigan Power v. DOE.'the Court of Appeals vacated the DOE's final interpretation and ruled that the DOE had an unconditional obligation to begin taking spent nuclear fuel. The Court did not specify a remedy because the DOE was not yet in default.

After the DOE failed to comply with the decision in Indiana Michigan Power v. DOE, a group of utilities petitioned the Court of Appeals in Northern States Power (NSP) v. DOE, seeking an order requiring the DOE to begin taking spent nuclear fuel by January 31, 1998. The DOE took the position that its delay was unavoidable, and the DOE was excused from performance under the terms and conditions of the contract.

The Court of Appeals found that the delay was not unavoidable, but did not order the DOE to begin taking spent nuclear fuel, stating that the utilities had a potentially adequate remedy by filing a claim for damages under the contract.'-

After the DOE failed to begin taking spent nuclear fuel by January 31, 1998, a group of utilities filed a

motion with the Court of Appeals to enforce the mandate in NSP v. DOE. Specifically, this group of utilities asked the Court to permit the utilities to escrow their waste fee payments, to order the DOE not to use the waste fund to pay damages to the utilities, and to order the DOE to establish a schedule for disposal of spent nuclear fuel. - The Court denied this motion based-primarily on the grounds that a review of the matter was premature, and that some of the requested remedies fell outside of the mandate in NSP v. DOE.

Subsequently, a number of utilities each filed an action for dama'ges in the Federal Court of Claims. The

- U.S. Circuit Court of Appeals (Federal Circuit) ruled that utilities may sue the DOE for damages in' the Federal Court of Claims instead of having to file an administrative claim with DOE.

In January 2004, PEC filed a complaint with the DOE claiming that the DOE breached the'Standard Contract for Disposal of Spent Nuclear Fuel by failing to accept spent nuclear fuel from various Progress Energy facilities on or before January 31, 1998. Damages due to DOE's breach will likely exceed $100

- million. Similar suits have been initiated by over two dozen other utilities. '

In July 2002,-Congress passed an override resolution to Nevada's veto of DOE's proposal to'locate a

- permanent underground nuclear waste storage facility at Yucca Mountain, Nevada. DOE plans to submit a license application for the Yucca Mountain facility by the end of 2004. In November 2003, Congressional negotiators approved S580 million for fiscal year 2004 for the Yucca Mountain project, $123 million more

.'than the previous year. In January. 2003, the State of Nevada, Clark County, Nevada, and the City of Las Vegas petitioned the U.S. Court of Appeals for the District of Columbia Circuit for review of the

Congressional override resolution. On July 9, 2004, the Court rejected the challenge to the constitutionality of the resolution approving Yucca Mountain, but ruled that the EPA was wrong to set a

-10,000-year compliance period. The DOE continues to state it plans to begin operation of the repository at Yucca Mountain in 2010. PEC cannot predict the outcome of this matter.

With certain modifications and additional approval by the NRC including the installation of onsite dry storage facilities at Robinson (2005) and Brunswick (2010), PEC's spent nuclear fuel storage facilities will be sufficient to provide storage space for spent fuel generated on its system through the expiration of the

operating licenses for all of its nuclear generating units. '
2. In August 2003, PEC was served as a co-defendant in a purported class action lawsuit styled as Collins
v. Duke Energy Corporation et al, in South Carolina's Circuit Court ofCommon Pleas for the Fifth Judicial

- Circuit. PEC is one of three electric utilities operating in South Carolina named in'the suit. The plaintiffs

- are seeking damages for the alleged improper use of electric easements but have not asserted a dollar amount for their damage claims. The complaint alleges that the licensing of attachments on electric utility

' poles, towers and other structures to non-utility third parties or telecommunication companies for other

-than the electric utilities' internal use along the electric right-of-way constitutes a trespass.

-
44

In September 2003, PEC filed a motion to dismiss all counts of the complaint oii substantive and procedural grounds. In October 2003, the plaintiffs filed a motion to amnend their complaint. PEC believes the amended complaint asserts the same factual allegations as are in te originalcmaitndlssek money damages and. injunctive relief. In November 2003, PEG filed a motion to dismiss the plaintiffs' first amended complaint. In March 2004, the plaintiffs in this case filed a notice of dismissal without prejudice

  • .oftheir claimnsagainst PEG and Duke En~ergy Corporation.
  • 3. -In 2001, PEG entered iinto a contract to purchase coal from Dynegy Marketing and Trade (DMT).. After
  • DMT experienced financial difficulties, including' credit ratings downgrades by certain credit reporting
  • .agencies, PEG requested credit enhancements in accordancew",ith the terms of the coal purchase agreement.

in July 2002.! When DMT did not offer credit'enhancements, as required by a provision in the contract, PEG terminaited the contract in July 2002.

PEG initiated a -lawsuit seeking a :declaratory judgment that the termiination was lawful. DMT

  • counterclaimed, stating the termination was a breach of contract. On March 23, 2004, the United States District Court for the Eastern District of North Carolina ruled that PEG was liable for breach of contract, but ruled against DMT on its unfair. and deceptive trade practices 'claim' On April 6, 2004, the Court entered a judgment against PEG in the amount of approximately $10 million. The Court did not rule on

.DMT's pending motion for attorneys' fees.

On May 4, 2004, PEG authorized its outside counsel to file a notice of appeal of the April 6, 2004 judgment and on May 7, 2004, the notice of appeal was filed with the United States Court of Appeals for~

the Fourth Circuit. On June 8, 2004 DMT filed a motion to dismiss the appeal in the appeals court on the ground that PEG's notice of appeal should have been filed on or before May 6, 2004. OnJne16204 PEG filed a mbtion'with the trial court requesting an 'extension of the deadline for the filing of the notice of appeal. On July 7, 2004, the parties agreed to postpone the appellate proceedings to'allow the trial court to

  • .~resolve PEC's motion for an extension of the notice of appeal deadline.

-PEG recorded a liability of approximately $10 million for the judgment and a regulatory'asset for the

  • probable recovery through its fuel adjustment clause in the first quarter of 2004:' PEG cannot predict the outcome of this matter. * .
  • 4. 'PEG and its subsidaries are involved in various litigation matters in the ordinary course of business, some of which involve substantial amounts. *Where appropriate, accruals have been made in accordance' with :SFAS No. .**5, "Acicounting 'for Contingenicies," to provide for such' matters. In the opinion of management, the final disposition of pending litigation would not have a material adverse effect on PEG's consolidated results of operations or financial position.*.
  • 45:

Item 2. Manazement's Discussion and Analysis of Financial Condition and Results of Operations The following Management's Discussion and Analysis contains forward-looking statements that involve estimates, projections, goals, forecasts, assumptions, risks and uncertainties that could cause actual results or outcomes to differ materially from those expressed in the forward-looking statements. Many, but not all of the factors that may impact actual results are discussed in the Risk Factors sections of Progress Energy's and PEC's annual report on Form 10-K for the year ended December 31, 2003, which were filed with the SEC on March 12,.2004. Please review "SAFE HARBOR FOR FORWARD-LOOKING STATEMENTS" for a discussion of the factors that may impact any such forward-looking statements made herein.

Amounts reported in the interim Consolidated Statements of Income are'not necessarily'indicative of amounts expected for the respective annual or future periods due to the effects of seasonal temperature variations on energy consumption, timing of maintenance on electric generating units and timing of synthetic fuel production, among other factors. :

This' discussion should be read in conjunction with the accompanying financial statements found elsewhere in this

' report and in conjunction with the 2003 Form 10-K.

RESULTS OF OPERATIONS

  • Progress Energy is an integrated energy company, with its primary focus on the end-use and wholesale electricity markets. The Company's reportable business segments and their primary operations include:
  • - .'-Progress

.. Energy Carolinas Electric (PEC Electric) -primarily'engaged in the generation, transmission,

-distribution and sale of electricity in portions 'of North Carolina and South Carolina;:

Progress Energy Florida (PEF) - primarily engaged in the generation, transmission, distrbution and sale

-: . .of electricity in portions of Florida; . .. -. . . -

  • Competitive Commercial Operations (CCO) - engaged in nonregulated electric generation operations and

- marketing activities primarily in the southeastern United States; .

. -Fuels - primarily engaged in natural gas drilling and production in Texas and Louisiana, coal terminal

- services, coal mining, the production of synthetic fuels and related services, and fuel transportation and

- .'delivery, all of which are located in Kentucky, West Virginia, and Virginia;

  • Rail Services (Rail) '- engaged in various rail and railcar related services in 23 states, Mexico and Canada; and
  • Other Businesses (Other) - engaged in other nonregulated business'areas, including telecommunications primarily in the eastern United States and energy service operations,'which do not meet the requirements for separate segment reporting disclosure.
  • In this section, earnings and the factors affecting earnings for the three and six months ended June 30, 2004 as compared to the same periods in 2003 are discussed.; The discussion begins with a summarized overview of the Company's consolidated earnings, which is followed by a more detailed'discussion and analysis by business segment. .

- OVERVIEW.

For the quarter ended June 30, 2004, Progress Energy's net income was $154 million or $0.63 per share compared to $157 million or $0.66 per share for the same period in 2003. For the six months ended June 30, 2004, Progress

-Energy's net income was $262 million or $1.08 per share compared to $376 million or $1.60 per share for the same period in 2003. The decrease in net income as compared toprior year was due primarily to:'

  • Lower off-system wholesale sales, primarily by.PEC Electric. - .

' Higher operations and maintenance (O&M) costs at the utilities due to increased spending for plant outages in both the Carolinas and Florida and planned reliability improvements in Florida.

  • Recording of litigation settlement reached in the civil suit by SRS.

Decreased nonregulated generation earnings due to receipt of a contract termination payment on a tolling

. agreement in 2003 and higher fixed costs and interest charges in 2004.

  • Unrealized losses recorded on contingent value obligations.
  • i* . ! The impact of tax levelization. .

, . .. 46 -.

-Partially offsetting these items were:

  • Favorable weather in the Caiolinas.

a Reduction in revenue sharing provisions in Flonida

  • Utility customer growth in both the Carolinas and Florida.

a-Lower depreciation and amortization costs at the utilities.

aIncreased natural gas earnings.

Basic earnings per share decreased in 2004 due in part to the factors outlined above.' Dilution related to the issuances under the Company's Investor Plus Stock Purchase Plan and employee benefit programs in 2003 and 2004 also reduced basic earnings per share by $0.02 for the second quarter of 2004 and $0.04 for the six month ended June 30, 2004.

Beginning in the fourth quarter of 2003, the Company ceased recording portions of Fuels segment's operations, primarily synthetic fuel facilities, one month in arrears. As a result, earniings for the year ended December 31, 2003 included .13 months of operations, resulting in a -net income increase of S2 million* for the year. The Company restated previously reported consolidated quarterly earning s to reflect the new reporting periods which resulted in four months earnings in the fis ure f20 n hne reotdntincome f6r subsequent quarters.

Earnings increased $4 million and $15 million, respectively, for the three and six months ended June 30, 2003 as compared to amounts originally reported..

The Company's segments contributed the following profits or losses for the' three and six months ended June 30, 2004 and 2003:

(inmillions) Three Months Ended Six Months Ended June 30 Jun30 Busitiess Segment' ~ 2004 2003 2004 -2003 PEC Electric :S 97 $ 89 S 213 $ 223 PEF 84 61. 133 132 Fuels .. 56 58 .104 97 CCO -52 (3) 11 Rail 4 2 -9 ()

Other .(30) - (31) .

-Total Segment Profit .26 12 425 463 Corporate. . (63) (58) (164) (102

-Income from continuing operations. .153 154 261 '361 NCNG discontinued operations A .3 .1 . .14 Cumulative effect of change in accounting

  • principle, net of tax .

Net income .S 154 -S 157 S 262 S 376 In March 2003, the SEC completed an audit of Progress Energy Service Company, LLC (Service Compan~r) and recommended that the Comp any change its cost allocation methodology for allocating Service Company costs. As part of the audit process, the Compan'ywas required to change the cost allocation methodology for 2003 and record retroactive reallocations between its affiliates in the first quarter of 2003 for allocations originally made in 2001 and 2002.- T1his change. in allocation methodology and the related retroactive adjustments have no impact on consolidated 'expense or:-earnings. The new allocation methodology, as compared to the previous allocation methodology, .generally decreases expenses in the regulated utilities and increases expenses in the nonregulated businesses. The regulated utilities' reallocations'are within operation aind maintenance (O&M) expense, while the diversified businesses' reallocations are gerierally within' diversified* business. expenses. The'impact on the individual lines of business is included in the following discussions.

47

PROGRESS ENERGY CAROLINAS ELECTRIC PEG Electric contributed segment p~rofits of S97 million an$9milo fo ihm hre months endedMac3120 and 2003, respectively, and $213 -million and $223 iiillion for the six months ended June 30, 2004 and 2003, respectively. The increase in profits for the three months ended June .30, 2004 as compared to the same period in 2003 is due. primarily. to* favorable weather, increased revenue from, customer growth, lower depreciation and amortization charges and the impact of losses booked on investments in limited partnerships in 2003, partially offset by higher operations and maintenance 'charges and lower wholesale sales. The decrease in profits for the six months ended June 30, 2004 a's compared to' the same period in 2003 is primarily due to lower 'off-system wholesale sales and higher O&M charges, partially offset by the- favorable impact of weather, increased revenues from customer.

growth and lower depreciation and amortization charges:..

PEG Electric's revenues for the three and six months ended June 30, 2004 and 2003, and the percentage change by customer class are as follows:

(in millions of S) .'. Three Months Ended June 30 Six Months Ended June 30 Customer Class 2004 Change  % Change 2003 2004 Change % Change 2003 Residential' .. S 284 S .36 -14.5 S248. S 655.. S 50 8.3 $605 Commercial ~.213 " 14 . 7.0 199 '420 20 5.0 400 Industrial 6 5 .3.2 .16 386 2.0 30 Governmental .1: . . 1 8 2,.. 5.6 36

  • Total retail revenues *. 677 . 56 . 9.0 . 621 "'1,421 .. 78. 5.8 1,343 Wholesale 139 (15) .(9.7) . 154 - 295 '(69) .(19.0). 6

.Unbilled 24I 23 1 8 . 7 Miscellaneous' 21 3 .':16.7 - 18 '45' 3 .7.1 42

  • Total electric revenues S 861'- S 45 -. 5.5 $ 816 $ 1,762 S 20 .1.1 $1,4
  • ,, PEG Electric's'cenergy sales 'or the three and six months ended June 30, 2004 and 2003, and the amount and percentage change by, customer class are as follows:

(in thousands of mWh) Three Months Ended June 30 -Six Months Ended June 30 Customer Class' 2004 Change .% Change - 2003 2004 Change % Change 2003 Residential '.3,525 473 . 15.5 3,052- 8,266 627 8.2 .7,639 Commercial ' 3,172 226 -7.7 .2,9.46 6,230 300. 5.1 .5,930

  • ' *. Industrial .  : 3,280 . 83 ': 2.6 .3,197 6,273 ' 71 1.1 .' 6,202 Governmental. 337 '20 '6.3 317 .682 ' 22 .3.3 .'.660 Total retail revenues 10,314 . 802 ' '8.4 9,512 2141 1,020. '5.0 20,431 Wholesale ' .. 3,114 '(187) (5.7) 3,301 ' 6,904 .'(1,016) (12.8) 7,920 Unbilled ' ' 404 8 ' 396' 20' '104 . 84)

Total mnWh sales .. 13,832 623 4.7 '13,209 28,375 .108 0.4 28,267 Three months ended Junie 3 0. 2004 compared to the three months ended June 3 0. 2003 PEG Electric' revenues,'ecuigrovabefl reveusof $156 million and $137 million for the three mionths

'ended June 30, 2004 and 2003, respectively, increased $26 rmillion. The increase in revenues was due primarily to.

  • .favorable weather, WIt cooling degree days 59% above prior year. In addition, 'customer growth was favorable compared to prior year. PEG Electric has approximately 26,000 additional customers as of June 30, 2004 compared to June. 30, 2003. .The' ~ncrease in retail revenues was offset partially by a reduction in wholesale. revenues.

'Revenues for 'the qluarter ended June .30, 2003 included strong off-system wholesale sales to the Northeastern

'United States in the month of April as a result of favorable market conditions.

'Fuel and purchased power costs represent the costs of generation, which 'includes fuel purchases for generation, as welsenergy purchased in' the market to meet cusoe la2Fuel and purchased power expenses are recovee primarily through cost recovery.clauses and, -as such, changes in these 'expenses do not have a material impact on' earnings.. The difference between fuel and purchased power costs incurred and associated fuel revenues that is subject to recovery is deferred for future collection or refund to cus'tomers.

48

Fuel and purchased power expenses increased $27 million from $246 million for the three months ended June 30, 2003 to $273 million for the three months ended June.30, 2004. Fuel used in electric generation increased $16

- million to $193 compared to the same period in the prior year. This increase is primarily due to higher system requirements caused by favorable weather and customer growth. Purchased power expenses increased $11 million to $80 million compared to prior year due primarily to an increase in price.

O&M costs were $226 million for the three months ended June 30, 2004, which represents a $16 million increase compared to the same period in 2003. O&M costs increased $13 million primarily due to an increase in outage scope and duration at the nuclear plants.

Depreciation and amortization expense decreased $15 million from $142 million for the quarter ended June 30,

-2003 to $127 million for the quarter ended June 30, 2004. During the first half of 2004, PEC Electric filed with the North Carolina Utilities Commission (NCUC) and obtained approval from the South Carolina Public Service Commission (SCPSC) for a depreciation study which allowed the utility to reduce the rates' used to calculate depreciation expense. The new depreciation study provides support for reducing depreciation expense on an annual basis by approximately $40 million for 2004. The reduction in depreciation expense is primarily attributable to' extended lives of nuclear generation, offset by increases for distribution assets. As a result depreciation expense decreased $10 million 'compared to the prior year quarter. In addition, 'clean air amortization decreased $18 million compared to the prior year. These items were partially offset by higher depreciation expense due to assets placed in service of $4 million and the impact of a $14 million adjustment booked in 2003 related to the implementation of

-SFAS No.' 143. In the prior year, PEC filed a request with the NCUC requesting deferral of the difference between expense pursuant to SFAS No. 143 'and expense as previously determined by the NCUC. The NCUC granted

-'deferral of the cumulative adjustment but denied deferral of the ongoing effects. As a result, PEC ceased deferral of the ongoing effects during the'second quarter of 2003 related to its North Carolina retail rate jurisdictions. This resulted in a reduction of depreciation and amortization expense for the quarter ended June 30, 2003 of $14 million which represented a decrease '-in non-ARO cost of removal expense partially' offset by an increase in decommissioning expense. In August of 2003, the NCUC revised its decision and approved deferral 'of the ongoing effects of SFAS No. 143 at which time the $14 million reduction was reversed.

Other expenses have' decreased S12 million'for the three months ended June 30, 2004 as compared to the same

period in the prior year.- This'decrease is primarily due 'to losses on limited investment partnerships recorded in 2003.

':Taxes other than on income have increased S10 million from $35 million for the three months ended June 30, 2003 to $45 million for the three months ended June 30, 2004. This increase is due to an increase in gross receipts taxes.

of S5 million related to an increase in revenues and a 2004 adjustment related to the prior year, and an increase in payroll taxes of $3 million.

Six months ended June 30. 2004 compared to the six months ended June 30.'2003 PEC Electric's revenues, excluding recoverable fuel revenues of $322 million and $293 million for the six months ended June 30, 2004 and '2003, respectively, decreased $9 million. The decrease in revenues was due primarily to lower wholesale sales. 'Revenues for the six months ended June 30, 2003 included strong 'sales to the Northeastern United States as a result of favorable market conditions. The decline in wholesale revenues was partially offset by increased retail .revenues as a result of 'favorable weather, with cooling' degree days 58% -above prior year. In

' 'addition, favorable customer growth partially offset the decrease in wholesale sales.

Fuel and purchased power costs represent the costs of generation, which includes fuel purchases for generation, as well as energy purchased in the market to meet customer load. Fuel and purchased power expenses are recovered primarily through cost recovery clauses and, as surch,'changes in 'these expenses do not have a material impact on

- eamings. 'The difference between fuel and purchased 'power costs incurred and associated fuel revenues that is subject to recovery is deferred for future collection or refund to customers.

Fuel and purchased power expenses were $559 million for the six months ended June 30, 2004, which represents a

$14 million increase compared to the same period in the'prior year. This increase is primarily due to higher system

' requirements caused by favorable weather and customer growth. ' -

49

O&M costs were $435 million for the six' months ended June 30, 2004, which represents a $35 million increase

' compared to the same period in :2003. O&M charges were favorably impacted by $16 million related to the retroactive reallocation of Service Company. costs in the prior year. In addition, O&M costs increased $18 million primarily due to an increase in outage scope and duration at the nuclear plants.

Depreciation and amortization expense decreased $27 million from $281 million for the six months ended June 30, 2003 to $254 million 'for the six months ended June 30, 2004. .As previously discussed, PEC filed a depreciation study which allowed the utility to reduce the rates used to calculate depreciation expense. The impact of the study for the six months ended June 30, 2004 was a reduction of depreciation of $18 million compared to the same prior year period. 'In addition,, clean air amortization for the six months ended June 30, 2004 decreased $23 million*

compared to the same prior year period. These items were partially offset by higher depreciation expense due to assets placed in service of $8 'million and the $14 'million impact of the adjustment booked in 2003 related to the implementation of SFAS No. 143 as previously discussed. '

Taxes other than on income have increased $9 million from $79 million for the six months ended June 30, 2003 to

$88 million for the six months ended June 30, 2004. This increase is due to an increase in gross receipts taxes of $5 million related to an increase in revenues and a 2004. adjustment related to the prior year, and an increase in property taxes of $2 million. ' " -

PROGRESS ENERGYFLORIDA '

PEF contributed segment profits of $84 million and $61 million for the'three months ended June 30, 2004 and 2003, respectively, and $133 million and $132 million for the six months ended June 30, 2004 and 2003, respectively.

The increase in profits for the three months ended June 30, 2004 when compared to 2003 is primarily due to a reduction 'in the provision for revenue sharing, the -additional return on investment for the Hines 2 plant and favorable customer growth. Profits for the six months ended June 30, 2004 increased slightly due to a reduction in the provision for revenue'sharing, favorable customer growvth, and the additional return on investment on the Hines 2 plant, partially offset by higher O&M charges and increased depreciation expense from assets placed in service.

PEF's electric revenues for the three and six months ended June 30, 2004 and 2003, and the amount and percentage change by customer class are as follows:

(in millions of S) - Three Months Ended June 30 Six Months Ended June 30 Customer Class 2004 Change % Change 2003 2004 Change % Change 2003 Residential S 422 S 8 1.9. S414 S 824 $ 26 .. 3.3 S 798 Commercial ' . . 214 - 22 11.5 192 395 .53 15.5 342 Industrial ' 66 10 17.9 - 56 128 24 23.1 104 Governmental 52 6 13.0 46 99'. 15 17.9 84 Retail revenue sharing (3) 25 (28) (7) 21 (28)

Total retail revenues - 751 - 71 -10.4 $ 680 1,439 . 139. ; 10.7 1,300 Wholesale - ' 55>. 3 6.0 . 50 -120 (1) (0.8) 121 Unbilled - .24 17 18 :11 - 777 Miscellancois  : 32 2 -6.7 30 67 . - - 67 Total electric revenues S 860 S 93 12.1 $ 767 S 1,644 S 149 10.0 S 1,495 PEF's electric energy 'sales for the three and six months ended June 30, 2004 and 2003, and the amount and

'"percentage change by customer class are as follows: ' '  ; " ' -

(in thousands of mWh) Three Months Ended June 30 Six Months Ended June 30 Customer Class 2004 Change % Change 2003 2004 Change % Change 2003 Residential 4,505 (198) (4.2) 4,703 8,797 '(459) (5.0) 9,256 Commnercial :- 2,941 -. : (10) (0.3) 2,951 5,431 - :38 0.7 5,393 Industrial -- 1,051 43 -4.3. 1,008 2,074 150 - 7.8 1,924 Governmental 751 ' 9 - 1.2 742 1,423 25  : 1.8 1,398 Total retail energy sales 9,248 (156) (1.7) 9,404 17,725 (246) - (1.4) 17,971 Wholesale 1,093 203 - 22.8 . 890 . 2,415 249 11.5 2,166 Unbilled .:: - 790 292 '. .498 655 101 . 554 Total niWh sales - 11,131 .339 . 3.1 10,792 20,795 - 104 0.5 20,691

.0 so

Three months ended June 30. 2004 compared to the three months ended June 30. 2003 PEF's revenues, excluding recoverable fuel and other pa.is-through revenies of $479 million and $422 million for the three months ended June 30,'2004 and 2003, respectively, increased S36 million. This increase was due primarily to a reduction in the provision for revenue sharing of S25 million. The provision for revenue sharing in the prior year included an additional $18 million related to 2002 as ordered by the FPSC and the year to date accrual for 2003 which was S7 million higher than the provisions recorded during 2004. Revenues were also increased $ 11 million' and S10 million, respectively, due to favorable customer growth and the return on investment on Hines Unit

- 2 which was placed in service December 2003. PEE has approximately 37,000 additional customers as of June 30; 2004 compared to June 30, 2003. Based on the'Stipulation and Settlement Agreement reached with the FPSC in' April 2002, beginning with the in-service date of PEF's Hines Unit 2 and continuing through December 2005, PEF will be allowed to recover through the fuel cost recovery clause a return on average investment and depreciation

expense for Hines Unit 2, to the extent such costs do not exceed 'the Unit's cumulative fuel savings over the recovery period. These increases were partially offset by the impact of milder weather in the current year of

- approximately $5 million.' - - '  : -

Fuel and purchased power costs represent the'costs of generation, which includes fuel purchases for generation, as well as energy purchased in the market to meet customer load. Fuel and purchased power expenses are recovered

-primarily through cost recovery clauses and, as such, changes in these expenses do not have a material impact on earnings. The difference between fuel and purchased power costs incurred and associated fuel revenues that is subject to recovery is deferred for future collection or refund to customers.

Fuel and purchased power expenses increased $57 million from $358 million for the three months ended June 30,'

- 2003 to $415 million for the three months ended June 30, 2004. This increase -is attributable primarily to an increase in fuel used in electric generation which increased $59 million. Higher system' requirements and increased fuel costs in the' current year account for $32 million of the increase in fuel used in electric generation. The remaining increase is-due to the recovery of fuel expens s'that were deferred in the prior year, as well as the deferral of current year expenses.

O&M costs decreased $2 million, when compared to the $154 million incurred during the three months ended June

- 30, 2003. This decrease is primarily related to the timing of outages and maintenance at generation facilities of $3

':million and a reduction in 'costs allocated from the Service Company of $1 million partially offset by higher costs associated with planned reliability improvements of approximately $2 million.

Depreciation and amortization decreased $8 million when compared to the $80 million incurred during the three months ended June 30, 2003, primarily due to the amortization of the Tiger Bay regulatory asset in the prior year.

The Tiger Bay regulatory asset, for contract termination costs, was recovered pursuant to an agreement between PEF which was'approved by the FPSC in 1997 and as such fluctuations in this expense did not have an impact on earnings. During the second quarter of 2003, Tiger Bay amortization was $15 million. The Tiger Bay asset was fully amortized in September 2003. The decrease in Tiger Bay amortization was partially offset by additional depreciation for assets placed in service. ' '

Six months ended June 30. 2004 compared to the six months ended June-30. 2003 PEF's revenues, excluding recoverable fuel and other pass-through revenues of S926 million and $794 million for the six months ended June 30, 2004 and 2003, respectively, increased $17 million.' This increase was due primarily to 'a reduction in the provision for revenue sharing of $21 million.' Results for 2003 included the accrual of an additional $18 million related,to the 2002 revenue sharing provision as ordered by the FPSC in June of 2003. In addition, the return on investment on Hines 2 and favorable customer growth increased revenues by S19 million and

$9 million, respectively. These increases were partially offset by the impact of milder weather in'the current year of approximately $17 million.-'

Fuel and purchased power costs represent the costs of generation, which includes fuel purchases for generation, as' well as energy purchased in the market to meet customer load. Fuel and purchased power expenses are recovered primarily through cost recovery clauses and, as such, changes in these expenses do not have a material impact on earnings. The difference between-fuel and purchased power costs incurred and associated fuel revenues that is

subject to recovery is deferred for future collection or refund to customers.

51

Fuel and purchased power expenses were $805 million for the six months ended June 30, 2004, which represents a S132 million increase compared to the same period in the prior year. This increase is due to an increase in fuel used in electric generation of $143 million offset by a reduction in purchased power costs. This increase in fuel used in electric generation is due to the recovery of fuel expenses that were deferred in the prior year, as well as the deferral of current year fuel expenses. In November 2003, the FPSC approved PEF's request for a cost adjustment in its annual fuel filing due to the rising costs of fuel. The new rates became effective January 2004. The decrease in purchased power expense of $11 miillion is attributable primarily to the Hines 2 Plant being placed in service in December of 2003, thereby reducing the need for purchased power.

O&M costs increased $17 million, when compared to the $295 million incurred during the six months ended June 30, 2003. This increase is primarily related to higher costs associated with scheduled plant outages and planned reliability improvements of approximately $9 million each.

Depreciation and amortization decreased $18 million when compared to the $159 million incurred during the six months ended'June 30, 2003; primarily due to the amortization of the Tiger Bay regulatory asset in the prior year.

The Tiger Bay regulatory asset, for contract termination costs; was recovered pursuant to an agreement between PEF which was approved by the FPSC in 1997, and as such fluctuations in this expense did not have an impact on eamings. During the six months ended June 30, 2003, Tiger Bay amortization was $30 million. The Tiger.Bay asset was fully amortized in September 2003. The decrease in Tiger Bay amortization was partially offset by additional depreciation for assets placed in service. . -- ' -

" DIVERSIFIED BUSINESSES

The' Company's diversified businesses consist of the Fuels segment, the OCO segment, the Rail segment and the

-Other segment. These businesses are explained in more detail below.

' FUELS The Fuels' segment operations include synthetic fuels production, natural gas production, coal extraction and

'- terminal operations. -Fuels' results for the six months ended June 30,'2003 were restated to reflect seven months of earnings for certain operations, primarily synthetic fuel facilities.

The following summarizes Fuels' segment profits for the three and six months ended June 30, 2004 and 2003:

Three Months Ended June 30 Six Months Ended June 30 (in millions) 2004 2003 2004 2003 Synthetic fuel operations - ' - S 36 $ 49 S 72 S 83

- Gasproduction ' 12. 9 25 16 Coal fuel and other operations 8 7 - (2)

Segments Profits - - S 56 $ 58 S 104 S 97 Synthetic Fuel Operations The synthetic fuel operations generated net profits of $36 million and $49 million for the three months ended June 30, 2004 and 2003,'respectively, and $72 million and $83 million for the six months ended June 30, 2004 and 2003,'

respectively. 'The production and sale of synthetic fuel generate operating losses, but qualify for tax credits under

, Section 29 of the Code, which more than offset the effect of such losses; See Note 12 to the Progress Energy Notes to the Consolidated Interim Financial Statements for further discussion of synthetic fuel tax credit matters.

- The operations resulted in the following for the three and six months ended June 30, 2004 and 2003:

Three Months Ended June 30 Six Months Ended June 30 (in millions) - -  : 2004 . 2003 2004 2003 Tons sold  :. 2.7 3.0 5.7 . 5.

Opeiating losses, excluding tax credits 'S(35) S(33) '(77) 5(65)

Tax credits generated - ' 71 82 . 149 - 148 Netprofits ' S 36 $ 49 572 S 83 52

Synthetic fuels' net profits decreased in the three months ended June 30, 2004 as compared to the same period in 2003 due primarily to a reduction irincredits earned of $4 million as a result of a decrease in tons sold and an increase in operating cost of S4 million after-tax. Synthetic fuel profits decreased in the six months ended June 30, 2004 due primarily to increases in operating cost of 510 million. The Company anticipates total synthetic fuel production of approximately 11 to 12 million tons for 2004 which is comparable to 2003 production levels.

Natural Gas OMerations Natural gas operations generated profits of S12 million and $9 million for the three months ended June 30,2004 and 2003, respectively, and $25 million' and $ 16 million for the six months ended June 30, 2004 and 2003. The increase in production resulting from the acquisition of North Texas Gas in late February 2003 and increased drilling and higher gas'prices in 2004 contributed to increased earnings in 2004 as compared to 2003. In October 2003, the Company completed the sale of-certain gas producing properties owned by Mesa-Hydrocarbons, LLC. The following summarizes the gas production, revenues and gross margins for the three and six months-ended June 30, 2004 and 2003 by production facility:

'Three Months Ended June 30 Six Months Ended June 30 2004 2003 2004 2003 Production in Bcf equivalent - .

Mesa 1.5- 3.2 Westchester ' - '4.9 . 3.1 9.0 6.3 North Texas Gas ' -2.7 1.8 - - 5.3 2.4 Total Production 7.6 6.4 14.3 11.9 Revenues in millions Mesa S- S3 S- $8 Westchester  : 26 16 48 31 North Texas Gas '14 10 27 - 14 Total Revenues '  : ' '40 S S29 S75 S 53 Gross Margin in millions of S' S 33 S 24 S 60 .$ 43 Asa%ofrevenues ' 83% 83% 80% 81%

'Coal Fuel and Other Operations Coal fuel and other operations generated segment profits of $8 million for the three months ended June 30, 2004 compared to zero segment profits for the comparable period in the prior year.' For the six months ended June 30, 2004, coal fuel and other operations' generated segment profits of $7 million compared to a segment loss of S2 million for the comparable period in the prior year. This increase in profits for the quarter and year to date is due to higher volumes and margins for coal fuel operations of $9 million after-tax offset by a reduction in profits of S4 million after-tax for fuel transportation operations related to the waterborne transportation ruling by the FPSC. See Note 4A of the Progress Energy Consolidated Interim Financial Statements. The increase in profits is also due to the impact of the retroactive Service Company allocation in the prior year. Results in the same period for the prior year were negatively impacted by the retroactive reallocation of Service Company costs of $4 million after-tax.

COMPETITIVE COMMERCIAL OPERATIONS CCO's operations generated segment profits of $5 million for the three months ended June 30, 2004 compared to S2 million of segment profits for the comparable period in the prior year. Results for the three months ended June 30, 2004 were favorably impacted by margins on new contracts and market sales of $15 million partially offset by an increase in fixed costs. Fixed costs increased S6 million from additional depreciation and amortization on plants placed in service and from an increase in interest expense of $4 million due primarily to interest no longer being capitalized due to the completion of construction in the prior year.

CCO's operations 'generated segment losses of $3 million for'the six months ended June 30, 2004 compared to $11 million of segment profits for the comparable period in the prior year. Results for the six months ended June 30, 2004 were favorably'impacted by increased gross margin which was offset by higher. fixed costs.' Revenues

'increased a net of $34 million in the six months ended June 30, 2004 due to increased revenues from marketing and'.

tolling contracts'offset by a termination payment received on a marketing contract in 2003 and mark to market

- losses of SI0 million. Expenses for the cost of fuel and purchased power to supply our marketing contracts offset 53

the increased revenues of $34 million netting to an increase in gross margin of $4 million for the six months ended June 30, 2004 as compared to the same prior year period. Fixed costs increased $14 million from additional depreciation and amortization on Plants placed into service in 2003 and from an increase in interest expense of $10 million due primarily to interest no longer being capitalized due to the completion of construction in the prior year.

Expenses were favorably impacted by a reduction in Service Company allocations. Results for 2003 were negatively impacted by the retroactive reallocation of Service Company costs of $3 million ($2 million after-tax).

Three Months Ended June 30 Six Months Ended June 30 (in millions) 2004 2003 2004 2003 Total revenues -$72 S 33 $105 S 71 Gross margin Inmillionsof$S42 - S 27  : S 65 S $61 As a % of revenues 58% 82% 62% 86%

I .. Segment profits (losses) S 5 $S 2 $ (3) $ 11 The Company has contracts for 93% of planned production capacity for'2004 and approximately 77% in both 2005 and 2006. The 2005 decline results from the expiration of three tolling contracts. The Company continues to pursue opportunities with both current and new potential customers.

RAIL' Rail's operations include railcar and locomotive repair, trackwork, rail parts reconditioning and sales, scrap metal recycling and other rail related services. The Company sold the majority'of the assets of Railcar Ltd., a leasing

-subsidiary, in 2004. See Note 3B of the Progress Energy Notes to the Consolidated Interim Financial Statements.

Rail contributed segment profits of $4 million and $2 million for the three months ended June 30, 2004 and 2003, respectively. Revenues have increased S71 million to $285 million for the three months ended June 30, 2004 compared to the same period in the prior year. ' This increase is due primarily to increased volumes and higher prices in recycling operations and in part to increased production and sales in locomotive and railcar services and engineering and track services.: Cost of goods sold increased $62 million compared to $188 million in the prior year.. The increase in costs of good sold is due to increased costs for inventory, labor and operations as a result of the increased'volume in the recycling operations, locomotive and railcar services and engineering and track services. "The increase in margins of $9 'million was partially offset by an increase in general and administrative "nee ictt t ererlv

n~tOrtNPe~5"l P~ - '
  • . ;s relateu pnmariiy to niguci prulesslumal icus.

Rail contributed segment profit of $9 million for the six months ended June 30, 2004 compared with a segment loss

-- of S1 million for the same period in the prior year. Revenues have increased $130 million to $523 million for the six months ended June 30, 2004 compared to the same period'in the prior year. This increase is due primarily to increased volumes and higher prices in recycling operations and in part to increased production and sales in

-locomotive and railcar services and engineering and track services. Cost of goods sold increased S112 million compared to $455 million in the prior year. - The increase in costs of good sold is due to increased costs for

inventory, labor and operations as a'result of the increased volume in the recycling operations, locomotive and railcar services and engineering and track services. Results in the prior year were negatively impacted by 'the retroactive 'reallocation of-Service Company, costs of $3 'million'after-tax. The favorability related to the reallocation'was offset by an increase in general and administrative costs in the current year related primarily to higher professional fees. ' ' ' '

OTHER BUSINESSES SEGMENT Progress Energy's Other segment primarily includes the operations' of SRS and the telecommunications operations

-of PTC LLC. SRS is engaged in providing energy services to industrial, 'commercial and institutional customers to help manage energy costs and currently focuses its activities in the southeastern United States. PTC LLC operations provide broadband capacity services, dark fiber and wireless services in Florida and the eastern United States.'

SRS recorded a net loss of $29 million for the three months ended June 30, 2004 compared with profits of less than

$1 million for the same period in the prior year. SRS recorded a net loss of $29 million for the six months ended June 30, 2004 compared to a net loss of less than $1 million for the six months ended June 30, 2004. The increased

'segment loss compared to the prior year is due primarily to the recording of the litigation settlement reached with San Francisco United School District related to civil proceedings. In June of 2004, SRS reached a settlement with

- the District which settled all outstanding claims for approximately $43 million pre-tax ($29 million after-tax).

54

CORPORATE SERVICES Corporate Services includes the operations of the Holding Company, the. Service Company and consolidation entities, as summarized below:

Three Months Ended June 30 Six Months Ended June 30 (in millions) 2004 2003 2004 2003 Other interest expes . 6) .5(0* (139) $ (141)

Contingent value olgtns(5) (2) (3 Tax levelizationi. (5) . (5) (43) 5 Tax reallocation . (9) (9) . (18)' (18)

  • Otherincome taxes 28 31 65 62 Other (6) ()(16) (0 Segment profit (loss) $ (63) . $ (58) S (164) $ (102)

Other inte rest expense decreased $4 million compared to $70 millihon for the three months ended June 30, 2003 and it decreased $2 million compared to $141 million for the six months ended June 30, 2003. Interest expense

-decreased during the current periods~ due to the repay-menit of a $500 million unsecured note by the Holding company on March'1, 2004 which~reduced interest expense by $8 million pre-tax for the qluarter and year to date..

This reduction was offset by interest no longer being capitalized due to the completion of construction at the CCO segment in~the prior year. Approximately $4 million ($2 million after-tax) and $10 million ($6 after-tax) was capitalized in the three and six months en~ded June 30, 2003, respectively. .

ProgressEnergy issued 98.6 million -contingent value obligations (CVOs) in connection with. the 2000 FPC acquisition. Each CVO represents the right to receive contingent payments based- on the performance of four synthetic fuel facilities owned by Progress Energy. Th ayments, if any, are based on the net after-tax cash flows the facilities generate.' At June 30, 2004 and 2003, the CV~s had fair market values of approximately $36 million

  • and $14 million, respectively:". Progress Energy recorded an unrealized loss of $5 million and $2 million for the three months ended June 30, 2004 and 2003, respectively, to record the changes in fair value of the CVOs, which had average unit prices of $0.36 and $0.14 at June 30, 2004 and 2003, respectively. .Progress Energy recorded an unrealized loss of $13 'million for -six months ended June 30, 2004. -The CVO values at June 30,. 2003 were unchanged from the January 1, 2003 values, thus 'requiring no recognition of unrealized gain or loss for the six' months ended June 30, 2003.

GAAP requires companies to apply a leve'lized effective tax rate to interim periods that is consistent with the

  • estimated annual'effective tax rate: Income tax expense was increased by $5 million for the three months ended June 30, 2004 and 2003, respectively, in order to maintain an effective tax rate'consisteht with the estimated annual
  • / rate. Income tax expenise was increased by $43 million and decreased by $5million for the six months ended June 30, 2004 and 2003, respectively. The tax credits associated with the Company's synthetic fuel operations primarily.

drive the required levclization amount. Fluctuations in estimated annual earnings and tax credits can also cause -

  • large swings in the effective tax rate for interim periods. Therefore, this adjustment will vary each quarter, but will have no effect on net income for the year:.' .

Other expenses increased $3 million and $6 million for the tlhre'e and six 'months ended June 30, 2004 and 2003, respectively, as compared to the same prior year peribds. This increase is -due primarily to. an . increase in depreciation expense at the Service Company'due to assets being placed in service.

DISCONTINUED OPERATIONS In 2002, the Company approveid the sale' of NCNG to Piedmont Natural Gas' Company, Inc. Th'allsed on' September 30, 2003. Net proceeds of approximately $443 million from the sale of NCNG were used to reduce

-outstanding short-term debt. NCNG contributed $1 million of net income for the three months ended June 30, 2004 compared with $3.million of net income for the same prior year period. During the three months ended June 30, 2004, the Company recorded an additional gain after taxes of approximately $1 million related tb deferred taxes on the loss from the NCNG sale. NCNG contributed $1 million of net income for the six months ended June 30, 2004 compared to $14 million for the comparable prior year period.

55

l as LTOUrDITY AND CAPITAL RESOURCES f .'- *-" i Progress Energy, Inc.

Progress Energy is a registered holding company and, as such, has no operations of its own. As a holding company, Progress Energy's primary cash obligations are its common dividend and interest expense. The ability to meet its obligations is primarily dependent'on the earnings and cash flows of its two electric utilities and nonregulated subsidiaries, and the ability of.'those 'subsidiaries to pay dividends or repay funds to Progress Energy.

Net cash provided by operating activities of $915 million increased $8 million for the six months ended June 30, 2004, when compared to $907 million in the corresponding period in the prior year. The slight improvement in cash from operating activities for the 2004 period is primarily due to approximately $100 million of lower operating cash

- flow at PEF for the .period in 2003, which resulted from an under recovery of fuel costs, and reduced working capital needs of nearly S50 million in the current year. These improvements in cash from operating activities were partially offset by a S114 million decrease in net income for the period.

- Net cash used in investing activities of $591 million decreased $604 million for the six months ended June 30, 2004, when compared to $1.2 billion in the corresponding period in the prior year. The decrease is primarily due to reduced nonregulated capital expenditures, primarily the purchase of North Texas Gas assets and a long-term power supply contract durii'n the first half of 2003. In addition, proceeds from the sale of Railcar Ltd. assets reduced net investing cash requirements during the first half of 2004.

For the first six months of 2004, Progress Energy's cash from operations less cash used in investing activities increased approximately $600 million. The improvement was due to the reduction in capital expenditures discussed above. The positive'cash flow'combinred with the equity issuance of $58 million, helped reduce the Company's consolidated leverage to 58.2% from 58.9% as of December 31, 2003.

' Progress Energy took advantage of favorable market conditions and entered into a new $1.1 billion five year line of credit, effective August'5, 2004,' and expiring August 4, 2009. .This facility replaces Progress Energy's $250 million 364 day line of credit and its three-year $450 million line of credit, which were set to expire in November 2004.

On July 28, 2004, PEC extended its $165 million 364-day line of credit, which was to expire on July 29, 2004. The

'line of credit will 'expire on July 27, 2005.-'

On April 30, 2004, PEC redeemed $34.7 million of Darlington County 6.6% Series Pollution Control Bonds at 102.5% of par,,$1.795 million of New Hanover County 6.3% Series Pollution Control Bonds at 101.5% of par, and S2.58 million of Chatham County 6.3% Series Pollution Control Bonds at 101.5% of par with cash from operations.

On March 1, 2004,'Progress Energy used available cash and proceeds from the issuance of commercial paper to retire $500 million 6.55% senior unsecured notes. Cash'and commercial paper capacity'were created primarily from the sale of assets and early long term debt financings in 2003. -

On January 15, 2004, PEC paid at maturity $150 million 5.875% First Mortgage Bonds with commercial paper proceeds.. On April 15, 2004,'PEC also paid at maturity $150 million'7.875% First Mortgage Bonds with' commercial paper proceeds and cash from operations. . '

On February 9, 2004, Progress Capital Holdings, Inc. paid 'at maturity $25 million 6.48% medium term notes with excess cash.

  • For the six months ended June 30,' 2004, the Company'issued approximately 1.3 million shares representing approximately $58 million in proceeds from its Investor Plus Stock Purchase Plan and its employee benefit plans.

'For the six months ended June 30, 2004 and 2003, the dividends paid on common stock were approximately $280 million and $268 million, respectively.

PEG has exclusively utilized external funding for'its decommissioning liability since' 1994. Prior to 1994, PEC

- retained

' its funds internally to meet its decommissioning liability. A North Carolina Utilities Commission (NCUC)

- order issued in February 2004 found that by January 1, 2008, PEC must begin transitioning these amounts to

- external funds. The transition of S 131 million must be completed by December 31, 2017, and at least 10% must be transitioned each year. -

56'

The amount and timing of future sales of company securities will depend on market conditions, operating cash flow, asset sales and the specific needs of the Company. The Company may from timie to time sell securities beyond the amount needed to meet capital requirements in order to allow for the early redemption of long-term debt, the redemption of preferred stock, the reduction of short-term debt or for other general corporate purposes.

FutureCommitments As of June 30, 2004, Progress Energy's contractual cash obligations and other commercial commitments have not changed materially from what was reported in the 2003 Annual Report on Form 1O-K

- The total amount of liquidity requirements associated with guarantees for the company's nionregulated portfolio and power supply agreements is $497 rmillion.

-;;As of June 30,2004, the current portion of long-term debt is $343 million.

As of June 30,2004, Progress Energy's guarantees issued on behalf of third parties were approximately $24 million.

OTHER MATTERS PEFRate Case Settlemin:ent In March 2002, the parties in PEF's rate case entered into a Stipulation and Settlement Agreement (the Agreement) related to retail rate matters. The Agreement was approved by the FPSC and is generally effective from May 1, 2002 through December 31, 2005; provided, however, that if PEF's base rate earnings fall below a 10% return on equity,'PEF may petition the FPSC to amend its base rates.

Synthetic Fuels Tax Credits -. ..

Progress Energy's synthetic fuel operations are subject to numerous risks that may impact the Company, its operations, and the value of its securities. Many of these risks are discussed in the Company's 2003 10-K, particularly the Risk Factors section. You should carefully read about these risks.

Progress Energy, through its subsidiaries, produces a coal-based solid synthetic fuel. The production and sale of the synthetic fuel from these facilities qualifies for'tax credits under Section 29 of the Code (Section 29) if certain requirements are satisfied, including'a requirement that the synthetic fuel differs significantly in chemical composition from the coal used to produce such synthetic fuel and that the fuel was produced from a facility that

-was placed in service before July l, 1998. Synthetic fuel' tax credit amounts not utilized are carried-forward indefinitely as alternative minimum tax credits. All of Progress Energy's synthetic fuel facilities have received private letter rulings (PLRs) from the Internal Revenue Service (IRS) with respect to their synthetic fuel operations.

These tax credits are subject to review by the IRS, a'nd if Progress Energy fails to prevail through the administrative or legal process, there could be'a significant tax liability owed for previously taken Section 29 credits, with a significant impact on earnings and cash flows. Additionally, the ability to use tax credits currently being carried forward could be denied. Total Section 29 credits generated to date (including those generated by FPC prior to its acquisition by. the Company) are approximately $1.4 billion, of which S584 million have been used and S807 million are being carried forward as deferred tax credits. The current Section 29 tax credit program expires at the end of 2007.

In September 2002, all of the Company's majority-owned synthetic fuel entities were accepted into the IRS's Pre-filing Agreement (PFA) program. The PFA program allows taxpayers to voluntarily accelerate the IRS exam process in order to seek resolution of specific issues. Either the Company or the IRS can withdraw from the program, and issues not resolved through the program may proceed to the next level of the IRS exam process.

-In July 2004, Progress Energy was notified that the Internal Revenue Service (IRS) field auditors anticipate taking an adverse position regarding the placed-in-service date of the Company's four Earthco synthetic fuel facilities. Due to the auditors' position, the IRS has decided to exercise its right to withdraw from the Pre-Filing Agreement (PFA) program with Progress Energy. With the IRS's withdrawal from the PFA program, the review of Progress Energy's Eathco facilities is back on the normal procedural audit path of the Company's tax returns. The IRS has indicated that the field audit team will provide its written recommendation later this year. After the field audit team's written recommendation is received, the Company will begin the Appeals process within the IRS. Through June 30, 2004 the Company, on a consolidated basis, has claimed $1.billion of tax credits generated by Earthco facilities. If these 57

credits were disallowed, the Company's one time exposure for cash tax payments would be $229 million (excluding interest), and earnings and equity would be reduced by.51 billion, excluding interest. The Company believes that the appeals process could take 'up' to two years to c6inplete, however it .cannot control the actual timing of resolution and cannot predict the outcome of this matter. '

In February 2004, subsidiaries of the Company finalized execution of the Colona Closing Agreement with the IRS concerning their Colona synthetic fuel facilities. The Colona Closing Agreement provided that the Colona facilities were placed in service before July 1, 1998, which is one of the qualification requirements for tax credits under Section 29. The Colona Closing Agreement further provides that the fuel produced by the Colona facilities in 2001 is a "qualified fuel" for purposes of the Section 29 tax'credits. This action concluded the IRS PFA'prograrn with respect to Colona.

In June 2004, the Company through its subsidiary, Progress Fuels sold, in two transactions, a combined 49.8 percent partnership interest in Colona Synfuel Limited Partnership, LLLP, one of its synthetic fuel facilities. Substantially all proceeds from the sales will be received over time, which is typical of such sales in the industry. Gain from the sales will be 'recognized on a cost recovery basis. The Company's book value of the interests sold totaled approximately $5 million. Based on projected production levels, the Company anticipates receiving total gross proceeds of approximately $30 million per year, on an annualized basis. Under the agreements, the buyers have a right to unwind the transactions if an IRS reconfirmation private letter ruling (PLR) is not received by October 15, 2004.; Therefore, no gain would be recognized prior to the expiration of that right.

In October 2003, the United States'Senate Permanent Subcommittee on Investigations began a general investigation concerning synthetic fuel tax credits claimed under Section 29. -The investigation is examining the utilization of the credits, the nature of the technologies and fuels created, the use of the synthetic fuel and other aspects of Section 29 and is not specific to the Company's synthetic fuel operations. Progress Energy is providing information in connection with this investigation. The Company cannot predict the outcome of this matter.

In management's opinion, Progress Energy is complying with all the necessary requirements to be allowed such credits under Section 29, and, although it cannot provide certainty, 'it believes that it will prevail in these matters.

Accordingly, the Company has no current plans to alter its synthetic fuel production schedule as a result of these matters.. However, should the Company fail to prevail in these matters,'there could be material liability for previously taken Section 29 credits, with a material adverse impact on earnings and cash flows.

NuclearMatters The United States Nuclear Regulatory Commission (NRC) on April 19, 2004, announced that it has renewed the operating license for PEC's Robinson Nuclear Plant (Robinson) for an'additional 20 years through July 2030. The

  • original operating license of 40 years was set to'expire in 2010. NRC operating licenses held by PEC currently expire in December 2014 and September 2016 for Brunswick Units 2 and 1, respectively. An application to extend these licenses 20 years is expected to be submitted in October 2004. The NRC operating license held by PEC for.

the Shearon Harris Nuclear Plant (Harris Plant) currently expires in October 2026. An application to extend this license 20 years is expected to be submitted in the fourth quarter of 2006. '

The NRC operating license held by PEF for Crystal River Unit No. 3 (CR3) currently expires in December 2016.'

An application to extend this license 20 years is expected to be submitted in the first quarter 2009.

On February 27, 2004, PEC requested 'to have its license for the Independent Spent Fuel Storage Installation at the

- ' Robinson Plant extended 20 years with an exemption request for an additional 20-year extension. Its current license is due to expire in August 2006. PEC expects to receive this extension.'

During the first' quarter 'of 2004, PEC met the requirements of both the NCUC 'and the SCPSC for the

; implementation of a depreciation study which allowed the utility to reduce the rates used to calculate depreciation expense.' The reduction in depreciation expense is primarily attributable to assumption changes for nuclear.

generation.'

In February 2004, the NRC issued a revised Order for inspection requirements for reactor pressure vessel heads at PWRs. Progress Energy has reviewed the required inspection frequencies and has incorporated them into long range plans. Harris will complete the required non-visual NDE inspection prior to February 2008. Both CR3 and Robinson will be required to inspect their new heads within 7 years or four refueling outages after replacement.

CR3 plans to inspect its new head prior to the end of 2009 and Robinson will need to inspect its new head prior to

-2012.

58

The NRC has issued various orders since September 2001 with regard to security at nuclear plants. These orders include additional restrictions on'access, increased security measures at nuclear facilities and closer coordination with the Company's partners in intelligence, military, law enforcement and emergency response at the federal, state and local levels. The Company is completingthe requirements as outlined in the orders by the established deadlines. As the NRC, other governmental 'entities and the industry continue to consider security'issues, it is possible that more extensive security plans could be required.

FranchiseLitieation - -

Three cities, with a total of approximately 18,000 customers, have litigation pending against PEF in various circuit*

courts in Florida. As discussed below, three other cities, with a total of approximately .30,000 customers, have subsequently settled their lawsuits with PEF and signed new, 30-year franchise agreements. The lawsuits principally seek 1) a declaratory judgment that the cities have the right to purchase PEF's electric distribution system located within the municipal boundaries of the cities, 2) a declaratory judgment that the value of the distribution system must be determined through arbitration, and 3) injunctive relief requiring PEF to 'continue to collect from PEF's customers and remit to the cities, franchise fees during the pending litigation, and as long as PEF continues to occupy the cities' rights-of-way to provide electric service, notwithstanding the expiration of the franchise ordinances under which PEF had agreed to collect such fees. Five circuit courts have entered orders requiring arbitration to establish the purchase price of PEF's electric distribution system within five cities. Two appellate courts have upheld these circuit court decisions and authorized cities to determine the value of PEF's electric distribution system within the cities through arbitration.

Arbitration in one of the cases (the City of Casselberry) was held in August 2002. Following arbitration, the parties entered settlement discussions, and in July 2003 the City approved a'settlement agreement and a new, 30-year franchise agreement with PEF. The settlement resolves all pending litigation with that city. A second arbitration (with the 13,000-customer City'of Winter Park) was completed in February 2003. That arbitration panel issued an award in May 2003 setting the value of PEF's distribution system within the City of Winter Park at approximately

$32 million, not including separation and reintegration costs and construction work in progress, which could add several million dollars to the award. The panel also awarded PEF approximately $11 million in stranded costs,

-which according to the award decreases over time. In September 2003, Winter Park voters passed a referendum that would authorize the City to issue bonds of up to approximately $50 million to acquire PEF's' electric distribution system. While the City has not yet definitively decided whether it will acquire the system,' on April 26, 2004, the

- 'City Commission voted 'to enter into a hedge agreement to lock into interest rates for the acquisition of the system and to proceed with the acquisition; The City sought and received wholesale power supply bids and on June 23,

-2004, executed a wholesale power supply contract with PEF. On May 12, 2004, the City solicited bids to operate and maintain the distribution system. The City received bids' on July 1, 2004, and expects to make its selection in August 2004. The City has indicated that its goal is to begin electric operations in June 2005. At this time, whether and when there will be further proceedings regarding the City of Winter Park cannot be determined.

A third arbitration (with the 2,500-customer Town of Belleair) was completed in June 2003. In September 2003, the arbitration panel issued an award in that case 'setting the value of the electric distribution system within' the Town at approximately $6 'million. The panel further required the Town to pay to'PEF its requested $1 million in

-separation and reintegration costs and approximately $2 million in stranded costs. The Town has not yet decided

'whether it will attempt to acquire the' system. At this time, whether'and when there will be further proceedings regarding the Town of Belleair cannot be determined.

A fourth arbitration (with the 13,000-customer City of Apopka) had been scheduled for January 2004. In December

'2003, the Apopka City Commission voted on first reading to' approve: a settlement agreement and a 30-year franchise with PEF. The settlement and franchise became effective upon approval by the Commission at a second reading of the franchise in January 2004. The settlement resolves all outstanding litigation between the parties.

Arbitration in the remaining city's litigation (the 1,500-customer City of Edgewood) has not yet been scheduled.

As part of the above litigation, two appellate courts have also reached opposite conclusions regarding whether PEF must continue 'to collect from its customers and remit to the cities "franchise fees" under the expired franchise ordinances. PEF has filed an appeal with'the Florida Supreme Court to resolve the conflict between the two appellate, courts. The Florida Supreme Court held oral argument in one of the appeals in August' 2003.

Subsequently, the Court requested briefing fr6m the parties in the other appeal, which was completed in November

'2003. The Company cannot predict the outcome of these matters at this time.

59.

Progress Energy Carolinas, Inc.

The information required by this itemn is incorporated herein by reference to the following portions of Progress Energy's Management's Discussion and Analysis of Financial Condition and Results of Operations, insofar as they relate solely to PEC: RESULTS OF OPERATIONS; LIQUIDITY AND CAPITAL RESOURCES and OTHER MATTERS. -

-RESULTS OF OPERATIONS The results of operations for the PEC Electric segment are identical between PEC and Progress Energy. The results of operations for PEC's non-utility subsidiaries for the three and six months ended June 30, 2004 and 2003 are not'

-.material to PEC's consolidated financial statements. ' -

LIOUIDITY AND CAPITAL RESOURCES As of June 30, 2004, PEC's' contractual cash obligations and other commercial commitments have not changed materially from what was reported in the 2003 Annual Report on Form 10-K.

Cash provided by operating activities decreased $45 million for the six months ended June 30, 2004, when

compared to the corresponding period in the prior year., The decrease was caused primarily by a S34 million increase in working capital requirements. '

Cash used in investing activities decreased S13 million for the six months ended June 30,' 2004, when compared to the corresponding period in the prior year primarily' due to lower construction spending.

$150 million of First Mortgage Bonds matured on January 15, 2004' and $150 million of First Mortgage Bonds

'matured on April 15, 2004. The remaining $300 million current'portion of long-term debt will be refinanced or retired through commercial paper, capital market transactions and internally generated funds.

On July 28, 2004, PEC extended its $ 165 million 364-day line of credit, which was to expire on July 29, 2004. The line of credit will expire on July 27, 2005.'

PEC his'exclusively utilized external funding for its decommissioning liability since 1994. Prior to 1994, PEC retained its funds internally to meet its decommissioning liability. A North Carolina Utilities Commission (NCUC) order issued in February 2004 found that by January 1, 2008,' PEC must begin transitioning these amounts to

external funds. 'The transition.of $131 million must be completed by December 31, 2017, and at least 10% must be transitioned each year. ' ' .

60 .

60':'

- ' Item 3. Quantitative and Oualitative Disclosures About Market Risk' Progress Energy, Inc.

Other than described below, the various risks that the Company is'exposed to has not materially changed since

December 31, 2003.;

Market risk represents the potential loss arising from adverse changes in market rates and'prices. Certain market risks are inherent in the Company's financial instruments, which arise from transactions entered into in the normal course of business.' The Company's primary exposures are changes in interest rates with respect to its long-term debt and commercial paper, and fluctuations in the return on marketable securities with respect to its nuclear decommissioning trust funds. The Company manages its market risk in accordance with its established risk management policies, which may include entering into various derivative transactions.

- : The Company's exposure to return on marketable securities for the decommissioning trust funds has not changed materially since December 31, 2003. The Company's exposure to market value risk with respect to the CVOs has also not changed materially since December 31, 2003. The exposure to changes in interest rate from the Company's commercial pa'per was not materially different than at December 31, 2003.

The exposure to changes in interest rates from the Company's fixed rate and variable rate long-term debt at June 30, 2004 has changed from December 31, 2003. The total fixed rate long-teri debt at June 30, 2004 was $8.6 billion, with an average interest rate of 6.53% and fair market value of $9.3 billion. The total variable rate long-term debt at June 30, 2004, was $ 1.1 billion, with an average interest rate of 1.70% and fair market value of $1.1 billion.

The company maintains a' portion of its outstanding debt with floating interest rates. As of June 30, 2004 approximately 22% of consolidated debt was in floating rate mode compared to 18% at the end of 2003.

Progress Energy uses interest rate derivative instruments to adjust the fixed and variable rate debt components of its debt portfolio and to hedge interest rates with regard to future fixed rate debt issuances.

- .~~~~~~. ..*-,,,.:..

-As of June 30, 2004, Progress Energy had $1 billion of fixed rate debt swapped to floating'rate debt by executing interest'rate derivative agreements.. Under terms of these swap rate agreements, Progress'Energy will receive a fixed rate and pay a floating rate based on 3-month LIBOR.' These agreements expire between March 2006 and March 2011. During the year, Progress Energy has entered into $350 million notional of open interest rate fair value hedges. In March 2004, two interest rate swap agreements totaling $200 million were terminated. These swaps were associated with Progress Energy 5.85% Notes due in 2008. The loss on the agreements was deferred

' and is being amortized over the life of the bonds as these agreements had been designated as fair value hedges for accounting purposes.. ' - '

As of June 30, 2004, PEC had $70 million notional of pay fixed forward starting swaps, entered into in March 2004, to hedge its exposure to interest rates with regard to a future issuance of debt and $26 million notional of pay fixed forward starting swaps, in April 2004, to hedge its exposure to interest rates with regard to an upcoming railcar

' lease. In July 2004, PEC entered into an additional $30 million notional pay fixed forward swap, increasing' the total to S126 million. These agreements have a computational period often years.

In May 2004, the Company terminated interest rate cash flow hedges, with a total notional amount of S400 million, related to projected outstanding balances of commercial paper. Amounts'in accumulated other comprehensive income related to these terminated hedges will be reclassified to earnings as the hedged interest payments occur.

The Company holds interest rate collars with a varying notional amount (currently at the maximum of $195 million)

-to hedge floating rate exposure associated with variable rate long-term debt at Progress Ventures. The Company is required to hedge 50% of the amount outstanding under its bank facility through March 2007. -

The notional amounts of interest rate derivatives are not exchanged and do not represent exposure to credit loss. In the event of default by a counterparty, the risk in the transaction is the cost of replacing the agreements at current market rates.. Progress Energy only enters into interest rate derivative agreements with banks with'credit ratings of single A or better. :

61

PEF has entered into derivative instruments to hedge its exposure to price fluctuations onr fuel oil purchases. These instruments did not have a material impact on the Company's consolidated financial position or results of operations.

Progress Fuels Corporation, through Progress Ventures, Inc.- (PVI), periodi6cliy enters into derivative instruments to hedge its exposure to price fluctuations on natural gas sales. As of June 30, 2004, Progress Fuels Corporation is hedging exposures to the price variability of portions of its natural gas production through December 2005. These instruments' did not have a material impact on the Company's consolidated financial position or results of operations.

Nonhedging derivatives, primarily electricity and natural gas contracts, are entered into for trading purposes and for economic hedging purposes. While management believes the economic hedges mitigate exposures to fluctuations in commodity prices, these -instruments are not designated as hedges for accounting purposes and are monitored consistent with trading positions. -

Progress Energv Carolinas, Inc.,

Other than described below, the various risks that PEC is exposed to has not materially changed since December 31, 2003..

PEC has certain market risks inherent in its financial instruments, which arise from transactions entered into in the normal course of business. PEC's primary exposures are changes in interest rates with respect to long-term debt and commercial paper, and fluctuations in the return on marketable securities with respect to its nuclear decommissioning trust funds. PEC's exposure to return on marketable securities for the decommission trust funds

  • has not changed materially since December 31, 2003.

The exposure to changes in interest rates from PEC's fixed rate long-term debt, variable rate' ong-term debt and commercial paper at June 30, 2004 was not materially different than at December 31, 2003.

As of June 30, 2004, PEC had $70 million notional of pay fixed foiward starting swaps, entered into in March 2004, to hedge its exposure to interest rates with regard to a future issuance of debt and $26 million notional of pay fixed forward starting swaps, in April 2004, to hedge 'its exposure to interest rates with regard to an upcoming railcar lease; -In July 2004, PEC entered into an additional $30 million notional pay fixed forward swap, increasing the

'total to $126 million. These agreements have a computational period of ten years. -

The notional amounts of the above contracts are not exchanged and do not represent exposure to credit loss. In the event of default by a' counterparty, the risk in the transaction is the 'cost of replacing the agreements at current market rates. PEC only enters into interest rate derivative agreements with banks with credit ratings of single A or better. ' '  :

. . I I ..

I .

62

.. i

. . I .1 . r I Item 4: Controls and Procedures Progress Energy. Inc.

Pursuant to the Securities Exchange Act of 1934, Progress Energy carried out an evaluation, with the participation of Progress Energy's management, i'ncluding Progress Energy's President anid Chief Executive Officer, and Chief Financial Officer, of the effectiveness of Progress Energy's disclosure controls and procedures (as defined under the Securities Exchange Act of 1934) as of the end of the period covered by this report. Based upon that evaluation, Progress Energy's President and Chief Executive Officer, and Chief Financial Officer concluded that Progress Energy's disclosure controls and procedures are effective in timely alerting them to material information relating to

. ;Progress Energy (including its consolidated subsidiaries) required to be included in Progress Energy's periodic SEC filings.:

There has been no change identified in Progress Energy's internal control over financial reporting during the quarter

- ended June 30, 2004 that has materially affected, or is reasonably likely to materially affect, Progress Energy's internal control over financial reporting.

Proerress Energy Carolinas. Inc.

Pursuant to the Securities Exchange Act of 1934, PEC carried out an-evaluation, with the participation of PEC's

-management, including PEC's .President and Chief Executive Officer, and Chief Financial Officer, of the effectiveness of PEC's disclosure controls and procedures (as defined under the Securities Exchange Act of 1934) as of the end of the period covered by this report. 'Based upon that evaluation, PEC's President and Chief Executive Officer, and Chief Financial Officer concluded that PEC's disclosure controls and procedures are

. effective in timely alerting them to material information relating to PEC (including its consolidated subsidiaries) required to be included in PEC's periodic SEC filings.:

There has been no change identified in PEC's internal control over financial reporting during the quarter ended June

30, 2004 that has materially affected, or is reasonably, likely to materially affect, PEC's internal control over financial reporting. - - -

I I .

. . . .63

-J, PART II. OTHER INFORMATION' Item I. Legal Proceedines Legal aspects of certain matters Paire set forth in Part I, Item l. See Note 12 to the Progress Energy, Inc.

'Consolidated Interim Financial Statements and Note 10 to the PEC's Consolidated Interim Financial Statements.

I. Strategic Resource Solutions Corp. ("SRS") v. San Francisco'Unified School District, et al.,

Sacramento Superior Court, Case No. 02AS033114 In November 2001, SRS filed a claim against the San Francisco Unified School District (the District) and other defendants claiming that SRS is entitled to approximately $10 million in unpaid contract payments and delay and impact damages related to the District's $30 million contract with SRS. 'In March 2002, the District filed a counterclaim, seeking compensatory damages and liquidated damages in excess of $120 million, for various claims, including breach of contract and demand on a performance bond. SRS asserted defenses to the District's claims.

- 'SRS amended its claims and asserted new claims against the District and'other parties, including a former SRS employee and a former District employee.

In March 2003,'the City Attorney and the District filed new claims in the form of a cross-complaint against SRS, Progress Energy, Inc., Progress Energy' Solutions, Inc., and certain individuals, alleging fraud, false claims, violations of California statutes, and seeking compensatory damages, punitive damages, liquidated damages, treble

'damages, penalties, attorneys' fees and injunctive relief. The filing stated that the City and the District seek "more than S300 million in damages and penalties." PEC was later added as a cross-defendant. In November 2003, PEC filed a motion to dismiss the plaintiffs' first amended complaint. '

In June 2004, the Company reached a settlement agreement with the District in this matter. The settlement totaled approximately. $43.1 million and was recorded as a charge to diversified business cost of sales in the Company's Consolidated Statement of Income for the three-months ended June 30, 2004. The accrual of the settlement was recorded on an undiscounted basis. The terms of the settlement require SRS to pay the District S10.1 million upon approval, and an additional $16 million in 2005 and S17 million 2006. In addition, during a transition period ending September 10,' 2004; SRS will provide maintenance and training on the equipment and software it installed

-and maintained for the District. The agreement, upon approval, settles all claims and cross-claims related to SRS, Progress Energy, Progress Energy Solutions and PEC.

-2. U.S. Global, LLC v. Progress Energy, Inc. et al, Case No.'03004028-03 and Progress Synfuel Holdings, Inc. et al, v. U.S. Global, LLC, Case No. 03004028-03 A number of Progress Energy, Inc. subsidiaries and affiliates are parties to two lawsuits arising out of an Asset Purchase Agreement dated as of October 19, 1999, by and among U.S. Global LLC (Global), EARTHCO, certain affiliates of EARTHCO (collectively the EARTHCO Sellers), EFC Synfuel LLC (which is.owned indirectly be Progress Energy, Inc.) and certain of its affiliates, including Solid Energy LLC, Solid Fuel LLC, Ceredo Synfuel LLC, Gulf Coast Synfiiel LLC (currently named Sandy River Synfuel LLC) (Collectively the Progress Affiliates),

as amended by an amendment to Purchase Agreement as of August 23,'2000 (the Asset Purchase Agreement).

Global has asserted that pursuant to the Asset Purchase Agreement it is entitled to (1) an interest in two synthetic

'fuel facilities currently owned by the Progress Affiliates, and (2) an option to purchase additional interests in the two synthetic fuel facilities.

'The first suit, U.S. Global, LLC v. Progress Energy, Inc. et al, was filed in the Circuit Court for Broward County, Florida in March 2003 (the Florida Global Case). The Florida Global Case asserts claims for breach of the Asset Purchase Agreement and other contract and tort claims related to the.Progress Affiliates' alleged interference with Global's rights under the Asset Purchase Agreement. The Florida Global Case requests an unspecified amount of compensatory damages, as well as declaratory relief. On December 15, 2003, the Progress Affiliates filed a motion to dismiss the Third Amended Complaint in the Florida Global Case. 'The motion to dismiss filed on behalf of the Progress Energy, Inc. subsidiaries and affiliates that are parties to the case was heard by the Circuit Court of Broward County, Florida on June 7,2004. The case was dismissed on procedural issues, but allowed the plaintiff to refile. The case was'refhled on June 23, 2004.

64

The second suit, Progress Synfuel Holdings, Inc. ct al. v. U.S. Global, LLC, was filed by the Progress Affiliates in the Superior Court for Wake County, North Carolina seeking declaratory relief consistent with the Company's interpretation'of the asset Purchase Agreement (the North Carolina Global Case). Global was served with the North Carolina Global Case on April 17, 2003. -

On May 15, 2003, Global moved to dismiss the North Carolina Global Case for lack of personal jurisdiction over Global. In the alternative, Global requested that the court decline to exercise its discretion to hear the Progress

'Affiliates' declaratory judgment action.' OnAugust 7, 2003, the Wake County Superior court denied Global's motion to dismiss and entered an' order staying 'the North Carolina Global Case, pending the outcome of the Florida Global Case. The Progress Affiliates have appealed the Superior court's order staying the case; Global has cross appealed the denial of its motion to dismiss for lack of personal jurisdiction.' The North Carolina Court of Appeals heard argument on the Progress Affiliates' Appeal and the Global's cross appeal on May 26, 2004. There has been no ruling on the appeal or the cross appeal. The Company cannot predict the outcome of these matters, but will vigorously defend against the allegations. '

3.: In re Progress Energy, Inc. Securities Litigation, Master File No. 04-CV-636 (JES)

On February 3, 2004,' Progress Energy, Inc. was served with a class action complaint alleging violations of federal security laws in connection with the Company's issuance of Contingent Value Obligations (CVOs). The action was filed by Gerber Asset Management LLC in the Uniited States District Court for the Southern District of New York and names Progress Energy, Inc.'s former Chairman William Cavanaugh III and Progress Energy, Inc. as defendants. The Complaint alleges that Progress Energy failed to timely disclose the impact of the Alternative Minimum Tax required under Sections 55-59 of the Internal Revenue Code (Code) on the value of certain' CVOs issued in connection with the Florida Progress Corporation 'merger. 'The suit seeks'unspecified compensatory damages, as well as, attorneys' fees and litigation costs.

On March 31, 2004, a second class action complaint was filed by Stanley Fried, Raymond X. Talamantes and Jacquelin Talamantes against William Cavanaugh III and Progress Energy, Inc. in the United States District Court for the Southern District of New York alleging violations of federal securities laws arising out of the Company's issuance of CVOs nearly identical to those alleged in the February 3,'2004 Gerber Asset Management complaint.

On April 29, 2004, the Honorable John E. Sprizzo ordered among other things that'(1) the two class action cases be consolidated, (2) Peak6 Capital Management LLC shall serve as the lead plaintiff in the consolidated action, and (3) the lead plaintiff shall file a consolidated amended complaint on or before June 14, 2004.

The lead plaintiffs filed a consolidated amended complaint on June 15, 2004. In addition to the allegations asserted

'in the Gerber Asset Management and Fried complaints, the consolidated amended complaint alleges that the Company failed to disclose that excess fuel credits could not be carried over from one tax year into later years. On July 30,2004, the Company filed a motion to dismiss the complaint.

The Company cannot predict the outcome of this matter, but will vigorously defend against the allegations.

65

Item 2. Changes in Securities. Use of Proceeds and Issuer Purchases of Equity Securities RESTRICTED STOCK AWARDS:

(a) Securities Delivered. On April 28, 2004, 23,300 restricted shares of the Company's Common Shares were granted to certain key employees pursuant to the terms of the Company's 2002 Equity Incentive Plan (Plan), which was approved by the Company's shareholders on May 8, 2002. Section 9 of the Plan provides for the granting of Restricted Stock by the Organization and Compensation Committee of the Company's Board of Directors, (the Committee) to key employees of the Company, including its Affiliates or any successor, and to outside directors of the Company. The Cornmon Shares delivered pursuant to the Plan:

were acquired in market transactions directly for the accounts of the recipients and do not represent newly

-issued shares of the Company.

(b) Underwriters and Other Purchasers. No underwriters were used in connection with the delivery of Common Shares described'above. The Common Shares were delivered to certain key employees of the

'Company. The Plan defines "key employee" as'an officer or other employee of the Company who is selected for participation in the Plan.

' (c) . Consideration. The Common Shares were delivered to'provide an incentive to the employee recipients to exert their utmost efforts on the Company's behalf and thus enhance the Company's performance while aligning the employee's interest with those of the Company's shareholders.

  • (d) Exemption from Registration Claimed. The Common Shares described in this Item were delivered on the basis of an exemption from registration under Section 4(2) of the Securities Act of 1933. Receipt of the

-Common Shares required no investment decision on the part of the recipients. All award decisions were made by the Committee, which consists entirely of non-employee directors.

.. t I .

., t, %.

I m. . . . .. : . ,1

66

'Item 4. Submission of Matters to a Vote of Security Holders Progress En~rgy Inc.

(a) The Annual Meeting of the Shareholders of Progress Energy, Inc. was held on May 12, 2004.

(b) The meeting involved the election of five Class III directors to serve for three-year terms.. Proxies for the meeting were solicited pursuant to Regulation 14, there was no solicitation in opposition to management's nominees as listed below, and all nominees were elected.

  • (c) The total votes for the election of directors were as follows:

Class III VtsFrVotes Withheld (Term Expiring in 2007)

Charles W. Coker 208,883,229 4,775,358 Robert B. McGehee 20,908 4,268,503.

E. Marie McKee 209,566,761 4,091,826 Peter S. Rummell 209,456,069 4,202,518 Jean Giles Wittner., 207,028,428 6,630,159 (d) The shareholder proposal relating to stock options for Director's and certain Executive Officers was presented,

- .but was not approved by the shareholders.

The number of shares voted for the proposal was 23,184,068 The number of shares voted against the proposal was 148,433,662

'The number of abstaining votes was 4,850,014

-The delivered not yoted total was 37,190,843 Carolina Power & Light Comlpany. doin~ business a's Progress En.ergy Carolinas.-Inc.

(a) The Annual Meeting of the Shareholders of Carolina Power & Light Company was held on May 12, 2004.

(b) The meeting involved the election of five Class III directors to serve three-year terms. Proxies for the meeting were solicited pursuant to Regulation' 14, there was no solicitation in opposition to management's nominees as..

listed below, and all nominees were elected. .

(c), The total votes for the election of directors were as follows:

Class III *.*Votes For Votes Withheld (Term Expiring in 2007)

Charles W.Coker 1 994,384 .6,8 Robert B. McGehee. 159,964,895 5,876 E. Marie McKee 196517 -5,254 Peter S. Rummell - 59,964,707 6,064.

Jean Giles Wittner 159,964,687, 6,064

.67-

Item S. Other Information APPOINTMENT OF PRESIDING DIRECTOR John H. Mullin, III was appointed Chairman of the Corporate Governance Committee of the Company's Board of Directors at the Board meeting that immediately followed the Company's Annual Meeting of Shareholders on May 12, 2004. By virtue of that position, Mr. Mullin is also the Presiding Director of the Board. (Mr. Mullin succeeds J.

Tylee Wilson, who retired from the Board on. May 12, 2004.) As Presiding Director, Mr. Mullin chairs the executive sessions of the non-employee Directors. Mr. Mullin can be contacted by writing to John H. Mullin, III, Presiding Director, Progress Energy Board of Directors,' co Corporate Secretary, P.O. Box 1551, Raleigh, NC.

27602. Progress Energy screens mail addressed to Mr. Mullin for security purposes and to ensure that it relates to discrete business matters that are relevant to Progress Energy.' Mail addressed to Mr. Mullin which satisfies these screening criteria will be forwarded to him.

. . I . I

. I. . . 1.

... I i

. I . . . . . I .

. .. . . 6 8 . . -

...  :; 1;

( 7 : .. .'j,,

-t. - :,

.. .1 . : I. , . I

. t i I 1:I; . 1 , . :, ,

I1tem 6. Exhibits and Reports on Form'8-K

  • (a) Exhibits

..Exhibit ..Progress

  • Progress Energy-Zumnber Deicription' ..Enerj'v. Inc. .. Carolinas. Inc.

I10(i) Progress Energy, Inc. S1,130,000,00 5-Year. .x Revolving Credit Agreement dated as of 31(a) Certifications pursuant to Section 302 of~ the. x x Sarbanes-Oxley Act of 2002- Chairman, President and Chief Executive Officer 31(b) -Certifications, pursuant -to Section 302 of the x x Sarbanes-Oxley Act of 2002 - Executive Vice Preiident and Chief Financial.Officer

.32(a) Certifications' pursuant to Section 906 of the x S arbanes-Oxley Act of 2002 '~Chairman,'

  • President 'and Chief Executive Officer 32(b) Certifications pursuant to Section 906 :of the x
  • . . SarbanesOiy c f 2002 -Executive Vie President and Chief Financial Officer

.(b) Reports filed or furnished on Form 8-K since the beginning of the quarter:

Progress Energy,.Inc.,

Financial Item Statements Reported *-Includedi *Date of Event* Date Filed or Furnished 9,12 Yes * -July.21 `2004 -- -July 21, 2004

5,9' No *-July 7,2~004.

7, 9 Yes June 15, 2004 June 16, 2004 7, 9 No' -May 28, 2004 May 28,2004 No 'May 13, 2004' May 18, 2004 7,-9 No April 28, 2004 April 28, 2004

  • 7, 11 No *April5, 2004 April 23, 2004

-9,12

  • Yes April 21, 2004'. April 21, 2004 fl. - -I?. T1L.<__ - T '-I-, l C.aroixna rower om Ligni Co..mpany

-d/b/a Projgress Energy Carolinas. Inc.

- rjuhiilLIai

.. Item Statements Reported - InMcluded Date of Event Date Filed or Furnished

.9, 12

  • Yes . -July 21, 2004 July 21, 2004 9, 12 .' ': - - Yes April 21, 2004 April 21, 2004

..69

. I . . . I. ~ .. .

. 1 .

SIGN4ATURES

.Pursuant to requirements of the'Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned thereunto duly authorized.

PROGRESS ENERGY. INC.

CAROLINA POWER & LIGHT COMPANY Date: August 6, 2004 (Registrants)

By: /sf Geoffrey S. Chatas Geoffrey S. Chatas Executive Vice President and Chief Financial Officer.

By: 1sl Robert H. Bazemore. Jr.

Robert H. Bazemore, Jr.

-Vice President and Controller Chief Accounting Officer 1.

I . . I .. z . .

70