MONTHYEARML24100A8062024-04-0909 April 2024 Duke Energy Sites Annual Assessment Meeting Presentation Slides April 23, 2024 ML23087A2972023-04-17017 April 2023 Annual Assessment Meeting Presentation ML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22130A0102022-04-28028 April 2022 Duke Presentation for April 28, 2022 Public Meeting - Containment Liner ML22130A0092022-04-28028 April 2022 Duke Presentation for April 28, 2022 Public Meeting - Bolting Integrity ML22109A2122022-04-20020 April 2022 Duke Energy Pre-Submittal Public April 20, 2022, Meeting Presentation ML22075A2012022-03-0707 March 2022 Duke 03/07/2022 Presentation - Bolting Integrity ML22067A1992022-03-0303 March 2022 Annual Assessment Meeting Presentation ML22301A1672022-02-0505 February 2022 Presentation 5 - Oconee Trip and Notification of Unusual Event on February 5, 2022 ML22063A1142022-01-17017 January 2022 Duke Presentation for Public Meeting on February 17, 2022 ML21322A3262021-11-29029 November 2021 Duke Energy November 29, 2021 Pre-Submittal Public Meeting Slides for EOF Relocation Licensing Amendment Request ML21235A0452021-08-25025 August 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Presentation ML21102A0632021-04-14014 April 2021 ONS Slides for Pre-Application Meeting to Discuss Proposed Relief Request Related to Code Case N-853 ML21089A1732021-03-30030 March 2021 EOC Slides Final ML21081A1242021-03-22022 March 2021 EOC Slides Final ML21034A5552021-01-26026 January 2021 SLRA - NRC Presubmittal Meeting Slides ML21034A5562021-01-26026 January 2021 SLRA - Duke Presubmittal Meeting Slides ML20300A0872020-10-27027 October 2020 Subsequent License Renewal Application NRC Environmental Pre-Application Meeting - Duke Energy Presentation ML20300A0902020-10-27027 October 2020 Subsequent License Renewal Environmental Pre-Application Meeting - NRC Presentation ML20134J0052020-05-13013 May 2020 EOC Slides (2) ML20125A2312020-05-0404 May 2020 EOC Slides ML19318F2912019-11-18018 November 2019 Duke Energy Presentation for the Pre-submittal Meeting on November 18, 2019, Regarding the RPV Stud Examination Relief Request ML19302E0512019-11-0606 November 2019 High Energy Line Break License Amendment Public Meeting ML19214A0562019-08-0707 August 2019 Presentation: Duke Energy Presubmittal Meeting - August 7, 2019 ML18086A7742018-02-21021 February 2018 LOR Program Biennial Inspection 71111.11B Exam Overlap Issues ML17296A1462017-10-24024 October 2017 Duke Energy Presentation to CRGR - Oconee Nuclear Station ML17258A0122017-09-26026 September 2017 Presentation Slide Regarding Committee to Review Generic Requirements Meeting on Oconee Nuclear Station Cable Separation TIA ML15348A2032015-12-14014 December 2015 Duke Energy Presentation in Support of December 15, 2015, Public Meeting with NRC Staff Cable Testing Discussion for Proposed 50.55a Alternative Request ML15282A0722015-10-0909 October 2015 Duke Energy Presentation in Support of October 13, 2015, Public Meeting with NRC Staff Pre-Application Meeting for LAR to Support Khu Stator Replacement ML15148A2632015-05-27027 May 2015 Meeting Slides from the May 27, 2015 Oconee Major Projects Between Duke Energy and NRC ML15113A6262015-04-23023 April 2015 April 14, 2015 Summary of Public Meeting on Oconee Nuclear Station, Units 1, 2 and 3 to Discuss the Annual Assessment ML14356A0062014-12-0303 December 2014 Presentation at December 3, 2014, Category 1 Public Meeting with Duke Energy Carolinas, LLC to Discuss NTTF Recommendation 2.1, Flooding Response ML14211A2162014-07-31031 July 2014 NRC Meeting Slides 7-31-14 Reg Conference ML14211A2132014-07-31031 July 2014 Duke Energy Presentation for 2014-07-31 Meeting ML14147A3652014-05-27027 May 2014 Annual Assessment Public Meeting Summary Memo ML14058A0772014-02-0404 February 2014 Slides on Oconee Ssf Flood Barrier Breach SDP Lessons Learned ML14058A0742014-02-0404 February 2014 Slides on Oconee Ssf Flood Barrier Breach SDP - Lessons Learned ML14055A4102014-02-0404 February 2014 Meeting Slides on Standby Shutdown Facility Flood Barrier Breach Violation Informal Reassessment ML14058A0352014-02-0404 February 2014 Meeting Slides on Oconee Flood Protection and the 10 CFR 50.54(f) Response ML14058A0512014-02-0404 February 2014 Slides on Oconee Nuclear Station - Standby Shutdown Facility (Ssf) Flood Barrier Breach Violation SDP Assessment ML13336A5452013-11-13013 November 2013 Presentation Slides from Meeting with Duke Energy Carolinas, LLC, Oconee Nuclear Station Units 1, 2, and 3, Keowee Hydro Unit Generator Field Pole Rewind Project - License Amendment Request ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. ML13275A2692013-10-0303 October 2013 10/3/13 Presentation Slides from Meeting with Duke Energy Carolinas, LLC, Oconee Nuclear Station Units 1, 2, and 3, Protected Service Water Alternate Cooling ML13275A2252013-09-24024 September 2013 9/24/13 Meeting Slides from Meeting with Duke Energy Carolinas, LLC, Oconee Nuclear Station Units 1, 2, and 3, Jocassee Dam Seismic Analysis ML13239A3402013-08-27027 August 2013 Presentation for NRC Projects ML13239A3372013-08-27027 August 2013 NRC Meeting Slides, Oconee Major Project Meeting - August 28, 2013 ML13226A2662013-05-0303 May 2013 E-mail from J. Boska, NRR to S. Hicks, Ois FW: Change in Public Availability of Slide Package ML13226A2592013-04-23023 April 2013 E-mail from D. Hubbard, Duke to J. Boska, NRR on Non-Security Sensitive Version of March 25th Presentation ML13226A2652013-04-23023 April 2013 E-mail from D. Hubbard, Duke to J. Boska, NRR on Security Sensitive Version 2024-04-09
[Table view] |
Text
I Duke UEnergy. Oconee Nuclear Site NRC Management Update January 28, 2003 1
~ Duke UEnergya AGENDA
"* Opening Remarks - Ron Jones
"* Oconee Performance Overview - Bruce Hamilton
"* D~sign Basis Projects - Dave Baxter
"* Closing Remarks - Ron Jones 2
Duke Oconee Performance
,Energy.
Indicator Index 120 98.5 100 93.2 89 Current Industry
-Median = 95%
84.2 80 73.1 60 40 20 0 -r -F 1998 1999 2000 2001 2002 Thru November 3
nI
-a (bqm 0o 0** O) 0 0 0 0 78.37 C
-I C):
89.22 dI C) 0r¢ 91.45 0m
-4 85.64 A
I93.03 j
PDuke UEnergyOconee Reactor Scrams Oconee Reactor Scrams 1998 - 2002 6
0 1998 1999 2000 2001 2002 Year 5
P Duke OlEnergy. Oconee Radiation Exposure ONS Dose History 1998 - 2002 700 600 500 400 U Dose PL 300 oDose - Without Head Renair 200 100 0
rozz r rfV 6
PkDuke OEnergy, 2002 Performance Highlights
"*Achieved outstanding INPO Rating
"*Implemented New Emergency Operating Procedures
"*Daily Schedule Effectiveness Routinely >95%
"*Corrective Work Order Inventory <60 and Those Greater Than 180 Days Old <20
"*Human Performance Indicators (MISPOs, Rework, Etc) Trending in Right Direction 7
SIDuke IvEnergy.
Underground Power Path Re lacement 8
I Duke Underground Power U Energy. Path Replacement 9
PkDuke Underground Power UEnergy.
Path Replacement 10
PiDuke Plant Infrastructure OrEnergy.
Upgrade 11
P Duke U Energy. Major Challenges 2003-2004
"*New Reactor Vessel Head Installation
"*New OTSG Installation
"*Keowee Upgrades
"*Modifications to ECCS
"*Caustic Addition System Upgrade 12
PDuke Major Challenges 2003-2004 vEnergy.
M
"*Control Room Outside Air Intake Relocation
"*Upper Surge Tank Mods
"*Addition of 600 Volt Capacity
"*New Digital EHC Controls
P Duke UEnergy. ONS Design Basis Initiative
"*Mission
- Provide a focused review of the design basis &
implement enhancements to improve design margins and reduce plant risk
"*Sc~ope established based on:
- Key safety systems
- Event mitigation strategies
- Design criteria / Design control
- Risk insights 14
I Duke Completed Initiatives UEnergy.
(as of August 200 1)
"* HPI/LPI SITA "* ECCS Design Study
"* OSRDC
"* QA-5
"* Configuration Management
"* Improved Tech Specs
"* Review of Risk Significant
"* UFSAR Reverification
"* Emergency Power Project Operator Actions
"* EFW Design Study & "* Chapter 15 Accident Submittal Reanalysis
"* Single Failure Analysis - 9
"* Oconee Specific Seal LOCA Key Systems
"* Unit 1 RCP Seal Mod Model 15
I Duke Completed Since Last VEnergy.
Region II Update
- 600/208 V Load Capacity (Unit 2)
- Completion of all 164 SQUG modifications
- LP-19/20 cabling (Units 1 and 2)
- LPSW auto-start circuitry (Units 1, 2,
- Tornado Licensing Basis Submittal
- Keowee auxiliary power modification and abnormal procedure
- Control Room Habitability Submittal
- Auxiliary Building curbs and sealing "* Generic Letter 96-06 Resolution of pump room penetrations Submittal
- LP-15/16 QA-1 power (Unit 2) "* Auxiliary Building Flooding Submittal
- BWST vacuum breaker modification (Unit 2) "* HELB Submittal
- MS Isolation Valve Replacements "* EFW Inventory Tech Spec Submittal (Units 1, 2, and 3) 16
I Duke UEnergy. Initiatives In Progress
"* SQUG Configuration
- Auxiliary Building Management Flooding
" EFW
"*High Energy Line Break Habitability
" Tornado
"*Time Critical Operator
- MSLB/FWLB in East Actions Penetration Room
"*ECCS Modifications
- Historical Calculation Enhancement
PDuke
[anergy. Self Assessment
- Self Assessment completed this summer to identify additional design basis focus areas
- Independent consultant was used to validate the scope of the assessment and review completed work
- Conclusion of independent review is that significant progress has been made in improving Oconee's design basis
- Recommendations from the assessment have been reviewed and prioritized by the Oconee Design Review Board 18
I Duke UEnergy. Future Focus Areas
"* Oconee's self assessment identified the following areas for additional review/initiatives
- Seismic risk
- SSF Reliability
- Appendix R
- Turbine Building flooding
- External flooding
- Containment isolation
- Spent Fuel Pool cooling
"* Lower level issues identified through the assessment are being resolved through the corrective action program 19
SIDuke VEnergy 0