Category:License-Monthly Operating Report
MONTHYEARML0513000752005-05-0909 May 2005 April 2005 Monthly Operating Report for Sequoyah Nuclear Plant ML0510100232005-04-0707 April 2005 March 2005 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0506800952005-03-0808 March 2005 February 2005 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0503900572005-02-0707 February 2005 January 2005 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0501202742005-01-11011 January 2005 December 2004 Monthly Operating Report for Sequoyah Nuclear Plant ML0434304902004-12-0808 December 2004 November 2004 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0431503852004-11-10010 November 2004 October 2004 Monthly Operating Report for Sequoyah Nuclear Plant ML0428604672004-10-0808 October 2004 September 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0425202092004-09-0707 September 2004 August 2004 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0422905392004-08-16016 August 2004 July 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0419804612004-07-14014 July 2004 June 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0416203062004-06-0808 June 2004 May 2004 Monthly Operating Report for Sequoyah Units 1 and 2 ML0413203182004-05-10010 May 2004 April 2004 Monthly Operating Report for Sequoyah Nuclear Plant ML0413101772004-05-10010 May 2004 April 2004 Monthly Operating Report for Sequoyah Nuclear Plant ML0410704252004-04-0909 April 2004 March 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0407005062004-03-0909 March 2004 February 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0404104282004-02-0909 February 2004 January 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0401402762004-01-12012 January 2004 December 2003 Monthly Operating Report for Sequoyah ML0401207492004-01-12012 January 2004 December 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0335106832003-12-0909 December 2003 November 2003 Monthly Operating Report for Sequoyah ML0331605002003-11-10010 November 2003 October 2003 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0329009412003-10-0909 October 2003 September 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0325503492003-09-11011 September 2003 August 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0322705892003-08-11011 August 2003 July 2003 Monthly Operating Report for Sequoyah ML0322606452003-08-11011 August 2003 July 2003 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0319902912003-07-10010 July 2003 June 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0316712232003-06-0909 June 2003 May 2003 Monthly Operating Report for Sequoyah, Units 1 & 2 ML0312906292003-05-0808 May 2003 April 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0310501832003-04-14014 April 2003 March 2003 Monthly Operating Report for Sequoyah ML0307104182003-03-10010 March 2003 February 2003 Monthly Operating Report for Sequoyah ML0305102472003-02-14014 February 2003 January 2003 Monthly Operating Report for Sequoyah ML0301401222003-01-13013 January 2003 December 2002 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0235003322002-12-13013 December 2002 November 2002 Monthly Operating Report for Sequoyah Nuclear Power Plant ML0228104042002-10-0707 October 2002 September 2002 Monthly Operating Report for Sequoyah Units 1 & 2 ML0226801512002-09-11011 September 2002 August 2002 Monthly Operating Report for Sequoyah Units 1 & 2 ML0223306392002-08-14014 August 2002 July 2002 Monthly Operating Report for Sequoyah ML0220004352002-07-15015 July 2002 June 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0217601482002-06-13013 June 2002 May 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0227603302002-05-13013 May 2002 April 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0209508092002-04-0808 April 2002 March 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0206508242002-03-0606 March 2002 February 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0203904112002-02-0808 February 2002 January 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0201503732002-01-11011 January 2002 December 2001 Monthly Operating Report for Sequoyah Nuclear Plant 2005-05-09
[Table view] |
Text
December 13, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:
In the Matter of ) Docket Nos. 50-327 Tennessee Valley Authority ) 50-328 SEQUOYAH NUCLEAR PLANT - NOVEMBER MONTHLY OPERATING REPORT The enclosure provides the November Monthly Operating Report as required by Sequoyah Technical Specification Section 6.9.1.10.
This letter is being sent in accordance with NRC RIS 2001-05.
There are no commitments associated with this letter. If you have any questions concerning this matter, please call me at (423) 843-7170 or J. D. Smith at (423) 843-6672.
Sincerely, Original signed by Pedro Salas Licensing and Industry Affairs Manager Enclosure
ENCLOSURE TENNESSEE VALLEY AUTHORITY SEQUOYAH NUCLEAR PLANT (SQN)
MONTHLY OPERATING REPORT NOVEMBER 2002 UNIT 1 DOCKET NUMBER 50-327 LICENSE NUMBER DPR-77 UNIT 2 DOCKET NUMBER 50-328 LICENSE NUMBER DPR-79
OPERATING DATA REPORT Docket No. 50-327 Unit Name SQN Unit 1 Date December 5, 2002 Completed By Tanya Hollomon Telephone (423) 843-7528 Reporting Period November 2002
- 1. Design Electrical Rating (Net MWe): 1160
- 2. Maximum Dependable Capacity (MWe-Net) 1125 Month Yr-to-Date Cumulative
- 3. Number of Hours Reactor was Critical 720.0 8,016.0 124,721.8
- 4. Hours Generator On-Line 720.0 8,016.0 122,796.6
- 5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6. Net Electrical Energy Generated (MWh) 828,046 9,095,338 133,425,898 Docket No. 50-328 Unit Name SQN Unit 2 Date December 5, 2002 Completed By Tanya Hollomon Telephone (423) 843-7528 Reporting Period November 2002
- 1. Design Electrical Rating (Net MWe): 1160
- 2. Maximum Dependable Capacity (MWe-Net): 1126 Month Yr-to-Date Cumulative
- 3. Number of Hours Reactor was Critical 720.0 7,102.8 128,609.0
- 4. Hours Generator On-Line 720.0 7,027.3 126,481.3
- 5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6. Net Electrical Energy Generated (MWh) 819,959 7,833,255 135,015,315 E-1
UNIT SHUTDOWNS DOCKET NO: 50-327 UNIT NAME: SQN-1 DATE: December 5, 2002 COMPLETED BY: Tanya Hollomon TELEPHONE: (423) 843-7528 REPORT PERIOD: NOVEMBER 2002 No. Date Type Duration Reason1 Method of Cause and Corrective Action to Prevent Recurrence F:Forced (Hours) Shutting S:Scheduled Down Reactor2 No power reductions of greater than 20 percent during November 2002.
Summary: Unit 1 operated near 100 percent power throughout the month of November with a capacity factor of 101.9 percent. No PORVs or safety valves were challenged in November.
1 2 Reason: Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-ContinuationOutage E-Operator Training / License Examination 5-Other (Explain)
F-Administrative G-Operational Error (Explain)
H- Other (Explain)
E-2
UNIT SHUTDOWNS DOCKET NO: 50-328 UNIT NAME: SQN-2 DATE: December 5, 2002 COMPLETED BY: Tanya Hollomon TELEPHONE: (423) 843-7528 REPORT PERIOD: NOVEMBER 2002 No. Date Type Duration Reason1 Method of Cause and Corrective Action to Prevent Recurrence F:Forced (Hours) Shutting S:Scheduled Down Reactor2 No power reductions of greater than 20 percent during November 2002.
Summary: Unit 2 operated near 100 percent power throughout the month of November with a capacity factor of 100.9 percent. No PORVs or safety valves were challenged in November.
1 2 Reason: Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-ContinuationOutage E-Operator Training / License Examination 5-Other (Explain)
F-Administrative G-Operational Error (Explain)
H- Other (Explain)
E-3