Category:License-Monthly Operating Report
MONTHYEARML0513000752005-05-0909 May 2005 April 2005 Monthly Operating Report for Sequoyah Nuclear Plant ML0510100232005-04-0707 April 2005 March 2005 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0506800952005-03-0808 March 2005 February 2005 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0503900572005-02-0707 February 2005 January 2005 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0501202742005-01-11011 January 2005 December 2004 Monthly Operating Report for Sequoyah Nuclear Plant ML0434304902004-12-0808 December 2004 November 2004 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0431503852004-11-10010 November 2004 October 2004 Monthly Operating Report for Sequoyah Nuclear Plant ML0428604672004-10-0808 October 2004 September 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0425202092004-09-0707 September 2004 August 2004 Monthly Operating Report for Sequoyah Nuclear Plant, Units 1 and 2 ML0422905392004-08-16016 August 2004 July 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0419804612004-07-14014 July 2004 June 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0416203062004-06-0808 June 2004 May 2004 Monthly Operating Report for Sequoyah Units 1 and 2 ML0413203182004-05-10010 May 2004 April 2004 Monthly Operating Report for Sequoyah Nuclear Plant ML0413101772004-05-10010 May 2004 April 2004 Monthly Operating Report for Sequoyah Nuclear Plant ML0410704252004-04-0909 April 2004 March 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0407005062004-03-0909 March 2004 February 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0404104282004-02-0909 February 2004 January 2004 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0401402762004-01-12012 January 2004 December 2003 Monthly Operating Report for Sequoyah ML0401207492004-01-12012 January 2004 December 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0335106832003-12-0909 December 2003 November 2003 Monthly Operating Report for Sequoyah ML0331605002003-11-10010 November 2003 October 2003 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0329009412003-10-0909 October 2003 September 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0325503492003-09-11011 September 2003 August 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0322705892003-08-11011 August 2003 July 2003 Monthly Operating Report for Sequoyah ML0322606452003-08-11011 August 2003 July 2003 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0319902912003-07-10010 July 2003 June 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0316712232003-06-0909 June 2003 May 2003 Monthly Operating Report for Sequoyah, Units 1 & 2 ML0312906292003-05-0808 May 2003 April 2003 Monthly Operating Report for Sequoyah Nuclear Plant ML0310501832003-04-14014 April 2003 March 2003 Monthly Operating Report for Sequoyah ML0307104182003-03-10010 March 2003 February 2003 Monthly Operating Report for Sequoyah ML0305102472003-02-14014 February 2003 January 2003 Monthly Operating Report for Sequoyah ML0301401222003-01-13013 January 2003 December 2002 Monthly Operating Report for Sequoyah, Units 1 and 2 ML0235003322002-12-13013 December 2002 November 2002 Monthly Operating Report for Sequoyah Nuclear Power Plant ML0228104042002-10-0707 October 2002 September 2002 Monthly Operating Report for Sequoyah Units 1 & 2 ML0226801512002-09-11011 September 2002 August 2002 Monthly Operating Report for Sequoyah Units 1 & 2 ML0223306392002-08-14014 August 2002 July 2002 Monthly Operating Report for Sequoyah ML0220004352002-07-15015 July 2002 June 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0217601482002-06-13013 June 2002 May 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0227603302002-05-13013 May 2002 April 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0209508092002-04-0808 April 2002 March 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0206508242002-03-0606 March 2002 February 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0203904112002-02-0808 February 2002 January 2002 Monthly Operating Report for Sequoyah Nuclear Plant ML0201503732002-01-11011 January 2002 December 2001 Monthly Operating Report for Sequoyah Nuclear Plant 2005-05-09
[Table view] |
Text
March 6, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:
In the Matter of ) Docket Nos. 50-327 Tennessee Valley Authority ) 50-328 SEQUOYAH NUCLEAR PLANT - FEBRUARY MONTHLY OPERATING REPORT The enclosure provides the February Monthly Operating Report as required by Sequoyah Technical Specifications Section 6.9.1.10.
This letter is being sent in accordance with RIS 2001-05.
If you have any questions concerning this matter, please call me at (423) 843-7170 or J. D. Smith at (423) 843-6672.
Sincerely, Original signed by Pedro Salas Licensing and Industry Affairs Manager Enclosure
ENCLOSURE TENNESSEE VALLEY AUTHORITY SEQUOYAH NUCLEAR PLANT (SQN)
MONTHLY OPERATING REPORT FEBRUARY 2002 UNIT 1 DOCKET NUMBER 50-327 LICENSE NUMBER DPR-77 UNIT 2 DOCKET NUMBER 50-328 LICENSE NUMBER DPR-79
OPERATING DATA REPORT Docket No. 50-327 Unit Name SQN Unit 1 Date March 1, 2002 Completed By T. J. Hollomon Telephone (423) 843-7528 Reporting Period
- 1. Design Electrical Rating (Net MWe): 1148
- 2. Maximum Dependable Capacity (MWe-Net) 1122 Month Yr-to-Date Cumulative
- 3. Number of Hours Reactor was Critical 672.0 1,416.0 118,121.8
- 4. Hours Generator On-Line 672.0 1,416.0 116,196.6
- 5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6. Net Electrical Energy Generated (MWh) 773,870 1,629,019 125,959,579 Docket No. 50-328 Unit Name SQN Unit 2 Date March 1, 2002 Completed By T. J. Hollomon Telephone (423) 843-7528 Reporting Period
- 1. Design Electrical Rating (Net MWe): 1148
- 2. Maximum Dependable Capacity (MWe-Net): 1117 Month Yr-to-Date Cumulative
- 3. Number of Hours Reactor was Critical 672.0 1,416.0 122,922.3
- 4. Hours Generator On-Line 672.0 1,416.0 120,870.1
- 5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6. Net Electrical Energy Generated (MWh) 857,349 857,349 128,813,668 E-1
UNIT SHUTDOWNS DOCKET NO: 50-327 UNIT NAME: SQN-1 DATE: March 1, 2002 COMPLETED BY: T. J. Hollomon TELEPHONE: (423) 843-7528 REPORT PERIOD: FEBRUARY 2002 No. Date Type Duration Reason Method of Cause and Corrective Action to Prevent Recurrence F:Forced 1 (Hours) Shutting S:Scheduled Down Reactor2 No power reductions of greater than 20 percent during February 2002.
Summary : Unit 1 operated near 100 percent power throughout the month of February with a capacity factor of 102 percent. No PORVs or safety valves were challenged in February.
1 2 Reason: Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-ContinuationOutage E-Operator Training / License Examination 5-Other (Explain)
F-Administrative G-Operational Error (Explain)
H- Other (Explain)
E-2
UNIT SHUTDOWNS DOCKET NO: 50-328 UNIT NAME: SQN-2 DATE: March 1, 2002 COMPLETED BY: T. J. Hollomon TELEPHONE: (423) 843-7528 REPORT PERIOD: FEBRUARY 2002 No. Date Type Duration Reason Method of Cause and Corrective Action to Prevent Recurrence F:Forced 1 (Hours) Shutting S:Scheduled Down Reactor2 No power reductions of greater than 20 percent during February 2002.
Summary: Unit 2 operated near 100 percent power throughout the month of February with a capacity factor of 103 percent. No PORVs or safety valves were challenged in February.
1 2 Reason: Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-ContinuationOutage E-Operator Training / License Examination 5-Other (Explain)
F-Administrative G-Operational Error (Explain)
H- Other (Explain)
E-3