December 2001 Monthly Operating Report for Sequoyah Nuclear Plant
ML020150373
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 01/11/2002
From: Salas P
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML020150373 (6)


Text

January 11, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:

In the Matter of

)

Docket Nos. 50-327 Tennessee Valley Authority

)

50-328 SEQUOYAH NUCLEAR PLANT - DECEMBER MONTHLY OPERATING REPORT The enclosure provides the December Monthly Operating Report as required by Sequoyah Technical Specifications Section 6.9.1.10.

This letter is being sent in accordance with RIS 2001-05.

If you have any questions concerning this matter, please call me at (423) 843-7170 or J. D. Smith at (423) 843-6672.

Sincerely, Original signed by J. D. Smith for Pedro Salas Licensing and Industry Affairs Manager Enclosure

ENCLOSURE TENNESSEE VALLEY AUTHORITY SEQUOYAH NUCLEAR PLANT (SQN)

MONTHLY OPERATING REPORT DECEMBER 2001 UNIT 1 DOCKET NUMBER 50-327 LICENSE NUMBER DPR-77 UNIT 2 DOCKET NUMBER 50-328 LICENSE NUMBER DPR-79

E-1 OPERATING DATA REPORT Docket No.

50-327 Unit Name SQN Unit 1 Date January 4, 2002 Completed By T. J. Hollomon Telephone (423) 843-7528 Reporting Period 1.

Design Electrical Rating (Net MWe):

1148 2.

Maximum Dependable Capacity (MWe-Net) 1122 Month Yr-to-Date Cumulative 3.

Number of Hours Reactor was Critical 744.0 8,012.1 116,705.8 4.

Hours Generator On-Line 744.0 7,989.6 114,780.6 5.

Unit Reserve Shutdown Hours 0.0 0.0 0.0 6.

Net Electrical Energy Generated (MWh) 854,592 9,018,985 124,330,560 Docket No.

50-328 Unit Name SQN Unit 2 Date January 4, 2002 Completed By T. J. Hollomon Telephone (423) 843-7528 Reporting Period 1.

Design Electrical Rating (Net MWe):

1148 2.

Maximum Dependable Capacity (MWe-Net):

1117 Month Yr-to-Date Cumulative 3.

Number of Hours Reactor was Critical 744.0 8,760.0 121,506.0 4.

Hours Generator On-Line 744.0 8,760.0 119,454.1 5.

Unit Reserve Shutdown Hours 0.0 0.0 0.0 6.

Net Electrical Energy Generated (MWh) 855,265 9,939,871 127,182,060

E-2 UNIT SHUTDOWNS DOCKET NO:

50-327 UNIT NAME:

SQN-1 DATE:

January 4, 2002 COMPLETED BY: T. J. Hollomon TELEPHONE:

(423) 843-7528 REPORT PERIOD: DECEMBER 2001 No.

Date Type F:Forced S:Scheduled Duration (Hours)

Reason 1

Method of Shutting Down Reactor2 Cause and Corrective Action to Prevent Recurrence Summary : Unit 1 operated at 100 percent power throughout the month of December with a capacity factor of 105 percent. No PORVs or safety valves were challenged in December.

1 Reason:

2 Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-ContinuationOutage E-Operator Training / License Examination 5-Other (Explain)

F-Administrative G-Operational Error (Explain)

H-Other (Explain)

E-3 UNIT SHUTDOWNS DOCKET NO:

50-328 UNIT NAME:

SQN-2 DATE:

January 4, 2002 COMPLETED BY: T. J. Hollomon TELEPHONE:

(423) 843-7528 REPORT PERIOD: DECEMBER 2001 No.

Date Type F:Forced S:Scheduled Duration (Hours)

Reason 1

Method of Shutting Down Reactor2 Cause and Corrective Action to Prevent Recurrence Summary: Unit 2 operated at 100 percent power throughout the month of December with a capacity factor of 105 percent. No PORVs or safety valves were challenged in December.

1 Reason:

2 Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-ContinuationOutage E-Operator Training / License Examination 5-Other (Explain)

F-Administrative G-Operational Error (Explain)

H-Other (Explain)