December 9, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:
In the Matter of
)
Docket Nos. 50-327 Tennessee Valley Authority
)
50-328 SEQUOYAH NUCLEAR PLANT - NOVEMBER MONTHLY OPERATING REPORT The enclosure provides the November Monthly Operating Report as required by Sequoyah Technical Specification Section 6.9.1.10.
If you have any questions concerning this matter, please call me at (423) 843-7170 or J. D. Smith at (423) 843-6672.
Sincerely, Original signed by:
Pedro Salas Licensing and Industry Affairs Manager Enclosure cc (Enclosure):
Mr. Michael L. Marshall, Jr., Senior Project Manager U.S. Nuclear Regulatory Commission MS O-8G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2739
ENCLOSURE TENNESSEE VALLEY AUTHORITY SEQUOYAH NUCLEAR PLANT (SQN)
MONTHLY OPERATING REPORT NOVEMBER 2003 UNIT 1 DOCKET NUMBER 50-327 LICENSE NUMBER DPR-77 UNIT 2 DOCKET NUMBER 50-328 LICENSE NUMBER DPR-79
E-1 OPERATING DATA REPORT Docket No.
50-327 Unit Name SQN Unit 1 Date December 4, 2003 Completed By Tanya Hollomon Telephone (423) 843-7528 Reporting Period November 2003
- 1.
Design Electrical Rating (Net MWe):
1160
- 2.
Maximum Dependable Capacity (MWe-Net) 1125 Month Yr-to-Date Cumulative
- 3.
Number of Hours Reactor was Critical 720.00 5,778.65 131,244.45
- 4.
Hours Generator On-Line 720.00 5,699.98 129,240.58
- 5.
Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6.
Net Electrical Energy Generated (MWh) 840,870 6,478,899 140,762,989 Docket No.
50-328 Unit Name SQN Unit 2 Date December 4, 2003 Completed By Tanya Hollomon Telephone (423) 843-7528 Reporting Period November 2003
- 1.
Design Electrical Rating (Net MWe):
1160
- 2.
Maximum Dependable Capacity (MWe-Net):
1126 Month Yr-to-Date Cumulative
- 3.
Number of Hours Reactor was Critical 214.00 7,080.65 136,306.15
- 4.
Hours Generator On-Line 214.00 7,030.48 134,128.08
- 5.
Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6.
Net Electrical Energy Generated (MWh) 238,542 7,881,563 143,605,665
E-2 UNIT SHUTDOWNS DOCKET NO:
50-327 UNIT NAME:
SQN-1 DATE:
December 4, 2003 COMPLETED BY:
Tanya Hollomon TELEPHONE:
(423) 843-7528 REPORT PERIOD: NOVEMBER 2003 No.
Date Type F:Forced S:Scheduled Duration (Hours)
Reason1 Method of Shutting Down Reactor2 Cause and Corrective Action to Prevent Recurrence Summary: Unit 1 gross maximum dependable capacity factor was 104.0 percent for the month of November.
1 Reason:
2 Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-ContinuationOutage E-Operator Training / License Examination 5-Other (Explain)
F-Administrative G-Operational Error (Explain)
H-Other (Explain)
E-3 UNIT SHUTDOWNS DOCKET NO:
50-328 UNIT NAME:
SQN-2 DATE:
December 4, 2003 COMPLETED BY: Tanya Hollomon TELEPHONE:
(423) 843-7528 REPORT PERIOD: NOVEMBER 2003 No.
Date Type F:Forced S:Scheduled Duration (Hours)
Reason1 Method of Shutting Down Reactor2 Cause and Corrective Action to Prevent Recurrence 031109 S
506.0 C
1 Unit 2 Cycle 12 refueling outage Summary: Unit 2 gross maximum dependable capacity factor was 29.5 percent for the month of November.
1 Reason:
2 Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-ContinuationOutage E-Operator Training / License Examination 5-Other (Explain)
F-Administrative G-Operational Error (Explain)
H-Other (Explain)