Category:E-Mail
MONTHYEARML24002A7272023-12-16016 December 2023 NRR E-mail Capture - (External_Sender) November 2023 FPL Marine Turtle Removal Monthly Report ML23332A0352023-11-27027 November 2023 Conversion to Improved Technical Specifications Change in Estimated Review Schedule ML23326A0252023-11-20020 November 2023 NRR E-mail Capture - (External_Sender) October 2023 FPL Marine Turtle Removal Monthly Report ML24008A1582023-11-14014 November 2023 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for October 2023 ML23254A2852023-09-11011 September 2023 NRR E-mail Capture - (External_Sender) August 2023 FPL Marine Turtle Removal Monthly Report ML23243A9182023-08-31031 August 2023 NRR E-mail Capture - Re Audit Plan - St. Lucie ITS Conversion LAR - Setpoints ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23228A1482023-08-16016 August 2023 NRR E-mail Capture - Acceptance Review Results - St. Lucie Nuclear Plant, Unit 2 Alternative PSL2-I5-RR-01 (L-2023-LLR-0038) ML23226A0762023-08-14014 August 2023 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Units 1 and 2 - Adopt 10 CFR 50.69 (L-2022-LLA-0182) ML23226A0692023-08-12012 August 2023 NRR E-mail Capture - (External_Sender) July 2023 FPL Marine Turtle Removal Monthly Report ML23223A0152023-08-11011 August 2023 NRR E-mail Capture - Acceptance Review Results - St. Lucie Nuclear Plant, Unit 2 Alternative PR-10 (L-2023-LLR-0039) ML23191A1952023-07-10010 July 2023 NRR E-mail Capture - (External_Sender) June 2023 FPL Marine Turtle Removal Monthly Report ML23216A1412023-06-30030 June 2023 August 2023 RP Inspection Document Request ML23248A1292023-06-29029 June 2023 NRR E-mail Capture - St Lucie 50.69 - Additional Audit Questions ML23198A0662023-06-22022 June 2023 NRR E-mail Capture - (External_Sender) Green Turtle Nest on Canal Bank, June 2023 ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23198A0642023-06-12012 June 2023 NRR E-mail Capture - (External_Sender) Loggerhead Nest on Canal Bank, May 2023 ML23163A1732023-06-10010 June 2023 NRR E-mail Capture - (External_Sender) May 2023 FPL Marine Turtle Removal Monthly Report ML23163A1222023-05-30030 May 2023 NRR E-mail Capture - (External_Sender) Nest on Intake Canal Bank ML23137A0942023-05-17017 May 2023 NRR E-mail Capture - Audit Plan - St Lucie Plant, Units 1 and 2 - 10 CFR 50.69 LAR ML23138A0212023-05-17017 May 2023 Telephone Record, Call with Florida Power and Light Regarding Decommissioning Funding Plan Update Dated March 30, 2021 ML23135A0292023-05-12012 May 2023 NRR E-mail Capture - (External_Sender) April 2023 FPL Marine Turtle Removal Monthly Report ML23129A8312023-05-0808 May 2023 NRR E-mail Capture - Audit Plan - St. Lucie ITS Conversion LAR - Setpoints ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23198A1592023-04-0707 April 2023 NRR E-mail Capture - (External_Sender) March 2023 FPL Marine Turtle Removal Monthly Report ML23074A2292023-03-15015 March 2023 NRR E-mail Capture - (External_Sender) February 2023 FPL Marine Turtle Removal Monthly Report ML23041A2262023-02-10010 February 2023 NRR E-mail Capture - (External_Sender) January 2023 FPL Marine Turtle Removal Monthly Report ML23065A1142023-02-0101 February 2023 NRR E-mail Capture - (External_Sender) FPL St. Lucie Plant Biological Opinion SERO-2019-03494 - Submittal ML23254A4022023-01-24024 January 2023 RP Inspection_2023-001_Document Request ML23019A0142023-01-18018 January 2023 NRR E-mail Capture - (External_Sender) Regarding St. Lucie Olive Ridley Capture 1/3/2023 ML23006A1882023-01-0606 January 2023 NRR E-mail Capture - (External_Sender) December 2022 FPL Marine Turtle Removal Monthly Report ML23006A1822023-01-0606 January 2023 NRR E-mail Capture - (External_Sender) Psl Smalltooth Sawfish Capture 1/5/23 ML23006A0242023-01-0505 January 2023 NRR E-mail Capture - (External_Sender) Psl Olive Ridley Capture 1323 ML23019A2052022-12-24024 December 2022 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors - Acceptance Review ML22348A1002022-12-14014 December 2022 NRR E-mail Capture - (External_Sender) November 2022 FPL Marine Turtle Removal Monthly Report ML22325A0682022-11-18018 November 2022 Email from Brian Harris (NRC) to Robert Coffey (FPL) - St. Lucie SLRA RAI Set 4 ML22319A0762022-11-15015 November 2022 NRR E-mail Capture - (External_Sender) October 2022 FPL Marine Turtle Removal Monthly Report ML22285A2222022-10-12012 October 2022 NRR E-mail Capture - (External_Sender) September 2022 FPL Marine Turtle Removal Monthly Report ML22270A1492022-09-26026 September 2022 Email from Brian Harris (NRC) to Robert Coffey (FPL) - St. Lucie SLRA Second Round RAI Letter 2 - Class 1 Fatigue ML22286A1612022-09-16016 September 2022 August 2022 FPL St. Lucie Marine Turtle Removal Report ML22234A1552022-08-22022 August 2022 NRR E-mail Capture - (External_Sender) July 2022 FPL Marine Turtle Removal Monthly Report ML22227A0522022-08-15015 August 2022 NMFS to NRC, Transmittal of Final Biological Opinion for Continued Operation of St. Lucie Nuclear Power Plant ML22217A0022022-08-0404 August 2022 Email from Brian Harris (NRC) to Robert Coffey (FPL) - St. Lucie SLRA Second Round RAI Letter 1) ML22210A0782022-07-22022 July 2022 Stl 2022003 Document Request ML22194A0482022-07-12012 July 2022 NRR E-mail Capture - (External_Sender) June 2022 FPL Marine Turtle Removal Monthly Report ML22193A0862022-07-11011 July 2022 Email - St. Lucie SLRA - Request for Additional Information Set 3 ML22165A2992022-06-14014 June 2022 NRR E-mail Capture - (External_Sender) May 2022 FPL Marine Turtle Removal Monthly Report ML22147A0862022-05-26026 May 2022 Email from Brian Harris (NRC) to Robert Coffey (FPL) - St. Lucie SLRA - RCI Set 1 2023-09-11
[Table view] |
Text
From: Noel Dudley To: Amritpal Gill; Brendan Moroney; Richard Eckenrode Date: 9/20/02 8:44AM
Subject:
Operating Plant issue at St. Lucie During the review of the St. Lucie, Units 1 and 2, license renewal application, the staff prepared the attached draft request for additional information (RAI). The draft RAI raised an issue related to the present operations of the plant. The draft RAI concerns the ability of operators to inhabit the main control room for the necessary length of time to cooldown the plant following a station blackout. The premise of the daft RAI is that ventilation will be lost and the resulting high temperature will make the main control room uninhabitable.
Since this is an operating plant issue, the draft RAI was not issued to the applicant. However, I am forwarding the draft RAI for your consideration.
- Thanks, Noel CC: Thierry Ross RAI 2.3.3.15-3 Section 9.4.1 of the Unit 1 UFSAR states that the control room ventilation system is designed to maintain the ambient temperature for personnel comfort during normal conditions only, whereas the Unit 2 UFSAR states the control room ventilation system is designed to control the environment in the control room envelope, for the comfort of control room personnel and to assure the operability of control components during normal plant operation, anticipated operational occurrences or abnormal occurrences.
Both St. Lucie units are credited with the ability to cope with a station blackout (SBO) event for a minimum of four hours. The Unit 1 UFSAR, Section 15.2.13, presents a SBO analysis that demonstrates that continuous operator action will be required during the first three and one half hours of the four hour coping period. However, UFSAR Section 9.4.1.2 states that a maximum control room air temperature of 125 oF could be reached 54 minutes after the loss of the air conditioning chiller units, a temperature at which continued habitability for periods of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> is permissible.
The staff is concerned that the St. Lucie Unit 1 control room may not be continuously habitable for the duration of an SBO event, as required by GDC 19 of 10 CFR 50, Appendix A. Section 9.4.1.2 of the Unit 1 UFSAR states, Through judicious allocation of plant operating personnel it will be possible to maintain continuous occupancy of the control room. In addition the operator can bring the plant to safe shutdown from outside the control room. Justify the exclusion of the Unit 1 components required to maintain the MCRE habitable during the SBO coping period or add these components to LRA Table 3.3-15. Justification provided should include the criteria and procedures to be used to allocate control room personnel during an extended SBO event.
Disposition: The concern that the control room many not be continuously habitable during a station blackout event is an operating plant issue. Therefore, this draft RAI was forwarded for consideration to the NRC Project manager for St. Lucie, the Chief of the human factors section, and the chief for the electrical section.