IR 05000282/2002004

From kanterella
(Redirected from ML022070457)
Jump to navigation Jump to search
IR 05000282-02-004; IR 05000306-02-004, on 4/1/02-5/16/02, Prairie Island Nuclear Generating Plant, Units 1 & 2; Physical Protection
ML022070457
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 07/25/2002
From: Lanksbury R
NRC/RGN-III/DRP/RPB5
To: Nazar M
Nuclear Management Co
References
IR-02-004
Download: ML022070457 (42)


Text

July 25, 2002

SUBJECT:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT NRC INSPECTION REPORT 50-282/02-04; 50-306/02-04

Dear Mr. Nazar:

On June 30, 2002, the NRC completed an inspection at your Prairie Island Nuclear Generating Plant. The enclosed report documents the inspection findings which were discussed on July 3, 2002, with you and members of your staff.

This inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, the NRC reviewed two security related issues that were evaluated under the risk significance determination process as having very low safety significance (Green). The NRC has also determined that a violation is associated with one of those findings which pertains to protection of Safeguards Information (SGI). The violation is being treated as a Non-Cited Violation (NCV), consistent with Section VI.A of the Enforcement Policy. The NCV is described in the subject inspection report. If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to the Regional Administrator, Region III, and the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001 and the NRC Resident Inspector at the Prairie Island Nuclear Generating plant.

The NRC has increased security requirements at Prairie Island in response to terrorist acts on September 11, 2001. Although the NRC is not aware of any specific threat against nuclear facilities, the NRC issued an Order and several threat advisories to commercial power reactors to strengthen licensees capabilities and readiness to respond to a potential attack. The NRC continues to monitor overall security controls and will issue temporary instructions in the near future to verify by inspection the licensee's compliance with the Order and current security regulations. In accordance with 10 CFR 2.790 of the NRC's Rules of Practice, a copy of this letter, its enclosure, and any response you provide, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Roger D. Lanksbury, Chief Project Branch 5 Division of Reactor Projects Docket Nos. 50-282; 50-306 License Nos. DPR-42; DPR-60

Enclosure:

Inspection Report 50-282/02-04; 50-306/02-04

REGION III==

Docket Nos:

50-282, 50-306 License Nos:

DPR-42, DPR-60 Report No:

50-282/02-04; 50-306/02-04 Licensee:

Nuclear Management Company, LLC Facility:

Prairie Island Nuclear Generating Plant Location:

1717 Wakonade Drive East Welch, MN 55089 Dates:

April 1 through June 30, 2002 Inspectors:

J. Adams, Senior Resident Inspector S. Ray, Senior Resident Inspector D. Karjala, Resident Inspector M. Mitchell, Radiation Specialist, DRS A. Dunlop, Reactor Engineer, DRS M. Farber, Reactor Engineer, DRS B. Winter, Reactor Engineer, DRS G. Pirtle, Physical Security Inspector, DRS Approved by:

Roger D. Lanksbury, Chief Project Branch 5 Division of Reactor Projects

SUMMARY OF FINDINGS IR 05000282-02-04; IR 05000306-02-04, on 4/1/2002-5/16/2002; Nuclear Management Company, Prairie Island Nuclear Generating Plant, Units 1 & 2; Physical Protection.

This report covers a 13-week routine resident inspection. The inspection was conducted by resident and regional inspectors. Two Green security-related findings were identified. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using IMC 0609, Significance Determination Process. Findings for which the Significance Determination Process (SDP) does not apply may be Green or be assigned a severity level after NRC management review. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.

A.

Inspector-Identified Findings No findings of significance were identified.

B.

Licensee Identified Findings Cornerstone: Physical Protection Two security-related findings of very low safety significance (Green) were identified by the licensee, one of which was a Non-Cited Violation, and were reviewed by the inspector. Corrective actions taken by the licensee have been entered into the licensees corrective action program. These findings and corrective action tracking numbers are listed in Sections 4OA3.2 and 4OA7 of this report.

Report Details Summary of Plant Status Unit 1 was operated at or near full power for the entire inspection period. Unit 2 was operated at or near full power for the entire inspection period.

1.

REACTOR SAFETY Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and Emergency Preparedness 1R01 Adverse Weather Protection (71111.01)

Hot Weather, Tornado, and Low Water Preparations a.

Inspection Scope The inspectors performed a detailed review of the summer plant operation, high wind, and tornado hazard procedures; Updated Safety Analysis Report (USAR); design bases documents (DBDs) for the screenhouse and emergency diesel generators (EDGs);

applicable Technical Specifications (TSs); and the Prairie Island Individual Plant Examination of External Events (IPEEE). The inspectors also reviewed a permanent plant modification of EDGs D1 and D2 that restored their operability with the design bases cooling water inlet temperature of 95 F (see Section 1R17). A detailed list of the documents reviewed during this inspection is included at the end of the report.

The inspectors conducted inspections of the following risk significant mitigating systems:

cooling water (common to both units);

offsite alternating current (AC) power;

Unit 1 and 2 AC Transformers;

Unit 1 EDG D1 and D2; and

Unit 2 EDG D5 and D6.

The inspectors reviewed the selected systems to verify that the material conditions and system configuration supported the systems availability and operability under adverse weather conditions, and to verify that additional cooling equipment specified in the summer plant operation procedure was available and operating as specified in the procedure. The inspectors conducted walkdowns of the areas specified in the tornado hazards surveillance procedure (SP) to verify that potential missile hazards to transformers and the switchyard had been removed or properly secured.

The inspectors reviewed a number of weather-related action requests (Ars) that entered problems that, if left uncorrected, could affect the performance of mitigating systems or result in an initiating event. The review was conducted to verify that the licensee entered problems into the corrective action program, identified appropriate corrective actions, and implemented those corrective actions.

b.

Findings No findings of significance were identified.

1R02 Evaluations of Changes, Tests, or Experiments (71111.02)

Review of Evaluations and Screenings for Changes, Tests, or Experiments a.

Inspection Scope The inspectors reviewed nine 10 CFR 50.59 evaluations and 21 screenings completed by the licensees engineering staff during the last 2 years and performed under the 10 CFR 50.59 process. These documents were reviewed to ensure consistency with the requirements of 10 CFR 50.59. The inspectors used Nuclear Energy Institute (NEI) 96-07, Guidelines for 10 CFR 50.59 Implementation, Revision 1, to determine acceptability of the completed evaluations and screenings. The NEI document was endorsed by the NRC in Regulatory Guide 1.187, "Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments, November 2000. The inspectors also consulted Inspection Manual, Part 9900, "10 CFR GUIDANCE: 10 CFR 50.59, Changes, Tests, and Experiments." Documents reviewed during the inspection are listed at the end of the report.

b.

Findings No findings of significance were identified.

1R04 Equipment Alignment (71111.04)

a.

Inspection Scope The inspectors performed a partial equipment alignment walkdown of the following risk significant mitigating systems:

On April 26, 2002, inspectors conducted an equipment alignment verification of the D5 EDG while the D6 EDG was unavailable for surveillance testing.

  • On June 19, 2002, inspectors conducted an equipment alignment verification of the 21 component cooling water pump while the 22 component cooling water pump was unavailable for preventative maintenance.
  • On June 24, 2002, inspectors conducted an equipment alignment verification of the D1 EDG while the D2 EDG was unavailable for surveillance testing.

The inspectors utilized the valve and electrical breaker status checklists to verify that system components and support systems were properly configured to support the operability of the available train. The inspectors performed a physical inspection of the available train, and reviewed outstanding work orders (WOs) and ARs to verify that the available train would be capable to perform its design function as described in USAR

and TSs. The inspectors also reviewed housekeeping in the area to verify that there were no housekeeping issues that could affect the available trains function.

The inspectors reviewed ARs to verify that minor deficiencies identified during these inspections were entered into the licensees corrective action system. A detailed list of the documents reviewed during this inspection is included at the end of the report.

b.

Findings No findings of significance were identified.

1R05 Fire Protection (71111.05)

a.

Inspection Scope The inspectors conducted fire protection walkdowns that were focused on the availability and accessibility of fire protection equipment, the condition of fire fighting equipment, the control of transient combustibles, and the condition and operating status of installed fire barriers. The inspectors selected fire areas for inspection based on their overall contribution to internal fire risk, as documented in the IPEEE; their potential to impact equipment which could initiate a plant transient; or their impact on the plants ability to respond to a security event. The inspectors reviewed the documents listed at the end of this report and toured fire areas to verify that fire hoses and extinguishers were in their designated locations and available for immediate use; that fire detectors and sprinklers were unobstructed; that transient material loading was within the analyzed limits; and that fire doors, dampers, and penetration seals appeared to be in satisfactory condition.

The inspectors assessed the following areas:

Fire Area 20, Bus 15 Switchgear Room;

Fire Area 22, Bus 111 Switchgear Room;

Fire Area 25, EDG D1 Room;

Fire Area 26, EDG D2 Room;

Fire Area 31, Auxiliary Feedwater (AFW) Pump 11 and 21 Room;

Fire Area 32, AFW Pump 12 and 22 Room;

Fire Area 33, Battery 11 Room;

Fire Area 34, Battery 12 Room;

Fire Area 80, Bus 121 Switchgear Room; and

Fire Area 81, Bus 16 Switchgear Room.

b.

Findings No findings of significance were identified.

1R06 Flood Protection Measures (71111.06)

.1 External Flood Protection Inspection a.

Inspection Scope The inspectors reviewed the applicable sections of the USAR and IPEEE associated with external flooding; the abnormal procedure for flooding; the most recently completed SP for the inspection of plant flooding barriers; the design bases document addressing internal and external hazards; and the design change package for flood panel and door design changes. Additionally, the inspectors reviewed the implemented corrective actions taken to correct the loss of safety function of plant flood barriers (see Section 4OA2) and Licensee Event Report (LER) 01-03-01 documenting the loss of safety function (see Section 4OA3).

The inspectors performed a physical inspection of all flood protection barriers with a specific focus on the deficiencies noted in the most recent performance of the SP for the inspection of plant flood barriers. The inspectors assessed whether the actions specified in the abnormal procedure for flooding could be performed in a timely manner if required, and if the necessary hardware and consumable materials were available and still within their shelf life. The inspectors also discussed the recent modifications of flood barriers with the project engineer.

The inspectors reviewed several ARs to verify that minor deficiencies identified during this inspection were entered into the licensees corrective action program, that problems associated with plant equipment relied upon to prevent or minimize flooding were identified at an appropriate threshold, and that corrective actions commensurate with the significance of the issue were identified and implemented. A detailed list of the documents reviewed during this inspection is included at the end of the report.

b.

Findings No findings of significance were identified.

.2 Internal Flood Protection Inspection a.

Inspection Scope The inspectors reviewed the applicable sections of the USAR and Individual Plant Examination (IPE) associated with internal flooding in the area of the Unit 1 and Unit 2 AFW pumps and instrument air compressors, the design bases document addressing internal and external hazards, and the design bases document for the D5/D6 EDG building. The inspectors conducted a physical walkdown of the Unit 1 and Unit 2 AFW pump rooms and the D5/D6 building to verify that piping systems in these areas were being maintained, that drain paths from these areas had been maintained, and that there were no accumulations of loose materials that could plug drain paths. The inspectors reviewed the response times assumed in the flood analysis for operator actions to verify that operators could reasonably be expected to complete the required actions in the assumed time.

The inspectors reviewed several ARs to verify that problems associated with plant equipment relied upon to prevent or minimize flooding were identified at an appropriate threshold, and that corrective actions commensurate with the significance of the issue were identified and implemented. A detailed list of the documents reviewed during this inspection is included at the end of the report.

b.

Findings No findings of significance were identified.

1R11 Licensed Operator Requalification Program (71111.11)

a.

Inspection Scope The inspectors observed an operating staff crew during an as found requalification examination on the simulator. The inspectors evaluated crew performance in the areas of:

clarity and formality of communications;

ability to take timely, appropriate, and safe actions;

prioritization, interpretation, and verification of alarms;

procedure use;

control board manipulations;

oversight and direction from supervisors; and

group dynamics.

The inspectors compared crew performance in the above areas to licensee management expectations and guidelines as presented in the operations section work instructions (SWIs) listed at the end of this report and to the critical tasks listed in the exercise guide at the end of this report. The inspectors also compared simulator configurations with actual control room board configurations. The inspectors observed licensee evaluators to verify that they noted weaknesses observed by the inspectors and discussed them in the critique at the end of the session.

b.

Findings No findings of significance were identified.

1R12 Maintenance Rule Implementation (71111.12)

a.

Inspection Scope The inspectors reviewed the licensees implementation of the maintenance rule requirements for the Unit 1 reactor protection system to ensure that the maintenance rule was properly implemented. This evaluation included the following aspects:

whether the reactor protection system was scoped in accordance with 10 CFR 50.65;

whether the reactor protection system had been assigned the proper safety significance classification;

whether the licensee properly classified the reactor protection system as (a)(1) or (a)(2) based on the systems performance; and

whether the performance criteria for the reactor protection system were appropriate for its (a)(2) classification.

The above aspects were evaluated by the inspectors during the review of the maintenance rule scoping and report documents. The inspectors also reviewed significant WOs and ARs to verify that failures were properly identified, classified, and corrected and that unavailable time had been properly calculated. A detailed list of the documents reviewed during this inspection is included at the end of the report.

b.

Findings No findings of significance were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

a.

Inspection Scope The inspectors reviewed the licensees management of plant risk during emergent maintenance activities and during activities where more than one risk significant system or train was unavailable. The activities were chosen based on their potential impact on increasing the probability of an initiating event or impacting the operation of safety significant mitigating equipment. The inspection was conducted to verify that evaluation, planning, control, and performance of the work were done in a manner to reduce the risk and minimize the duration, where practical, and that contingency plans were in place where appropriate. The inspectors reviewed the licensees daily configuration risk assessment records, observed shift turnover meetings, observed daily plant status meetings, and reviewed risk assessment documents listed at the end of this report to verify that the equipment configurations were properly listed, that protected equipment was identified and controlled, and that significant aspects of plant risk were communicated to the necessary personnel. The inspectors discussed daily and emergent risk assessments with operators and risk assessment engineers.

The inspectors reviewed the following emergent and planned maintenance activities associated with maintenance rule risk significant systems:

On April 12, 2002, the D5 EDG was out-of-service for planned maintenance when an emergent failure of the 12 diesel driven cooling water pump lubricating water supply occurred;

On June 4, 2002, the D1 EDG was out-of-service for replacement of the water supply solenoid valve and the 12 boric acid transfer pump was inoperable during a period of possible severe weather;

  • On June 12, 2002, the 12 diesel driven cooling water pump was declared inoperable because of erratic governor operation during a routine surveillance test; and

On June 26, 2002, the 12 component cooling water pump and the 11 boric acid storage tank were out-of-service for planned maintenance, two of the eight intake traveling screens were out-of-service for corrective maintenance, one intake traveling screen was degraded, and both bypass intake traveling screen bypass gates were degraded.

The inspectors reviewed several ARs to verify that problems associated with plant risk assessment were identified at an appropriate threshold, and that corrective actions commensurate with the significance of the issue were identified and implemented. A detailed list of the documents reviewed during this inspection is included at the end of the report.

b.

Findings No findings of significance were identified.

1R15 Operability Evaluations (71111.15)

a.

Inspection Scope The inspectors evaluated plant conditions, selected condition reports (CRs), and corrective action program (CAP) documents for risk significant components and systems in which operability issues were questioned. These conditions were evaluated to determine whether the continued operability of the components and systems were justified. The inspectors compared the component or systems function and design criteria in the applicable sections of the TSs and USAR to the licensees evaluations to verify that the components and systems were operable. The inspectors reviewed equipment to verify that compensatory measures necessary to maintain operability were in place, functioned as intended, and were properly controlled. A detailed list of the documents reviewed during this inspection is included at the end of the report.

The inspectors evaluated the following conditions:

Inaccurate assumptions used in the analysis for the non-return check valves in the main steam line break event (General Condition Report 2002 01283);

Improper classification of safety-related cooling water pump lubrication water supply components as nonsafety-related (AR CAP 023064);

Okonite/Scotch Equipment Qualification (EQ) splices installed in a non-tested configuration (AR CAP 023138);

EQ Okonite Tape Splice Configuration Turnover Evaluation;

Scaffold 1109R was found in contact with 21 component cooling water pump discharge header (AR CAP 023905);

Potential excessive end play on the 11 safety injection pump (AR CAP 023818);

and

Incorrect o-ring material install on the Units 1 and 2 pressurizer power operated relief valve block valves (AR CAP 023907).

b.

Findings No findings of significance were identified.

1R16 Operator Workarounds (OWA) (71111.16)

a.

Inspection Scope The inspectors reviewed newly identified OWAs to verify that the functional capability of the system, human reliability in responding to an initiating event, or the ability of operators to implement abnormal or emergency operating procedures was not significantly affected.

The inspectors reviewed the following OWAs:

Diesel generator D6 fuel oil storage tank level indication from the emergency response computer system; and

Unit 2 loop A pressurizer spray valve controller in manual.

The inspectors reviewed the applicable sections of the USAR and TSs and discussed the OWAs with control room operators. The inspectors reviewed several ARs to verify that problems associated with D6 fuel oil storage tank level indication and the loop A pressurizer spray valve controller were identified at an appropriate threshold, and that corrective actions commensurate with the significance of the issue was identified and scheduled for implementation. A detailed list of the documents reviewed during this inspection is included at the end of the report.

b.

Findings No findings of significance were identified.

1R17 Permanent Plant Modifications (71111.17)

.1 Permanent Plant Modification Installed On-Line a.

Inspection Scope The inspectors reviewed design change 02D101 which added several valves to the D1 and D2 coolant systems to eliminate coolant cross-flow. The licensee determined that this modification was necessary to restore the EDGs to a configuration that could provide the rated load with a cooling water flow of 400 gallons per minute at 95F. The inspectors reviewed the modification to verify that it did not adversely affect the availability, reliability, or the functional capability of the D1/D2 EDGs. The inspectors also reviewed three supporting engineering calculations, a 10 CFR Part 21 notification from the diesel vendor, WOs for the installation of the modification, the post-modification testing, and commercial grade dedication of components. The inspectors performed a physical walkdown of the D1 and D2 EDGs and observed the operation of both engines following the installation of the modifications. A detailed list of the documents reviewed during this inspection is included at the end of the report.

b.

Findings No findings of significance were identified.

.2 Biennial Review of Recent Permanent Plant Modifications a.

Inspection Scope The inspectors reviewed 20 permanent plant modifications that were performed by the licensees engineering staff during the last 2 years. These were divided among the various programs that the licensee used to make changes to the plant. Nine of the modifications were done under the design change process. In addition, the inspectors evaluated 2 setpoint changes, 2 equivalent engineering change evaluations, 3 substitution part/component equivalent evaluations, and 4 commercial grade evaluations. The modifications were chosen based upon the effect on systems that had high probabilistic risk analysis significance or high maintenance rule safety significance.

The modifications were reviewed to verify that the completed design changes were in accordance with specified design requirements and the licensing bases, and to confirm that the changes did not affect the modified system or other systems safety function.

As applicable to the status of the modification, post-modification testing was reviewed to verify that the system, and associated support systems, functioned properly and that the modification accomplished its intended function. The inspectors evaluated the modifications against the licensees design basis documents and the USAR. The inspectors also used applicable industry standards, such as the American Society of Mechanical Engineers Code, to evaluate acceptability of the modifications.

b.

Findings No findings of significance were identified.

1R19 Post-Maintenance Testing (71111.19)

a.

Inspection Scope The inspectors reviewed post-maintenance testing activities associated with maintenance on important mitigating, barrier integrity, and support systems to ensure that the post-maintenance testing was performed adequately, demonstrated that the maintenance was successful, and that operability was restored after the testing. The inspectors reviewed the appropriate sections of the TSs, the USAR, and maintenance documents to determine the systems safety functions and the scope of the maintenance. In addition, the inspectors reviewed ARs to verify that minor deficiencies identified during these inspections were entered into the licensees corrective action system. A detailed list of the documents reviewed during this inspection is included at the end of the report.

The inspectors observed and evaluated the post-maintenance activities for the following:

D5 Overspeed Trip Repair and Temporary Modification Removal on April 11, 2002;

12 Diesel Cooling Water Pump Governor Adjustment on June 13, 2002; and

22 Component Cooling (CC) Pump Preventive Maintenance (PM) on June 19, 2002.

b.

Findings No findings of significance were identified.

1R22 Surveillance Testing (71111.22)

a.

Inspection Scope The inspectors observed selected surveillance tests and/or reviewed test data to verify that the equipment performance met SP acceptance criteria. The inspectors observed the tested equipment to verify that it was capable of performing its intended safety functions as described in TSs and the USAR. The inspectors reviewed documents to verify that the testing met the required TS frequency; that the tests were conducted in accordance with the applicable procedures; that operators met prerequisites and established the proper plant conditions; and that the results of the tests were properly reviewed and recorded. In addition, the inspectors reviewed several ARs to verify that the licensee was identifying surveillance test problems at an appropriate threshold, and that corrective actions commensurate with the significance of the issue were identified and implemented. A detailed list of the documents reviewed during this inspection is included at the end of the report.

The following tests were observed and/or evaluated:

SP 1102, 11 Turbine Driven AFW Pump Monthly Test on April 17, 2002;

SP 2307, D6 Diesel Generator 6-Month Fast Start Test on April 25, 2002;

SP 1335, D2 Diesel Generator 18-Month 24-Hour Load Test on April 28, 2002; and

SP 2102, 22 Turbine-Driven AFW Pump Monthly Test on May 20, 2002.

b.

Findings No findings of significance were identified.

1R23 Temporary Modifications (71111.23)

a.

Inspection Scope The inspectors reviewed temporary modification 02T121. This temporary modification installed a ground strap on the Unit 2 source range monitor 2N31 to reduce the noise-induced counts. The inspectors reviewed the temporary modification description and the 10 CFR 50.59 screening to ensure they were completed in accordance with the licensee administrative work instruction (AWI) guidance. In addition, the inspectors reviewed the applicable sections of the USAR and TSs to verify that the installation did not affect the specified design function or operability of the system. The inspectors

discussed installation and removal WOs, plans for permanent corrective action, and temporary modification removal with engineering personnel. The inspectors also reviewed documents to verify that minor deficiencies identified during the course of inspections were entered into the licensees corrective action program. A detailed list of the documents reviewed during this inspection is included at the end of the report.

b.

Findings No findings of significance were identified.

1EP6 Drill Evaluation (71114.06)

a.

Inspection Scope The inspectors observed the licensee perform an emergency preparedness drill on April 3, 2002. The inspectors observed activities in the control room simulator, technical support center, and emergency operations facility. The inspectors also attended the post-drill facility critiques in the technical support center and emergency operations facility immediately following the drill and the overall drill critique on April 4. The focus of the inspectors activities was to note any weaknesses and deficiencies in the drill performance and ensure that the licensee evaluators noted the same weaknesses and deficiencies and entered them into the corrective action program. The inspectors placed emphasis on observations regarding event classification, notifications, protective action recommendations, and site evacuation and accountability activities. As part of the inspection, the inspectors reviewed the drill package listed at the end of this report.

b.

Findings No findings of significance were identified.

2.

RADIATION SAFETY Cornerstone: Occupational Radiation Safety 2OS1 Access Control to Radiologically Significant Areas (71121.01)

.1 Plant Walkdowns a.

Inspection Scope The inspector reviewed the radiological conditions of radiation areas and high radiation areas (HRAs) in the auxiliary and radwaste buildings. The inspector performed walkdowns and reviewed licensee controls to determine if the controls (i.e., surveys, postings, and barricades) were adequate to meet the requirements of 10 CFR Part 20 and the licensees TSs.

b.

Findings No findings of significance were identified.

Cornerstone: Public Radiation Safety 2PS2 Radioactive Material Processing and Transportation (71122.02)

.1 Walkdown of Radioactive Waste Systems a.

Inspection Scope The inspector reviewed the liquid and solid radioactive waste system description in the USAR and the most recent information regarding the types and amounts of radioactive waste generated and disposed. The inspector performed walkdowns of the liquid and solid radwaste processing systems to verify that the systems agreed with the descriptions in the USAR and the Process Control Program, and to assess the material condition and operability of the systems. The inspector reviewed the current processes for transferring waste resins into transportation containers to determine if appropriate waste stream mixing and/or sampling procedures were utilized. The inspector also reviewed the methodologies for waste concentration averaging to determine if representative samples of the waste product were provided for the purposes of waste classification in accordance with 10 CFR 61.55. During this inspection, the licensee was not conducting waste processing.

b.

Findings No findings of significance were identified.

.2 Waste Characterization and Classification a.

Inspection Scope The inspector reviewed the licensees radiochemical sample analysis results for each of the licensees waste streams, including dry active waste, resins, and filters.

The inspector also reviewed the licensees use of scaling factors to quantify difficult-to-measure radionuclides (e.g., pure alpha or beta emitting radionuclides). The reviews were conducted to verify that the licensees program assured compliance with 10 CFR 61.55 and 10 CFR 61.56, as required by Appendix G of 10 CFR Part 20. The inspector also reviewed the licensees waste characterization and classification program to ensure that the waste stream composition data accounted for changing operational parameters and thus remained valid between the annual sample analysis updates.

b.

Findings No findings of significance were identified.

.3 Transportation Records a.

Inspection Scope The inspector reviewed five exempt and non-exempt package shipment manifests completed in 2000 and 2001 to verify compliance with NRC and Department of Transportation requirements (i.e., 10 CFR Parts 20 and 71 and 49 CFR Parts 172 and 173). The licensee did not have any non-exempt package preparation or shipping underway during the inspection.

b.

Findings No findings of significance were identified.

.4 Identification and Resolution of Problems a.

Inspection Scope The inspector reviewed a Quality Assurance audit of the Radioactive Waste and Transportation Program, along with self-assessments of the Radioactive Waste and Transportation Programs to evaluate the effectiveness of the self-assessment process to identify, characterize, and prioritize problems. The inspector also reviewed corrective action documentation to verify that previous radioactive waste and radioactive materials transportation related issues were adequately addressed. The inspector also selectively reviewed year 2001 CRs that addressed radioactive waste and radioactive materials transportation program deficiencies, to verify that the licensee had effectively implemented the corrective action program.

b.

Findings

No findings of significance were identified.

3.

SAFEGUARDS Cornerstone: Physical Protection 3PP1 Access Authorization (AA) Program (Behavior Observation Only) (71130.01)

a.

Inspection Scope The inspector interviewed five supervisors and five non-supervisors (both licensee and contractor employees) to determine their knowledge level and practice for implementing the licensees program responsibilities. Selected procedures pertaining to the Behavior Observation Program and associated training activities were reviewed. Also licensee Fitness-For-Duty (FFD) semi-annual test results were reviewed. In addition, the inspector reviewed a sample of licensee self-assessments and security logged events.

The inspector also interviewed security managers to evaluate their knowledge and use of the licensees corrective action program.

b.

Findings

No findings of significance were identified.

3PP2 Access Control (Identification, Authorization and Search of Personnel, Packages, and Vehicles) (71130.02)

a.

Inspection Scope

The inspector reviewed the licensees protected area access control equipment testing and maintenance procedures. The inspector observed licensee testing of all access control equipment to determine if testing and maintenance practices were performance based. On two occasions, during peak ingress periods, the inspector observed in-processing search of personnel, packages, and vehicles to determine if search practices were conducted in accordance with regulatory requirements and that staffing was sufficient to adequately control the ingress process. Interviews were conducted and records were reviewed to verify that security staffing levels were consistently and appropriately implemented, and that procedures were prepared to address denial of unescorted access authorization. Also the inspector reviewed the licensees process for limiting access to only authorized personnel to the protected area and vital equipment.

The inspector reviewed the licensees program to control security keys and security related computer data.

The inspector reviewed a sample of licensee self-assessments, maintenance request records, and security logged events for identification and resolution of problems. In addition, the inspector interviewed security managers to evaluate their knowledge and use of the licensees corrective action system.

b.

Findings No findings of significance were identified.

4.

OTHER ACTIVITIES 4OA1 Performance Indicator (PI) Verification (71151)

.1 Initiating Events Cornerstone Performance Indicators a.

Inspection Scope The inspectors reviewed the PI data submitted by the licensee for completeness and accuracy for the following PIs in the Initiating Events Cornerstone:

1.

Unplanned Scrams per 7,000 Critical Hours, and 2.

Unplanned Scrams with Loss of Normal Heat Removal The inspectors compared the data reported by the licensee to the definitions and guidance contained in the NEI guidance listed at the end of this report. The inspectors

reviewed licensee event reports, monthly operating reports, and NRC inspection reports for the period July 2001 through March 2002 to verify that the licensee had reported all occurrences for those three quarters.

b.

Findings No findings of significance were identified.

.2 Physical Protection Performance Indicators a.

Inspection Scope The inspector verified the data for the Physical Protection Performance Indicators (PI)

pertaining to Fitness-For-Duty Personnel Reliability, Personnel Screening Program, and Protected Area Security Equipment. Specifically, a sample of plant reports related to security events, security shift activity logs, fitness-for-duty reports, and other applicable security records were reviewed for the fourth quarter of 2001 and the first quarter of 2002.

b.

Findings No findings of significance were identified.

4OA2 Identification and Resolution of Problems (71152)

.1 Review of Corrective Actions For the D5/D6 Fuel and Lubricating Oil Incompatibility Event a.

Inspection Scope The inspectors evaluated the completeness and the effectiveness of licensee corrective actions for a previous finding that involved the incompatibility of the fuel oil and lubricating oil in the Unit 2 D5 and D6 EDGs. Inspectors reviewed the completion of corrective actions and ensured that the timeliness of the licensees corrective actions were commensurate with the safety significance of the issue.

b.

Findings No findings of significance were identified.

.2 Review of Corrective Actions For the Loss of Function Associated with Flood Barriers a.

Inspection Scope The inspectors evaluated the completeness and the effectiveness of licensee corrective actions for a previous finding that involved deficiencies with the plant flood barriers.

These deficiencies resulted in the plant being in an unanalyzed condition. The inspectors reviewed CR 20015571 that initially documented the deficient flood barriers, the subsequent root cause evaluation, LER 1-03-01, LER 1-03-01 Supplement 1, and

the documentation associated with the permanent plant modification that implemented the corrective actions that restored the function of the flood barriers.

The inspectors assessed whether the timeliness of the licensees corrective actions were commensurate with the safety significance of the issue. The inspectors compared the completion dates of the actions that restored function to the flood barriers to the annual period when the plant experiences a high susceptibility to external flooding. The inspectors reviewed USAR and IPEEE sections discussing external flooding and which indicated that the period of high susceptibility existed in the months of March and April.

The inspectors reviewed all corrective actions completed by the end of January 2002 to verify these actions restored the flood barrier function.

The inspectors reviewed other corrective actions, not required for the restoration of flood barrier function and which had not been completed by January 2002, to verify that they would not prevent the flood barriers from protecting the plant in the event of external flooding.

The inspectors performed a physical walkdown of the flood barriers to assess the current material condition of the flood barriers and note any deficiencies that would prevent the barriers from performing their function. The inspectors also observed the performance of SP 1293, Inspection of Flood Control Measures, to verify that all acceptance criteria were met.

b.

Findings No findings of significance were identified.

.3 Identification and Resolution of Problems Associated With Permanent Plant Modifications a.

Inspection Scope The inspectors reviewed 12 CRs associated with Prairie Islands permanent plant modifications and 10 CFR 50.59 program to verify that the licensee had an appropriate threshold for identifying issues and to verify the effectiveness of corrective actions for the identified issues.

b.

Findings No findings of significance were identified.

4OA3 Event Followup (71153)

.1 (Closed) LER 1-01-03, Supplement 1: Plant in Unanalyzed Condition Due to Flood Panel Deficiencies.

This event report described a licensee-identified condition where 16 of 17 flood panels, that would be installed during a flood condition where water level crest is predicted to exceed 692' elevation, were degraded. The issue included not having the correct

gasket materials, inadequate anchor bolt installation capabilities, and the inability to install the panels in a timely manner. A Phase 3 risk assessment was completed using information from the IPEEE. Based on the assessment, it was determined that the issue was of very low risk significance (Green).

The inspectors reviewed Supplement 1 to this event report and noted that the licensee identified two additional deficiencies during the implementation of corrective actions to correct the D5/D6 flood panel deficiencies discussed in the original LER. These additional deficiencies did not change the significance of the event since the flood panels in question were determined to have been non-functional due to degraded gasket material. These new deficiencies were identified during corrective actions to restore the flood barrier function. The newly identified deficiencies were entered into the corrective action program with AR CAP 023003 and CAP 023071. Corrective actions had been completed and the function of all flood panels had been fully restored.

.2 (Closed) Licensee Event Report No. 50-282/01-06-00: Security Responders Out-of-Position Due to Plant Fire.

Green. On August 3, 2001, a fire occurred within the protected area (PA) due to an electrical fault in non-safeguards Bus 12. The Red Wing Fire Department responded to assist in the control of the fire. While involved in fire control support activities, some armed responders were in locations that would have prevented them from being able to respond to their established defensive positions within the time lines established (specific time lines are SGI and exempt from public disclosure). The responders were out of position for between 15 minutes and two hours. During these time periods, the responders were always within the PA and able to provide some level of contingency response, but not within the specific time lines established for their positions.

Since the incident occurred prior to September 11, 2001, the regulatory requirement for the minimum number of armed responders was identified in the security plan (number of required armed responders is SGI and exempt from public disclosure). In this case, the number of actual armed responders exceeded the minimum number required by the security plan and no violations of NRC requirements occurred. The licensee had developed a response strategy and voluntarily added responders to enhance their capabilities. Part of that strategy included self-imposed requirements regarding the timeliness of responders. This incident effected that timeliness.

Additionally, within an hour of the start of the fire an additional supervisor, qualified for armed response duties, arrived onsite and could have provided an additional level of response in case of a contingency event. This issue was reported to the NRC within one hour, and a written Licensee Event Report was submitted to the NRC within 30 days. No prior similar events have occurred. Interviews with the security director disclosed that in the future, armed responders would not be used as they were in this incident, with a limited exception.

This issue was evaluated through the SDP and determined to be of low safety significance (Green). The issue is considered greater than minor, but of low safety significance, because, although the cornerstone attribute relating to response was effected (for a limited time and only a small portion of the capability) it represented a

vulnerability in the response system because it increased the potential for failure; but there were no actual intrusions and less than two similar findings were identified during the past four quarters. Moreover, the fire within the PA was an unpredictable event and the mis-positioning of the responders would have been unknown to an adversary.

4OA6 Meeting(s)

.1 Interim Exit Meeting Summary of the Access Control, As-Low-As-Is-Reasonably Achievable (ALARA), Instrumentation, and Transportation The results of the access control, ALARA, instrumentation, and transportation inspection were presented to Mr. Mano Nazar and other members of licensee management at the conclusion of the inspection on May 17, 2002. The licensee acknowledged the information presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.

.2 Interim Exit Meeting Summary of the Permanent Plant Modification and Evaluations of Changes, Tests, and Experiments Inspection The results of the permanent plant modification and evaluations of changes, tests, and experiments inspection were presented to Mr. Mano Nazar and other members of licensee management at the conclusion of the inspection on June 21, 2002. The licensee acknowledged the information presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary.

No proprietary information was identified.

.3 Interim Exit Meeting Summary of the Physical Security Inspection The results of the Safeguards inspection were presented to Mr. Mano Nazar and other members of the licensee management at the conclusion of the inspection on June 21, 2002. The licensee staff was advised that an unresolved item pertaining to protection of SGI was identified, and that they would be advised later of the resolution of the issue.

The inspector asked the licensee whether any materials examined during the inspection should be considered safeguards or proprietary information. No safeguards or proprietary information was identified.

On July 9, 2002, the licensee was advised that the unresolved item discussed above pertaining to inadequate protection of SGI was a licensee identified severity level IV Non-Cited Violation.

.4 Exit Meeting The resident inspectors presented the inspection results to Mr. Mano Nazar and other members of licensee management at the conclusion of the inspection on July 3, 2002.

The licensee acknowledged the findings presented. No proprietary information was identified.

4OA7 Licensee-Identified Violations The following violation of very low safety significance (Green) was identified by the licensee and is a violation of NRC requirements which meets the criteria of Section VI of the NRC Enforcement Policy, NUREG-1600, for being dispositioned as an NCV.

10 CFR 73.21(d)(2) states in part, While unattended, SGI shall be stored in a locked security storage container.

Contrary to this requirement, SGI (lesson plans and portions of security plans) found in the security trainers office (located outside of the protected area) was not stored in a locked security storage container. The duration of this issue is not know, but may have existed for up to one year (50-282/306/02-04-01).

The licensee inventoried and assumed control of the SGI, entered the issue into their corrective action program (CAP 023101), and entered the incident in their safeguards event log. Because there was no evidence that the significant SGI (portions of security plans) was compromised, this violation is not more than of very low significance, and is being treated as a Non-Cited Violation.

On April 12, 2002, the licensee discovered some lesson plans marked as SGI, and a double-enveloped package (both envelopes sealed) with SGI (portions of security plans)

within it. It was stored in an unlocked filing cabinet in the security trainers office located outside of the protected area. The outer sealed envelope was addressed to the security trainer with no SGI markings, and the inner sealed envelope was marked as SGI. The inadequate storage of the SGI may have occurred for up to one year. The individual the package was addressed to had not worked in the security trainer position and office for up to a year prior to the discovery date (April 12, 2002), and had terminated employment prior to the discovery date. Therefore, he was not available for the licensee or inspector to interview to determine further circumstances and details pertaining to receipt, transportation, or use of the SGI material.

This issue was evaluated through the SDP and determined to be of low safety significance (Green). The inspectors review of the material determined that the information in the lesson plans would not substantially assist an individual in gaining unauthorized or undetected access to the plant. The most significant documents were pages of the Point Beach and Prairie Island security plans (stored within a double sealed envelope) that described the location and description of vital areas, which could assist in radiological sabotage if the information was compromised. Although the SGI material was subject to compromise (not stored adequately) for up to a year, the fact that both envelopes were sealed when discovered indicates that the material was not compromised.

KEY POINTS OF CONTACT Licensee T. Amundson, Manager Business Support P. Huffman, Manager of System Engineering B. Jefferson, Director Site Operations J. Jensen, Interim Director of Engineering A. Johnson, General Superintendent Radiation Protection and Chemistry J. Kivi, Licensing Engineer R. Lingle, Operations Manager J. Maki, Production Planning Manager M. McKeown, Manager of Design Engineering L. Meyer, General Superintendent Plant Maintenance M. Nazar, Site Vice President J. Waddell, Superintendent Security M. Werner, Plant Manager R. Womack, Manager of Engineering Programs D. Blakesley, Senior Nuclear Security Consultant J. Corwin, Nuclear Security Consultant H. Nyberg, Training Coordinator, The Wackenhut Corporation J. Waddell, Security Manager

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED Opened 50-282/306/20-04-01 NCV SGI was not Adequately Protected (Section 4OA7)

Closed 50-282/01-01-03, Supplement 1 LER Plant in Unanalyzed Condition Due to Flood Panel Deficiencies (Section 1R15)

50-282/01-06-00 LER Security Responders Out of Position Due to Plant Fire (Section 4OA3)

50-282/306/20-04-01 NCV SGI was not Adequately Protected (Section 4OA7)

Discussed None

LIST OF ACRONYMS USED AB Abnormal Operating Procedure AC Alternating Current ADAMS Agencywide Documents Access and Management System AFW Auxiliary Feedwater ALARA As-Low-As Reasonably Achievable AR Action Request AWI Administrative Work Instruction CAP Corrective Action Program CC Component Cooling CE Condition Evaluation CFR Code of Federal Regulations CR Condition Report DBD Design Bases Document DRS Division of Reactor Safety EDG Emergency Diesel Generator EQ Equipment Qualification ERCS Emergency Response Computer System FFD Fitness-For-Duty GEN General Condition Report HRA High Radiation Area IMC Inspection Manual Chapter INPO Institute of Nuclear Power Operations IPE Individual Plant Examination IPEEE Individual Plant Examination of External Events IR

Inspection Report

LCO

Limiting Conditions for Operation

LER

Licensee Event Report

NEI

Nuclear Energy Institute

NRC

Nuclear Regulatory Commission

OPR

Operability Determination

OWA

Operator Workaround

PA

Protected Area

PARS

Publicly Available Records

PI

Performance Indicator

PINGP

Prairie Island Nuclear Generating Plant

PM

Preventive Maintenance

PRA

Probalistic Risk Assessment

RCP

Reactor Coolant Pump

SDP

Significance Determination Process

SGI

Safeguards Information

SI

Safety Injection

SP

Surveillance Procedure

SWI

Section Work Instruction

TCN

Temporary Change Notice

TS

Technical Specification

USAR

Updated Safety Analysis Report

WO

Work Order

XOE

External Operating Experience

LIST OF DOCUMENTS REVIEWED

1R01 Adverse Weather Protection

SP 1039 (WO 0116291)

Tornado Hazard Monthly Site Inspection

Revision 6

Abnormal Operating

Procedure (AB) 2

Tornado/Severe Thunderstorm

Revision 19

Test Procedure 1636

(WO 0117413)

Summer Plant Operation

Revision 10

Temporary Instruction

02-29

D1/D2 Cooling Water Configuration

March 22, 2002

NSPLMI-96001

Individual Plant Examination of External

Events, Section C2

Revision 0

Design Bases Document

(DBD) STR-04

Design Bases Document for the Prairie

Island Screenhouse, Page 60

Revision 3

DBD TOP-03

Design Bases Document - Environmental

Qualification of Electrical Equipment,

Section 2.10, Page A-20

Revision 3

ENG-ME-178

Screenhouse Ventilation Evaluation

DBD SYS-38A

Design Bases Document - Emergency

Diesel Generators, Section 4.2.5, Page 91

Revision 2

DBD TOP-03

Design Bases Document - Environmental

Qualification of Electrical Equipment,

Section 2.7, Page A-17

Revision 3

USAR

Diesel Ventilation, Section 10.3.12

Revision 23

AR CAP 023084

2RY Transformer Local Alarm Received

April 12, 2002

AR CAP 023259

Missile Hazards During Tornado Season

April 24, 2002

Condition Evaluation (CE)

000122

Evaluation of Policy Related to Leaving

Carts In or Near the Vehicle Trap

April 26, 2002

AR CAP 023298

Missing Roof Hatch Allowing Rain to Leak

On Energized Equipment

April 28, 2002

CE 000136

Evaluate Missing Roof Hatch Above Motor

Control Center 2F

April 29, 2002

AR CAP 023324

Tornado Missiles Near D1/D2

April 30, 2002

Corrective Action (CA)

001022

Tornado Missile Hazard Correction

May 2, 2002

CE 000149

Evaluate Change to the Tornado Missile

Protection Process

May 2, 2002

AR CAP 023641

Received Equipment High Temperature

Alarms on 11Circ Water Pump

May 30, 2002

AR CAP 023751

SP 1039 Tornado Hazard Monthly Site

Inspection

June 7, 2002

AR CAP 023949

1GT Generator Main Transformer High Oil

Temperature

June 23, 2002

AR CAP 023965

Evaluate the Effectiveness of the Summer

Operation Procedure

June 24, 2002

AR CAP 023967

Failure to Change Generation Transformer

Filter Media

June 24, 2002

AR CAP 023969

Known Overheating Problem Caused by

Filter Media

June 25, 2002

1R02

Evaluations of Changes, Tests, or Experiments

Procedures

NMC 50.59 Resource Manual

Revision 1

5AWI 3.3.5

50.59 Screenings

Revision 5

5AWI 3.3.6

10CFR50.59 Evaluations

Revision 2

5AWI 4.9.0

Safety Analysis Reports

Revision 8

5AWI 6.1.4

Design Change Project Description/Safety

Assessment

Revision 2

1C18 AOP1

Makeup or Boration of the Reactor Coolant

System Using a Safety Injection Pump

Revision 0

1E-0

Reactor Trip or Safety Injection

Revision 21

1ECA-0.0

Loss of All Safeguards AC Power

Revision 15

1ES-0.1

Reactor Trip Recovery

Revision 19

Condition Reports Written as a Result of Inspection

AR CAP 023916

Incorrect Completion of PINGP [Prairie

Island Nuclear Generating Plant] 279 for

Safety Evaluation 584

June 20, 2002

AR CAP 023917

Distribution of Completed 50.59 Evaluations

June 20, 2002

AR OTH 020549

Clarity USAR Page 6.2-23 Concerning

Safety Injection (SI) Accumulator Check

Valves

June 21, 2002

10 CFR 50.59 Screenings

218

11/22 Diesel Driven Cooling Water Pump

Shaft Bearing Isolation Valves

April 29, 2002

1017

Update to 2 Emergency Contingency

Action 0.0

June 26, 2001

1063

00RV01, Bottom Mount Reduced Inventory

Thermocouples

July 24, 2001

1173

Substitution Part/Component Equivalent

ME-0690

September 19,

2001

1189

Use SI Pump for Borated Water Makeup

October 12, 2001

1098

Cross-Connect CC Pumps

August 23, 2001

1215

Turbine Driven AFW Pump Control Switch

in Manual

January 15, 2002

1259

22 Diesel Cooling Water Pump Governor

Replacement

November 1, 2001

1262

WO 0114936, Setpoint Change 2456

November 2, 2001

1285

Calculation ENG-ME-481

January 8, 2002

1296

Temporary Modification 01T102

January 11, 2002

1402

Temporary Change to SP 1106A

February 16, 2002

1419

Replace FV-PCV-1025 DC45/46 with

LPN-RK Fuses

February 28, 2002

1423

Equipment Engineering Change 1406,

Bearing Change

March 8, 2002

1430

11, 21, and 22 CC Unit Cooler Coil

Replacement

March 18, 2002

1435

Calculation ENG-ME-499, Revision 0

April 3, 2002

1458

WO 0108013 - Fuse Change

April 10, 2002

1464

12 & 22 Diesel Cooling Water Panel Audible

Alarms

April 17, 2002

1468

Fuse Replacement for BKR 253-21/Setpoint

2462. WO 0203609

April 18, 2002

1482

Loop Delta T Emergency Response

Computer System (ERCS) Alarm Setpoint

Changes WO 0203637 & 0203639

May 7, 2002

01VC01

Reactor Coolant Pump (RCP) Seal Water

Injection Check Valve Replacement/

Relocation

January 8, 2002

50.59 Evaluations

123

Downgrading Chemical and Volume Control

System Charging Pump

November 30,

2001

181

Safety Evaluation for the Improper Install of

Raychem Manufactured Heat Shrinkable

Tubing at Prairie Island Unit 1

December 21,

2001

251

Charging Pump Reclassification

December 14,

1994

252

Molded Case Circuit Breakers on Safety

Related Equipment

January 26, 2002

265

Untraceable Molded Case Circuit Breakers

Installed in Safety Related Applications

January 26, 2002

584

Appendix R Program Document Update -

Containment Sump B Valve Hot Short Issue

April 18, 2001

1004

Spent Fuel Pool Cooling

January 23, 2002

1007

Steam Generator Level and Containment

Temperature Restrictions in Support of Main

Steam Line Break Analysis

April 1, 2002

02D101

Isolate D1/D2 Coolant System Crossflow

May 1, 2002

USAR

6.2.1

Safety Injection System Design Basis

Revision 22

10.2.3

Chemical and Volume Control System

Revision 23

10.4.2

Component Cooling System

Revision 22

11.9.1.2

Auxiliary Feedwater System Design Basis

Revision 23

11.9.2.2

Auxiliary Feedwater System Description

Revision 23

USAR Submittal Inputs

000309

Single Failure Discussion

December 7, 2000

000302

Single Failure Analysis Containment Spray

System

December 3, 2000

010004

AFW System

January 10, 2001

010034

Cooling Water

February 25, 2001

010056

Containment Isolation Valves

March 22, 2001

Miscellaneous

10 CFR 50.71(e) Letter to

NRC

Submittal of Revision No. 23 to the USAR

July 1, 2001

10 CFR 50.59

Changes, Tests, or Experiments

NEI 96.07

Guidelines for 10 CFR 50.59 Evaluations

Revision 1

1R04

Equipment Alignment

D5 EDG

TS 3.7

Auxiliary Electrical Systems

Revision 110

USAR Section 8.4

Plant Standby Diesel Generator Systems

Revision 23

Integrated Checklist

C1.1.20.7-9

D5 Diesel Generator Valve Status

Revision 9

Integrated Checklist

C1.1.20.7-10

D5 Diesel Generator Auxiliaries and Local

Panels and Switches

Revision 5

Integrated Checklist

C1.1.20.7-11

D5 Diesel Generator Main Control Room

Switch and Indicating Light Status

Revision 3

Integrated Checklist

C1.1.20.7-12

D5 Diesel Generator Circuit Breakers and

Panel Switches

Revision 8

WO 0109522

D5 2B Start Air Receiver Pressure

Transmitter

21 CC Pump

TS 3.3.C

Component Cooling Water System

Revision 91

USAR Section 10.4.2

Component Cooling System

Revision 22

Integrated Checklist

C1.1.14-2

Unit 2 Component Cooling System

Revision 22

WO 0203695

2CC-1-13 Has an Oil Leak on Actuator Gear

Box

April 22, 2002

AR CAP 023905

Tubing on Scaffold 1109 Touching CC

Pump 21

June 19, 2002

AR CAP 023948

Scaffolds Erected Too Close to Equipment

June 23, 2002

D1 EDG

TS 3.7

Auxiliary Electrical Systems

Revision 110

USAR Section 8.4

Plant Standby Diesel Generator Systems

Revision 23

Integrated Checklist

C1.1.20.7-1

D1 Diesel Generator Valve Status

Revision 19

Integrated Checklist

C1.1.20.7-2

D1 Diesel Generator Auxiliaries and Room

Cooling Local Panels

Revision 8W

Integrated Checklist

C1.1.20.7-3

D1 Diesel Generator Main Control Room

Switch and Indicating Light Status

Revision 13

Integrated Checklist

C1.1.20.7-4

D1 Diesel Generator Circuit Breakers and

Panel Switches

Revision 11

1R05

Fire Protection

Plant Safety Procedure

F5

Fire Fighting

Revision 27

Plant Safety Procedure

F5, Appendix A

Detection Zones and Fire Areas, Fire

Detection Zone 82, Emergency Diesel

Generator D-1 Room

Revision 10

Plant Safety Procedure

F5, Appendix A

Detection Zones and Fire Areas, Fire

Detection Zone 6, Emergency Diesel

Generator D-2 Room

Revision 10

Plant Safety Procedure

F5, Appendix A

Detection Zones and Fire Areas, Fire

Detection Zone 2, Auxiliary Feedwater

Pump Rooms

Revision 10

Plant Safety Procedure

F5, Appendix A

Detection Zones and Fire Areas, Fire

Detection Zone 1, Batteries 11 and 12

Rooms

Revision 7

Plant Safety Procedure

F5, Appendix A

Detection Zones and Fire Areas, Fire

Detection Zone 11, Bus 15 & 16 Switchgear

Rooms

Revision 7

Plant Safety Procedure

F5, Appendix A

Detection Zones and Fire Areas, Fire

Detection Zone 43, Bus 111 & 121

Switchgear Rooms

Revision 7

Plant Safety Procedure

F5, Appendix F

Fire Hazard Analysis

Revision 12

Plant Safety Procedure

F5, Appendix D

Impact of Fire Outside Control/Relay Room

Revision 8

Plant Safety Procedure

F5, Appendix A

Fire Strategies

Revision 7

IPEEE NSPLMI-96001

Appendix B

Internal Fires Analysis

Revision 2

1R06

Flood Protection Measures

External Flooding

USAR Section 2.4.3.5

Floods

Revision 21

USAR Appendix F

Probable Maximum Flood Study

Revision 4

IPEEE NSPLMI-96001

Appendix C, Section

C.2.3.1

External Flooding

Revision 0

DBD-TOP-05

Design Bases Document for Harzards

Revision 2

AB 4

Flood

Revision 20

SP 1293 (WO 0113018)

Inspection of Flood Control Measures

Revision 9

Design Change 01BM02

Flood Panel and Door Design Changes

Revision 1

50.59 Screening 1184

Design Change 01BM02, Revision 1

Revision 1

AR CAP 023335

Review of Surveillance SP 1293 Inspection

of Flood Control Measures

May 1, 2002

AR CAP 023129

121 Cooling Tower Pump House Sump

Pump Tripped on Overload

April 16, 2002

AR CAP 023071

Defect in Weld in Flood Panel MK-1

April 11, 2002

Internal Flooding

IPE NSPLMI-94001

Section 3.3.8

Internal Flooding Evaluation

Revision 0

IPE NSPLMI-94001

Section 6.3

Class FEH-TB1, Flood with Loss of

Secondary Cooling and Bleed and Feed

Revision 0

DBD-TOP-05

Design Bases Document for Harzards

Revision 2

DBD-STR-05

Design Bases Document for the D5/D6

Building

Revision 2

AR CAP 023110

Burned Up Starter Coil Found On Breaker

253-21 for 21 Turbine Building Sump Pump

April 15, 2002

AR CAP 023910

Evaluate as a Temporary Modification Bilge

Pumps in the Turbine Building Drain - Unit 1

Condenser Pit North West Corner

June 20, 2002

1R011 Licensed Operator Requalification Program

Simulator Exercise Guide

Simulator Cycle Quiz 37

Revision 0

SWI O-0

Conduct of Operations

Revision 1

SWI O-2

Shift Organization, Operations, and

Turnover

Revision 46

SWI O-10

Operation Manual Usage

Revision 41

SWI O-25

Periodic Data Acquisition and Logkeeping

Revision 29

1R12

Maintenance Rule Implementation

General

2000 Equipment Performance Annual

Report

April 20, 2001

Maintenance Rule System Basis Document,

Volume 1A

Revision 3

Maintenance Rule System Basis Document,

Volume 1B

Revision 3

NUMARC 93-01

NEI Industry Guideline for Monitoring the

Effectiveness of Maintenance at Nuclear

Power Plants

Revision 2

Regulatory Guide 1.160

Monitoring the Effectiveness of Maintenance

at Nuclear Power Plants

Revision 2

AR CAP 023100

1PC-478 A/B Repeatedly Found Out-of-

Tolerance

April 12, 2002

Apparent Cause

Evaluation 008290

Perform Apparent Cause Evaluation Into

Why 1PC-478 A/B Has Been Found 1PC-4

Found Out-of-Tolerance Repeatedly

April 18, 2002

CE 000057

Conduct Rework Analysis Into the Repeated

Instances of 1PC-478 A/B is Found Out-of-

Tolerance During the Performance of

Quarterly SP 1003

April 18, 2002

Maintenance Rule

Evaluation 000005

Evaluate 1PC-478 A/B Out-of-Tolerance

May 31, 2002

AR CAP 023395

Repeated Calibration Trend Based on

SP 1003

May 6, 2002

AR CAP 023657

AR CAPs Were Found Not Flagged as

Potential Maintenance Rule Functional

Failure or Assigned a Maintenance Rule

Evaluation During Screening

May 31, 2002

AR CAP 023908

Decreasing Bay Levels Due to Lost Intake

Screens

June 19, 2002

1R13

Maintenance Risk Assessments and Emergent Work Control

TS 3.7

Auxiliary Electrical Systems

Revision 110

USAR Section 8.4

Plant Standby Diesel Generator Systems

Revision 23

5AWI 1.9.0

Look Ahead Process

Revision 0

5AWI 15.1.7

Voluntary Limiting Conditions for Operation

(LCO) Process

Revision 1

WO 0204455

D1 Water Supply Solenoid Valve

May 14, 2002

TS 3.3.D

Cooling Water System

Revision 131

USAR Section 10.4

Plant Cooling System

Revision 22

AR CAP 023800

12 Diesel Driven Cooling Water Pump

Inoperable Due to Governor Hunting

June 12, 2002

AR CAP 023170

12 Diesel Driven Cooling Water Pump

Speed Hunting

April 19, 2002

Daily Risk Assessments

April, 12, 2002,

June 4, 12, and

26, 2002

Probalistic Risk

Assessment (PRA)

Project File V.SPA.02.008

Risk Significance of Intake Traveling

Screens/Bypass Gates Failure Event

June 24, 2002

H 24.1

Assessment and Management of Risk

Associated with Maintenance Activities

Revision 3

AR CAP 023088

Units 1 and 2 in PRA Orange Condition

April 12, 2002

AR CAP 023133

11 Condensate Pump Removed from

Service for Maintenance Prior to Risk

Assessment

April 16, 2002

AR CAP 023154

Failure to Log Entry into PRA Orange

Condition

April 18, 2002

AR CAP 023257

Apparent Error in Prairie Island IPEEE

April 24, 2002

AR CAP 023970

Stopped Work Control Center from Tagging

Out 21 Cooling Water Strainer with D2 Out-

of-Service During B Week

June 25, 2002

AR CAP 023986

LCO Time Extended Because Breaker

Inspection Not Performed in a Timely

Manner

June 26, 2002

1R15

Operability Evaluations

General Condition Report

(GEN) 2002 01283

Inaccurate Assumptions Used in the

Analysis for the Non-Return Check Valves in

the Main Steam Line Break Event

February 11, 2002

P. Huffman Update to

GEN 2002 01283

Inaccurate Assumptions Used in the

Analysis for the Non-Return Check Valves in

the Main Steam Line Break Event

February 22, 2002

Detailed Basis For

Operability 2002-02-08

Operability Determination Addendum

March 13, 2002

Nuclear Analysis

Department File

OC.PX.2002.021

H. Nelson Memo to P. Huffman

March 4, 2002

Reportability

Determination for GEN

2002 01283

Inaccurate Assumptions Used in the

Analysis for the Non-return Check Valves in

the Main Steam Line Break Event

H. Nelson Memo to S.

Thomas, Nuclear Analysis

Department

OC.PX.2002.024

Main Steam Line Break Significance

Determination Analysis

March 14, 2002

50.59 Evaluation Analysis

1007

Steam Generator Level and Containment

Temperature Restrictions in Support of Main

Steam Line Break Analysis

Revsion 0

USAR Section 14.5.5

Rupture of a Steam Pipe

Revision 22

AR CAP 023064

Assess Classification of the Bearing

Lubricating Water Supply Piping and Flow

Switches

April 10, 2002

AR CAP 023118

Incomplete Engineering Judgement

April 15, 2002

USAR Section 10.4

Plant Cooling Water System

Revision 23

Evaluation of Vertical Cooling Water Pump

Flow Switches

April 15, 2002

AR CAP 023138

Okonite/Scotch EQ Splices Installed in a

Non-Tested Configuration

April 17, 2002

EQ Okonite Tape Splice Configuration

Turnover Evaluation

Clarification on EQ Okonite Tape Splice

Configuration Turnover Evaluation, Section

Number of Wraps Around Splice

April 23, 2002

AR CAP 023737

A Pipe Hanger Near MV-32034 in Old

Screenhouse is Contacting Conduit

June 6, 2002

Operability Determination

(OPR) 000315

Pipe Hanger Rubbing Against Conduit for

the 121 Motor Driven Cooling Water Pump

June 10, 2002

AR CAP 023905

Scaffold 1109 Touching Component Cooling

Pump 21

June 19, 2002

AR CAP 023948

Scaffolds Erected Too Close to Equipment

June 23, 2002

AR CAP 023948

(Supplement)

Supplemental Engineering Information

June 27, 2002

AR CAP 023818

11 SI Pump Motor is Seeking Magnetic

Center

June 13, 2002

OPR 000316

Evaluate the Operability of 11 SI Pump

June 13, 2002

Vendor Manual

XH-1-1393

Bingham Willamette SI Pump

WO 0205412

Perform Test Procedure 1087A

June 13, 2002

AR CAP 023907

Incorrect O-Ring Material Was Used for EQ

MOVs [Motor-Operated Valves] in

Containment

June 19, 2002

OPR 000319

Operability Determination for the Use of

Incorrect O-Ring Material on Power

Operated Relief Valve (PORV) Block Valves

June 19, 2002

TS Section 3.1.A.2

Pressurizer PORVs

Revision 135

TS Bases, Section 3.1

Reactor Coolant System Bases

Revision 135

USAR, Section 4.4

Reactor Pressure Relief System

Revision 23

1R16

OWAs

D6 Fuel Oil Level

AR CAP023556

D6 Fuel Oil Storage Tank ERCS Level

Indication

May 20, 2002

WO 0201784

ERCS PT 2U8003A is Erratic and Unreliable

TS 4.6.A

Diesel Generators

Revision 147

SP 2001

Unit 2 Daily Control Room Log

Revision 56

2C38

D5/D6 Fuel Oil System, Attachment A

Revision 15

Temporary Instruction

02-13

24 D6 Fuel Oil Storage Tank ERCS Point

Unit 2 Pressurizer Spray Valve A in Manual

TS Section 3.1.B.2

Pressure/Temperature Limits

Revision 135

USAR, Section 4.4

Reactor Pressure Relief System

Revision 23

DBD SYS-04

Design Bases Document for the Reactor

Coolant System

Revision 2

AR CAP 023297

Unit 2 Loop A Pressurizer Spray Valve

CV-31228 is Controlling Erratically

April 27, 2002

CE 000135

Evaluate Control Response of the Unit 2

Loop A Pressurizer Spray Valve

April 29, 2002

1R17

Permanent Plant Modifications

USAR, Section 8.4

Plant Standby Diesel Generator System

Revision 23

Design Change Notice

02D101

Isolate D1/D2 Coolant System Cross-Flow

Revision 0

WO 0202198

Install Cross Flow Isolation Valve, Air Vent,

Coolant Sample Valve, and Re-Route

Expansion Tank Overflow Pipe at D1 Diesel

Generator

May 13, 2002

WO 0202199

Install Cross Flow Isolation Valve, Air Vent,

Coolant Sample Valve, and Re-Route

Expansion Tank Overflow Pipe at D2 Diesel

Generator

May 21, 2002

Coltec Industries Letter

Standby Diesel Generator Crossflow

July 8, 1992

Coltec Industries

10 CFR 21 Notification

Part 21 Notification for Fairbanks Morse

Engine Division Model 38TD8-1/8 Cooling

System Investigation - Arkansas Nuclear

One Unit 2

September 13,

1991

ENG-ME-409

Unit 1 Emergency Diesel Generator Heat

Exchanger Performance with Reduced

Cooling Water Flow

April 9, 2002

ENG-ME-479

Tube Plugging Criteria for Unit 1 Diesel

Generator Heat Exchanger

September 27,

2001

ENG-ME-480

Operability Determination for Unit 1 Diesel

Generator Heat Exchangers with Tubes

Plugged and 85F Cooling Water

September 28,

2001

Commercial Grade

Evaluation Number

PI-0348

Application of the Armstrong Model AV-11

Vent in the D1/D2 Diesel Generator Jacket

Coolant Lines

Revision 0

Drawing NF-39255-1

Diesel Generator D1 & D2 Units 1 and 2

Flow diagram

Revision Z

Permanent Plant Modifications Biennial Inspection Documents

Procedures

5AWI 3.14.1

Setpoint Control

Revision 12

5AWI 3.14.2

Electrical Process and Protection Setpoint

Control

Revision 8

5AWI 6.1.0

Design Change General

Revision 7

5AWI 6.1.1

Design Inputs

Revision 3

5AWI 6.1.2

Design Documents, Review, and Verification Revision 4

5AWI 6.1.3

Design Change Package, Logs and

Records

Revision 2

5AWI 6.1.5

Design Change Implementation Plans

Revision 3

5AWI 6.1.6

Design Change Review and Approval

Revision 5

5AWI 6.1.7

Design Change Work Orders

Revision 5

5AWI 6.1.8

Engineering Change Requests

Revision 2

5AWI 6.1.9

Design Change Turnover for Operation

Revision 3

5AWI 6.1.10

Design Change Close-out

Revision 2

5AWI 6.2.0

Equipment Engineering Change Evaluation

Revision 4

5AWI 6.4.0

Existing Component Functional

Performance and Design Requirements

Identification

Revision 1

5AWI 6.4.0

Existing Component Functional

Performance and Design Requirements

Identification

Revision 1

5AWI 8.2.3

Dedication of Commercial Grade Items

Revision 3

C1.1.20.7-1

D1 Diesel Generator Valve Status

Revision 19

C70300

Remote Alarm Response Procedure (Raw

Water Supply Not Available)

Revision 1

H9

Fuse Control Program

Revision 6

SP 1210

Monthly Safeguards Hold Verification

Revision 18

Commercial Grade Evaluations

PI-0064

Cooling Water Strainer Parts

Revision 4

PI-0190

VP 591 Flowrite Double Seated Valves and

Valve Parts

Revision 4

PI-0343

Westinghouse Test Relay Model 1161540

Revision 1

PI-0348

Armstrong Model AV-11 Vent

Revision 0

Design Changes

99DC02

Replace 12 & 22 Batteries

Revision 0

99DC03

Relocation of 125 Volts Direct Current EQ

Circuits

Revision 1

99SF02

Replace Spent Fuel Pool Heat Exchanger

Revision 0

99SI02

Repower Residual Heat Removal Sump B

Suction Valves

Revision 0

00FP01

PORV and PORV Block Valve Cable

Reroute

Revision 0

00RV01

Bottom Mount Reduced Inventory

Thermocouples

Revision 0

01EA01

Bus 12 Control & Instrument Cable

Restoration

Revision 0

01VC01

RCP Seal Water Injection Check Valve

Replacement/Relocation

Revision 0

02D101

Isolate D1/D2 Coolant System Crossflow

Revision 0

Equipment Engineering Change Evaluations

1020

AFW Pump Suction and Discharge

Pressure Switches

January 31, 2002

1023

RCP Seal Water Injection Check Valves

February 4, 2002

Drawings

NE-40008, Sh. 39

11 Containment Sump B Isolation Valve B-1

MV 32077

Revision BU

Setpoint Changes

2TM-405R

New Gains per SP 2722 Loop Delta T

Revision 5

2TR-2002/3

Increase to 190 Degrees. After

Replacement Return Setpoint to Original

185 Degrees

Revision 2

Substitution Part/Component Equivalent

ME-0336

Charging Pump Drive Shaft Keyway

Dimensions

December 14,

2001

ME-0690

Replace Diesel Driven Cooling Water Pump

Discharge Check Valves

September 27,

2001

PN-0617

Diesel Driven Cooling Water Pump Heat

Exchanger Cooling Outlet Valves

April 6, 2001

USAR

4.4.4

Reactor Pressure Relief System Design

Basis

Revision 23

10.2.2

Spent Fuel Pool Cooling System

Revision 23

Miscellaneous

Temporary Change

Notice (TCN) 2002-1056

Unit 1 Startup Procedure

April 9, 2002

TCN 2001-1405

Air Removal System

April 4, 2001

Engineering Design Standard for Motor

Control Center Control Circuit Fuse

Selection Criteria, Section 3.3.1.6

Revision 1

1R19

Post-Maintenance Testing

WO 0200988

Replace 2SSH-5566, D5 Engine 1

Overspeed Detector High

SP 2295

D5 Diesel Generator 6-Month Fast Start

Revision 23

TS 3.7

Auxiliary Electrical Systems

Revision 110

USAR Section 8.4

Plant Standby Diesel Generator Systems

Revision 23

WO 0204455

D1 Water Supply Solenoid Valve

May 14, 2002

TS 3.3.D

Cooling Water System

Revision 131

USAR Section 10.4

Plant Cooling System

Revision 22

AR CAP 023800

12 Diesel Cooling Water Pump Inoperable

Due to Governor Hunting

June 12, 2002

SP 1106A

12 Diesel Cooling Water Pump Monthly Test Revision 59

TS 3.3.C

Component Cooling Water System

Revision 91

USAR Section 10.4.2

Component Cooling System

Revision 22

WO 0115753

P3119-1-22 22 Component Cooling Pump

PM

June 19, 2002

Preventive Maintenance

Procedure PM 3119-1-22

22 CC Pump Annual Inspection

Revision 13

1R22

Surveillance Testing

SP 1102

11 Turbine-Driven AFW Pump Monthly Test

Revision 75

SP 2102

22 Turbine-Driven AFW Pump Monthly Test

Revision 68

TS 4.8.A

Auxiliary Feedwater System

Revision 116

USAR Section 11.9.2.2

Auxiliary Feedwater System

Revision 23

WO 0201947

Steam Leak on Control Valve 31060

February 28, 2002

SP 1335

D2 Diesel Generator 18-Month 24-Hour

Load Test

Revision 7

SP 2307

D6 Diesel Generator 6-Month Fast Start

Test

Revision 17

TS 4.6

Periodic Testing of Emergency Power

Systems

Revision 113

USAR Section 8.4

Plant Standby Diesel Generator Systems

Revision 23

SP 2094

Bus 25 Load Sequencer Test

Revision 16

TS 4.1-1c, Item 11

Auto Load Sequencers

Revision 161

USAR Section 8.3.2.2

Load Sequencing

Revision 21

AR CAP 023175

Both PORVs Not Declared Inoperable

During Performance of SP 1182A (Over-

Pressure Protection System Test)

April 19,2002

SP 1182A

Overpressure Protection System Refueling

Outage Functional Test

Revision 13W

TS Section 3.1.A.2

Pressurizer Power Operated Relief Valves

Revision 135

1R23

Temporary Modifications

5AWI 6.5.0

Temporary Modifications

Revision 11

AR CAP 023902

No AR Written for Portable Fan Set Up at

RMU 141

June 19, 2002

Temporary Modification

Package 02T121

Installation of a Ground Strap on 2N31

Preamplifier

50.59 Screening 1408

Temporary Modification 02T121

Revision 0

WO 0201740

Installation of Temporary Modification

02T121

WO 0201741

Remove Temporary Modification 02T121

TS Section 3.5

Instrumentation

Revision 111

USAR, Section 7.3

Nuclear Instruments

Revision 23

1EP6

Drill Evaluation

Prairie Island Nuclear Generating Plant

Emergency Plan Rehearsal Drill Package

April 3, 2002

Revision 0

AR CAP 000092

Technical Support Center Ventilation Door is

Not Always Closed After Ventilation is Set

Up

AR CAP 023008

Accountability Report Included Names of

Individuals Who Are No Longer Employed

4OA1 Performance Indicator Verification

NEI 99-02

Regulatory Assessment Performance

Indicator Guideline

Revision 2

LER 1-01-04

Water Intrusion into a Control Rod Electrical

Cabinet Results in Dropped Rods Causing a

Negative Flux Reactor Trip

Revision 0

LER 1-01-05

Fault and Fire in Non-Safeguards Circuit

Breaker Results in Reactor Trip and AFW

System Actuation

Revision 0

LER 2-01-04

Manual Turbine Trip/Reactor Trip Due to

High Differential Condenser Backpressure

Revision 0

LER 2-01-05

Manual Reactor Trip on Unit 2 Initiated in

Response to a High Differential Pressure

Between the Turbine Steam Condensers

Caused by an Inadvertent Venting of One

Condenser While Isolating a Steam Leak

Revision 0

Monthly Operating

Reports

July 2001 Through March 2002

NRC Inspection Reports

01-15, 01-16, 01-17, 01-18, and 01-19

4OA2 Identification and Resolution of Problems

USAR Section 2.4.3.5

Floods

Revision 21

USAR Appendix F

Probable Maximum Flood Study

Revision 4

IPEEE NSPLMI-96001

Appendix C, Section

C.2.3.1

External Flooding

Revision 0

AB 4

Flood

Revision 20

SP1293

Inspection of Flood Control Measures

Revision 9

Design Change 01BM02

Flood Panel and Door Design Changes

Revision 1

50.59 Screening 1184

Design Change 01BM02, Revision 1

Revision 1

LER 1-01-03

Plant in an Unanalyzed Condition Due to

Flood Panel Deficiencies

September 10,

2001

LER 1-01-03,

Supplement 1

Plant in an Unanalyzed Condition Due to

Flood Panel Deficiencies

April 12, 2002

AR CAP 023003

Defect Weld in Flood Panel MK-4

April 1, 2002

AR CAP 023071

Defect Weld in Flood Panel MK-1

April 11, 2002

AR OTH 023859

AR OTH 000188 Related to D6 Root Cause

Closed with Incomplete Action

June 14, 2002

AR OTH 001239

Followup on Status of Technical

Communication

May 24, 2002

AR OTH 000188

Revise Communication Process

May 26, 2002

CR 20014617

Prairie Island Not Receiving Technical

Service Notes

May 27, 2001

CR 20014518

Perform Independent Review of SACM

Related External Operating Experience

(XOE) Assessments

May 23, 2001

CR 20015167

Establish Standards for Independence of

Technical Advice from Outside Vendors

June 21, 2001

CR 20013446

Develop/Implement Process on Use of

Operating Experience

May 14, 2001

CR 20014150

Reassess XOE

May 9, 2001

CR 20014252

Submit LER 2-01-03 for Unit 2 Shutdown

May 14, 2001

CR 20014601

Revise 18-Month PMs for Six-Year AMOT

Valves

May 25, 2001

CR 20014611

Evaluate Organization & Programmatic

Issues

May 26, 2001

CR 20014612

Review Use of Shell Rotella T in D5 and D6

May 26, 2001

CR 20014696

Develop, Implement, and Reinforce

Standardized Tools for Problem Solving

May 30, 2001

CR 20015166

Enforce Management Expectations

Involving Independence of Technical

Reviews for XOEs

June 21, 2001

CR 20015168

Add a Process to XOE Responses to

Monitor Critical Characteristics

June 21, 2001

CR 20017857

Have a Living, Component Specific

Database of Operating Experience

September 23,

2001

CR 200185151

Perform a Self-Assessment of the

Effectiveness of the Operating Experience

Program

October 17, 2001

Permanent Plant Modifications Biennial Inspection Documents

CR 20016428

Screening 1025 Did Not Identify the

Function or Performance Requirement for

the Component Being Changed

August 1, 2001

CR 20016467

Screening 1035 Does Not Adequately

Identify Design Function

August 3, 2001

CR 20016619

Incomplete 50.59 Screening

August 10, 2001

CR 20016829

Screened Vent Opening Cut in Ends of

Buses 11 and in 1990 Without Modification,

Now Design Change Process

August 17, 2001

CR 20017759

PINGP 1300 - TCN Marked That Change

Was Not Exempt from 50.59 Screening but

No Screening Was Documented (20011405)

September 20,

2001

CR 20018422

Screening 1195 and 1194 Did Not

Sufficiently Address Why Setpoint Increase

Is Not Adverse

October 11, 2001

CR 200185705

50.59 Screening 1196 Did Not Identify in

Part 2 That the Activity Involved Could

Initiate a Transient

November 1, 2001

CR 200185788

50.59 Screening 1208 & 1209 Not in

Compliance with 5AWI 3.3.5

November 5,

2001

CR 200186587

The Second Factory Acceptance Test for 22

Replacement Battery

November 29,

2001

CR 200187181

Self-Assessment of 50.59 Process

December 18,

2001

CR 200200116

Drawing Changes Contain Errors - Mod

94L473

February 5, 2002

CR 200200204

Turnover on Modification Was Done Without

Work Being Completed. WO Status Was

85 Work Complete and Then Was Lost.

Work Not Done.

February 27, 2002

CR 200200514

Inadequate Work Order Reviews and/or

Walkdowns

January 21, 2002

CR 200200625

Modification 99SF04 Not Closed Within

1 Year as Required by 5AWI6.1.0

January 22, 2002

CR 200200988

Drawing X-H-106-1936 Was Not Updated to

Reflect Changes Associated with

Modification 79L537

February 1, 2002

CR 200201209

22 Battery Rack Had One HILTI Bolt -

Required Minimum Embedment Not Met

February 5, 2002

CR 200201241

Foreign Material Found in One Battery Cell

February 7, 2002

CR 200201335

Piece of Battery Plug Floating Inside 22

Battery Cell

February 9, 2002

CR 200202163

TCN to SP 2103 and SP 2101 Implemented

Without 50.59 Screening.

March 5, 2002

AR CAP 000023

Drawing NF 92190 Not Upgraded During

Design Change 96C006

March 22, 2002

AR CAP 023224

Potential Negative Trend in Modification

Turnovers and Reviews

April 22, 2002

AR CAP 023385

Less Than Adequate Design Change

Planning Activities

May 6, 2002

AR CAP 023506

Pipe Support Installed at Wrong Elevation

May 15, 2001

CE 000243

Standard Quality Part Used Where Safety

Related Parts are Required

May 17, 2001

4OA3 Event Followup

LER 1-01-03

Plant In Unanalyzed Condition Due to Flood

Panel Deficiencies

September 10,

2001

LER 1-01-03,

Supplement 1

Plant In Unanalyzed Condition Due to Flood

Panel Deficiencies

April 12, 2002

Design Change 01BM02

Flood Panel and Door Design Changes

Revision 1

AR CAP 023003

Defect Weld in Flood Panel MK-4

April 1, 2002

AR CAP 023071

Defect Weld in Flood Panel MK-1

April 11, 2002

3PP Plant Protection

Administrative Work

Instruction 5AWI 5.1.0

Site Security

Revision 7

Administrative Work

Instruction 5AWI 3.18.0

Fitness-For-Duty Program

Revision 5

Corporate Control

Directive N1ACD 2.12

Fitness-For-Duty Program

Revision 3

Fitness-For-Duty Program Performance

Data

June 30 and

December 31,

2001

Security Event Logs

September 2001

through May

2002

Nuclear Oversight

Observation Report

(NOOR) 2001-06-1116

Fitness-For-Duty

August 6 and

September 6,

2001

NOOR 2001-06-130

Corrective Actions

September 17-

19, 2001

NOOR 2001-06-131

Self-Assessments

September 21,

2001

Security Administrative

Procedure SAP 2.8

Quarterly Security Report

Revision 2

Security Instruction

Procedure (SIP) 1.1

Badge Control

Revision 0

SIP 1.5

Escort Responsibilities

Revision 0

SIP 4.1

Testing and Inspection of Systems and

Equipment

revision 2

SIP 4.2

Calibration and Surveillance Procedure

Revision 0

SIP 5.1

Reporting of Security Events

Revision 3

SP 1620

Quarterly Metal Detector Calibration

Revision 10

SP 1621

Explosive Vapor Detector Annual Test

Revision 13

SP 1653

Quarterly X-Ray Machine Test

Revision 6

Summary of Access Equipment

WO/PM/SPS

July 17.2001

through

June 14, 2002

Security Activity Reports

October 2001

through March

2002

4OA1 Performance

Indicator Verification

FFD Personnel Reliability, Personnel

Screening, and Security Equipment

Performance Indicator Data

Fourth Quarter

2001 through

First Quarter

2002

SAP 2.8

Quarterly Security Report

Revision 2

Security Event Logs

October 2001

through March

2002