Withdrawal of Exemption Request for Dry Shielded Canisters 11 - 16 Due to Nonconforming Dye Penetrant Examinations, Supplemental Information
ML14351A155
Person / Time
Site: Monticello  Xcel Energy icon.png
Issue date: 12/16/2014
From: Fili K
Northern States Power Co, Xcel Energy
To:
Document Control Desk, NRC/NMSS/SFST
References
L-MT-14-104, TAC L24939
Download: ML14351A155 (2)


Text

(l Xcel Energy Monticello Nuclear Generating Plant 2807 W County Rd 75 Monticello, MN 55362 December 16, 2014 L-MT-14-104 10 CFR 72.7 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket No. 50-263 Renewed Facility Operating License No. DPR-22 Independent Spent Fuel Storage Installation Docket No. 72-58 Withdrawal of Exemption Request for Dry Shielded Canisters 11 - 16 Due to Nonconforming Dye Penetrant Examinations, Supplemental Information (TAC No. L24939)

References:

1) NSPM letter to NRC Document Control Desk, L-MT-14-016, Exemption Request for Dry Shielded Canisters 11 - 16 Due to Nonconforming Dye Penetrant Examinations, dated July 16, 2014 (ADAMS Accession No. ML14199A370).
2) NSPM letter to NRC Document Control Desk, L-MT-14-082, Exemption Request for Dry Shielded Canisters 11 - 16 Due to Nonconforming Dye Penetrant Examinations, Supplemental Information, dated November 3, 2014 (ADAMS Accession No. ML14309A194).

Pursuant to 10 CFR 72.7, "Specific Exemptions", the Northern States Power Company, a Minnesota corporation (NSPM), doing business as Xcel Energy, submitted Reference 1 to request an exemption to the requirements of 10 CFR 72.212(b)(3) and 10 CFR 72.212(b)(11) for six (6) NUHOMS Dry Shielded Canisters (DSCs) due to nonconforming dye penetrant (PT) examinations performed during the loading campaign started in September 2013. That exemption request was supplemented by Reference 2.

This letter hereby withdraws the exemption request subm itted in Reference 1.

Document Control Desk Page 2 Summary of Commitments This letter makes no new commitments and no revision s to existing commitments.

Karen:Fili Site Vice-President Monticello Nuclear Generating Plant Northern States Power Company-Minnesota No enclosures cc: Administrator, Region Ill, USNRC Terry Beltz, Project Manager, Monticello Nuclear Generating Plant, USNRC Jennifer Davis, Project Manager, Spent Fuel Storage and Transportation, USNRC Resident Inspector, Monticello Nuclear Generating Plant, USNRC