Pipe Cracks in Stagnant Borated Water Systems at PWR PlantsML031180155 |
Person / Time |
---|
Site: |
05000000 |
---|
Issue date: |
07/17/1979 |
---|
From: |
NRC/IE |
---|
To: |
|
---|
References |
---|
IN-79-019, NUDOCS 7907230164 |
Download: ML031180155 (7) |
|
|
---|
Category:NRC Information Notice
MONTHYEARInformation Notice 1990-15, Reciprocity Notification of Agreement State Radiation Control Directors Before Beginning Work in Agreement States1990-03-17017 March 1990 Reciprocity Notification of Agreement State Radiation Control Directors Before Beginning Work in Agreement States Information Notice 1990-18, Potential Problems With Crosby Safety Relief Valves Used on Diesel Generator Air Start Receiver Tanks1990-03-0909 March 1990 Potential Problems With Crosby Safety Relief Valves Used on Diesel Generator Air Start Receiver Tanks Information Notice 1990-18, Potential Problems with Crosby Safety Relief Valves Used on Diesel Generator Air Start Receiver Tanks1990-03-0909 March 1990 Potential Problems with Crosby Safety Relief Valves Used on Diesel Generator Air Start Receiver Tanks Information Notice 1990-17, Weight and Center of Gravity Discrepancies for Copes-Vulcan Valves1990-03-0808 March 1990 Weight and Center of Gravity Discrepancies for Copes-Vulcan Valves Information Notice 1990-16, Compliance with New Decommissioning Rule1990-03-0707 March 1990 Compliance with New Decommissioning Rule Information Notice 1990-14, Accidental Disposal of Radioactive Materials1990-03-0606 March 1990 Accidental Disposal of Radioactive Materials Information Notice 1990-13, Importance of Review and Analysis of Safeguards Event Logs1990-03-0505 March 1990 Importance of Review and Analysis of Safeguards Event Logs Information Notice 1990-11, Maintenance Deficiency Associated with Solenoid-Operated Valves1990-02-28028 February 1990 Maintenance Deficiency Associated with Solenoid-Operated Valves Information Notice 1990-12, Monitoring or Interruption of Plant Communications1990-02-28028 February 1990 Monitoring or Interruption of Plant Communications Information Notice 1990-09, Extended Interim Storage of Low-Level Radioactive Waste by Fuel Cycle and Materials Licensees1990-02-0505 February 1990 Extended Interim Storage of Low-Level Radioactive Waste by Fuel Cycle and Materials Licensees Information Notice 1990-08, KR-85 Hazards From Decayed Fuel1990-02-0101 February 1990 KR-85 Hazards From Decayed Fuel Information Notice 1990-08, KR-85 Hazards from Decayed Fuel1990-02-0101 February 1990 KR-85 Hazards from Decayed Fuel Information Notice 1990-07, New Information Regarding Insulation Material Performance and Debris Blockage of PWR Containment Sumps1990-01-30030 January 1990 New Information Regarding Insulation Material Performance and Debris Blockage of PWR Containment Sumps Information Notice 1990-06, Potential for Loss of Shutdown Cooling While at Low Reactor Coolant Levels1990-01-29029 January 1990 Potential for Loss of Shutdown Cooling While at Low Reactor Coolant Levels Information Notice 1990-05, Inter-System Discharge of Reactor Coolant1990-01-29029 January 1990 Inter-System Discharge of Reactor Coolant Information Notice 1990-03, Malfunction of Borg-Warner Bolted Bonnet Check Valves Caused by Failure of the Swing Arm1990-01-23023 January 1990 Malfunction of Borg-Warner Bolted Bonnet Check Valves Caused by Failure of the Swing Arm Information Notice 1990-02, Potential Degradation of Secondary Containment1990-01-22022 January 1990 Potential Degradation of Secondary Containment Information Notice 1990-01, Importance of Proper Response to Self-Identified Violations by Licensees1990-01-12012 January 1990 Importance of Proper Response to Self-Identified Violations by Licensees Information Notice 1989-89, Event Notification Worksheets1989-12-26026 December 1989 Event Notification Worksheets Information Notice 1989-88, Recent NRC-Sponsored Testing of Motor-Operated Valves1989-12-26026 December 1989 Recent NRC-Sponsored Testing of Motor-Operated Valves Information Notice 1989-87, Disabling of Emergency Diesel Generators by Their Neutral Ground-Fault Protection Circuitry1989-12-19019 December 1989 Disabling of Emergency Diesel Generators by Their Neutral Ground-Fault Protection Circuitry Information Notice 1989-85, Epa'S Interim Final Rule on Medical Waste Tracking and Management1989-12-15015 December 1989 Epa'S Interim Final Rule on Medical Waste Tracking and Management Information Notice 1989-86, Type Hk Circuit Breakers Missing Close Latch Anti-Shock Springs1989-12-15015 December 1989 Type Hk Circuit Breakers Missing Close Latch Anti-Shock Springs Information Notice 1989-83, Sustained Degraded Voltage on the Offsite Electrical Grid and Loss of Other Generating Stations as a Result of a Plant Trip1989-12-11011 December 1989 Sustained Degraded Voltage on the Offsite Electrical Grid and Loss of Other Generating Stations as a Result of a Plant Trip Information Notice 1989-83, Sustained Degraded Voltage on the Offsite Electrical Grid and Loss of Other Generating Stations As a Result of a Plant Trip1989-12-11011 December 1989 Sustained Degraded Voltage on the Offsite Electrical Grid and Loss of Other Generating Stations As a Result of a Plant Trip Information Notice 1989-82, Recent Safety-Related Incidents at Large Irradiators1989-12-0707 December 1989 Recent Safety-Related Incidents at Large Irradiators Information Notice 1989-59, Suppliers of Potentially Misrepresented Fasteners1989-12-0606 December 1989 Suppliers of Potentially Misrepresented Fasteners Information Notice 1989-81, Inadequate Control of Temporary Modifications to Safety-Related Systems1989-12-0606 December 1989 Inadequate Control of Temporary Modifications to Safety-Related Systems Information Notice 1989-80, Potential for Water Hammer, Thermal Strafication, and Steam Binding in High-Pressure Coolant Injection Piping1989-12-0101 December 1989 Potential for Water Hammer, Thermal Strafication, and Steam Binding in High-Pressure Coolant Injection Piping Information Notice 1989-79, Degraded Coatings and Corrosion of Steel Containment Vessels1989-12-0101 December 1989 Degraded Coatings and Corrosion of Steel Containment Vessels Information Notice 1989-56, Questionable Certification of Material Supplied to the Defense Dept. by Nuclear Suppliers1989-11-22022 November 1989 Questionable Certification of Material Supplied to the Defense Dept. by Nuclear Suppliers Information Notice 1989-56, Questionable Certification of Material Supplied to the Defense Dept. By Nuclear Suppliers1989-11-22022 November 1989 Questionable Certification of Material Supplied to the Defense Dept. By Nuclear Suppliers Information Notice 1989-78, Failure of Packing Nuts on One-Inch Uranium Hexafluoride Cylinder Valves1989-11-22022 November 1989 Failure of Packing Nuts on One-Inch Uranium Hexafluoride Cylinder Valves Information Notice 1989-76, Biofouling Agent: Zebra Mussel1989-11-21021 November 1989 Biofouling Agent: Zebra Mussel Information Notice 1989-77, Debris in Containment Emergency Sumps and Incorrect Screen Configurations1989-11-21021 November 1989 Debris in Containment Emergency Sumps and Incorrect Screen Configurations Information Notice 1989-75, Falsification of Welder Qualifications for Contractor Employees1989-11-20020 November 1989 Falsification of Welder Qualifications for Contractor Employees Information Notice 1989-74, Clarification of Transportation Requirements Applicable to Return of Spent Radiopharmacy Dosages from Users to Suppliers1989-11-0707 November 1989 Clarification of Transportation Requirements Applicable to Return of Spent Radiopharmacy Dosages from Users to Suppliers Information Notice 1989-73, Potential Overpressurization of Low Pressure Systems1989-11-0101 November 1989 Potential Overpressurization of Low Pressure Systems Information Notice 1989-72, Failure of Licensed Senior Operators to Classify Emergency Events Properly1989-10-24024 October 1989 Failure of Licensed Senior Operators to Classify Emergency Events Properly Information Notice 1989-71, Diversion of the Residual Heat Removal Pump Seal Cooling Water Flow During Recirculation Operation Following a Loss-Of-Coolant Accident1989-10-19019 October 1989 Diversion of the Residual Heat Removal Pump Seal Cooling Water Flow During Recirculation Operation Following a Loss-Of-Coolant Accident Information Notice 1989-70, Possible Indications of Misrepresented Vendor Products1989-10-11011 October 1989 Possible Indications of Misrepresented Vendor Products Information Notice 1989-68, Evaluation of Instrument Setpoints During Modifications1989-09-25025 September 1989 Evaluation of Instrument Setpoints During Modifications Information Notice 1989-67, Loss of Residual Heat Removal Caused by Accumulator Nitrogen Injection1989-09-13013 September 1989 Loss of Residual Heat Removal Caused by Accumulator Nitrogen Injection Information Notice 1989-66, Qualification Life of Solenoid Valves1989-09-11011 September 1989 Qualification Life of Solenoid Valves Information Notice 1989-65, Potential for Stress Corrosion Cracking in Steam Generator Tube Plugs Supplied by Babcock and Wilcox1989-09-0808 September 1989 Potential for Stress Corrosion Cracking in Steam Generator Tube Plugs Supplied by Babcock and Wilcox Information Notice 1989-64, Electrical Bus Bar Failures1989-09-0707 September 1989 Electrical Bus Bar Failures Information Notice 1989-63, Possible Submergence of Electrical Circuits Located Above the Flood Level Because of Water Intrusion and Lack of Drainage1989-09-0505 September 1989 Possible Submergence of Electrical Circuits Located Above the Flood Level Because of Water Intrusion and Lack of Drainage Information Notice 1989-62, Malfunction of Borg-Warner Pressure Seal Bonnet Check Valves Caused by Vertical Misalignment of Disk1989-08-31031 August 1989 Malfunction of Borg-Warner Pressure Seal Bonnet Check Valves Caused by Vertical Misalignment of Disk Information Notice 1989-61, Failure of Borg-Warner Gate Valves to Close Against Differential Pressure1989-08-30030 August 1989 Failure of Borg-Warner Gate Valves to Close Against Differential Pressure Information Notice 1989-58, Disablement of Turbine-Driven Auxiliary Feedwater Pump Due to Closure of One of the Parallel Steam Supply Valves1989-08-0303 August 1989 Disablement of Turbine-Driven Auxiliary Feedwater Pump Due to Closure of One of the Parallel Steam Supply Valves 1990-03-09
[Table view] |
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
WASHINGTON, D. C. 20555 July 17, 1979 IE Information Notice No. 79-19 PIPE CRACKS IN STAGNANT BORATED WATER SYSTEMS AT PWR PLANTS
Description of Circumstances
During the period of November 1974 to February 1977 a number of cracking
incidents have been experienced in safety-related stainless steel piping
systems and portions of systems which contain oxygenated, stagnant or essentially
stagnant borated water. Metallurgical investigations revealed these cracks
occurred in the weld heat affected zone of 8-inch to 10-inch type 304 material
(schedule 10 and 40), initiating on the piping I.D. surface and propagating
in either an intergranular or transgranular mode typical of Stress Corrosion
Cracking. Analysis indicated the probable corrodents to be chloride and oxygen
contamination in the affected systems. Plants affected up to this time were
Arkansas Nuclear Unit 1, R. E. Ginna, H.B.Robinson Unit 2, Crystal River Unit 3, San Onofre Unit 1, and Surry Units 1 and 2. The NRC issued Circular 76-06 (copy attached) in view of the apparent generic nature of the problem.
During the refueling outage of Three Mile Island Unit 1 which began in February
of this year, visual inspections disclosed five (5) through-wall cracks at welds
in the spent fuel cooling system piping and one 1 at a weld in the decay heat
removal system. These cracks were found as a result of local boric acid build- up and later confirmed by liquid penetrant tests. This initial identification of
cracking was reported to the NRC in a Licensee Event Report (LER) dated May 16,
1979. A preliminary metallurgical analysis was performed by the licensee on a
section of cracked and leaking weld joint from the spent fuel cooling system.
The conclusion of this analysis was that cracking was due to Intergranular Stress
Corrosion Cracking (IGSCC) originating on the pipe I.D. The cracking was
localized to the heat affected zone where the type 304 stainless steel is
sensitized (precipitated carbides) during welding. In addition- to the main
through-wall crack, incipient cracks were observed at several locations in
the weld heat affected zone including the weld root fusion area where a miniscule
lack of fusion had occurred. The stresses responsible for cracking are believed
to be primarily residual welding stresses in as much as the calculated applied
stresses were found to be less than code design limits. There is no conclusive
evidence at this time to identify those aggressive chemical species which
promoted this IGSCC attack. Further analytical efforts in this area and on
other system welds is being pursued.
7907230164
IE Information Notice No. 79-19 July 17, 1979 Based on the above analysis and visual leaks, the licensee initiated a
broad based ultrasonic examination of potentially affected systems utilizing
special techniques. The systems examined included the spent fuel, decay
heat removal, makeup and purification, and reactor building spray systems
which contain stagnant or intermittently stagnant, oxygenated boric acid environ- ments. These systems range from 2 1/2-inch (HPCI) to 24-inch (borated
water storage tank suction), are type 304 stainless steel, schedule 160
to schedule 40 thickness respectively. Results of these examinations were
reported to the NRC on June 30, 1979 as an update to the May 16, 1979 LER.
The ultrasonic inspection as of July 10, 1979 has identified 206 welds out
of 946 inspected having UT indications characteristic of cracking randomly
distributed throughout the aforementioned sizes (24"-14"-12"-10"-8"-2" etc.)
of the above systems. It is important to note that six of the crack indications
were found in 2 1/2-inch diameter pipe of the high pressure injection lines
inside containment. These lines are attached to the main coolant pipe and
are nonisolable from the main coolant system except for check valves. All
of the six cracks were found in two high pressure injection lines containing
stagnated borated water. No cracks were found in the high pressure injection
lines which were occasionally flushed during makeup operations. The ultrasonic
examination is continuing in order to delineate the extent of the problem.
Enclosures:
1. IE Circular 76-06
2. List of Information
Notices Issued in 1979
-- rJ~;
r -at
November 26, 1976 IE Circular No. 76-06 STRESS CORROSION CRACKS IN STAGNANT, LOW PRESSURE STAINLESS
PIPING CONTAINING BORIC ACID SOLUTION AT FWR' 6
DESCRIPTION OF CIRCUMSTANCES
During the period November 7, 1974 to November 1, 1975, several incidents
of through-wall cracking have occurred in the 10-inch, schedule 10 type
304 stainless steel piping of the Reactor Bulldlng Spray and Decay Heat
- Removal Systems at Arkansas Nuclear Plant No. 1.
On October 7, 1976, Virginia Electric and Power also reported through- wall cracking in the 1.0-inch schedule 40 type 304 stainless discharge
piping of the "A" recirculation spray lhcat exchanger at Surry Unit
No. 2. A recent inspection of Unit 1.Containnent Recirculation Spray
Piping revealed cracking similar to Unit 2.
On October 8, 1976, another incident of similar cracking in 8-inch
schedule 10 type 304 stainless piping of the Sefety Injection Pump
Suction Line at the Ginna facilitv was rpnnrrtd hv rh. llrnnA..
Jnfnfiat1nn rorpivoct nn thp tnpt:4ll.fg4rzra l mannlyd4.Q ectrnnAvr- te sto
indicates that the failures were the result of intergranular stress
corrosion cracking that initiated on tie inside of the piping. A
commonality of factors observed associated with the corrosion mechanism
were:
1. flu CLAIV. were adjacent to and propagated along weld zones of tne
thin-walled low pressure piping, not part of .the reactor coolant
system.
2. Cracking occurred in piping containing relatively stagnant boric
acid solution not required for normal operating conditions.
3. Analysis of surface products at this time indicate a chloride ion
interaction with oxide formation in the relatively stagnant boric
acid solution as the probable corrodant, with the state of stress
probably due to welding and/or fabrication.
The source of the chloride ion is not definitely known. However, at
ANO-1 the chlorides and sulfide level observed in the surface tarnish
film near welds is believed to have been introduced into the piping
during testing of the sodium thiosulfate discharge valves, or valve
leakage. Similarly, at Ginna the chlorides and potential oxygen
_ 2 - November 26, 1976 lE Circular No. 76-06 availability were assumed to have been present since original
construction of the borated water storage tank which is vented to
atmosphere. Corrosion attack at Surry is attributed to in-leakage of
chlorides through recirculation spray heat exchange tubing, allowing
buildup of contaminated water in an otherwise normally dry spray piping.
ACTION TO BE TAKEN BY LICENSEE:
1. Provide a description of your program for assuring continued
integrity of those safety-related piping systems which are not
frequently flushed, or which contain nonflowing liquids. This
program should include consideration of hydrostatic testing in
accordance with ASME. Code Section XI rules (1974 Edition) for
all active systems required for safety injection and containment
modsb at. aLut_% %j[ WiLeL
oprOy. X1IcLUU2L1 tI:1LC zcL:+/-LLt;u+/-4L.1or 9 supply up to the second isolation valve of the primary system.
Similar tests should be considered for other safety-related piping
systems.
2. Your program shoutl also consider volumetfic examination of a
representative number of circumferential pipe welds by non- destructive examination techniques. Such examinations should
be performed generally in accordance with Appendix I of
Section XI of the ASME Code, except that the examined area
should cover a distance of approximately six (6) times the
pipe wall thickness (but not less than 2 inches and need not
exceed 8 inches) on each side of the weld. Supplementary
examination techniques, such as radiography, should be used
where necessary for evaluation or confirmation of ultrasonic
indications resulting from such examination.
3. A report describing your program and schedule for these inspec- tions should be submitted within 30 days after receipt of this
Circular.
4. The NRC Regional Office should be informed within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, of any adverse findings resulting during noude!;tructiva
evaluation of the accessible piping welds identified above.
5. A summary report of the examinations and evaluation of results
should be submitted within 60 days from the date of completion
of proposed testing and examinations.
I
- .. .r-'
rs Ad 17
.o
4- ~^70rsb _ * 'l 1lit.-v.ti~r +/-6. +/-976
This summary report should also include a brief description of
plant conditions, operating procedures or other activities
which provide assurance that the effluent chemistry will maintain
low levels of potential corrodants in such relatively stagnant
regions within the piping.
L111 utCt4%$=c
iour responses atnUUa ve tUiUtvt.LLLc LtU LLIW "JLL-:LVL UC
with a copy to the NRC Office of Inspection anad Enforcement, Division
of Reactor Inspection Programs, Washington, D.C. 20555.
Approval of NRC requirements for reports concerning possible generic
problems has been obtained tinder 44 U.S.C 3152 from the U.S. General
Accounting Office. (GAO Approval B-180255 (R0062), expires 7/31/77.)
IE Information Notice No. 79-19 Enclosure
July 17, 1979 LISTING OF IE INFORMATION NOTICES
ISSUED IN 1979 Information Subject Date Issued To
Notice No. Issued
79-01 Bergen-Paterson Hydraulic 2/2/79 All power reactor
Shock and Sway Arrestor facilities with an
OL or a CP
79-02 Attempted Extortion - 2/2/79 All Fuel Facilities
Low Enriched Uranium
79-03 Limitorque Valve Geared 2/9/79 All power reactor
Limit Switch Lubricant facilities with an
OL or a CP
79-04 Degradation of 2/16/79 All power reactor
Engineered facilities with an
Safety Features OL or a CP
79-05 Use of Improper Materials 3/21/79 All power reactor
in Safety-Related Components facilities with an
OL or CP
79-06 Stress Analysis of 3/23/79 All Holders of
Safety-Related Piping Reactor OL or CP
79-07 Rupture of Radwaste Tanks 3/26/79 All power reactor
facilities with an
OL or CP
79-08 Interconnection of 3/28/79 All power reactor
Contaminated Systems with facilities with an
Service Air Systems Used OL and Pu Processing
As the Source of Breathing fuel facilities
Alr
79-09 Spill of Radioactively 3/30/79 All power reactor
Contaminated Resin facilities with an
OL
79-10 Nonconforming Pipe 4/16/79 All power reactor
Support Struts facilities with a
CP
79-11 Lower Reactor Vessel Head 5/7/79 All holders of Reactor
Insulation Support Problem OLs and CPs
He >,,
- ,.
IE Information Notice No. 79-19 Enclosure
July 17, 1979 LISTING OF IE INFORMATION NOTICES
ISSUED IN 1979 Information Subject Date Issued To
Notice No. Issued
79-12 Attempted Damage to New 5/11/79 All Fuel Facilities
Fuel Assemblies Research Reactors, and Power Reactors
with an OL or CP
79-13 Indication of Low Water 5/29/79 All Holders of Reactor
Level in the Oyster Creek OLs and CPs
Reactor
79-14 NRC Position of Electrical 6/11/79 All Power Reactor
Cable Support Systems Facilities with a
CP
79-15 Deficient Procedures 6/7/79 All Holders of Reactor
OLs and CPs
79-16 Nuclear Incident at Three 6/22/79 All Research Reactors
Mile Island and Test Reactors
with OLs
79-17 Source Holder Assembly Damage 6/20/79 All Holders of Reactor
Damage From Misfit Between OLs and CPs
Assembly and Reactor Upper
Grid Plate
79-18 Skylab Reentry 7/5/79 All Holders of Reactor
OLs
|
---|
|
list | - Information Notice 1979-01, Bergen-Paterson Hydraulic Shock & Sway Arrestors (Hssa) (2 February 1979)
- Information Notice 1979-01, Bergen-Paterson Hydraulic Shock & Sway Arrestors (HSSA) (2 February 1979)
- Information Notice 1979-03, Limitorque Valve Geared Limit Switch Lubricant (9 February 1979)
- Information Notice 1979-04, Degradation of Engineered Safety Features (16 February 1979)
- Information Notice 1979-05, Use of Improper Materials in Safety-Related Components (21 March 1979)
- Information Notice 1979-06, Stress Analysis of Safety-Related Piping (23 March 1979, Topic: Earthquake)
- Information Notice 1979-07, Rupture of Radwaste Tanks (26 March 1979)
- Information Notice 1979-08, Interconnection of Contaminated Systems with Service Air Systems Used as Source of Breathing Air (28 March 1979)
- Information Notice 1979-08, Interconnection of Contaminated Systems With Service Air Systems Used As Source of Breathing Air (28 March 1979)
- Information Notice 1979-09, Spill of Radioactively Contaminated Resin (30 March 1979, Topic: Hydrostatic)
- Information Notice 1979-19, Pipe Cracks in Stagnant Borated Water Systems at PWR Plants (17 July 1979, Topic: Boric Acid, Hydrostatic, Liquid penetrant)
- Information Notice 1979-20, NRC Enforcement Policy - NRC Licensed Individuals (7 September 1979)
- Information Notice 1979-21, Transportation & Commercial Burial of Radioactive Material (7 September 1979)
- Information Notice 1979-22, Qualification of Control Systems (14 September 1979)
- Information Notice 1979-24, Overpressurization of Containment of a PWR Plant After a Main Steam Line Break (1 October 1979)
- Information Notice 1979-25, Reactor Trips at Turkey Point Units 3 & 4 (1 October 1979)
- Information Notice 1979-26, Breach of Containment Integrity (5 November 1979)
- Information Notice 1979-28, Overloading of Structural Elements Due to Pipe Support Loads (16 November 1979)
- Information Notice 1979-29, Loss of Nonsafety-Related Reactor Coolant System Instrumentation During Operation (16 November 1979)
- Information Notice 1979-30, Reporting of Defects & Noncompliances, 10 CFR Part 21 (6 December 1979)
- Information Notice 1979-31, Use of Incorrect Amplified Response Spectra (13 December 1979)
- Information Notice 1979-32, Separation of Electrical Cables for HPCI and ADS (21 December 1979, Topic: Fire Watch)
- Information Notice 1979-33, Improper Closure of Primary Containment Equipment Access Matches (21 December 1979)
- Information Notice 1979-34, Inadequate Design of Safety-Related Heat Exchangers (27 December 1979)
- Information Notice 1979-35, Control of Maintenance & Essential Equipment (31 December 1979)
- Information Notice 1979-36, Computer Code Defect in Stress Analysis of Piping Elbow (31 December 1979)
- Information Notice 1979-37, Cracking in Low Pressure Turbine Discs (28 December 1979, Topic: Turbine Missile)
|
---|