Annual Assessment Letter for Callaway Plant (Report 05000483/2025006)
ML26064A041
Person / Time
Site: Callaway 
(NPF-030)
Issue date: 03/11/2026
From: Ami Agrawal
NRC/RGN-IV/DORS/PBB
To: Karenina Scott
Union Electric Co
Bloodgood M
Shared Package
IR 2025006 List:
References
IR 2025006
Download: ML26064A041 (0)


Text

March 11, 2026

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2025006)

Dear Kent Scott:

The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Callaway Plant, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2025, through December 31, 2025. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was partially completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program -

Operations Phase due to the impact on federal government operations because of the federal government shutdown from October 1, 2025, to November 12, 2025, during which only excepted activities were performed.

The NRC determined the performance at Callaway Plant, during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2027.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Please contact me at 817-200-1411 with any questions you have regarding this letter.

Sincerely, Ami N. Agrawal, Chief Reactor Projects Branch B Division of Operating Reactor Safety Docket No. 05000483 License No. NPF-30 Enclosure:

Inspection Plan cc w/ encl: via GovDelivery Subscriber Signed by Agrawal, Ami on 03/11/26

ML26064A041 SUNSI Review By: MRB Publicly Available and Non-Sensitive Non-Publicly Available and Sensitive OFFICE SPE:DORS:PBB BC:DORS:PBB NAME MBloodgood AAgrawal SIGNATURE

/RA/

/RA/

DATE 03/09/26 03/11/26

Site Inspection Activity Plan Callaway 01/01/2026 - 12/31/2027 Unit Start End Activity CAC Title Staff Count EP Program & PI Inspection (2026) - CWY

1 4/20/2026 4/24/2026 IP 71114.02 000717 Alert and Notification System Testing

4/20/2026 4/24/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System

4/20/2026 4/24/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes

4/20/2026 4/24/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness Age-Related Degradation Inspection - Callaway

1 6/8/2026 6/12/2026 IP 71111.21N.04 001832 Age-Related Degradation

6/22/2026 6/26/2026 IP 71111.21N.04 001832 Age-Related Degradation CWY 2026 INITIAL EXAM

1 5/31/2026 6/6/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

7/5/2026 7/11/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Security 71130.02/.07/.08

1 8/17/2026 8/20/2026 IP 71130.02 000734 Access Control

8/17/2026 8/20/2026 IP 71130.07 000739 Security Training

8/17/2026 8/20/2026 IP 71130.08 000740 Fitness-For-Duty Program

8/17/2026 8/20/2026 IP 71130.09 001656 Security Plan Changes RP 1,3,PI - CW

1 10/5/2026 10/9/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

10/5/2026 10/9/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

10/5/2026 10/9/2026 IP 71151 000746 Performance Indicator Verification Inservice Inspection - CWY

1 10/12/2026 10/23/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Security 71130.01/.02/.04

1 2/8/2027 2/12/2027 IP 71130.01 000733 Access Authorization

2/8/2027 2/12/2027 IP 71130.02 000734 Access Control

2/8/2027 2/12/2027 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance

2/8/2027 2/12/2027 IP 71130.09 001656 Security Plan Changes

2/8/2027 2/12/2027 IP 71151 001338 Performance Indicator Verification Cybersecurity-CWY

1 3/1/2027 3/5/2027 IP 71130.10 000741 Cybersecurity MC&A - CW

1 3/8/2027 3/12/2027 IP 71130.11 000742 Material Control and Accounting (MC&A)

Comprehensive Engineering Team Inspection - CWY

Prepared on 3/2/2026 3:40:46 PM 1 of 3

Site Inspection Activity Plan

3/29/2027 4/2/2027 IP 71111.21M 000713 Comprehensive Engineering Team Inspection

4/12/2027 4/16/2027 IP 71111.21M 000713 Comprehensive Engineering Team Inspection FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - CWY

1 4/19/2027 4/23/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing

5/17/2027 5/21/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing RP 1,4,PI - CW

1 5/17/2027 5/21/2027 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

5/17/2027 5/21/2027 IP 71124.04 000728 Occupational Dose Assessment

5/17/2027 5/21/2027 IP 71151 000746 Performance Indicator Verification CWY 2027 BRQ

1 6/20/2027 6/26/2027 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance EP Exercise & PI Inspection (2027) - CWY

1 9/20/2027 9/24/2027 IP 71114.01 000716 Exercise Evaluation

9/20/2027 9/24/2027 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes

9/20/2027 9/24/2027 IP 71151 001397 Performance Indicator Verification RP 5,8 - CW

1 11/15/2027 11/19/2027 IP 71124.05 000729 Radiation Monitoring Instrumentation

11/15/2027 11/19/2027 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Prepared on 3/2/2026 3:40:46 PM 2 of 3

Site Inspection Activity Plan Callaway Nuclear Plant 01/01/2026 - 12/31/2027 Unit Start End Activity CAC Title Staff Count Callaway ISFSI Loading and Triennial Inspection (one week during campaign, date TBD)

4/1/2027 5/30/2027 IP 60855 001001 Operation of an Independent Spent Fuel Storage Installation Prepared on 3/2/2026 3:40:46 PM 3 of 3