December 11, 2025
SUBJECT:
CALLAWAY PLANT - SECURITY BASELINE INSPECTION REPORT 05000483/2025401
Dear Kent Scott:
On December 03, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Callaway Plant and discussed the results of this inspection with Sarah Kovaleski, Senior Director, Nuclear Plant Support, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Christopher A. Jewett, Acting Chief Physical Security Branch Division of Radiological Safety & Security Docket No. 05000483 License No. NPF-30
Enclosure:
As stated
Inspection Report
Docket Number:
05000483
License Number:
Report Number:
Enterprise Identifier:
I-2025-401-0002
Licensee:
Union Electric Company
Facility:
Callaway Plant
Location:
Steedman, MO 65077
Inspection Dates:
December 01, 2025, to December 03, 2025
Inspectors:
D. Holman, Sr Physical Security Inspector
Approved By:
Christopher A. Jewett, Acting Chief
Physical Security Branch
Division of Radiological Safety & Security
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Callaway Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.02 - Access Control
The inspector evaluated the access control program through completion of the following inspection elements:
Access Control (1 Sample)
(1)
- Tier I: 13 Requirements (02.01a-c,e; 02-02c-f; 02.03a, 02.04a,b,e; 02.05a)
- Tier II: 5 Requirements (02.06a,c; 02.08a,b,i)
- Tier III: 1 Requirement (02.09)
71130.09 - Security Plan Changes
The inspector evaluated the security plan changes through completion of the following procedure elements:
Security Plan Changes (1 Sample)
- (1) Since the last NRC baseline inspection of this program area, Security Plan Revision 13 to 14 was implemented. Based on the Ameren evaluation, and in accordance with 10 CFR 50.54(p)(2), the changes resulted in no decrease in safeguards effectiveness of the security plan and the revised security plan changes continue to meet the requirements of 10 CFR 73.55(b). The inspector conducted a review of the security plan changes to evaluate for a potential decrease in safeguards effectiveness of the security plan; however, this review does not constitute formal NRC approval of those changes. Therefore, the changes remain subject to future NRC inspection in their entirety.
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification The inspector verified licensee performance indicator submittals listed below:
PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17) (1 Sample)
- (1) January 1, 2025, through November 28, 2025.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspector verified no proprietary information was retained or documented in this report.
- On December 3, 2025, the inspector presented the security baseline inspection results to Sarah Kovaleski, Senior Director, Nuclear Plant Support, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective
Action
Documents
25502391;
2501931;
2502531;
2502065;
2501596
Condition Report
Miscellaneous
Email From:
Benjamin
French To:
Doreen
Douglas
Subject: Evaluate inspecting
Mortise locksets
05/01/2025
APA-ZZ-
01106
Lock and Key Control
Revision
030
SDP-PI-
MAFST
MAF Search Train
Revision
036
SDP-PI-
STORE
Storeroom Officer
Revision
030
Procedures
SDP-PI-
VEHAC
Vehicle Access/Control
Revision
057
Miscellaneous
Physical
Security Plan
Callaway Plant Unit 1
Revisions
and 14