Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2025006)
ML26064A037
Person / Time
Site: Cooper 
(DPR-046)
Issue date: 03/11/2026
From: Patricia Vossmar
NRC/RGN-IV/DORS
To: Dia K
Nebraska Public Power District (NPPD)
Shared Package
IR 2025006 List:
References
IR 2025006
Download: ML26064A037 (0)


Text

March 11, 2026

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR COOPER NUCLEAR STATION (REPORT 05000298/2025006)

Dear Khalil Dia:

The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Cooper Nuclear Station, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2025, through December 31, 2025. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was partially completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase due to the impact on federal government operations because of the federal government shutdown from October 1, 2025, to November 12, 2025, during which only excepted activities were performed.

The NRC determined the performance at Cooper Nuclear Station during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2027.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. The NRC also plans to implement one non-routine inspection to follow-up on NOV 05000298/2023012-01, Failure to Notify the NRC of Reactor Operators Disqualifying Conditions within 30 Days, and any related issues using inspection procedure IP 92702, Follow-Up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, and Orders. The NRC will contact you at a later time to schedule this inspection.

The Regional Administrator has approved implementation of this inspection procedure.

This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Please contact me at (817) 200-1148 with any questions you have regarding this letter.

Sincerely, Douglas E. Dodson II, Chief Reactor Projects Branch C Division of Operating Reactor Safety Docket No. 05000298 License No. DPR-46 Enclosure:

Inspection Plan cc w/ encl: Distribution via GovDelivery Subscriber Signed by Dodson, Douglas on 03/11/26

ML26064A037 SUNSI Review By: DED Non-Sensitive and Publicly Available Sensitive and Non-Publicly Available OFFICE SPE:DORS/PBC BC:DORS/PBC NAME RKumana DDodson SIGNATURE

/RA/

/RA/

DATE 03/05/26 03/11/26

Site Inspection Activity Plan Cooper 01/01/2026 - 12/31/2027 Unit Start End Activity CAC Title Staff Count FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - CNS

1 3/30/2026 4/3/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing

4/20/2026 4/24/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing EP Exercise & PI Inspection (2026) - CNS

1 5/11/2026 5/15/2026 IP 71114.01 000716 Exercise Evaluation

5/11/2026 5/15/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes CNS 2026 INITIAL EXAM

1 4/26/2026 5/2/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

6/7/2026 6/13/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Security 71130.01/.02/.04

1 7/6/2026 7/9/2026 IP 71130.01 000733 Access Authorization

7/6/2026 7/9/2026 IP 71130.02 000734 Access Control

7/6/2026 7/9/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance

7/6/2026 7/9/2026 IP 71130.09 001656 Security Plan Changes

7/6/2026 7/9/2026 IP 71151 001338 Performance Indicator Verification Fire Protection Inspection - CNS

1 8/3/2026 8/21/2026 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

Inservice Inspection - CNS

1 10/5/2026 10/9/2026 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

RP 1,3,PI - CNS

1 10/5/2026 10/9/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

10/5/2026 10/9/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

10/5/2026 10/9/2026 IP 71151 000746 Performance Indicator Verification Focused Engineering Inspection 1 - CNS

1 1/25/2027 1/29/2027 IP 71111.21N 000714 Focused Engineering Inspections (FEI Placeholder)

2/8/2027 2/12/2027 IP 71111.21N 000714 Focused Engineering Inspections (FEI Placeholder)

2027 Problem Identification and Resolution Inspection - Cooper

1 4/5/2027 4/9/2027 IP 71152B 000747 Problem Identification and Resolution

4/19/2027 4/23/2027 IP 71152B 000747 Problem Identification and Resolution EP Program & PI Inspection (2027) - CNS

1 5/3/2027 5/7/2027 IP 71114.02 000717 Alert and Notification System Testing

5/3/2027 5/7/2027 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System

5/3/2027 5/7/2027 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Prepared on 3/2/2026 11:43:21 AM 1 of 2

Site Inspection Activity Plan

5/3/2027 5/7/2027 IP 71114.05 000720 Maintenance of Emergency Preparedness

5/3/2027 5/7/2027 IP 71151 001397 Performance Indicator Verification CNS 2027 INITIAL EXAM

1 4/25/2027 5/1/2027 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

6/6/2027 6/12/2027 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

RP 5,8 - CNS

1 6/21/2027 6/25/2027 IP 71124.05 000729 Radiation Monitoring Instrumentation

6/21/2027 6/25/2027 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Security 71130.02/.05

1 7/19/2027 7/23/2027 IP 71130.02 000734 Access Control

7/19/2027 7/23/2027 IP 71130.05 000737 Protective Strategy Evaluation

7/19/2027 7/23/2027 IP 71130.09 001656 Security Plan Changes

7/19/2027 7/23/2027 IP 71130.14 000743 Review of Power Reactor Target Sets

7/19/2027 7/23/2027 IP 71151 001338 Performance Indicator Verification CNS 2027 BRQ

1 10/3/2027 10/9/2027 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP 1,4,PI - CNS

1 11/1/2027 11/5/2027 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

11/1/2027 11/5/2027 IP 71124.04 000728 Occupational Dose Assessment

11/1/2027 11/5/2027 IP 71151 000746 Performance Indicator Verification Prepared on 3/2/2026 11:43:21 AM 2 of 2