|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217K1051999-10-19019 October 1999 Ack Receipt of Ltr Dtd 990707,which Transmitted Rev 29 to Callaway Plant Physical Security Plan,Under Provisions of 10CFR50.54(p).Based on Determination That Changes Do Not Decrease Effectiveness of Plan,No NRC Approval Required ML20217G2071999-10-14014 October 1999 Forwards Insp Rept 50-483/99-10 on 990913-16.No Violations Noted.Insp Was to Review Emergency Plan & Procedures During Biennial Emergency Preparedness Exercise ML20217B5901999-10-0505 October 1999 Informs That Staff Concludes That Licensee Responses to GL 97-06 Provides Reasonable Assurance That Condition of Util SG Internals in Compliance with Current Licensing Bases for Callaway Plant,Unit 1 ML20217B5711999-10-0505 October 1999 Discusses GL 98-01 Issued by NRC on 980511 & Uec Responses for Callaway NPP Unit 1 ,990224 & 990628.Informs That Staff Reviewed Responses & Concluded That All Requested Info for GL 98-01 Provided ML20212G0221999-09-22022 September 1999 Forwards Insp Rept 50-483/99-11 on 990812-20.No Violations Noted.Team Found,Weakness in flow-accelerated Corrosion Monitoring Program Resulted in No Previous Insp of Pipe Segment Which Failed ML20212D9341999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of Callaway Plant.In Area of Ep,C/As Taken in Response to Problems Identified During Previous Exercises Warrant More in-dept Review.Details of Insp Plan Through March 2000 Encl ML20217D5791999-09-15015 September 1999 Provides Formal Documentation of Reviews & Discussions Re Technical Ltr Rept for Proprietary Info.Review of Ltr Was Discussed in Telcon & Via e-mail Messages. Summary of Telcons as Documented on 990708,included ML20212A4921999-09-13013 September 1999 Forwards Insp Rept 50-483/99-08 on 990725-0904.Two Severity Level IV Violations of NRC Requirements Identified & Being Treated as Noncited Violations Consistent with App C of Enforcement Policy ML20212A4701999-09-10010 September 1999 Rssponds to NRC 990709 RAI Re Util Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection Iwe. Acceptance Criteria for Liner Plate Pressure Boundary Thickness Will Be Limited to 10% Nominal Thinning ML20212B1521999-09-10010 September 1999 Forwards Insp Rept 50-483/99-07 on 990809-13.No Violations Noted.Inspectors Used Annual Licensed Operator Requalification Exams to Assess Licensed Operator Performance ML20211N0321999-09-0202 September 1999 Forwards SE Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20211B0241999-08-18018 August 1999 Ack Receipt of Ltr Dtd 990714,transmitting Scenario for Licensee Upcoming Biennial Exercise.Based on Review,Nrc Determined That Exercise Scenario Sufficient to Meet Emergency Plan Requirements & Exercise Objectives ML20210T9121999-08-13013 August 1999 Forwards Insp Rept 50-483/99-06 on 990613-0724.One Severity Level 4 Violation Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy ML20210R7241999-08-12012 August 1999 Forwards semi-annual Fitness for Duty Program Performance Data Rept for Callaway Nuclear Plant for 990101-990630,IAW 10CFR26.71(d) ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ULNRC-04085, Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power1999-08-11011 August 1999 Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power ML20210P0371999-08-10010 August 1999 Forwards SE Granting Licensee 980710 Requests for Relief (ISI-13 - ISI-18) from Requirements of Section XI of 1989 Edition of ASME B&PV Code for Second 10-year Interval ISI at Plant,Unit 1 ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ULNRC-04079, Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal1999-08-0202 August 1999 Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal ML20210H6381999-07-30030 July 1999 Forwards SE Accepting Relief Request for Approval for Use of Alternate Exam Requirement for Plant Inservice Insp Program A93443, Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves1999-07-28028 July 1999 Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves ULNRC-04075, Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves1999-07-28028 July 1999 Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves ULNRC-04076, Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs1999-07-28028 July 1999 Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs ULNRC-04070, Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power1999-07-27027 July 1999 Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power 05000483/LER-1998-008, Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved1999-07-27027 July 1999 Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved ULNRC-04071, Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-021999-07-27027 July 1999 Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-02 ML20210B5611999-07-20020 July 1999 Forwards Review of Ltr & Encl Objectives for Plant,Unit 1,1999 Emergency Plan Exercise Scheduled for 990914 ML20210B4021999-07-19019 July 1999 Ack Receipt of Facility Emergency Plan Implementing Procedure EIP-ZZ-00101, Classification of Emergencies, Rev 23,issued on 990513,under Provisions of 10CFR50,App E, Section V ML20210B4401999-07-19019 July 1999 Ack Receipt of Revs to Facility Radiological Emergency Response Plan,Chapters 8.0 & 4.0,issued Respectively on 990512-14,under Provisions of 10CFR50,App E,Section V ML20212A3291999-07-15015 July 1999 Forwards Scenario Manual Containing Description of Callaway Plant 1999 Biennial Emergency Response Plan Exercise to Be Conducted 990914.Correspondence to Satisfy 60-day Submittal Requirement ML20209F3471999-07-0909 July 1999 Forwards Response to NRC 990624 RAI to Complete NRC Review of Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection IWE ML20209E5591999-07-0808 July 1999 Informs That as Result of NRC Review of Util Responses to GL 92-01,rev 1,suppl 1 & Suppl 1 Rai,Staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2.TAC MA0531 Closed ML20209H2471999-07-0707 July 1999 Forwards Rev 29 to Physical Security Plan,Per 10CFR50.54(p). Rev Withheld,Per 10CFR73.21 ML20196J9501999-07-0202 July 1999 Ack Receipt of Plant Ep,Rev 22,received on 981207 & Submitted Under Provision of 10CFR50,App E,Section V.Changes Does Not Decrease Effectiveness of EP & Continues to Meet Stds of 10CFR50.47(b).NRC Approval Not Required ML20209B6851999-06-28028 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness of Computer Systems at Nuclear Power Plants. Disclosure Rept Encl ML20209C0171999-06-28028 June 1999 Forwards Special Rept 99-01 Re Fifteenth Year Inservice Containment Bldg Tendon Surveillance Failure.Observed Voids in Sheathing Filler Grease Do Not Indicate Degradation of post-tensioning Sys,Based on Encl Evaluation ML20196F8101999-06-25025 June 1999 Informs That J Donohew Will Assume Project Manager Responsibilities,Effective 990621 ML20196H2521999-06-25025 June 1999 Forwards Insp Rept 50-483/99-05 on 990502-0612.Two Violations Occurred & Being Treated as Noncited Violations, Consistent with App C of Enforcement Policy ML20196F8181999-06-24024 June 1999 Forwards RAI Re 990111 Request for Relief from Certain ASME Code ISI Requirements for Containment Liners.Response Requested within 30 Days from Date of Agreement ML20196G5621999-06-21021 June 1999 Informs NRC of Implementation of Amend 132 to Callaway License NPF-30 to Allows Installation of Electrosleeves for Steam Generator Tube Repair for Two Cycles Following Installation of First Electrosleeve IR 05000483/19990041999-06-18018 June 1999 Refers to GL 96-05 Issued by NRC on 960918,UE Responses & 970313 & NRC Insp Rept 50-483/99-04,dtd 990427. Forwards Request for Addl Info Re GL 96-05 Program at Callaway Plant,Unit 1 ML20212J2441999-06-18018 June 1999 Submits Request for Alternate Exam Requirements for Plant Re ISI Program Plan.Plant Does Not Torque Bolted Connections to Stress Values Greater than 100 Ksi ML20195H0971999-06-14014 June 1999 Discusses Une 990407 Request That Proprietary Document Entitled, Thermal Stability Assessment - Electrosleeved Tubes, Be Withheld from Public Disclosure.Determined Info to Be Proprietary & Will Be Withheld from Public Disclosure ML20207H3751999-06-14014 June 1999 Discusses 990407 Une Request That Proprietary Version of Document Entitled, Evaluation of Severe Accident Simulation, Dtd April 1999,be Withheld from Public Disclosure.Determined Info Proprietary & Will Be Withheld ML20195H9731999-06-11011 June 1999 Forwards Requested Addl Info Related to Relief Request ISI-16,encountered During Refuel 9 ML20195J9301999-06-0808 June 1999 Informs That Refuel 9 OAR-1 Owners Data Rept for ISI & Summary Rept for Interval 2 Was Submitted with Typographical Error,In That Commercial Service Date Should Be 841219,vice 941219.Please Substitute Encl Corrected Document ML20207G3201999-06-0707 June 1999 Ack Receipt of Change Notice 98-008 Dtd 980918,which Transmitted Changes to Callaway Plant Ep,Rev 21,under Provisions of 10CFR50,App E,Section V.No NRC Approval Required.No Violations Identified ML20207G3151999-06-0707 June 1999 Ack Receipt of Callaway Plant EP Implementing Procedure EIP-ZZ-001001M,Classification of Emergencies,Rev 22,issued on 981222 Under 10CFR50,App E,Section V Provisions.No Violations Identified ML20195C5131999-05-28028 May 1999 Forwards Revs to Sections 3.9 & 5.6 of Its,Based on Resolution Telcons Held Between NRC Staff & Util on 990526 & 27 A98803, Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS1999-05-27027 May 1999 Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS 1999-09-22
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217K1051999-10-19019 October 1999 Ack Receipt of Ltr Dtd 990707,which Transmitted Rev 29 to Callaway Plant Physical Security Plan,Under Provisions of 10CFR50.54(p).Based on Determination That Changes Do Not Decrease Effectiveness of Plan,No NRC Approval Required ML20217G2071999-10-14014 October 1999 Forwards Insp Rept 50-483/99-10 on 990913-16.No Violations Noted.Insp Was to Review Emergency Plan & Procedures During Biennial Emergency Preparedness Exercise ML20217B5901999-10-0505 October 1999 Informs That Staff Concludes That Licensee Responses to GL 97-06 Provides Reasonable Assurance That Condition of Util SG Internals in Compliance with Current Licensing Bases for Callaway Plant,Unit 1 ML20217B5711999-10-0505 October 1999 Discusses GL 98-01 Issued by NRC on 980511 & Uec Responses for Callaway NPP Unit 1 ,990224 & 990628.Informs That Staff Reviewed Responses & Concluded That All Requested Info for GL 98-01 Provided ML20212G0221999-09-22022 September 1999 Forwards Insp Rept 50-483/99-11 on 990812-20.No Violations Noted.Team Found,Weakness in flow-accelerated Corrosion Monitoring Program Resulted in No Previous Insp of Pipe Segment Which Failed ML20212D9341999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of Callaway Plant.In Area of Ep,C/As Taken in Response to Problems Identified During Previous Exercises Warrant More in-dept Review.Details of Insp Plan Through March 2000 Encl ML20212A4921999-09-13013 September 1999 Forwards Insp Rept 50-483/99-08 on 990725-0904.Two Severity Level IV Violations of NRC Requirements Identified & Being Treated as Noncited Violations Consistent with App C of Enforcement Policy ML20212B1521999-09-10010 September 1999 Forwards Insp Rept 50-483/99-07 on 990809-13.No Violations Noted.Inspectors Used Annual Licensed Operator Requalification Exams to Assess Licensed Operator Performance ML20211N0321999-09-0202 September 1999 Forwards SE Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20211B0241999-08-18018 August 1999 Ack Receipt of Ltr Dtd 990714,transmitting Scenario for Licensee Upcoming Biennial Exercise.Based on Review,Nrc Determined That Exercise Scenario Sufficient to Meet Emergency Plan Requirements & Exercise Objectives ML20210T9121999-08-13013 August 1999 Forwards Insp Rept 50-483/99-06 on 990613-0724.One Severity Level 4 Violation Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210P0371999-08-10010 August 1999 Forwards SE Granting Licensee 980710 Requests for Relief (ISI-13 - ISI-18) from Requirements of Section XI of 1989 Edition of ASME B&PV Code for Second 10-year Interval ISI at Plant,Unit 1 ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML20210H6381999-07-30030 July 1999 Forwards SE Accepting Relief Request for Approval for Use of Alternate Exam Requirement for Plant Inservice Insp Program ML20210B5611999-07-20020 July 1999 Forwards Review of Ltr & Encl Objectives for Plant,Unit 1,1999 Emergency Plan Exercise Scheduled for 990914 ML20210B4401999-07-19019 July 1999 Ack Receipt of Revs to Facility Radiological Emergency Response Plan,Chapters 8.0 & 4.0,issued Respectively on 990512-14,under Provisions of 10CFR50,App E,Section V ML20210B4021999-07-19019 July 1999 Ack Receipt of Facility Emergency Plan Implementing Procedure EIP-ZZ-00101, Classification of Emergencies, Rev 23,issued on 990513,under Provisions of 10CFR50,App E, Section V ML20209E5591999-07-0808 July 1999 Informs That as Result of NRC Review of Util Responses to GL 92-01,rev 1,suppl 1 & Suppl 1 Rai,Staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2.TAC MA0531 Closed ML20196J9501999-07-0202 July 1999 Ack Receipt of Plant Ep,Rev 22,received on 981207 & Submitted Under Provision of 10CFR50,App E,Section V.Changes Does Not Decrease Effectiveness of EP & Continues to Meet Stds of 10CFR50.47(b).NRC Approval Not Required ML20196F8101999-06-25025 June 1999 Informs That J Donohew Will Assume Project Manager Responsibilities,Effective 990621 ML20196H2521999-06-25025 June 1999 Forwards Insp Rept 50-483/99-05 on 990502-0612.Two Violations Occurred & Being Treated as Noncited Violations, Consistent with App C of Enforcement Policy ML20196F8181999-06-24024 June 1999 Forwards RAI Re 990111 Request for Relief from Certain ASME Code ISI Requirements for Containment Liners.Response Requested within 30 Days from Date of Agreement IR 05000483/19990041999-06-18018 June 1999 Refers to GL 96-05 Issued by NRC on 960918,UE Responses & 970313 & NRC Insp Rept 50-483/99-04,dtd 990427. Forwards Request for Addl Info Re GL 96-05 Program at Callaway Plant,Unit 1 ML20207H3751999-06-14014 June 1999 Discusses 990407 Une Request That Proprietary Version of Document Entitled, Evaluation of Severe Accident Simulation, Dtd April 1999,be Withheld from Public Disclosure.Determined Info Proprietary & Will Be Withheld ML20195H0971999-06-14014 June 1999 Discusses Une 990407 Request That Proprietary Document Entitled, Thermal Stability Assessment - Electrosleeved Tubes, Be Withheld from Public Disclosure.Determined Info to Be Proprietary & Will Be Withheld from Public Disclosure ML20207G3151999-06-0707 June 1999 Ack Receipt of Callaway Plant EP Implementing Procedure EIP-ZZ-001001M,Classification of Emergencies,Rev 22,issued on 981222 Under 10CFR50,App E,Section V Provisions.No Violations Identified ML20207G3201999-06-0707 June 1999 Ack Receipt of Change Notice 98-008 Dtd 980918,which Transmitted Changes to Callaway Plant Ep,Rev 21,under Provisions of 10CFR50,App E,Section V.No NRC Approval Required.No Violations Identified ML20207E2711999-05-25025 May 1999 Ack Receipt of in Response to & Insp Rept Confirming Commitment as Stated by M Taylor During Telephonic Exit Meeting on 990413 ML20207A8711999-05-24024 May 1999 Informs That NRR Reorganized,Effective 990328.Forwards Organization Chart ML20207A4131999-05-19019 May 1999 Forwards Insp Rept 50-483/99-03 on 990321-0501.One Violation of NRC Requirements Identified & Being Treated as Noncited Violation,Consistent with App C of Enforcement Policy ML20206K6511999-05-10010 May 1999 Forwards RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions ML20206N3981999-05-10010 May 1999 Responds to Comments & Questions Submitted to NRC Staff Re Recent License Amend Issued by NRC to Callaway Unit 1 License.Provides Context for Conclusion That Reracking of Callaway SFP Maintains Adequate Protection of Public Safety ML20206H1101999-05-0606 May 1999 Forwards Results of Gfes of Written Operator Licensing Exam, Administered on 990407,to Nominated Employees of Facility. Requests That Training Dept Forward Individual Answer Sheets & Results to Appropriate Individuals.Without Encl ML20206H1821999-05-0606 May 1999 Forwards RAI Re Licensee Request for Relief from Certain ASME Code ISI Requirements Submitted by .Response Requested within 30 Days of Receipt of Ltr ML20206F4931999-05-0303 May 1999 Forwards Exam Rept 50-483/99-302 on 990416.Insp Included Evaluation of Applicant for Reactor Operator License ML20205S2571999-04-19019 April 1999 Discusses Plans to Sponsor Testing of Electrosleeved Tubes to Better Understand Behavior of Electrosleeve Matl Under Severe Accident Conditions ML20205Q5461999-04-19019 April 1999 Forwards Safety Evaluation Relief Request from Certain ASME Section XI Requirements for Concrete Containment ISI for Plant ISI Program ML20205K7641999-04-0808 April 1999 Ack Receipt of Re Comments & Questions Concerning Recent Amend to Plant,Unit 1.Response to Comments & Questions Should Be Completed by mid-May ML20205J8701999-04-0606 April 1999 Ack Receipt of ,In Response to NRC Insp Rept 50-483/99-02,dtd 990225 Re Verbal Commitment Made During Exit Meeting for Insp.Understands Next Rev of Security Plan Will Include Increased Min Staffing of Three Armed Guards ML20205J8721999-04-0505 April 1999 Refers to Meeting Conducted in Emergency Operations Facility at Callaway Plant on 990401 Re Plant Performance Review for Plant Completed on 990211.Year 2000 Readiness Issues & New Reactor Licensee Performance Assessment Also Discussed ML20205J9401999-04-0505 April 1999 Forwards Insp Rept 50-483/99-01 on 990207-0330.One Violation Occurred & Being Treated as Noncited Violation,Consistent with App C of Enforcement Policy IR 05000019/20250011999-04-0202 April 1999 Informs That Version of Topical Rept BAW-10219P,Rev 3 Dtd Oct 1998 & Document 51-5001925-01,dtd 980828 Will Be Marked as Proprietary & Be Withheld from Public Disclosure Pursuant to 10CFR2.790(b)(5) & Section 103(b) of Atomic Energy Act ML20205A3821999-03-19019 March 1999 Advises of NRC Planned Insp Effort Resulting from Callaway Plant Performance Review for Period 970510-990125. Historical Listing of Plant Issues & Details of NRC Insp Plan for Next 8 Months Encl ML20204E7281999-03-18018 March 1999 Ack Receipt of Which Transmitted Rev 28 to Callaway Plant Physical Security Plan,Per 10CFR50.54(p).No NRC Approval Is Required,Since Util Determined Changes Do Not Decrease Effectiveness of Plan ML20204E3671999-03-18018 March 1999 Informs That During 990128 Telcon Between D Lantz & H Bundy, Arrangements Were Made for Administration of Retake Written Operator Licensing Exam at Plant,During Wk of 990419 ML20204B7091999-03-15015 March 1999 Informs That Changes Described in ,Submitting Rev 20 to Plant Operational QA Manual,Appear Consistent with Guidelines for non-reduction in Committments ML20204C4241999-03-15015 March 1999 Forwards Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20207F4731999-03-0404 March 1999 Discusses 990302 Public Meeting Re Program Updates & Organizational Changes in Emergency Preparedness & Security. List of Attendees & Licensee Presentation Encl ML20207L6491999-03-0404 March 1999 Informs That Util 990111 Response to Request for Addl Info Re Question 4 Will Be Marked as Proprietary & Will Be Withheld from Public Disclosure Pursuant to 10CFR2.709(b)(5) & Section 103(b) of Atomic Energy Act of 1954,as Amended 1999-09-22
[Table view] |
Text
.
<
@ Recut UNIT ED STATES
'
., t NUCLEAR REGULATORY COMMISSION-g o g ;
g REGION IV
% 611 RYAN PLAZA DRIVE. SulTE 400 AR LINGTON, TEXAS 76011-8064
+9*****+0[
-
April 8,1998 EA 97-469 Garry L. Randolph, Vice President and Chief Nuclear Officer Union Electric Company
,
P.O. Box 620 Fulton, Missouri 65251 SUBJECT: RESPONSE TO NRC INSPECTION REPORT 50-483/97-11 AND NOTICE OF VIOLATION
Dear Mr. Randolph:
Thank you for your letter of February 6,1998, in response to our December 24,1997, letter and i Notice of Violation conceming the findings of the Maintenance Rule baseline inspection at the Callaway Plant. We have reviewed your reply, and require additional information for each of the three violations.
Violation A ,
,
I In regard to your response to Example 1, additional information regarding the planned change to !
the performance criteria for the containment isolation function is needed in order to evaluate the effectiveness of the corrective actions. Specifically, we request that you provide the definition of
" failure" which is referred to in item 2 of the planned changes to the performance criteria on page 5 of your response. As presently stated, simultaneous failures of both valves in a penetration could be interpreted to mean: both valves of a penetration exceeding their individual-administrative leakage limits; both valves, as well as, eight other valves exceeding their administrative leakage limits; or both valves exceeding 0.4 l . Please explain simultaneous failure of both valves in a penetration with regard to test program leakage.
In regard to your response to Example 2, you did not agree that a violation had occyrred in your monitoring of feedwater heaters. We agree with your position that the feedwater heaters are not classified as run-to-failure and are presently being monitored at the plant level. We also recognize that a design change to replace the feedwater heater tube bundles with an improved
' design is in progress. However, additional information is needed before we can further consider you denial of this portion of Violation A, Example 2. Specifically, have there been, or could there be, occasions where tube failures have been repaired without incurring a power loss?. In --
addition, how will your plant-level performance criteria recognize and capture degraded heater performance using unplanned capacity loss when there is an existing reduced power level for core axial offset, or any other reason?
.
.-
9004130212 980408 PDR s. ' ADOCK 05000483 G PDR Y- x .
L. -
r Union Electric Company -5-E-Mail report to T. Frye (TJF)
E-Mail report to D. Lange (DJL)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
E-Mail report to Richard Correia (RPC)
E-Mail report to Frank Talbot (FXT)
bec to DCD (IE01)
'
bec distrib. by RIV:
Regional Administrator Resident inspector DRS Director DRS Deputy Director DRP Director DRS-PSB Branch Chief (DRP/B) MIS System Project Engineer (DRP/B) RIV File Branch Chief (DRP/TSS)
C. Goines (RIV Al 98-0058)
C. Gordon (RIV Al 98-0058)
OE File .
-
f a
\
.
D DOCUMENT NAME: r:\_cw\cw711ak. jew *Previously concurred To receive copy of document, indicate in box:"C" = Copy without enclosures "E" = Copy with enclosures "N" a No qepy RIV: SRI:MB * C:MB* C NRR* C:PBB* D:DRLf JEWhittemore/imb DAPowers RCorreia WDJohnson ATHd4eh lli 02/26/98 02/26/98 02/27/98 03/31/98 04/7/98
'
OFFICIAL RECORD COPY
'
l30011 u
/
o
,j. 4 ,
- r ~
>
Union Electric Company -2-In regar'dto your response to Example 2 that addressed heater drain pump seals, the planned
- corrective action to evaluate the heater drain pump seals for monitoring in a run-to-failure mode is satisfactory. We will verify the implementation of your planned corrective action during future inspection activities at the Callaway site.
,
!/ Violation B l:
'
In regard to your response to Violation B, we note that you intend to review all suggestion occurrence solution reports that have been initiated since July 10,1993, in order to verify that all'
structures, systems, or components (SSCs) within the program secpe have been properly L evaluated and classified as Category (a)(1) or.(a)(2). This corrective action is satisfactory and l will be reviewed during a future inspection. However, we request clarification on your completed -
, corrective action. In particular, the team noted in the inspection report that a failure would not be i classified as a functional failure on the basis that an equipment operator was available at the -
.
L valve to open it and that personnel errors during the performance of maintenance activities were not considered for functional failure evaluations. As a result of your response to Violation C, e please discuss your current position relative to taking credit for operator intervention for -
functional failure evaluation. Also, please describe how your program evaluates personnel
- errors in determining whether functional failures have occurred.
-
! .
Violation _Q
! . In regard to your response that provides train unavailability criteria for monitoring the reactor.
protection trip system, we find the planned corrective action to be acceptable. We will review the implementation of the corrective action during a future inspection.
- Your planned program change concoming the evaluation of unavailability does not take into consideration the unavailability of risk-significant SSCs during surveillance if there is a minimal restoration time for those SSCs and is, therefore, not acceptable because this action would not necessarily preclude future violations. Your reference to INPO performance indicator reporting guidelines for taking credit for operator action to quickly restore SSCs undergoing surveillance is not endorsed by NRC. NUMARC 93-01 guidance, which is endorsed by NRC, is clear with i respect to availability determination in that SSCs, which respond automatically, must be subject to direct control or function automatically without human action to be considered available. Your.
approach does not take into consideration that maintenance / surveillance time be counted as
- unavailable for the purpose of determining the effectiveness of the maintenance and
. surveillance performed on SSCs.' Furthermore, your stated tr.tention to take exception to the guidance of NUMARC 93-01 for availability determination, by allowing a " minimal * intervention
- time, was not accompanied by an acceptable alternative for NRC review, L ~
L
,
.
.
..Z
.-
' *
a I
j ;,
Union Electric Company -3- g
- You are required to respond to our concems relating to your response to Violations A, B,'and C within 30 days of receipt of this letter. If you have questions about this letter, please contact Dr. Dale A. Powers at 817/860-8195. For your completed and planned corrective actions that are considered to be appropriate, we will review the implementation of those corrective actions '
. during a future inspection to determine that full compliance has been achieved and will be maintained.
As discussed in our letter of December 24,1997, we wish to hold a management meeting with
. Union Electric to discuss your plans to improve your Maintenance Rule program. At this meeting, we want to include, as agenda items, the results of your continuing corrective action -
~" evaluations that were targeted for completion by April 30,1998, and your response'to the
- questions in this letter. As discussed between Messrs. Mark Reid.meyer and Dale Powers on
'
February 17,1998, we understand that your proposed time for this meeting is near the end of May _1998. Dr. Powers will be contacting your representative to obtain details for the meeting and to establish the meeting date.
Sincerely,
,.
~
'
ArthurT. H eli lli,' Director Division of ctor Safety -
Docket No.: 50 483 i
License No.: NPF-30 cc:-
Professional Nuclear Consulting, Inc.
19041 Raines Drive Derwood, Maryland 20855-
'
'.. Gerald Chamoff, Esq.
Thomas A. Baxter, Esq.
L Shaw, Pittman, Potts & Trowbridge 2300 N. Street, N.W.
Washington, D.C.- 20037 H. D. Bono, Supervising Engineer Quality Assurance Regulatory Support Union Electric Company.~
P.O. Box 620 Fulton, Missouri 65251
-
..
'
. '
.-
, . .
(
Union Electric Company -4-Manager- Electric Department Missouri Public Service Commission 301 W. High .
>
'
P.O.' Box 360 Jefferson City, Missouri 65102 Ronald A. Kucera, Deputy Director Department of Natural Resources P.O. Box 176 ,
i- , Jefferson City, Missouri 65102 Otto L. Maynard, President and -
Chief Executwe Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, Kansas 66839
- - ..' Dan I. Bolef, President
>
= Kay Drey, Representative Board of Directors Coalition .
l- for the Environment 6267 Delmar Boulevard University City, Missouri 63130 l
- Lee Fritz, Presiding Commissioner
! Callaway County Court House 10 East Fifth Street Fulton, Missouri 65151 Alan C. Passwater, Manager
,
Licensing and Fuels
- AmorenUE *
i One Ameren Plaza q
/
1901 Chouteau Avenue j P.O. Box 66149 '
'
St. LoiJis, Missouri 63166-6149_
J. V. Laux, Manager Quality Assurance a Union Electric Company. 1 P.O. Box 620 I
Fulton, Missouri 65251 I
, r<
Q .. . . , , . . . . ,
-
, .
. . ._-