IE Insp Rept 50-461/82-07 on 820517-20.No Noncompliance Noted.Major Areas Inspected:Followup of 10CFR50.55e Repts, IE Bulletins & Circulars
ML20054K618
Person / Time
Site: Clinton Constellation icon.png
Issue date: 06/19/1982
From: Walker R, Wescott H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20054K616 List:
References
50-461-82-07, 50-461-82-7, IEB-78-04, IEB-78-12, IEB-78-4, IEB-80-02, IEB-80-04, IEB-80-16, IEB-80-17, IEB-80-2, IEB-80-4, IEB-81-02, IEB-81-03, IEB-81-2, IEB-81-3, NUDOCS 8207020383
Download: ML20054K618 (7)


Text

_ _ _ - _

.

,

i U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-461/82-07(DPRP)

Docket No. 50-461 License No. CPPR-137 Licensee: Illinois Power Company 500 South 27th Street Decatur, IL 62525 Facility Name: Clinton Power Station, Unit 1 Inspection At: Clinton Site, Clinton, IL Inspection Conducted: May 17 - 20, 1982 Inspector: 11. M. Wescott ACCf /. f f4 ff /Q b!I Approved By: . Walke , Chief '

Reactor Projects Section 1C Inspection Summary Inspection on May 17-20, 1982 (Report No. 50-461/82-07(DPRP)

Areas Inspected: Followup of 10 CFR 50.55(e) reports; IE Bulletins and Circulars. The inspection involved a total of 26 inspector-hours onsite by one NRC inspecto Results: No items of noncompliance or deviations were identifie PDR ADOCK 05000461 O PDR

_ - _ _ _ _ _ - _ _ _ _ -

.

.

DETAILS Persons Contacted Illinois Power Company G. W. Bell, Supervisor, Audits and Surveillance A. Budnick, QA Director W. Calhoun, Supervisor, Electrical Construction R. Campbell, Supervisor, Programs and Procedures J. Canfield, Director of Construction E. Connon, Director of Compliance J. Koch, Vice President E. Korneman, Assistant Director of Construction J. O. McHood, Vice President and Project Manager T. Plunkett, Plant Manager J. S. Spencer, Director of Design Engineering R. Weber, Station QA Engineer Baldwin Associates G. Chapman, Manager of Technical Services J. E. Findley, Manager- of Quality and Technical Services W. J. Harrington, Project Manager J. W. Smart, Manager of QA H. R. Swift, Project Engineer T. G. Yearick, Assistant Project Manager General Electric Company J. R. Logan, Site Manager The above personnel were in attendance at the exit meeting held on May 20, 198 . Licensee Action on Previously Identified Items (Closed) 10 CFR 50.55(e) Report No. 50-461/77-02. Subject:

Breakdown in Quality Assurance concerning procurement of service water pipin The inspector reviewed the " Investigation of Reportable Deficiency,"

Y-2016, L14-PY-77 (08-29) -9 explaining the cause of the deficiency and action taken to prevent further breakdown in procurement activ-itie In addition the licensee has used concrete bash fill at the buried portion of the service water line and installed a cathodic protection system to control corrosio (0 pen) 10 CFR 50.55(e) Report No. 50-461/81-01. Subject: Lack of control of preheat of main steam line closure spool welding to the reactor safe end .

The inspector reviewed the following: Letter GE to L. Dozier, GSI-013-81, dated 1/7/81, stating problem and lift of stop work order and that a detailed investigation is underway and the results will be forwarded to you when receive GE FDDR No. LH-163-81 dated 1/12/81, stating that surface hardness readings indicate that hardness was unaffecte Letter IPC to GE, DEK-836-IPC, dated 1/12/81, stating observa-tions mad This item remains open pending the licensee obtaining a copy of the engineering analysis performed by GE (see item a. above)

for review by NRC Region II (Closed) 10 CFR 50.55(e) Report No. 50-461/80-03, Subject: Break-down in QA concerning procurement of Rosemount pressure transmitters in that the transmitters did not meet environmental qualification per IEhE-324-197 The inspector reviewed the following: Record of coordination dated March 19, 1980, stating that GE's PQC's for the transmitters did not indicate any noncon-formances while the transmitters were not environmentally qualifie Eight GE PQC's Revision 1, revised to reflect that the transmitters were not environmentally qualisted, Baldwin Associates FCR No. 4768 dated 6/9/8 This item appears to be in conformance with IPC's final report to NRC, Region III, U-0137, L14-80(04-30) -9, and is considered closed. Other deficiencies with Rosemount pressure transmitters are the subject of IE Bulletin No. 80-16 and IE Circular 80-16 which remain ope (Closed) Noncompliance (50-461/80-02-04). The inspector reviewed the following: Baldwin Associates QA No. 140 Revision 4, dated 10/6/81, which now requires a QA NCR revie Baldwin Associates QAM Section 13, "Nonconformances" Revision 2, dated 4/19/82, paragraph 13.3.2 C which provides for generic corrective actio Baldwin Associates QAM Section 14 " Corrective Action," Revision 2, dated 4/19/8 .

. IPC's surveillances and audit report as follows:

(1) Y-11595, Baldwin Associates Trend Process (2) Y-12026 Baldwin Trending and Associated Corrective Actio (3) Audit report Mo. Q36-81-7 of U.S. Testing Fourteen (14) NCR's including IP QA Document Review trans-mittals for eac This item is considered closed as the licensee appears to have adequate control and overview of nonconformances, corrective actions and trend analysis system (Closed) Licensee tracking No. 50-461/81-23. This item concerns a management meeting report wherein the licensee committed to take certain actions (see report No. 50-461/81-03, item No. 2). The inspector considers this item closed as the licensee appears to have honored his commitment . IE Bulletins (Closed) 50-461/78-04 - Environmental Qualification of Certain Stem Mounted Limit Switches Inside Reactor Containment. The inspector reviewed IPC's letter to NRC, Region III, U-0069, LO8-PU-78(04-18),

stating that NAMCO D 2400X and EA-170-320 Snap Lock Switches will not be used in any safety related equipment in primary containment at CP (Closed) 50-461/78-12-12A-12B - A Typical Weld Material in Reactor Pressure Vessel Weld The inspector reviewed IPC's letter to NRC, Region III, U-0095, LO8-79 (05-29)-9 and CB & I's generic report to I& (Closed) 50-461/80-02 - Inadequate Quality Assurance for Nuclear Supplied Equipment. The inspector reviewed IPC's response letter to NRC, Region III, LO8-80(02-01)-0, stating that CPS uses feedwater spargers fabricated by CB&I that were purchased in May 1977. Action items 2 and 3 were not applicable as Clinton Unit No. 1 is not operationa (Closed) 50-461/80-04 - Analysis of a PWR Main Steam Line Break With Continued Feedwater Addition. This bulletin is not applicable as Clinton Unit No. 1 is a BW (0 pen) 50-461/80-16 - Potential Missapplication of Rosemount In Models 1151 and 1152 Pressure Transmitters with either A or D Output Codes. This bulletin remains open pending replacement and recalibration of Rosemount Models 1151 and 1152 pressure trans-

.

mitters. The licensee also intends to replace those used in nonsafety application (0 pen) 50-461/80-17 thru Supplement No. 5 - Failure of 76 of 185 Control Rods to Fully Insert During a Scram at a BWR. The inspector reviewed a letter from IPC to Standardization and Special Protects Branch, Division of Licensing, USNRC, U-0342, L 17-81(12-03)-6, with attached "LRG-II Position Papers Volume II" dated 12/3/8 This bulletin remains open pending closcout by Standardization and Special Projects Branc (Closed) 50-461/81-02- with Supplement No. 1 - Failure of Gate Type Valves to Close Against Differential Pressure. The inspector re-viewed IPC letter to NRC, Region III, U-0293, LO8-81(09-23)-6, stating that CPS has no safety related motor operated gate valves manufactured by Westinghouse - EM (Closed) 50-461/81-03 - Flow Blockage of Cooling Water to Safety System Components by Corbicula Sp. (Asiatic Clam) and Myfilus S (Mussel). The inspector reviewed IPC letter to NRC, Region III, U-0256, LO8-81(07-14)-6, stating that IP has a proposed system for controlling clams should they become a problem. IE Circulars (Closed) 50-461/77-10 - Vacuum Conditions Resulting in Damage to Liquid Process Tank IP's circular status sheet states that Rad waste tcnks (35) are all vented. Other possible detrimental effects mitigated since the Area Radiation Monitors / Process Radiation Monitors monitor for release of activity, and berms / curbs direct liquid releases to drains for processin (Closed) 50-461/77-12 - Dropped Fuel Assemblies at BWR Facilities -

IPC's circular status sheet states that, " low load sensing ongrapple cable; speed reducer is coupled to hoist drum which has light to indicate positive engagement."

(Closed) 50-461/78-06 - Potential Common Mode Flooding of ECCS equipment rooms at BWR Facilities - IPC's circular status sheet states that, "each ECCS room h9s its own sumps and pumps that pump through check valves to rad waste. There is no common header as described in the circular."

(Closed) 50-461/78-15 - Tilting Disc Check Valves Fails to Close with Gravity in Vertical Position. The inspector reviewed S&L letter to IPC, SLMI-5013, dated 7/30/80, stating that it was de-termined that only 3 check valves were installed in the vertical risers only one was of the type discussed in the circular. Anchor Darling advised that this one valve does not have the tilting disc design; is designed such that the center of gravity does not allow the valve to hang ope !

-

. ..

(Open) 50-461/78-19 - Manual Override Bypass of Safety Actuation Signals - This circular remains open pending licensee review of design and action as necessar (0 pen) 50-461/79-05 - Moisture Leakage in Stranded Wir IPC's circular status sheet states that, "S&L is investigating prcblems relative to transmitters and motors."

(0 pen) 50-461/79-12 - Potential Diesel Generator Turbocharger Problem - This circular remains open pending completed action by license .

(Open) 50-461/79-13 - Replacement of Diesel Fire Pump Starting Contractors - This circular remains open pending licensee verifica-tion that contactors have been installe (Closed) 50-461/79-17 - Contact Problem in SB-12 Switches on General Electric Metal Clad Circuit Breaker IPC's cire.ular status sheet states that, "no GE switchgear shipped to site between 8/1/78 thru 7/1/79. All other switchgear furnished by Westinghouse."

(Closed) 50-461/79-21 - Prevention of Unplanned Releases of Radio-activity - IPC's circular status sheet states that, "IPC is in com-pliance with the circular."

(Closed) 50-461/80-10 - Failure to Maintain Environmental Qualifica-tion of Equipment - IPC's circular status sheet states that, "IPC is to comply with NUREG 0588."

(0 pen) 50-461/80-16 - Operational Deficiencies on Rosemount Model 510DU Trip Units and Model 1152 Pressure Transmitters. This circular remains open pending licensee verification of the modificatio (Closed) 50-461/81-02 - Performance of NRC Licensed Individuals While on Duty - The inspector reviewed IPC's " Document Review Form" dated 2/23/81 indicating that prospective licensed operational personnel had reviewed the circula (Closed) 50-461/81-05 - Self Aligning Rod End Bushings for Pipe Supports - IPC's circular status sheet states that, "all bearings have been staked at the factory, Pacific Scientific; as preemptive corrective action, also preservice inspection program will include visual inspection of snubbers."

(Open) 50-461/81-06 - Potential Deficiency Affecting Certain Foxboro 10 to 50 Mil 11 ampere Transmitters - This circular is open pending final action by the license (Closed) 50-461/81-09 - Containment Effluent Water that Bypasses Radioactivity Monitor - IPC's circular status sheet states that,

" CPS cooler fan motors are air cooled. No other water system effluent problems were noted in the review."

..-

(Closed) 50-461/81-12 - Inadequate Periodic Test Procedure of PWR Protection System - This circular is not applicable to CP (0 pen) 50-461/81-13 - Torque Switch Electrical Bypass Circuit For Safeguard Service Valve Motors - This circular remains open pending the licensee's verification that the revision to the electrical scheme and wiring diagram to show torque switch bypass are complet (0 pen) 50-461/81-14 - Main Steam Isolation Valve Failure To Clos This circular remains open pending the licensee's completion of the recommended corrective actio . Exit Interview The inspector met with licensee representatives (denoted in Persons Contacted) at the conclusion of the inspection on May 20, 198 The inspector summarized the scope and findings of the inspectio The licensee acknowledged the informatio l 7