IR 05000456/2022003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000456/2022003 and 05000457/2022003 and Exercise of Enforcement Discretion
ML22291A068
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 10/25/2022
From: Laura Kozak
NRC/RGN-III/DORS/RPB3
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
EA-22-088 IR 2022003
Download: ML22291A068 (1)


Text

SUBJECT:

BRAIDWOOD STATION - INTEGRATED INSPECTION REPORT 05000456/2022003 AND 05000457/2022003 AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Mr. Rhoades:

On September 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station. On October 6, 2022, the NRC inspectors discussed the results of this inspection with Mr. G. Gugle, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

October 25, 2022 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Laura L. Kozak, Acting Chief Branch 3 Division of Operating Reactor Safety Docket Nos. 05000456 and 05000457 License Nos. NPF-72 and NPF-77

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000456 and 05000457

License Numbers:

NPF-72 and NPF-77

Report Numbers:

05000456/2022003 and 05000457/2022003

Enterprise Identifier:

I-2022-003-0044

Licensee:

Constellation Energy Generation, LLC

Facility:

Braidwood Station

Location:

Braceville, IL

Inspection Dates:

July 01, 2022 to September 30, 2022

Inspectors:

R. Bowen, Illinois Emergency Management Agency

A. Demeter, Acting Resident Inspector

G. Edwards, Health Physicist

D. Kimble, Senior Resident Inspector

P. Smagacz, Resident Inspector

Approved By:

Laura L. Kozak, Acting Chief

Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Braidwood Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status EDG EA-22-088 Failure to Comply with 10 CFR Part 37 71124.08 Open

PLANT STATUS

Unit 1 began the inspection period operating at full power. On September 3, 2022, the unit reached the end of the fuel cycle and power coast down operations commenced in preparation for a planned refuel outage. The unit continued to reduce power in accordance with the licensees approved reactivity management plan, and was operating at approximately 80 percent power at the end of the inspection period.

Unit 2 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities and load changes requested by the transmission system dispatcher, the unit remained operating at or near full power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial physical alignment verifications of the following systems/trains:

(1) The 2A Containment Spray (CS) Train following planned 2B CS Train maintenance during the weeks ending August 13 through August 20, 2022
(2) The Unit 1 Residual Heat Removal (RH) System during a planned 1B CS Train maintenance window, as documented in Work Order (WO) 5213824 during the week ending August 20, 2022
(3) The 2B Component Cooling (CC) Train during planned 2A CC Train maintenance, as documented in WOs 512398, 5155287, and 5142044 during the week ending September 3, 2022
(4) The 0A Motor-Driven Fire Pump during extended maintenance on the 0B Diesel-Driven Fire Pump, as documented in WO 5179895 during the weeks ending September 3 through September 24, 2022 Complete Walkdown Sample (IP Section 03.02) (1 Partial)

The inspectors evaluated system configurations during complete physical alignment verifications of the following systems/trains:

(1)

(Partial)

The Unit 1 CS System complete physical alignment verification performed, in part, during the week ending August 13, 2022.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting physical inspections and reviews to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 11.5-0 Center; Auxiliary Building, 401' Elevation, Unit 2 General Area during the week ending July 23, 2022
(2) Fire Zone 11.3-0 North, South, and Center; Auxiliary Building 364; Elevation, Units 1 and 2 Auxiliary Building General Areas during the week ending July 23, 2022
(3) Fire Zone 11.4-0 North, South, and Center; Auxiliary Building 383' Elevation, Units 1 and 2 Auxiliary Building General Areas during the week ending July 23, 2022
(4) Fire Zones 5.4-2, 5.5-1, 5.5-2, 5.6-1, and 5.6-2; Auxiliary Building 451' Elevation, Units 1 and 2 Miscellaneous Electric Equipment and Battery Rooms during the week ending July 30, 2022
(5) Fire Zone 11.2-0; Auxiliary Building 346' Elevation, Units 1 and 2 Auxiliary Building during the week ending July 30, 2022
(6) Fire Zone 11.6-0 North, South, and Center; Auxiliary Building 426' Elevation, Units 1 and 2 Auxiliary Building General Areas during the week ending August 13, 2022
(7) Fire Zone 18.12-0; Lake Screen House during the weeks ending August 13 through September 3, 2022

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors conducted physical inspections in the plant and selected document reviews to evaluate internal flooding mitigation protections in the following area(s):

(1) The Unit 1 and Unit 2 Auxiliary Building 330' and 346' Elevations during a Unit 0 CC Heat Exchanger repair work window with flood barriers removed and/or impaired during the week ending September 17, 2022

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors conducted a review that evaluated readiness and performance of the following safety-related heat exchanger:

(1) The 1B CS Cubical Cooler Heat Exchanger, as documented in WO 4764712 during the weeks ending August 20 through September 3, 2022

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

The inspectors observed and evaluated the following activities performed by licensed operators in the facility's main control room:

(1) Various activities involving on-watch operations crews. These activities included, but were not limited to:

Unit 1 Essential Service Water (SX) Pump swaps during the week ending August 6, 2022

Various pump and valve manipulations on the 1A Safety Injection Train for testing during the week ending August 27, 2022

End-of-cycle reactivity maneuvers leading into Unit 1 coast down operations for the A1R23 Refuel Outage during the week ending September 10, 2022

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

The inspectors observed and evaluated the following licensed operator training activity, which included the administration of the annual requalification operating test required by 10 CFR 55.59(a)(2) in the facility's control room simulator:

(1) A complex casualty graded scenario involving a crew of licensed operators was observed in facility's simulator during the conduct of the annual requalification operating test on September 6, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Maintenance effectiveness review associated with issues and repair activities for the 0B Diesel-Driven Fire Pump during the weeks ending September 3 through September 30, 2022

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance, quality control activities, and component performance histories to ensure the following SSCs remain capable of performing their intended function:

(1) Maintenance effectiveness review of the 1B CS System during replacement of the 1B CS Pump Cubicle Cooler Essential Service Water Return Valve (1SX091B) during the weeks ending August 20 through September 3, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Evaluation of the planned work associated with a 1B CS work window, as documented in WO 5213824 during the week ending August 20, 2022
(2) Evaluation of the planned work associated with filling the spent fuel pool (SFP) from the 0A Radwaste Monitor Tank, as documented in WO 5287466 during the week ending September 10, 2022
(3) Evaluation of the planned work associated with new fuel receipt and inspection in preparation for the Unit 1 A1R23 Refueling Outage, as documented in WO 517946 during the weeks ending August 13 through September 17, 2022
(4) Evaluation of the planned work associated with repairs to the Unit 0 CC Heat Exchanger, as documented in Issue Report (IR) 4510008 during the week ending September 17, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Evaluation of the operability of the 1A Charging (CV) Pump following identification of a degraded pump outboard seal package, as documented in IR 4510008 during the week ending July 16, 2022
(2) Evaluation of the operability of the 1B CS Train following identification of degraded cooling water flow to the pump cubicle cooler, as documented in IR 4510738 during the weeks ending July 16 through 23, 2022
(3) Evaluation of the operability of the 1A SX Pump following identification of reduced margin in differential pressure during ASME surveillances, as documented in IRs

===4511236 and 4503733 during the weeks ending July 30 through August 6, 2022

(4) Evaluation of the operability of the Unit 2 Reactor Coolant System (RCS) following identification of a step increase in RCS unidentified leakage rate, as documented in IR 4522009 during the weeks ending September 17 through September 24, 2022
(5) Evaluation of the operability of the station's fire protection and detection system and safety-related SSCs following identification of missed fire rated assembly visual inspections, as documented in IR 4522164 during the week ending September 24, 2022

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

=

The inspectors evaluated the following temporary configuration change to the facility:

(1) Review of the temporary plant modification per Engineering Changes (ECs) 634192 (Unit 1) and 635519 (Unit 2): Temporarily Exchange A Train and B Train Core Exit Thermocouples, during the weeks ending July 26 through August 27, 2022

Severe Accident Management Guidelines (SAMG) Update (IP Section 03.03) (1 Sample)

The inspectors verified the site Severe Accident Management Guidelines (SAMGs) were updated in accordance with the Pressurized Water Reactor Generic Severe Accident Technical Guidelines and validated in accordance with Nuclear Energy Institute (NEI) 14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents, Revision 1, as follows:

(1) Changes to the Braidwood Unit 1 and Unit 2 SAMGs were reviewed during the weeks ending July 23, through September 17, 2022

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1) Functional and operational testing of the Unit 0 CC Pump and discharge check valves following a Unit 0 CC Train work window, as documented in WOs 5122696 and

===5125839 during the weeks ending July 30 through August 6, 2022

(2) Functional and operational testing of the 2A RH Pump following a 2A RH Train work window, as documented in WOs 5145601, 5142646, and 5263410 during the weeks ending August 6 through 13, 2022
(3) Functional and operational testing of the 1A SX Pump following issues with newly installed test flow measurement instrumentation, as documented in WO 5270865 during the weeks ending August 20 through August 27, 2022
(4) Functional and operational testing of the 1B CS System following a planned work window, as documented in WOs 5213824 and 4763712 during the weeks ending September 3 through September 10, 2022
(5) Functional and operational testing of the 0B Diesel-Driven Fire Pump following a planned work window, as documented in WO 5278379 during the weeks ending August 27 through September 17, 2022
(6) Functional and operational testing of Main Steam Safety Valve (MSSV) 1MS017A following set pressure testing and adjustments, as documented in WO 5160505 during the week ending September 30, 2022

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities:

Surveillance Tests (other) (IP Section 03.01)

(1)2BwOSR 3.8.1.2-2; 2B Emergency Diesel Generator (EDG) Operability Surveillance, as documented in WO 5271794 during the weeks ending July 23 through 30, 2022

(2) Steam Generator 2A Channel II and Channel IV narrow range level instrument calibrations, as documented in WOs 5115059 and 5115063 during the week ending July 30, 2022
(3) The Unit 1 and Unit 2 Diesel-Driven Auxiliary Feedwater (AF) Pump surveillances, as documented in WOs 5277318 and 5279829 during the weeks ending August 13 through 20, 2022
(4) Diagnostic testing for Limitorque Motor-Operated Valve 2SI8920, 2B Safety Injection Pump Minimum Flow Isolation Valve, as documented in WO 4903613 during the weeks ending September 17 through 30, 2022 Inservice Testing (IP Section 03.01)===
(1) Main Steam Safety Valve Set Pressure Testing, as documented in WO 5160505 during the week ending September 30, 2022
(2) AF Train full flow testing, as documented in WO 5165923 during the week ending September 30,

RADIATION SAFETY

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Radioactive Material Storage (IP Section 03.01)

The inspectors evaluated the licensees performance in controlling, labeling and securing the following radioactive materials:

(1) Radioactive materials in the radioactive waste on-site storage facility
(2) Radioactive materials stored in the instrumentation room

Radioactive Waste System Walkdown (IP Section 03.02) (2 Samples)

The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:

(1) Resin processing equipment
(2) Liquid processing equipment

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

The inspectors evaluated the following characterization and classification of radioactive waste:

(1) Resin waste streams at the facility
(2) Dry activated waste (DAW) stream at the facility

Shipping Records (IP Section 03.05) (3 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1) Shipment RWS22-003 UN3321 LSA-II; Resin Liner P0698226-30 in Cask 14-215
(2) Shipment RWS22-005 UN2916 Type B; Resin Liner P0694669-5 in Cask RT-100
(3) Shipment RWS21-001 UN3321 LSA-II; Resin Liner P0695283-14 in Cask 14-215

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07)===

(1) Unit 1 (July 1, 2021 through June 30, 2022)
(2) Unit 2 (July 1, 2021 through June 30, 2022)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (July 1, 2021 through June 30, 2022)
(2) Unit 2 (July 1, 2021 through June 30, 2022)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (July 1, 2021 through June 30, 2022)
(2) Unit 2 (July 1, 2021 through June 30, 2022)

71152A - Annual Follow-Up Problem Identification and Resolution Annual Follow-Up of Selected Issues (Section 03.03)

The inspectors conducted an in-depth review of the licensees implementation of the corrective action program (CAP) related to the following issue:

(1) Review and assessment of the station's corrective actions following identification of the mis-assembly of Unit 1 and Unit 2 Core Exit Thermocouples during Unit 1 Refuel Outage A1R22 and Unit 2 Refuel Outage A2R22, as documented in IRs 4419609 and 4458973 during the weeks ending August 27 through September 17,

INSPECTION RESULTS

Enforcement Discretion Enforcement Action EA-22-088: Failure to Comply with 10 CFR Part 37 71124.08

Description:

On January 15, 2016, the licensee was issued NRC Inspection Report No.

05000456/2015407;05000457/2015407, which documented a licensee identified violation of 10 CFR Part 37, Physical Protection of Category 1 and Category 2, Quantities of Radioactive Material at Facilities with a 10 CFR Part 73, Physical Protection Program. The violation met the criteria for Enforcement Discretion as described in Enforcement Guidance Memorandum (EGM) 14-001, "Interim Guidance for Dispositioning 10 CFR Part 37 Violations with Respect to Large Components or Robust Structures Containing Category 1 or Category 2 Quantities of Material at Power Reactor Facilities Licensed Under 10 CFR Parts 50 and 52."

Subsequently, the inspectors re-evaluated this activity and found that while a violation of regulatory requirements continues to exist, the conditions remain within the criteria for enforcement discretion established within EGM 14-001 Corrective Actions: As specified in EGM 14-001, the application of discretion is authorized until the underlying technical issue is dispositioned through rulemaking or other regulatory action. Additional corrective actions are not required.

Corrective Action References: Not applicable.

Enforcement:

Violation: On January 15, 2016, a violation of 10 CFR Part 37 was documented in Braidwood Inspection Report No. 05000456/2015407;05000457/2015407. The inspectors determined that the previously identified violation remains.

Basis for Discretion: This violation met the criteria for Enforcement Discretion as described in Enforcement Guidance Memorandum (EGM) 14-001, "Interim Guidance for Dispositioning 10 CFR Part 37 Violations with Respect to Large Components or Robust Structures Containing Category 1 or Category 2 Quantities of Material at Power Reactor Facilities Licensed Under 10 CFR Parts 50 and 52."

Observation: Error in Reconnection of Core Exit Thermocouples (CETCs)

Following Reactor Refueling 71152A The inspectors performed a detailed review of IR 4419609, U1 CETC, Nozzle 74 Connections Swapped Affecting Indicators. The issue involved Instrument Maintenance Department (IMD)

CETC reconnection procedure BwIP 2000-023, Unit One Reactor Head Instrument Cable Reconnect With 40-Pin Reactor Vessel Level Indication System (RVLIS) Connectors Installed, which was performed under Work Order (WO) 4980915, 1RC01R Head Disconnect CETC & RVLIS Outage, during the Unit 1 A1R22 Refuel Outage.

On April 20, 2021, as part of the Unit 1 reactor reassembly sequence, IMD technicians were identifying the appropriate mating connectors for each CETC. Per procedure BwIP 2000-024, Reactor Head Instrument Cable Removal with 40-Pin RVLIS Connectors Installed, Step 4.2.1, each half of the cable was to have been previously properly labeled to allow for correct reconnection as the reactor was being restored following refueling. The procedure steps identified the correct cable numbers associated with the CETCs, and technicians performing the work in the field determined that colored electrical tape had been properly used to mark the connections previously during disassembly. All comments in the WO package indicated that the reconnections were completed satisfactorily. However, on April 25, 2021, during the Unit 1 power ascension following reactor restart, a part of scheduled surveillance 1BwOS TRM 3.3.h.1, Unit One Power Distribution Monitoring System (PDMS) Operability Weekly Surveillance, having to do with symmetric CETC temperature limits yielded unsatisfactory results. Reactor Engineering personnel subsequently determined that the Unit 1 CETC connections associated with Reactor Vessel Closure Head Nozzle 74 had been improperly reconnected during the A1R22 restoration activities, affecting the indications of 12 CETCs in quadrant 2 of the Unit 1 reactor.

As discussed in the stations Technical Specification (TS) Bases, CETCs are used as a primary means to determine reactor coolant system subcooling margin and are also utilized extensively within the stations emergency operating procedures for such things as termination or re-initiation of Safety Injection during accident scenarios, as well as for the verification and extended monitoring of the effectiveness of post-accident core cooling. The inspectors chose this issue for an in-depth review of the licensees actions within their CAP because of the inherent safety significance associated with the potential reduction in the effectiveness of the CETCs.

Following the A1R22 CETC reconnection error, IMD performed an evaluation as part of the licensees CAP process. In part, IMD was tasked to address why corrective actions taken after a similar occurrence in 2012 were not effective (IR 1451512, Unit 2 CETC, Nozzle 77 Connections Swapped Affecting Indication). The occurrence from 2012 mirrored the A1R22 issue, with the exception that it took place on Unit 2 at Nozzle 77. For the 2012 issue on Unit 2, IMD had also performed the CAP evaluation, and both evaluations, from 2012 and May 2021 as well, had concluded that the omission of a first line supervisor (FLS) hold point and inconsistencies with the labeling and/or marking of cables were the likely contributors to the errors.

In November 2021 during power ascension following the Unit 2 A2R22 Refuel Outage, planned testing by the licensee identified that 12 CETCs in quadrant 2 of the Unit 2 reactor had again been swapped during reconnection activities at the end of that outage. The licensee entered IR 4458973, Unit 2 CETC, Nozzle 74 Connections Swapped Affecting Indications, into their CAP on November 5, 2021, to document the error. Although it was originally recommended that the CAP evaluation for this issue be assigned to IMD, the stations Electrical Maintenance Department (EMD) was eventually assigned the CAP evaluation. As a result, IMD actions and possible contributors to the issue were not evaluated.

With the Unit 1 A1R23 Refuel Outage scheduled to begin on October 3, 2022, the inspectors examined the licensees corrective actions from the previous three events (Unit 2 in 2012, Unit 1 in 2021, and Unit 2 in 2021) in an effort to determine whether or not vulnerabilities associated with the process to reconnect CETCs following reactor refueling accurately might still exist. Several observations by the inspectors were discussed station management, which included but were not limited to:

Procedures for the disconnection and reconnection of the CETCs were not updated to reflect certain CAP evaluation learnings in a timely fashion. Despite changes being submitted, the procedures had not been updated during the time of the inspectors reviews. In one case, a due date for had been rescheduled 11 times out to March 15, 2023, months after the scheduled occurrence of the Unit 1 A1R23 Refuel Outage in October 2022. Following discussions with the inspectors, this due date was readjusted and the procedure change process was reinitiated.

The procedures to be updated did not encompass the totality of the procedures used for CETC disconnection and reconnection work activities. Procedure BwIP 2000-023 only pertains to Unit 1. A separate procedure, BwIP 2000-014, Unit Two Reactor Head Instrument Cable Reconnect, is used for the reconnection of cables for Unit 2, and no similar procedure revision at the time of the inspectors reviews existed for updating the BwIP 2000-014. Additionally, upon further review by the licensee, it was determined that some of the procedures referenced were intended to be superseded by a newer procedure, and this had not yet been accomplished.

The CAP evaluation duties between EMD and IMD in the aftermath of these issues were not entirely consistent or coordinated. As a result, each respective department generated corrective actions independently, and the failure of the departments to effectively communicate and coordinate their actions contributed to a mixed approach towards issue resolution. For example, EMD took a CAP action involving the addition of FLS hold points in their applicable procedures, while IMD took no similar action even though their CAP evaluation noted such an enhancement would be beneficial.

In reviewing each issue, the inspectors determined that the licensees failures to properly reconnect CETCs following reactor refueling operations constituted a performance deficiency that was within their ability to foresee and which should have been prevented. However, in each case the licensee was able to compensate for the CETC reconnection errors by applying a temporary configuration change to the system. Essentially, CETC lines were intentionally swapped again further downstream away from the reactor head so that ultimately the correct signal was being processed at its terminus. As such, there was no loss of function and the inspectors determined that issues were of minor significance and not subject to formal actions per Section 2.3.1 of the NRC Enforcement Policy. Consequently, no findings or violations of NRC requirements of more than minor safety significance were identified by the inspectors in the course of this review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On October 6, 2022, the inspectors presented the integrated inspection results to Mr. G. Gugle, Site Vice President, and other members of the licensee staff.

On August 19, 2022, the inspectors presented the radiation protection inspection results to Mr. G. Gugle, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

BwOP RH-M1

Operating Mechanical Lineup Unit 1 1A RH Train

BwOP CS-E1

Electrical Lineup Unit 1 Containment Spray System

Electrical Lineup

BwOP CS-M1

Core Spray Operating Mechanical Lineup Unit 1

BwOP FP-E1

Electrical Lineup for the Unit 0 Fire Protection System Unit

Operating

BwOP FP-E1

Electrical Lineup for the Unit 0 Fire Protection System Unit

Operating

BwOP FP-E2

Electrical Lineup for the Unit 0 Fire Protection System Unit

Operating

2E1

BwOP FP-E3

Unit 0 Electrical Lineup Unit 0 Operating

BwOP FP-M1

Operating Mechanical Lineup Unit 0 LSH and Outside Ring

HDR Operating

BwOP FP-M6

Operating Mechanical Lineup Unit 0 Auxiliary Building Ring

Header Operating

71111.04

Procedures

BwOP RH-E1

Residual Heat Removal Electrical Lineup Unit 1

Pre-Fire Plan No.

100

Fire Zone 11.2-0; Auxiliary Building 346' Elevation Unit 1

Auxiliary Building General Area (NE)

Pre-Fire Plan No.

101

Fire Zone 11.2-0; Auxiliary Building 346' Elevation Unit 2

Auxiliary Building General Area (South)

Pre-Fire Plan No.

111

Fire Zone 11.3-0 Center; Unit 2 Auxiliary Building General

Area (Center)

Pre-Fire Plan No.

2

Fire Zone 11.3-0 South; Unit 1 Auxiliary Building General

Area (North)

Pre-Fire Plan No.

113

Fire Zone 1.3-0 South; Unit 2 Auxiliary Building General Area

(South)

Pre-Fire Plan No.

2

Fire Zone 11.4-0; Auxiliary Building 383' Elevation Auxiliary

Building General Area Center

Pre-Fire Plan No.

133

Fire Zone 11.4-0 North; Auxiliary Building 383' Unit 1,

Auxiliary Building General Are North

71111.05

Fire Plans

Pre-Fire Plan No.

134

Fire Zone 11.4-0 South; Auxiliary Building 383' Elevation Unit

Auxiliary Building General Area South

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Pre-Fire Plan No.

146

Fire Zone 11.5-0 Center; AB 401' Unit 2 Auxiliary Building

General Area Center

Pre-Fire Plan No.

156

Fire Zone 11.6-0; Auxiliary Building 426' Elevation Auxiliary

Building General Area Center

Pre-Fire Plan No.

156

Fire Zone 11.6-0; Auxiliary Building 426' Elevation Unit 1

Auxiliary Building General Area North

Pre-Fire Plan No.

156

Fire Zone 11.6-0; Auxiliary Building 426' Elevation Unit 2

Auxiliary Building General Area South

Pre-Fire Plan No.

165

Fire Zone 11.6C-0; Auxiliary Building 426' Elevation Auxiliary

Building Laundry Room

Pre-Fire Plan No.

24

Fire Zone 18.12-0; Lake Screen House 602' Elevation

Pre-Fire Plan No.

Fire Zone 5.4-2; Auxiliary Building 451' Elevation, Unit 2

Division 22 Miscellaneous Electric Equipment Room and

Battery Room

Pre-Fire Plan No.

Fire Zone 5.6-2; Auxiliary Building 451' Elevation, Unit 2

Division 21 Miscellaneous Electric Equipment Room and

Battery Room

ER-BR-600-1069

Site List of High Risk Fire Areas Braidwood Unit 1 and

Unit 2

Procedures

OP-AA-201-008

Pre-Fire Plan Manual

Miscellaneous

CC-AA-201-F-01

Plant Barrier Impairment Permit for 1SXFSO1-3 Access

Plate during Common Heat Exchanger Work Window

09/12/2022

BwAP 1110-3

Plant Barrier Impairment Program

Operability

Evaluations

BwMP 3100-094

Removal and Installation of Flood Seal Opening Barriers

0BwOA PRI-8

Auxiliary Building Flooding Unit 0

Procedures

BwOP PBI-1

Plant Barrier Impairment Program Pre-Evaluated Barrier

Matrix

71111.06

Work Orders

252064

SX Piping Leakage at the Outlet of U-0 CC HX

09/07/2022

4510738

1B CS Pump Cubicle Cooler Flow

07/12/2022

Corrective Action

Documents

4516287

Update on 1B CS Cubicle Cooler Flow

08/11/2022

71111.07A

Work Orders

4764712

LR-1VA03SB PM Clean 1B CS Pump Cubicle Cooler

08/18/2022

Miscellaneous

BR1C23-09.0

Braidwood 1 Cycle 23 Coastdown Reactivity Plan

08/08/2022

71111.11Q

Procedures

1BwOSR

Group A Inservice Testing Requirements for 1A Safety

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5.5.8.SI-10A

Injection Pump (1SI01PA)

BwOP SI-1

Safety Injection System Startup

BwOP SI-2

Safety Injection System Shutdown

OP-AA-101-111-

1001

Operations Standards and Expectations

OP-AA-101-113

Operator Fundamentals

OP-AA-101-113-

1006

4.0 Crew Critique Guidelines

OP-AA-103-102

Watch-Standing Practices

OP-AA-103-102-

1001

Strategies for Successful Transient Mitigation

OP-AA-103-103

Operation of Plant Equipment

OP-AA-104-101

Communications

OP-AA-111-101

Operating Narrative Logs and Records

OP-AA-300

Reactivity Management

OP-BR-108-101-

1002

Operations Department Standards and Expectations

TQ-AA-10

Systematic Approach to Training Process Description

TQ-AA-150

Operator Training Programs

TQ-AA-155

Conduct of Simulator Training and Evaluation

TQ-AA-201

Examination Security and Administration

TQ-AA-306

Simulator Management

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

Security Actions

260334

OI Benchmark 2019 NEIL Property Workshop

06/28/2019

4309174

OTI-FP8023 Temp Indicator Erratic

01/09/2020

20048

Request Additional Vibe Readings Taken During March

DDFP Run

2/21/2020

22158

0FP03PB Diesel Driven Fire Pump JW Heater Leak at Fitting

2/28/2020

4357805

0FP03PB Diesel Driven Fire Pump JW Heater Leak Getting

Worse

07/20/2020

4367479

0B FP Jockey Pump Seal Leakage

09/04/2020

71111.12

Corrective Action

Documents

4391511

Abnormal Oil Results for 0FP03PB-CC

2/21/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4391873

Follow Up Oil Sample 0FP03PB

2/23/2020

4411466

Abnormal Oil Results 0FP03PB

03/25/2021

24281

0B FP Excessive Seal Leakage

05/18/2021

24281

0B FP Excessive Seal Leakage

05/18/2021

24549

DDFP Auto Start Requirements for Monthly Runs per NEIL

05/19/2021

24838

Excessive Packing Leak on 0B FP Jockey Pump

05/20/2021

4459495

1SX091B Stem is Bound

11/08/2021

4517219

1SX091B Needs to be replaced, can not be repaired

08/16/2022

4518611

0B Fire Pump Overheated During PMT Test

08/24/2022

4518908

0FP03PB Coolant Expansion Tank Sight Glass

08/26/2022

4518909

0B Fire Pump, 0BwOS FP.2.1.E-1B Failed Acceptance

Criteria

08/26/2022

4519018

0B Fire Pump Exhaust Filling Room

08/26/2022

4519144

Time Clock Will Be Exceeded for BwAP 1110-1A2

08/27/2022

Engineering

Changes

636697

Evaluate Freeze Seal on 1SX54AB-3" to Support Work on

1SX091B Valve

05/11/2022

Quality Receipt Inspection Package Receipt #251181 for 3"

Globe Valve

10/10/2018

Quality Receipt Inspection Package Receipt #133026 for

Valve Stem

04/03/2007

Quality Receipt Inspection Package Receipt #129199 for

Valve Disc

11/21/2006

Quality Receipt Inspection Package Receipt #114201 for

Disc Union

07/01/2005

Quality Receipt Inspection Package #116114 for Valve Yoke

and Bushing

09/20/2006

Quality Receipt Inspection Package Receipt #251182 for 3"

Globe Valve Bonnet, and Body

10/10/2018

Miscellaneous

OP-AA-201-004

Hot Work Permit for Replacement of

1SX091B Valve

08/16/2022

Procedures

1BwOSR 3.7.8.1

Unit One Essential Service Water System Surveillance

4865223

Create WR to Install Upgraded Valve for 1SX2183D

08/16/2022

Work Orders

4865224

Create WR to Install Upgraded Valve for 1SX2183B

08/16/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

213824

1S091B Stem is Bound

08/16/2022

20647

BwOP FC-11 Procedure Change Request Action (PCRA) to

Add Step to Fill Spent Fuel Pool from 0A Radwaste Monitor

Tank

09/04/2022

Corrective Action

Documents

22241

Pipe Diviots Below Backing Ring

09/14/2022

Engineering

Changes

636697

1B Containment Spray Pump Cubicle Cooler Return Isolation

Valve Freeze Seal Assessment

05/20/2022

BwMP 3300-054-

F-01

Freeze Checklist and Communication Tool

BwOP WX-131

Radwaste Monitor Tank Recirculation

CC-AA-403

Maintenance Specification: Selection and Control of Freeze

Seal Location

CY-AP-120-330

Spent Fuel Pool/Transfer Canal/Refuel Pool

ER-AA-330-009

ASME Section XI Repair/Replacement Program

ER-AA-600

Risk Management

ER-AA-600-1042

On-Line Risk Management

MA-AA-736-610

Application of Freeze Seal to All Piping

MA-AA-736-620

Application of Freeze Seal Using Rigid Superfreeze SF-2500

OP-AA-107

Integrated Risk Management

OP-AA-108-117

Protected Equipment Program

OU-AP-200

Administrative Controls During Fuel Handling Activities for

Byron and Braidwood

OU-AP-201

New Fuel Receipt and Inspection for Byron, Braidwood, and

Ginna

OU-AP-203

Operation of the New Fuel Elevator for Byron and Braidwood

OU-AP-204

Fuel Movement in the Spent Fuel Pool for Byron and

Braidwood

OU-AP-216

Operation of the Spent Fuel Pool Bridge Crane for Byron and

Braidwood

Procedures

WC-AA-101-1006

On-Line Risk Management and Assessment

5179476

Reactor Services New Fuel Receipt

07/26/2022

71111.13

Work Orders

287466

Fill the Spent Fuel Pool Utilizing Water from the 0A

Radwaste Monitor Tank

08/28/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4503733

Reduce Margin for 1A Essential Service Water Pump

06/03/2022

4510008

Larger Than Usual Leakage on 1A CV Outboard Seal

07/08/2022

4510392

1BwOSR 3.4.13.1 Results Action Level 2 and 3

07/11/2022

4511236

1A Essential Service Water Pump Flowmeter Data

Inconsistent with Previous Test

07/15/2022

4517150

NOSA-BRW-22-05 Braidwood Fire Protection Audit

08/16/2022

4519683

Unexpected Alarm 2-7-A2 2B Seal Injection Filter DP HIGH

08/30/2022

4519727

Unexpected Annunciator 2-7-B2

08/30/2022

20009

Unit 2 RCS Leakrate Deviation Action Level III Exceeded

08/31/2022

20133

Unit 2 RCS Leakrate Deviation Action Level II Exceeded

09/01/2022

21202

2CV01FB - 2B Seal Injection Filter Housing

09/07/2022

21439

2CV8385B is Broken in the Open Position

09/08/2022

22009

Unit 2 RCS Leakrate Exceeds STD Action Level I

09/13/2022

22164

NOS ID: Fire Rated Assembly Visual Inspections Were

Missed

09/13/2022

Corrective Action

Documents

22897

NOS Finding: Fire Rated Assemblies Not Visually Inspected

08/16/2022

SONARtrac System Performance Report for Commissioning

of CIDRA Flow Meter

07/31/2022

Miscellaneous

SONARtrac System Performance Report of CEDRA Flow

Meter Data Following Reduced Margin in 1A Essential

Service Water Pump Differential Pressure

07/27/2022

1BwOSR

5.5.8.SX-3A

Group A IST Requirements for 1A Essential Service Water

Pump (1SX01PA)

1BwOSR

5.5.8.SX-6A

Comprehensive Inservice Test (IST) Requirements for 1A

Essential Service Water Pump (1SX01PA)

BwAP 1110-1

Fire Protection Program System Requirements

BwAP 1110-1

Fire Protection Program System Requirements

BwAP 1110-1A1

OGCAR Required Compensatory Measure Action Response

Fire Detection Instrumentation

BwAP 1110-1A7

Fire Rated Assemblies Required Compensatory Measures

Action Response Cover Sheet

BwMS FP.7.1.E-1

Fire Rated Assemblies Visual Inspection

71111.15

Procedures

BwMS FP.7.1.E-

Fire Rated Assemblies Visual Inspection Accessible Areas

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1A0

(CM-1) Data Sheets

NO-AA-210

Nuclear Oversite Regulator Audit Procedure

OP-AA-106-101-

1006

Operational Decision Making Process

OP-AA-108-111

Adverse Condition Monitoring and Contingency Planning

1451512

U2 CETC, Nozzle 77 Connections Swapped Affecting

Indications

2/12/2012

4419609

U1 CETC, Nozzle 74 Connections Swapped Affecting

Indications

04/28/2021

24250

U1 CETC, Nozzle 74 Connections Swapped Affecting

Indications

05/18/2021

4458973

U2 CETC, Nozzle 74 Connections Swapped Affective

Indications

11/05/2021

Work Orders

266841

1FE-SX146 1A Essential Service Water Pump Flow Meter

08/03/2022

634192

Temporarily Exchange A Train and B Train Core Exit

Thermocouples at Reactor Head Penetration 74 (E-15) for

Unit 1

05/26/2021

Engineering

Changes

635519

Temporarily Exchange A Train and B Train Core Exit

Thermocouples at Reactor Head Penetration 74 (E-15) for

Unit 2

11/17/2021

Miscellaneous

SAMG Diagnostic Process Guideline

2/18/2019

CC-AA-112

Temporary Configuration Changes

71111.18

Procedures

SAMG TSG-3

Site Capabilities

Corrective Action

Documents

4511236

1A Essential Service Water Pump Flowmeter Data

Inconsistent with Previous Tests

07/15/2022

0BwOS

FP.2.2.M-2

Diesel Driven Fire Pump Surveillance

0BwOSR

5.5.8.CC-1

A IST Requirements for Component Cooling Pump 0CC01P

and Discharge Check Valves

1BwOSR

5.5.8.RH-5A

Group A IST Requirements for Residual Heat Removal

Pump 1RH01PA

1BwOSR

5.5.8.SX-3A

Group A IST Requirements for 1A Essential Service Water

Pump (1SX01PA)

71111.19

Procedures

BwMP 3305-003

Main Steam Safety Valve Testing Using Setpoint Verification

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Device

BwMSR 3.7.1.1

Main Steam Safety Valve Operability Test (Setpoint

Verification Using the Furmainte Trevitest System)

BwOP RH-2

Securing the RH System for Recirculation

BwOP RH-5

RH System Startup for Recirculation

4865223

Create WR to Install Upgraded Valve for 1SX2183D

08/17/2022

4865224

Create WR to Install Upgraded Valve for 1SX2183B

08/17/2022

22696

Perform Oil Change-Out for Shaft Bearing

07/27/2022

25306

LR-0B Fire Protection Pump Flow and Pressure Test

08/26/2022

25839

Change Grease in CPLG and Perform Inspection of CPLG

Internals

07/27/2022

5142646

UMP Oil Change & Sample, Visually Inspect for Degradation

08/04/2022

5145601

LMB Oil Change & Sample, Visually Inspect for Degradation

08/04/2022

5160505

IST-RT-1MS013S/014S/015S/016S/017S-MSSV Operability

Test

09/28/2022

213824

1SX091B Stem is Bound

08/17/2022

263410

IST-2RH01PA ASME Group A Test & CC-2SI8958A

08/04/2022

270865

LR-ISTFor 1SX002A SRV ReQMTS for 1A Essential

SERVC W

06/21/2022

Work Orders

287229

0B Fire Pump Overheated During PMT Test

09/02/2022

25800

Standing Water in AF Tunnel Lowest Elevation

09/30/2022

25871

OSP-R Water Buildup Around AF Tunnel Dehumidifier

09/30/2022

25890

00-OSP-R: 1A AF Pump Inboard Seal Weeping

09/30/2022

Corrective Action

Documents

25898

OSP-X 1LL1-33 Emergency Light Green 'Ready' Light Bulb

Non On

09/30/2022

1BwOSR 3.7.5.4-

Unit One Diesel Driven Auxiliary Feedwater Pump

Surveillance

1BwOSR

5.5.8.AF-4A

Unit One Comprehensive Inservice Testing (IST)

Requirements for 1A Auxiliary Feedwater Pump

1BwOSR

5.5.8.AF-4B

Unit One Comprehensive Inservice Testing (IST)

Requirements for 1B Auxiliary Feedwater Pump

71111.22

Procedures

2BwOSR 3.7.5.4-

Unit Two Diesel Driven Auxiliary Feedwater Pump

Surveillance

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2BwOSR 3.8.1.2-

Unit Two 2B Diesel Generator Operability Surveillance

ER-AA-302

Motor-Operated Valve Program Engineering Procedure

MA-AA-723-300

Diagnostic Testing of Motor Operated Valves

MA-AA-723-300-

1005

Review and Evaluation of Motor Operated Valve Test Data

4903613

2SI8920 Motor Operated Valve Diagnostic Testing

Surveillances

09/15/2022

5115059

Electrical Calibration of Steam Generator 2A Narrow Range

Level Loop 2L-0517

07/26/2022

5115063

Electrical Calibration of Steam Generator 2A Narrow Range

Level Loop 2L-0519

07/26/2022

5165923

IST - Unit 1 AF Pumps Comprehensive Full Flow Test and

Equipment Response

09/30/2022

271794

LR-IST-2B D/G Operability Monthly

07/21/2022

277318

LR-OP U-1 Diesel Driven Auxiliary Feedwater Pump Monthly

Run

08/12/2022

Work Orders

279829

OP U-2 Diesel Driven Auxiliary Feedwater Pump Monthly

Run

08/12/2022

AR 04315942

Flow Path Could Not Be Established to 0A RW DEMIN

2/06/2020

AR 04369760

Radwaste High Level Drum Area Radiation Monitor in Alarm

09/16/2020

Corrective Action

Documents

AR 04513257

U1 CAF Tank Needs to be Emptied in Radwaste

07/22/2022

CFR 61 Dry Activated Waste Analysis

05/26/2022

Miscellaneous

CFR 61 Spent Resin Filter Analysis

10/29/2021

NISP-RP-007

Control of Radioactive Material

RP-AA-500-1003

CFR 37 Material Accountability Program

Procedures

RW-AA-100

Process Control Program for Radioactive Wastes

RWS21-001

Shipment RWS21-001 UN3321 LSA-II; Resin Liner

P0695283-14 in Cask 14-215.

01/13/2022

RWS22-003

Shipment RWS22-003 UN3321 LSA-II; Resin Liner

P0698226-30 in Cask 14-215.

04/27/2022

71124.08

Shipping Records

RWS22-005

Shipment RWS22-005 UN2916 Type B; Resin Liner

P0694669-5 in Cask RT-100.

03/17/2022

71151

Miscellaneous

NRC Performance Indicator Data; Mitigating Systems

07/02/2021 -

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Mitigating System Performance Index for Heat Removal

Systems

06/30/2022

NRC Performance Indicator Data; Mitigating Systems

Mitigating System Performance Index for Residual Heat

Removal Systems

07/01/2021 -

06/30/2022

NRC Performance Indicator Data; Mitigating Systems

Mitigating System Performance Index for Cooling Water

Systems

07/01/2021 -

06/30/2022

LS-AA-2001

Collecting and Reporting of NRC Performance Indicator Data

Procedures

LS-AA-2200

Mitigating System Performance Index Data Acquisition and

Reporting

Corrective Action

Documents

4418835

1BwOS TRM 3.3.H.1 Failed Symmetric CETC Temperature

Limits

04/25/2021

BwIP 200-023

Unit One Reactor Head Instrument Cable Reconnect with

40-Pin RVLIS Connectors Installed

0E1

BwIP 2000-014

Unit Two Reactor Head Instrument Cable Reconnect

71152A

Procedures

BwIP 2000-024

Reactor Head Instrument Cable Removal with 40-Pin RVLIS

Connectors Installed

1