IR 05000456/1985031

From kanterella
Jump to navigation Jump to search
Insp Repts 50-456/85-31 & 50-457/85-30 on 850617-21.No Violations or Deviations Noted.Major Areas Inspected: Licensee Actions on Previous Insp Findings,Ie Circulars & Allegations
ML20133E161
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 07/10/1985
From: Little W, Patricia Pelke
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20133E136 List:
References
50-456-85-31, 50-457-85-30, NUDOCS 8508070587
Download: ML20133E161 (7)


Text

. '. th 8 U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-456/85031(DRP); 50-457/85030(DRP)

Docket Nos. 50-456; 50-457 Licenses No. CPPR-132; CPPR-133 Licensee: Commonwealth Edison Company Post Office Box 767 Chicago, IL 60690 Facility Name: Braidwood Nuclear Power Station, Units 1 and 2 Inspection At: Braidwood Site, Braidwood, Illinois Inspection Conducted: June 17 through June 21, 1985

-

.

Inspector: P. R. Pelke 7h/hC Date c 8Al -

Approved By: S Li r [/8 [

Bra dwood Project Dag /

Inspection Summary Inspection on June 17 through June 21, 1985 (Report No. 50-456/85031(DRP);

! 50-457/85030(DRP))

Areas Inspected: Routine, unannounced safety inspection of licensee actions on previous inspection findings, IE Circulars, and allegations. The inspection involved a total of 37 inspector-hours onsite by one inspecto Results: No violations or deviations were identified.

l l

l

!

l l

l l

'

!

I 8508070587 850710 ..

PDR ADOCK 05000456

. LtoL

. .

,

DETAILS 1. Persons Contacted Commonwealth Edison Company (CECO)

  • Wallace, Project Manager
  • C. Schroeder, Licensing and Compliance Superintendent
  • D. Shamblin, Construction Superintendent
  • L. Kline, Licensing and Compliance Supervisor
  • D. Boone, Construction Engineer
  • T. Quaka, Quality Assurance Superintendent
  • W. Vahle, Project Field Engineering Manager
  • D. Cecchett, Project Licensing and Compliance
  • C. Tomashek, Startup Superintendent
  • G. Marcus, Project Management
  • E. Wendorf, Project Field Engineer
  • J. Geiseker, Project Construction Department
  • J. Phelan, Project Field Engineer
  • H. Zimmerman, Testing Supervisor T. Ronkoske, Field Engineer I. Rivera, OAD L. K. Comstock (LKC)-
  • R. Seltmann, Quality Assurance Manager
  • Dewald, Quality Control Manager
  • J. Klena, Project Engineer
  • F. Rolan, Project Manager G. K. Newberg (GKN)
  • R. Donica, Quality Assurance Manager
  • D. Craven, Project Manager L. Tinker, Area Superintendent Phillips Getschow Company (PGCo)
  • T. O'Connor, Project Manager
  • J. Stewart, Project Engineer
  • K. Kranz, Quality Assurance Site Manager Sargent and Lundy (S&L)
  • K. Fus l

l l

l

  • '

. .

'

Nuclear Regulatory Commission (NRC)

  • L. McGregor, Senior Resident Inspector
  • Schulz, Senior Resident Inspector
  • Little, Director, Braidwood Project
  • Denotes those attending the June 21, 1985 exit meetin Additional licensee and contractor personnel were contacted during the course of the inspectio . Licensee Action on Previously Identified Items (Closed) Noncompliance (456/82-01-04; 4b7/82-01-03): Nine out of 25 post tensioning vendor drawings on the rack in the Braidwood site construction office for Unit 1 were superseded and not identified as such, six out of 22 similar drawings for Unit 2 were also superseded and not identified as such, and the latest revisions of the superseded drawings were not e

distributed and used at this prescribed locatio The drawing files were updated the day after the discrepancies were identified. The vendor drawings in the Project Construction Office have all been stamped "For Information Only" and are not controlled. The site contractors' files were used whenever controlled construction vendor prints were needed. This item is considered to be close (Closed) Open Item (456/83-18-07): During a review of MCC 1AP26E, the inspectors observed that the field welds between the equipment channels and the embedded sills had not been painte The inspector verified, by visual inspection, that the welds on MCC 1AP26E have been painte L. K. Comstock Procedure 4.8.3, " Weld Inspection", Revision H, dated February 5,1985, was revised to state in Paragraph 3.25 that, "LKC QC shall perform an inspection of released areas to assure that painting of field welds has been completed. The inspection shall take place when the walkdown inspection takes plac Results of the inspection shall be documented on a General Inspection

>

Report." This item is considered to be closed.

4 (Closed) Open Item (456/84-23-03): During a review of the terminations in junction box 1JB428R-K1R, it appeared that the copper conductor was not inserted far enough into the lug barrel to provide a good mechanical and electrical connection on three terminations. Also, it appeared that the copper conductor extended too far beyond the lug barrel on one

'

termination so as to cause interference when installing the termination screw. The licensee was requested to reinspect these terminations and determine their acceptabilit An LKC Inspection Correction Report (ICR) was written and work was completed to correct the termination deficiencies. The inspector verified that the terminations were acceptabl This item is considered to be close l 3 I l

. ___ _ . _ - . _ _ _ . _

___l

-

. .

The inspector noted that the drain wire for circuit IRC226 was terminated on TB1 at Point 9. The applicable drawing, 20E-1-4105M, Revision J, does not show this termination. LKC Procedure 4.3.9, " Cable Termination Installation", Revision C, dated March 7, 1984, Paragraph 3.10.1.2, states, "when no termination of the drain wire is indicated on the construction drawing, the drain wire shall be bent back and insulated with tape or heat shrinkable tubing."

The inspector reviewed LKC ICR No. 7000 which controlled this installatio The ICR referenced the wrong drawing and the work was QC accepted. Additionally, the cable de-termination and re-termination cards, dated June 1,1985, for this activity referenced the wrong drawing and the re-termination card has a QC inprocess inspection signature. LKC wrote a nonconformance report to address these concerns. This is an unresolved item pending the inspectors' review of the licensee's corrective actions (456/85031-01).

(Closed) Open Item (456/84-23-04; 457/84-22-02): Review the revised LKC NCR procedure, as approved, and personnel training record The inspector reviewed LKC Procedure 4.11.1, " Nonconforming Items,"

Revision F, dated June 18, 1984 (Effective December 7, 1984). The disposition category " reject" has been removed from the procedur The disposition categories "use-as-is, rework, repair, scrap, and other",

have been define The inspector reviewed LKC records which documented a December 10, 1984 training session on this revised procedur This item is considered to be close No violations or deviations were identifie . IE Circulars For the IE Circular listed below, the inspector verified that the circular was received by the licensee's management, that a review for applicability was performed, and that if the circular was applicable to the facility, appropriate corrective actions were taken or were scheduled to be take (Closed) IE Circular 76-06: Stress Corrosion Cracks in Stagnant, Low Pressure Stainless Piping Containing Boric Acid Solution at PWR's. This circular relates to several occurrences of through-wall cracking in low pressure stainless steel piping containing boric acid solution. The failure mechanism was intergranular stress corrosion cracking in all observed instances. Once Braidwood is operational, inservice inspections will provide for a VT-2 examination every period (40 months) of the Class 2 and 3 portions of systems containing boric acid. This circular is considered to be close No violations or deviations were identifie . .

,

4. Review of Allegations (Closed) Allegation (RIII-85-A-0022): On February 5,1985, Region III received an anonymous allegation that during winter months, salt was being used for ice control in the Braidwood parking lots. The alleger was cor.cerned with the potential for salt being tracked into the building areas, being transferred to safety-related equipment and causing corrosion. This allegation was forwarded to the licensee for their review in a letter dated March 27, 198 The inspector reviewed the results of the licensee's review. Since the start of construction at Braidwood, no salt has been purchased, brought onsite or used to control ice and snow. Commonwealth Edison has only used sand on the main roads and paved areas to ease sliding condition This sand is applied by two dump trucks with spreader boxes similar to those used by highway department vehicles. The sand used is from the batch plant stockpile. This was done to prevent having two sand stockpiles, Category thus eliminating I concret thethat In areas possibility have been of using(the wrong stoned rather sand than in paved),

CA-6 (Road Mix), a graded aggregate, is hand spread to provide better footing. The inspector interviewed the Newberg Area Superintendent responsible fer these activities and he confirmed that no salt was used for ice contro Additionally, during 1983 and 1984, a liquid ice preventer was used on side walks and around buildings. A total of 275 gallons of this product has been used at the site. A sample of this product was submitted to the CECO Systems Materials Analysis Department for an analysis for halogens, sulfur, and heavy metals. The sample was analyzed using ion chromatography and atomic absorption spectroscopy. The results of the analysis indicated that this product is not corrosiv This allegation was not substantiated and is considered to be close (Closed) Allegation (RIII-85-A-0009): Region III received an unsigned letter on January 24, 1985, alleging that a former Daniel International Corporation Level II civil Quality Inspector at Fermi 2 had not been properly trained or certified as a Level II Civil Quality Inspector. The alleger expressed specific concerns that he felt the individual was unable to correctly perform calculations relative to sand cone tests, cross sectional area of concrete cylinders, minimum distance between two concrete wedge anchors of differing diameters, or the revised torque value of anchor bolts using a torque wrench adaptor. This allegation was not substantiated and was closed for Fermi 2 in Report N /85019(DRS). However, the alleger requested Region III to ensure that the individual and other Daniel inspectors who were transferred to Braidwood have the proper training before they can sign QC document _ _ . .. . -. - - - .- _- -- .. , .

.,

, l J

The inspector determined that the individual is currently certified at

!

Braidwood as a BCAP Civil / Structural Level II inspector. The inspector reviewed the individual's certification package which contained the following information:

The individual arrived onsite during December 1984.

The individual had six years and two months of previous experienc The individual had passed both written and oral examinations, and the Vision Acuity Test. The individual had completed all required readin A letter of recommendation for certification as a Level II from his supervisor was in the certification packag The individual was certified on May 7, 198 The certification package was approved by BCAP Q The inspector determined that the individual was properly certified in accordance with BCAP Procedure BCAP-08, " Qualification and Certification of Reinspection Personnel," and ANSI N45.2.6 (1978).

Additionally, the inspector determined that other inspectors previously employed by Daniel Construction Company at the Fermi 2 plant were assigned to the Braidwood BCAP Program. During a previous inspection (Report No. 50-456/84-25; 50-457/84-24), an unresolved item was

.

'

identified by the NRC BCAP inspector that a number of the BCAP inspectors were previously certified by Daniel Construction Company under a certification process which was not, on the surface, compatible

.

with Braidwood site requirements. The affected inspectors had been

'

performing inspections, at facilities under construction by Daniel

Construction Company, for at least six months. The NRC BCAP inspector requested the licensee to review the affected inspectors' experience, education, and prior certifications to ensure that their certification

, at Braidwood would satisfy the requirements of ANSI N45.2.6. This

unresolved item was closed in Report No. 50-456/85025; 50-457/8502 In followup to the unresolved item, the NRC BCAP inspector reviewed the education and experience data for 18 BCAP taskforce inspector In each case, the documented data exceeded the requirements delineated in ANSI N45. Based on these reviews, this allegation is considered to be close No violations or deviations were identifie . Unresolved Items Unresolved items are matters about which more information is required in order to ascertain whether they are acceptable items, items of noncompliance, or deviations. An unresolved item disclosed during the inspection is discussed in Paragraph .

6

. - - - _ - . _ - _ _ - - - - -_ __ _ _

-

o . -

, ,

.

6. Exit Interview The inspector met with licensee and contractor representatives denoted in Paragraph 1 during and at the conclusion of the inspection on June 21, 1985. The inspector summarized the scope and results of the inspection and discussed the likely content of this inspection report. The licensee acknowledged the information and did not indicate that any of the information disclosed during the inspection could be considered proprietary in natur