IR 05000445/1981017

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-445/81-17 & 50-446/81-17 on 811102-06.No Noncompliance Noted.Major Areas Inspected:Const Activities & Records for Welding of Unit 1 Reactor Containment Bldg Liner
ML20038B831
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 11/19/1981
From: Gilbert L, Randy Hall
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20038B824 List:
References
50-445-81-17, 50-446-81-17, NUDOCS 8112090137
Download: ML20038B831 (3)


Text

-. _.

-

._

_-

-

-_

.--

i

.

APPENDIX A U.S. NUCLEAR REGULATORY COPWISSION

REGION IV

,

Report:

50-445/81-17; 50-446/81-17 Docket:

50-445; 50-446 Category A2

Licensee:

Texas Utilities Generating Company

2001 Bryan Tower Dallas, Texas 75201 Facility Name:

Comanche Peak, Units 1 and 2 Inspection at:

Comanche Peak Steam Electric Station Inspection conducted:

November 2-6, 1981 Inspector:

'

// 9 j p D. Gilbert, Reactor Inspector, Engineering and Dater

!

W Materials Section i

Approved:

_

.

//[// /

.

R. E. Hall, Acting Chief, Engineering and Materials Date'

l Section Inspection Summary:

Inspection During November 2-6, 1981 (Report 50-445/81-17; 50-446/81-17)

Areas inspected:

Routine, unannounced inspection of construction activities j

including site tour; observation of work and review of records for weldtc; of the Unit 1 Reactor Containment Building liner; and observation of work and review of records for safety-related pipe welding in Unit 2.

The inspec-tion involved 34 inspector-hours by one NRC inspector.

Results:

No violations or deviations were identified.

8112090137 811120'

PDR ADOCK 05000445 G

PDR

- -

-

-

-

-

-

- -

-

- - -

-

-

-

-

_-

.

..

..

_-

_

-______

.

DETAILS 1.

Persons Contacted Principal Licensee Personnel

  • R. G. Tolson, Site QA Supervisor, TUGC0
  • J. T. Merritt, Manager, Engineering and Construction, TUSI Other Personnel

W. E. Baker, Senior Project Welding Engineer, Brown & Root (B&R)

G. Willis, QC Mechanical Senior Superintendent, B&R G. Bennetzen, QC Supervisor, B&R D. Williams, Welding /QA Supervisor, Chicago Bridge & Iron (CB&I)

The NRC inspector also interviewed other licensee and contractor employees during the course of the inspection.

  • Denotes those attending the exit interview.

2.

Site Tour The NRC inspector toured the Reactor Building, Auxiliary Building, and Fuel Handling Building for Units 1 and 2 to observe construction in progress and to inspect housekeeping.

No violations or deviations were identified.

3.

Reactor Building Containment Welding - Unit 1 The NRC inspector inspected the CB&I welding activities related to closing of the construction opening in the Reactor Containment Building liner.

In the areas inspected, welding and spot radiography were con-sistent with Welding Procedure Specification WPS-E8018-C1, Revision 4; Radiography Procedure RTP-74-2427/8, Revision 7; and CB&I Quality Assurance Manual for Steel Portions of Concrete Containment Vessels Issue No. 6.

i No violations or deviations were identified.

4.

Safety-Related Pipe Welding Activities - Unit 2 The NRC inspector observed the repair welding of two butt welds which (

were identified as follows:

'

FW-1 in Containment Spray Line 16" CT-2-140-151R-2 on Isometric Drawing CT-2-RB-092

,,

.

..

_ _ _ _ _ _

=

.

FW-1 in Safety Injection Line 16" SI-2-073-151R-2 on Isometric Drawing SI-2-RB-088 In the areas inspected, no discrepancies were noted concerning compliance with B&R Welding Procedure Specification WPS 11020.

The NRC inspector selected ten field welds for visual examination and found the final weld surface condition to be consistent with the require-ments of B&R Procedure QI-QAP-10.2-7, Revision 1 for visual examination of weldments and ASME B&PV Code Section III,1974 Edition, including Summer 1974 Addenda for Class 1 and 2 piping.

The Class 1 field welds were identified as FW-2, FW-4, FW-10, FW-12, FW-18, FW-20, and FW-29 on Isometric Drawing RC-2-520-1 for the Reactor Coolant Loop Piping System.

The Class 2 field welds for the Safety Injection Piping System were identified as FW-2 and 3 on Isometric Drawing SI-2-RB-081 and W3-3A on Isometric Drawing SI-2-RB-46.

The NRC inspector also reviewed the postweld heat treatment records for four field welds in the Feed Water Piping System, FW-8, FW-9, FW-14, and FW-15 on Isometric Drawing FW-2-SB-001A.

The postweld heat treatments were found to be consistent with B&R Procedure CP-CMP-6.9D and ASME B&PV Code,Section III, 1974 Edition, including Summer 1974 Addenda for Class 2 pipe welds.

No violations or deviations were identified.

5.

Exit Interview The NRC inspector met with licensee representatives (denoted in paragraph 1) and P G. Taylor (NRC Resident Reactor Inspector) on November 6, 1981, and summarized the scope and findings of the inspection.

3