r o
U. S. NUCLEAR REGULATORY COMMISSION i
0FFICE OF INSPECTION AND ENFORCEMENT
REGION IV
Report:
50-445/81-07; 50-446/81-07 Docket:
50-445; 50-446 Category A2 Licensee:
Texas Utilities Generating Company 2001 Bryan Tower Dallas, Texas 75201 Facility Name:
Comanche Peak, Units 1 and 2 Inspection at:
Comanche Peak Steam Electric Station Inspection conducted:
April 6-10, 1981 Inspectors.
f/#/S /
L. D. Gilbert, Reactor Inspector, Engineering and
'Date Materials Section, (Paragraphs 1, 2, 3, 4 and 6)
' 'S,9&w,$.
$~/6-lT )
/
pl.E. Martin,ReactorInspector,ReactorProjects Date Section No. 3 (Paragraphs 2 and 5)
Other Accompanying Personnel:
K. A. Whittlesey, Reactor Inspector Trainee, Engineering and Materials Section Approved:
MMb MT/S'/
p W. A. Crossman, Chief, Reactor Projects Section No. 3 Date
'h b
R. E. Hall, Acting Chief, Engineering and Materials Oat'e Section i
I l
'stoese 2A 2,
.
.
.
__ __
_.
..
. --_.
--
..
r
-
.
Inspection Summary
_
!.ispection During April 6-10, 1981 (Report 50-445/81-07; 50-446/81-07)
Areas Inspected:. Routine, unannounced inspection of construction activities including site tour; observation of work and review of records for safety related welding activities in Unit No. 2; observation of work and review of records for safety-related electrical activities in Unit No. 1; and follow up of previously reported unresolved items.
The inspection involved 63 inspector-hours by two NRC inspectors.
Results:
No violations or deviations were identified, o
<,,..--,--a
,,
-
,--------m ww-,-----+-w-e
- - -,
s
- r-
- ~~ '" '
~w
' ' '
w'#'~*
'*' *
' *' *
'~
r
-
.
DETAILS 1.
Persons Contacted Principal Licensee Personnel
- R. G. Tolson, Site QA Supervisor, TUGC0
- J. T. Merritt, Manager, Engineering and Construction, TUSI J. Lowry, Quality Engineer, TUGC0 Other Personnel J. V. Hawkins, Project QA Manager, Brown & Root (B&R)
W. E. Baker, Senior Project Welding Engineer, B&R F. Nichols, Supervisor Welder Qualification Test Center, B&R T. B. Maxwell, Site NDE Level III The NRC inspectors also interviewed other licensee and contractor employees during the course of the inspection.
- Denotes those attending the exit interview.
2.
Follow Up of Previously Reported Unresolved Items (Closed) Unresolved Item (50-445/80-28; 50-446/80-28):
Incorrect Designa-tion of QC Hold Points on Weld Data Card.
The licensee performed a review of 600 Weld Data Cards which represented approximately 20 percent of the outstanding Weld Data Cards and found no QC hold point errors.
The NRC inspector reviewed an additional 25 completed Weld Data Cards and found no QC hold point errors.
The Weld Data Card with the QC hold points erroneously marked is therefore considered an isolated case.
The NRC inspector had no further questions on this matter.
(Closed) Unresolved Item (50-445/79-06; 50-446/79-06):
Non-Class IE Cable Tray in Seismic Category I Structures.
The NRC inspector reviewed the following procedures:
CP-QP-11.10, Revision 0, " Inspection of Electrical Raceway Support Systems" QI-QP-11.10-2, Revision 2, " Cable Tray Hanger Inspection" QI-QP-11.10-4, Revision 4, " Inspection of Seismically Mounted Conduit Supports"
- - - -
..
-.
..-
r
.
The precedures adequately address the quality assurance requirements and acceptance criteria for non-Class IE raceway and supports in Seismic Category I structures.
This item is considered closed.
3.
Site Tour The NRC inspectors toured the Reactor Building, Auxiliary Building and Control Building for Units 1 and 2 to observe construction in progress and to inspect housekeeping.
No violations or deviations were identified.
4.
Safety-Related Welding Activities - Unit 2 The NRC inspector observed the welding of a butt weld in the Main Steam (MS) system and three butt welds in the Component Cooling (CC) system which were identified as follows:
FW 11A in Line No. 32" MS-2-03-1303-2 on Isometric Drawing MS-2-RB-26; FW 3-1 and FW 3-2 in Line No. 8" CC-2-249-152-3 on Isometric Drawing CC-2-RB-084; and FW 7A in Line No. 8" CC-2-203-152-2 on Isometric Drawing CC-2-RB-97.
In the areas inspected, no discrepancies were noted concerning welder qualification, procedure compliance, material control and weld documentation.
The NRC inspector selected five field welds for visual examination and found the final weld surfaces to be consistent with the requirements of Procedure CP-CPM-6.9 and ASME B&PV Code,Section III, 1974 Edition includ-ing Summer 1974 Addenda for Class 2 components, The field welds observed were:
FW 13 and FW 14 in Line No. 4" SI-2-300-1501R-2 on Isometric Drawing SI-2-SB-013; FW 2 and FW 3 in Line No. 16" CT-2-001-151R-2 on Isometric Drawing CT-2-SB-29; and FW 2 in Line No. 12" CT-2-005-151R-2 on Isometric Drawing CT-2-SB-05.
The NRC inspector also observed various phases of welder qualification testing for nine welders that included:
testing, training before retest-ing, retesting, surveillance of qualification testing, bend testing and l
radiographic examination.
Qualification of welders was observed to be consistent with requirements of Procedure WES-16 and ASME B&PV Code,
'
l Section IX, 1980 Edition including Summer 1980 Addenda.
No violations or deviations were identified.
5.
Electrical Systems and Components The NRC inspector reviewed receiving and installation records for safety-related electrical equipment.
These records were reviewed to determine compliance with CPSES Final Safety Analysis Report, 10 CFR Part 50, IEEE and NEMA Standards, and the appropriate Gibbs & Hill Specifications.
The
r
<
.
following is a list of the records that were reviewed by equipment name and spin number:
a.
Diesel Generator 1EG2, Spin No. CP1-MEDGEE-02 Gibbs & Hill Specification 2323-MS-34, Revision 1 Purchase Order CP-0034 Material Receiving Reports CP2419, 5221, 2447, and 5359 Receiving Inspection Reports 6582, 6572, 7577, and 10846 Delaval Inspection Report 4850 Delaval Failure Analysis Report 1487 Delaval Field Service Report 4-2568 Delaval Generator Diagnostic Test Record Delaval Standard Test Record For Stator 17604916-200 Delaval Engineering Order 9632 and the Associated Inspection Report Delaval D. C. Test Data Sheet Delaval Generator No Load Saturation Curve Brown & Root Operational Installation Travelers EE-81-001-2901, EE-79-182-2901, EE-79-183-2901, EE-79-134-2901, EE-79-185-2901, and M-78-100-29 GA/GB.
b.
7kV Switchaear 1EA2, Spin No. CP1-EPSWEA-02 Gibbs & Hill Specification 2323-ES-5, Revision 1 Purchase Order CP-0425 Material Receiving Reports CP 3431 and CP 3432 Receiving Inspection Reports 8098 and 8252 Quality Assurance Release 2491 B&R Operational Travelers CE-80-057-0200, EE-79-005-02AB, EE-19-007-02AB, EE-80-228-02AB, and EE-80-332-02AB
.
- - - -..,
y
.--
_
., - -.
-
-
. -.,..
-,
r
-
.
Nonconformance Reports E1251, E1255, and E1614 Design Change Authorization 3120 c.
480 Volt Motor Control Center IEBA-2, Spin No. CP1-EPMCEB-06 Gibbs & Hill Specification 2323-ES-7 Purchase Order CP-0435 Material Receiving Report CP6977 Receiving Inspection Reports 13292 and 13089 Gould Certification of Inspection Gould Final Operational Test Repor+
B&R Operational Travelers RI-80-319-0200, EE-80-346-02AJ, EE-79-250-02AJ.3, EE-80-128-0200, and EE-80-213-0200 Nonconformance Report E-80-319-0200 d.
480 Volt Switchaear 1E84, Spin No. CP1-EPSWEB-04 Gibbs & Hill Specification 2323-ES-6, Revision 3 Purchase Order CP0430 Material Receiving Records CP4325 and CP5905 Receiving Inspection Reports 09376 and 11792 Quality Assurance Release 2519 Certificate of Compliance for IEEE 383 Wiring Gould Deviation Notice No. 1 B&R Operational Travelers RI-79-179-0200, EE-79-257-02AF, EE-80-103-02AF, EE-79-024-02AF, EE-79-087-02AF, and CE-80-050-0200
'
Nonconformance Report E-80-00182S
!
Design Change Authorizations 3625 and 2633
i
.. _-._,.. -
.,, _. _. _ _ _. _ _ - -
_
r
.
..
e.
480 Volt Motor Control Center XEB4-3, Spin No. CPX-EPMCEB-06 Material Receiving Report CP 7568 B&R Operational Travelers EE-80-348-02AJ, EE-80-328-02AJ.1 and EE-80-329-02AJ.1 Nonconformance Reports E-80-000375, E-80-00995, and E-2037 Inspection Reports E-21299 and ME-2630 f.
480 Volt Motor Control Center IEB3-4, Spin No. CP1-EPMCEB-06 B&R Operational Travelers EE-79-110-020, EE-80-348-02AJ, and RI79-277-0700 Nonconformance Report E-80-00104 Inspection Report E-21292 g.
480 Volt Motor Control Center Starter Units Material Receiving Reports CP 6549, 7535, 6551, ar.d 7271 Receiving Inspection Reports 14010, 13092, 12601, and 13827 No violations or deviations were identified.
6.
Exit Interview The NRC inspectors met with licensee representatives (denoted in paragraph 1) and R. G. Taylor (NRC Resident Reactor Inspector) on April 10, 1981, and summarized the scope and findings of the inspection.