IR 05000445/1980010

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-445/80-10 & 50-446/80-10 on 800325-27.No Noncompliance Noted.Major Areas inspected:safety-related Const,Review of Records & Plant Tour
ML19323C785
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 04/10/1980
From: Crossman W, Stewart R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19323C783 List:
References
50-445-80-10, 50-446-80-10, NUDOCS 8005190187
Download: ML19323C785 (3)


Text

8005190pi U. S. NUCLEAR REGULATORY COMMISSION h

0FFICE OF INSPECTION AND ENFORCEMENT

REGION IV

Feport No. 50-445/80-10; 50-446/80-10 i

Docket No. 50-445; 50-446 Category A2 Licensee: Te::as Utilities Generating Company 2001 Bryan Tower Dallas, Texas 75201 Facility Name:

Comanche Peak, Units 1 and 2 l

Inspection at:

Comanche Peak Site, Glen Rose, Texas Inspection conducted: March 25-27, 1980 b4fW 4 /* co Inspector:

R'. C. Stewa'rt, Reactor Inspector, Projects Section

'Datd Other Accompanying Personnel:

M. J. Rucker, Reactor Inspector Aide P. G. Wisco, Philippine AEC

'

Approved:

///' [O

,

W. A. Crossman, Chief, PMjects Section

' Dat'e Inspection Summary:

Inspection on March 25-27, 1980 (Report No. 50-445/80-10; 50-446/80-10)

Areas Inspected:

Routine, unannounced inspection of safety-related construction activities pertaining to installation and record review of safety-related com-ponents and a site tour.

The inspection irvolved twenty-one inspector-hours by

'

one hTC inspector.

Results:

No items of noncompliance or deviations were identifie. -

.

.

.

--_

__ _ ____ _ - _-_

.

DETAILS 1.

Persons Contacted Principal Licensee Personnel

.

  • R. Tolson, Site QA Supervisor, Texas Utilities Generating Co. (TUGCO)

i J. Hawkins, QC Supervisor, Brown & Root /Gibbs & Hill (B&R/G&H)

Other Personnel T. Summerville, QA/QC Document Control Supervisor, B&R R. Cormears, QA Start-Up Supervisor, B&R The IE inspector also interviewed other licensee and contractor personnel including members of the engineering and QA/QC staffs.

  • Denotes those attending the exit interview.

2.

Site Tour The IE inspector toured the Units 1 and.2 Reactor Containment Buildings and Auxiliary Building to observe construction activities in progress and to inspect housekeeping.

No items of noncompliance or deviations were identified.

3.

Installation of Safety-Related Components - Observation or Work and Work Activities The IE inspector conducted a follow-on inspection of the Unit 1 Reactor

Containment Building, Safeguards Building and Auxiliary Building to

'

observe installation and protection of safety-related components.

Observations were made on all principal levels of each building to observe conformance with requirements prescribed by B&R Procedure,

" Storage and Storage Maintenance of Mechanical and Electrical Equipment,"

l MCP-10, Revision 4, dated June 14, 1979, and TUSI Procedure QI-QP-11.3.31,

dated January 5, 1980.

No items of noncompliance or deviations were identified.

4.

Safety-Related Components - Review of Quality Control Records The IE inspector conducted a follow-on review of QA/QC records relative to safety-related component installations.

The IE inspector selected the Containment Spray Pump, Serial No. CPI-CTAPCS-03M and the Safety Injec-tion Pump, Serial TBX SIAPSI-01, for a QA/QC documentation review.

,

5

,

,

_ _.

,,, _.

-

-'

"

'"

' l

....

<

' *

Documents reviewed included G&H Specification 2323-MD-12; B&R Procedure QI-MCP-10.1, " Mechanical Equipment Storage Maintenance," Revision 0, dated May 17, 1979; FSAR, Section 6.2.2, " Containment Heat Removal System";

and the related "QA Data Package" files for each component.

No items of noncompliance or deviations were identified.

5.

Exit Interview The IE inspector met with the licensee representatives (denoted in

paragraph 1) on March 27, 1980, and summarized the purpose, scope and findings of the inspection.

!