Forwards IE Insp Repts 50-445/80-10 & 50-446/80-10 on 800325-27.No Noncompliance Noted
ML19323C782
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 04/10/1980
From: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Gary R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
Shared Package
ML19323C783 List:
References
NUDOCS 8005190184
Download: ML19323C782 (2)


See also: IR 05000445/1980010

Text

3005190f%

UNITED STATES

f'e' "E cw%,

NUCLEAR REGULATORY COMMISSION

f ' *, *

'

$

REGloN IV

/

' : , o

611 RYAN PLAZA DRIVE, SUITE 1000

I

7 ,,

',y

ARLINGTON, TEXAS 76012

e

C;,

p.

~

*9/a_f

%

4.,,..'

April 10, 1980

In Reply Ref.c To:

RIV

Docket Ko. 50-445/Rpt. 80-10

50-446/Rpt. 80-10

Texas Utilities Generating Company

ATTN:

Mr. R. J. Gary, Executive Vice

President and General Manager

2001 Bryan Towe:

Dallas, Texas

75201

Gentlemen:

This refers to the inspection conducted by Mr. R. C. Stewart of our staff

during the period March 25-27, 1980, of activities authorized by NRC Construction

Permits No. CPPR-126 and 127 for the Comanche Peak facility, Units No. I and 2,

and to the discussion of our findings with Mr. R. G. Tolson and other members

of your staff at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examination of procedures and representative records, inte.niews

with personnel, and observations by the inspector.

Within the scope of the inspection, no items of noncompliance were identified.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If the

report contains any information that you believe to be proprietary, it is

necessary that you submit a written application to this office, within 20 days

of the date of this letter, requesting that such information be withheld from

public disclosure. The application must include a full statement of the reasons

why it is claimed that the information is proprietary.

The application should

be prepared so that any proprietary information identified is contained in an

enclosure to the application, since the application without the enclosure will

also be placed in the Public Document Room. If we do not hear from you in this

regard within the specified period, the report will be placed in the Public

Document Room.

l

,

-

-_.

.

Texas Utilities Generating Company

2

April 10, 1980

Should you have any questions concerning this inspection, we will.be pleased

to discuss them with you.

Sincerely,

,. h '

&

W.C.heidle\\, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE inspection Report No. 50-445/80-10

50-446/80-10

i

cc: w/ enclosure

Texas Utilities Generating Company

ATTN:

Mr. H. C. Schmidt, Project Manager

'

2001 Bryan Tower

Dallas, Texas

75201

,

l

i

-

,.

, . . .

...