IR 05000445/1979030

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-445/79-30 on 791217-18.No Noncompliance Noted.Major Areas Inspected:Procedures for Preservice Insp, Observation of Work,Review of Insp Records & Interviews W/ Insp Personnel
ML19296D885
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 01/09/1980
From: Crossman W, Randy Hall, Tomlinson D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19296D884 List:
References
50-445-79-30, NUDOCS 8003130413
Download: ML19296D885 (4)


Text

.

U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT

REGION IV

Report No.

50-445/79-30 Docket No.

50-445 Category A2 Licensee:

1exas Utilities Generating Company 2001 Bryan Tower Dallas, Texas 75201 Facility Name:

Comanche Peak, Unit 1 Inspection at:

Comanche Peak Site, Glen Rose, Texas Inspection conducted:

December 17-18, 1979 Inspector: _

/!/

'

p D. P. Tomlinson, Reactor Inspector, Engineering

'Ddte Support Section

/[f/[8 Approved:

w W. A. Crossman, Chief, Projects Section Date

.

}lf 23

R. E. Hall, Chief, Engineering Support Section Dafe Inspection Summary:

Inspection on December 17-18. 1979 (Report No. 50-445/79-30)

Areas Inspected:

Routine, unannounced inspection of construction activities including site tour; review of procedures for preservice inspection, Unit 1; observation of work; review of inspection records and interviews with inspection personnel.

The inspection involved sixteen inspector-hours by one NRC inspector.

Results:

In the areas inspected, no items of noncompliance or deviations were identified.

Up3nt4L3

.

.

DETAILS 1.

Persons Contacted Principal Licensee Personnel

  • R. G. Tolson, TUGCO, Site QA Supervisor The IE inspector also interviewed other licensee and contractor personnel during the course of the inspection.
  • Denotes attendance at the exit interview.

2.

Review of Procedures for Preservice Inspection The IE inspector reviewed six Westinghouse procedures currently being used in the performance of the preservice inspection of Unit No. 1.

This review was to assure that the procedures were in accordance with ASMI B&PV Code,Section XI, and the commitments described in the PSAR.

Because this phase of the inspection was limited in scope and covered only a portion of the total preservice requirements, only those documents in use at this time were examined.

Procedures reviewed were:

ISI-8 (Rev. 7)

Visual Examination Procedure ISI-11 (Rev. 9)

Liquid Penetrant Examination Procedure ISI-47 (Rev. 2)

Manual Ultransonic Examination of.

';ircumferential and Longitudinal Butt Welds in Ferritic Vessels of 2\\" Thick and Greater ISI-205 (Rev. 2)

Manual Ultrasonic Examination of Full Penetration Circumferential and Longitudinal Butt Welds NSD-ISI-10 (Rev. 4)

Preservice and Inservice Examination Manual Ultrasonic Equipment Qualification OPS-NSD-101 (Rev. 5)

Preservice and Inservice Inspection Documentation No items of noncompliance or deviations were noted during this portion of the inspection.

.

3.

Observation of Work Activities During Preservice Inspection The IE inspector verified that the personnel qualification records for the preservice inspection team were complete and in accordance with the requirements of SNT-TC-1A.

Records of written and practical tests were reviewed along with the results of each inspector's vision examination to assure compliance and currentness.

This review covered only the records for the Level II and I inspectors. The records for the responsible Level III inspector were not available.

The IE inspector also interviewed each of the four inspectors on site to assure that each had sufficient knowledge of the test methods employed to adequately and reliably perform these inspections.

The IE inspector reviewed the certifications for the two ultrasonic calibration standards being used along with the records for the ultra-sonic instruments, transducers and couplant.

The actual calibration of the ultrasonic equipment was witnessed prior to inspection as was one periodic check and the post-inspection calibration verification.

The IE inspector accompanied the inspection team to the job site and witnessed the ultrasonic inspection of five circumferential piping welds on the No. 3 Reactor Coolant Loop.

These joints were No. 5, 6, 8,11 and 13 as identified on drawing No. TBX-1-4300.

As this was a partial and preliminary inspection, only the longitudinal beam was employed.

Shear wave inspection will be performed on these welds at a later date.

No items of noncompliance or deviations were noted during this portion of the inspection.

4.

Data Review and Evaluation The IE inspector reviewed the available records for the partial pre-service inspection performed on Reactor Coolant Loops No. I and 3 and for the welds inspected on the pressurizer.

This review was con-ducted to verify that the inspection records included all pertinent and required data such as dates, personnel, equipment used, areas inspected, extent of inspection, methods used, procedures used and the results of the inspections.

These results covered only the visual, liquid penetrant and longitudinal ultrasonic inspection of the pressurizer welds and piping welds identified on Drawings No. TEX-1-2100, TBX-1-4100 and TBX-1-4300.

Several of the piping welds exhibited rejectable conditions when inspected visually or by the liquid penetrant method and were therefore not inspected ultrasonically pending disposi-tion of these anomalies.

No items of noncompliance or deviations were noted during this portion of the inspection.

..

.

5.

Exit Interview The IE inspector met with the licensee representative (denoted in paragraph 1) and with the hTC Resident Reactor Inspector at the conclusion of the inspection on December 18, 1979.

The IE inspector summarzzed the purpose, scope and findings of the inspection.

The licensee representative acknowledged the statements by the inspector.

.

4